2
1.0 INTRODUCTION
3
4
Hydro One’s Asset Management Plan is a systematic approach to determine and optimize
5
on-going operating and maintenance expenditures and capital investments in its
6
distribution system and general plant. Hydro One has adopted an Asset Management
7
model since its inception. The objective of this plan is to ensure all funding is spent in the
8
most effective manner to realize the best value for Hydro One stakeholders and
9
customers and to minimize total bill impacts. To accomplish this objective, Hydro One
10
applies a consistent approach to assess the relative asset risk impacts on business values
11
and strategic objectives by considering and balancing asset performance (including
12
physical condition), costs and risks, lifecycle management from an overall power system
13
perspective and assigning asset risk scores to the corresponding investment planning
14
actions for in-service assets. Hydro One’s mission and vision is “We will be an
15
innovative and trusted company, delivering electricity safely, reliably and efficiently to
16
create value for our customers”. The asset management process at Hydro One supports
17
the corporation mission and vision.
18 19
2.0 THE ASSET MANAGEMENT PLAN OVERVIEW
20
21
The Hydro One Asset Management Plan is incorporated throughout the evidence as
22
documented below:
23
• Voice of the Customer (Exhibit A, Tab 5, Schedule 1)
24
• Summary of Distribution Business (Exhibit A, Tab 6, Schedule 1)
25
• Planning Process (Exhibit A, Tab 17, Schedule 1)
26
• Investment Plan Development (Exhibit A, Tab 17, Schedule 3)
27
• Investment Prioritization Process (Exhibit A, Tab 17, Schedule 4)
28
• Project/Program Approval and Control (Exhibit A, Tab 17, Schedule 5)
1
• Work Execution Strategy (Exhibit A, Tab 17, Schedule 6)
2
• Asset Risk Assessment (Exhibit A, Tab 17, Schedule 7)
3
• Regional Planning Process (Exhibit A, Tab 17, Schedule 8)
4
• Common Corporate Costs OM&A – Asset Management (Exhibit C1, Tab 2, Schedule
5
9)
6
• Distribution Assets Investment Overview (Exhibit D1, Tab 2, Schedule 1)
7 8
The results of this process is the five year capital and OM&A investment plan filed at and
9
Exhibit D1, Tab 3 and Exhibit C1, Tab 2.
10
11
3.0 THE ASSET MANAGEMENT PLAN
12
13
This section provides more detailed descriptions of the aspects of the Asset Management
14
Plan.
15
16
3.1 Voice of the Customer
17
18
Customers are a major driver of long-term success. Hydro One listens to its customers,
19
analyzes their needs and then modifies its work activities and work programs to address
20
those needs. The many channels through which Hydro One listens to its customer’s
21
needs are discussed in Exhibit A, Tab 5, Schedule 1.
22
23
3.2 Summary of Distribution Business
24
25
The Summary of Distribution Business (Exhibit A, Tab 6, Schedule 1) provides an
26
overview of the Hydro One distribution system including the evolution of the system,
27
Corporate values, strategic goals and performance targets. All of these factors are
2
considered to inform the Asset Management model and work plan.
3
4
3.3 Planning Process
5
6
Business planning is performed annually and focuses on the development of a detailed
7
plan for each year in the plan. The results as they apply to the test years form the basis for
8
this Custom Rate Application.
9
10
3.4 Investment Plan Development
11
12
Hydro One utilizes a systematic investment approach to plan and optimize on-going
13
capital, operating and maintenance expenditures. Five investment categories; sustaining,
14
development, operations, customer service and common corporate costs, follow a
15
common investment plan development process described in Exhibit A, Tab 17, Schedule
16
3.
17 18
3.5 Investment Prioritization Process
19
20
The investment prioritization process is part of the overall company risk-based asset
21
management planning process (see Exhibit A, Tab 17, Schedule 4). The prioritization
22
process converts Hydro One Distribution’s business values and key performance
23
indicators into investment criteria and guidelines that are used for managing risk and
24
facilitating trade-offs between investments to achieve the optimal balance of cost
25
effectiveness, customer expectations, asset and business needs within the constraints and
26
criteria imposed.
27
3.6 Project / Program Approval and Control
1
2
Once the preliminary investment plans have been accepted at the proof-of-concept stage
3
and have gone through the investment prioritization process, a detailed analysis of the
4
preferred alternatives and costs is completed for individual projects, programs and
5
business cases. Based on the detailed analysis, cost estimates are prepared for review and
6
approval by senior management and ultimately the Hydro One Board of Directors. See
7
Exhibit A, Tab 17, Schedule 5 for more details.
8
9
3.7 Work Execution Strategy
10
11
Hydro One Distribution’s Work Execution Strategy provides increased work execution
12
capacity and necessary flexibility to accommodate the planned distribution work
13
programs. The strategy will also address the continuing global business challenges such
14
as the uncertainty regarding material availability and qualified personnel to undertake the
15
work. A focus on efficiency continues throughout Hydro One’s work planning and
16
execution activities and processes. See Exhibit A, Tab 17, Schedule 6 for more details.
17 18
3.8 Asset Risk Assessment
19
20
Hydro One’s Asset Risk Assessment methodology is built on the Asset Condition
21
Assessment approach previously filed in proceeding EB-2009-0096. Since then, Hydro
22
One has completed an asset inventory of its key distribution assets that has been linked to
23
other non-condition based information such as outage and customer data. This has
24
enabled Hydro One to extend its assessment methodology to improve its focus on non-
25
condition risk factors. More details are found in Exhibit 17, Tab 17, Schedule 7.
26
2
In accordance with the Ontario Energy Board report, “Renewed Regulatory Framework
3
for Electricity Distributors: A Performance Based Approach (“RRFE”), all distributors
4
are required to participate and align wth the regional planning process and activities.
5
Exhibit A, Tab 17, Schedule 8 describes Hydro Ones participation in the regional
6
planning process.
7
8
3.10 Common Corporate Costs OM&A – Asset Management
9
10
The Hydro One Transmission and Distribution businesses are operated using the Asset
11
Management model. The model separates the asset management functions of planning,
12
decision-making and approvals from the services functions of engineering, construction,
13
customer service and grid operations which execute approved plans. The Asset
14
Management organization focuses on ensuring that the necessary transmission and
15
distribution assets are planned, acquired, constructed, maintained and operated such that
16
they deliver the required function and level of performance expected by customers in a
17
sustainable manner over the long term. See Exhibit C1, Tab 2, Schedule 9 for more
18
detail.
19 20
3.11 Distribution Assets Investment Overview
21 22
The Distribution Asset Investment Overview (Exhibit D1, Tab 2, Schedule 1)
23
summarizes the results of the Asset Risk Assessment process for the key distribution
24
assets and their primary risk factors. These results are utilitize in the identification and
25
prioritization of asset needs to assist in the investment plan development of both the
26
capital and operating and maintenance work programs.
27