Project Finance Structuring:
Case Study - Nam Theun 2
Session on Finance
Sidharth Sinha
Indian Institute of Management, Ahmedabad
er Infrastructure: A Tool
kit
Project History
• 1970s - Mekong secretariat identified the hydropower potential of the Nam Theun River
• 1989/91- World Bank feasibility study undertaken by Snowy Mountains Engineering Corp
• 1993 - Government of Lao PDR (GOL) and private sponsors (leader: Transfield) sign an agreement to develop the project
• 1994 - GOL asks World Bank to participate to the project financing
• 1997 - A first series of environmental and social safeguard documents is produced
• 1997/98- Asian crisis: Laos and Thailand agree to delay the project development
Cross-Bord
er Infrastructure: A Tool
kit
Project History (continued)
• 2001- Shareholders agreement signed between EDFI, EDL,
EGCO and ITD (September 2001)
• 2002- NTPC is created as a Lao company (September 2002)
• Concession agreement signed (October 2002)
• Joint work between GOL, World Bank and NTPC to finalize
safeguards documents
• 2003 - Power purchase agreement signed (November 2003)
• 2004- Project financing activities
• Completion of safeguards documents with the participation of WB,
ADB and AFD
• 2005 - Financial close (June 2005) and beginning of full construction activities
• 2009 - Beginning of commercial operation (December 2009)
er Infrastructure: A Tool
kit
Cross-Bord
er Infrastructure: A Tool
kit
Project Details
• The development, construction, and operation of a 1,070 MW transbasin diversion power plant on the Nam Theun, a tributary of the Mekong.
• The project site is in the central provinces of Khammuane and Bolikhamxay, about 250 kilometers southeast of Vientiane, and stretches from the top of the annamite mountain chain along the Lao PDR-Viet Nam border, to the Nakai Plateau, and ultimately to the confluence of the lower Xe Bang Fai with the Mekong.
• It will capture the flow of water from the watershed of the Nam Theun and the Nakai Plateau by building a dam 39 meters (m) high at the northwestern end of the plateau.
er Infrastructure: A Tool
kit
Project Details (continued)
• The project will create a reservoir of 450 square kilometers (km2) on the Nakai Plateau.
• Water from the reservoir will drop about 350 meters to a powerhouse at the base of the Nakai escarpment near the town of Gnommalat.
• The water discharged from the powerhouse will then flow through a 27 km channel to the Xe Bang Fai, which drains into the Mekong approximately 150 km south of the Nam Theun confluence.
• A regulating pond will be constructed downstream of the powerhouse to ensure smooth release of water into the downstream water courses.
Cross-Bord
er Infrastructure: A Tool
kit
Sponsors
• Franco-Lao-Thai partnership with multilateral support
• Nam Theun 2 Power Company Limited (NTPC) is a Lao company established in Sept 2002 with the following shareholders:
¨35% EDF International (EDFI)
¨25% Electricity Generating Public Company Limited (ECGO)
¨25% Government of the Lao PDR (GOL)
¨15% Italian-Thai Development Public Company Limited (ITD)
• EDF is also acting as head contractor, managing three civil work subcontracts and two electromechanical works subcontracts.
er Infrastructure: A Tool
kit
Contractual Arrangements
• Concession agreement signed between GOL and
NTPC on 3 October 2002 for a 25 year period following the beginning of commercial operation
• Power purchase agreements signed on 11 November
2003 for a 25 year operating period
¨between EGAT and NTPC (5,600 GWh per year), ¨between EDL and NTPC (300 GWh per year).
Cross-Bord
er Infrastructure: A Tool
kit
Contractual Arrangements (continued)
• Head construction contract between NTPC and
EDF-CIH provides for a date certain, fixed-price turnkey contract and comprises five major sub-contracts
• NTPC will take full responsibility for O&M for the project
• All environment and social commitments described in
the concession agreement:
¨Long term ¨Binding
¨E&S : ~ 10% of total project costs
er Infrastructure: A Tool
Cross-Bord
er Infrastructure: A Tool
kit
Summary of Project Base Cost Estimates ($ million)
Item ExchangeForeign Currency Local Total
a. Construction cost 396.2 315.3 711.5 b. Environmental-social mitigation 48.8 0.0 48.8 c. Development cost A 150.6 14.0 164.6 d. Financing cost B 173.0 106.3 279.3 e. Base contingencies 27.1 18.7 45.8
Total base cost 795.7 454.3 1,250.0
Total contingent costs 116.6 83.4 200.0
Total 912.3 537.7 1,450.0
63% 37% 100%
er Infrastructure: A Tool
kit
Project Capital Structure
US dollar THB Total % ($ million) ($ million equivalent) ($ million) Equity 345.2 4.8 350.0 28.0% Debt 450.0 450.0 900.0 72.0% Total 795.2 454.8 1,250.0 100.0% % 63.6% 36.4% 100.0%
Cross-Bord er Infrastructure: A Tool kit
Financing Plan
er Infrastructure: A Tool kitExchange Rate Risk
• Debt and equity are denominated in a mix of dollars
(63%) and baht (37%) to match the composition of the two currencies in project base costs.
• The 50/50 mix of US dollar and baht debt is designed
to match the tariff paid by EGAT and EdL.
• EGAT and EdL will carry exchange rate risk.
• To the extent the Lao PDR government will receive
royalty and taxes in dollars some of the risk will be mitigated.
Cross-Bord
er Infrastructure: A Tool
kit
Hydrology Risk
Historic Flow Records
0 2000 4000 6000 8000 10000 12000 14000 1950 1952 1954 1956 1958 1960 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 m ill ion cubi c m et er s
Total Flow capacity
er Infrastructure: A Tool
kit
Hydrology Risk
• The annual inflows have varied historically, on average,
by approximately 20 percent from the long-term average of 7,526 million m3. This is almost double the capacity of the reservoir, so that in an average year, the reservoir should be fully replenished even after operating the plant at full capacity during the dry season.
• The minimum water flow recorded was 3,776 million m3
in 1998. This was the result of El Nino that brought droughts over much of Southeast Asia.
Cross-Bord
er Infrastructure: A Tool
kit
Hydrology Risk (continued)
• The reservoir’s probable maximum capacity is 3,910
million m3 amounting to an annual mean energy of 5,700 GWh.
• 1998 would have been the only year since 1950 when
the flow would not have been sufficient to fill the reservoir from empty.
• However, as the reservoir will not be fully emptied during
operations but will always retain a minimum water level, even in 1998 the reservoir’s probable maximum active storage of 3,530 million m3 could have been filled by the water inflows
er Infrastructure: A Tool
kit
• At full supply level (FSL) at an elevation of 538.0 m,
the reservoir would have an area of 450 sq km and would hold 3,910 million cubic meters of water.
• The powerhouse would have an installed capacity of
1,070 MW.
Cross-Bord er Infrastructure: A Tool kit Energy Component Quantity GWh/year (1) EGAT Obligation to Purchase Applicable Tariff Payment Primary Energy (PE) 4,406 100% 50% in USD, 50% in THB (2) USD and THB respectively Secondary Energy 1 (SE1) 948 100% 50% in USD, 50% in THB (2) 100 % THB (3) Secondary Energy 2 (SE2) 282 0% 100 % THB Fixed over the Term 100 % THB Total 5,636 95% er Infrastructure: A Tool kit
Declarations
• NTPC makes periodic declarations to EGAT.
Declarations contain information as to the energy availability which may be provided by NTPC. Declarations serve two main functions:
¨to determine the amount of NTPC’s revenues payable by EGAT; and
¨to determine the amount of liquidated damages payable by NTPC to EGAT.
• Any unavailability reduces the revenues payable by
EGAT, whilst any outage results in liquidated damages payable by NTPC
Cross-Bord
er Infrastructure: A Tool
kit
Dispatch
• EGAT has the flexibility to dispatch NTPC on a unit by unit basis as it requires, subject only to certain operational constraints.
• As EGAT is not required to dispatch all of NTPC’s
declaration, if it dispatches less, dispatch shortfall occurs.
• As EGAT would have paid NTPC based on all of that declaration, it has the right to “make-up” subsequently, i.e. the right to dispatch for electrical energy without incurring any additional payment obligation.
• Dispatch excess: EGAT may dispatch more than all of NTPC’s declaration, subject to the limitations to be observed by EGAT in NTPC’s declarations
er Infrastructure: A Tool
kit
Excess Dispatch
• An excess energy month is:
¨any month in which there is spillage of water from the reservoir;
¨August or September and the water level is above 537.5 m ASL on the last day of the preceding month; or
¨as elected by NTPC.
• Increased risk of spillage during an excess energy month.
• All the dispatch excess energy as determined at the end
of an excess energy month shall be accounted as SE2, provided, however, that the outstanding amount of
Cross-Bord
er Infrastructure: A Tool
kit
er Infrastructure: A Tool
Cross-Bord er Infrastructure: A Tool kit er Infrastructure: A Tool kit
Offtake Risk
• Thailand now has surplus generating capacity, because
of the economic downturn in the late 1990s and the large amount of capacity that was then under development and could not be stopped on reasonable terms.
• On the basis of demand forecast, excluding new plant
from end-2003, the capacity surplus will be consumed by 2006.
• By the time of NT2 COD, the project will supply about
one-half year of energy demand growth. NT2 would provide about 6 percent of the incremental energy requirement over 2009 to 2016.
Cross-Bord er Infrastructure: A Tool kit
Offtake Risk
er Infrastructure: A Tool kitCross-Bord
er Infrastructure: A Tool
kit
er Infrastructure: A Tool
kit • Graph shows comparative economic costs for the most
prominent large-scale generation options available to Thailand.
• A screening curve shows the cost per kWh of a
generation plant at a range of capacity utilization rates (or CU rates).
• While CCGT has a lower investment cost per kW of
capacity than does NT2, it has variable operating and fuels costs that NT2 does not have.
• At CU rates above 30 percent, NT2 is the least-cost
Cross-Bord
er Infrastructure: A Tool
kit
Liquidity Risk
• The debt has to be repaid within 15 years - much less
than the life of the project.
• The royalty and tax rates to be applied in each year
have been designed specifically for the project on the basis of NTPC’s debt repayment schedule.
¨NTPC is exempt from income tax over the 2009–2014 period and then pays the following the rates over the remainder of the concession; 5.0% between 2015 and 2021, 15.0% between 2022 and 2027, and 30.0% between 2028 and 2034.
er Infrastructure: A Tool
kit
Liquidity Risk
• The royalty and tax rates...(continued)
¨The increase in the income tax rate from 5.0% to 15.0% is not implemented until immediately after all NTPC debt is repaid at the end of 2021.
¨The royalty is applied at 5.2% between 2009 and 2024, 15.0% between 2025 and 2029, and 30.0% over the remainder of the concession.
Cross-Bord
er Infrastructure: A Tool
kit
Country Risk
• Loans are guaranteed by
¨World Bank, ADB
¨Export Credit Agencies
• Development agencies loans