1.
Bert plug load management install is to be scheduled by the school district as per meeting on 5/24/17.
2.
Change Order 3 Approved for new Chiller compressor for High School on 8/21/17.
3.
Transformer Replacement at High School will take place on 9/9/17.
Date:
September 8, 2017
Prepared By:
Wyatt Ferguson
Page:
1
Overall Construction Progress: 68%
of:
15
O v er al l P er c ent age B loom fi el d B O E O ff ic es B er k el ey E S B loom fi el d M S B loom fi el d H S B rook dal e E S C ar ter et E S D em ar es t E S F ai r V iew E S F or es t G llen E E C F rank lin E S O ak V iew E S W at s es s ing E S ECM1 - Lighting/Electrical A - Lighting Upgrades 11% B - Vending Misers 0%
C - Plug Load Management 0% D - De-Stratification Fans 100% E - High Efficiency Transformers 0% ECM2 - Mechanical
A - Boiler Replacements 67%
B - Steam Trap/Thermostatic CV Replacement 100%
C - Piping Insulation 100%
ECM3 - Building Management Systems 40%
ECM4 - Building Envelope Improvements 100%
Not Applicable ON Schedule
In Progres s Behind Sched
Page 2 of 15
ECM 1 – Lighting:
ECM 1a: Lighting Upgrades
Building Start Finish Punch List Date
Carteret ES 7/28/17 9/15/17 TBD
Watsessing ES 9/5/17 9/22/17 TBD Forest Glen EEC 9/25/17 10/13/17 TBD Bloomfield BOE Offices 9/20/17 11/3/17 TBD
Brookdale ES 11/3/17 11/24/17 TBD Oak View ES 11/24/17 12/22/17 TBD Demarest ES 12/22/17 1/12/18 TBD Franklin ES 1/12/18 2/14/18 TBD Fair View ES 2/14/18 3/7/18 TBD Berkeley ES 3/7/18 3/28/18 TBD Bloomfield MS 3/28/18 5/16/18 TBD Bloomfield HS 5/16/18 7/11/18 TBD
Substantial Completion Date: TBD Percent Complete: 11%
Carteret Elementary School
Page 3 of 15
Room 213 Original Lighting
Room 213 New Fixtures
Watsessing Elementary School
Page 4 of 15
Room 306 Original Lighting
Room 306 New LED
Page 5 of 15
ECM 1b: Vending Misers
Building Start Date Est. Completion Date Punch List Date
Bloomfield HS TBD TBD TBD
Forest Glen ECC TBD TBD TBD
Bloomfield BOE Offices TBD TBD TBD
Bloomfield MS TBD TBD TBD
Brookdale ES TBD TBD TBD
Demarest ES TBD TBD TBD
Watsessing ES TBD TBD TBD
Substantial Completion Date: TBD Percent Complete: 0%
ECM 1c: Plug Load Management
Building Start Date Est. Completion Date Punch List Date
Bloomfield BOE Offices TBD TBD TBD
Berkeley ES TBD TBD TBD Bloomfield MS TBD TBD TBD Bloomfield HS TBD TBD TBD Brookdale ES TBD TBD TBD Carteret ES TBD TBD TBD Demarest ES TBD TBD TBD Fair View ES TBD TBD TBD
Forest Glen EEC TBD TBD TBD
Franklin ES TBD TBD TBD
Oak View ES TBD TBD TBD
Watsessing ES TBD TBD TBD
Substantial Completion Date: TBD Percent Complete: 0%
ECM 1d: De-Stratification Fans
Building Start Date Est. Completion Date Punch List Date
Oak View ES 6/26/17 6/27/17 TBD
Brookdale ES 6/28/17 6/29/17 TBD
Page 6 of 15
Forest Glen EEC 7/3/17 7/5/17 TBD
Fair View ES 7/6/17 7/7/17 TBD Bloomfield MS 7/7/17 8/23/17 TBD Franklin ES 7/17/17 7/19/17 TBD Berkeley ES 7/18/17 7/18/17 TBD Carteret ES 7/20/17 7/21/17 TBD Bloomfield HS 7/21/17 8/4/17 TBD Watsessing ES 8/7/17 8/9/17 TBD
Substantial Completion Date: 8/23/17 Percent Complete: 100%
ECM 1e: High Efficiency Transformers
Building Start Date Est. Completion Date Punch List Date
Bloomfield HS 9/9/17 9/9/17 TBD
Substantial Completion Date: TBD Percent Complete: 0%
ECM 2 – Mechanical Systems Upgrades:
ECM 2a: Boiler Replacements
Building Start Date Est. Completion Date Punch List Date
Franklin ES 7/17/17 9/29/17 TBD
Forest Glen ECC 7/31/17 10/13/17 TBD
Substantial Completion Date: TBD Percent Complete: 67%
Page 7 of 15
Original Franklin Boilers
Page 8 of 15
After Abatement of Franklin Boilers
New Pads – Franklin Boilers
Page 9 of 15
Progress of Franklin Boilers
Page 11 of 15
Forest Glen Boiler Old Boiler
Page 12 of 15
Progress
Page 13 of 15
ECM 2b: Steam Trap/Thermostatic Control Valve Replacement
Building Start Date Est. Completion Date Punch List Date
Carteret ES 6/12/17 7/18/17 TBD Watsessing ES 6/19/17 7/17/17 TBD Berkeley ES 6/21/17 6/27/17 TBD Oak View ES 6/22/17 7/5/17 TBD Demarest ES 7/5/17 7/12/17 TBD Fair View ES 7/13/17 7/19/17 TBD Brookdale ES 7/13/17 7/25/17 TBD Franklin ES 7/14/17 8/1/17 TBD
Substantial Completion Date: 8/15/17 Percent Complete: 100%
ECM 2c: Piping Insulation
Building Start Date Est. Completion Date Punch List Date
Watsessing ES 8/10/17 8/15/17 TBD
Fairview ES 8/15/17 8/25/17 TBD
Substantial Completion Date: 8/25/17 Percent Complete: 100%
Watsessing Elementary
Page 15 of 15
ECM 3 – Building Management Systems
ECM 3: Building Management System Upgrades
Building Start Date Est. Completion Date Punch List Date
Bloomfield High School 7/11/17 9/15/17 TBD
Demarest ES 7/17/17 12/8/17 TBD
Franklin ES 10/2/17 12/8/17 TBD
Substantial Completion Date: TBD Percent Complete: 40%
ECM 4 – Building Envelope
ECM 4: Building Envelope
Building Start Date Est. Completion Date Punch List Date
Bloomfield HS 6/12/17 6/15/17 8/31/17 Bloomfield BOE Offices 6/15/17 6/15/17 8/31/17
Watsessing ES 6/16/17 6/20/17 8/31/17 Demarest ES 6/20/17 6/22/17 8/31/17 Carteret ES 6/22/17 6/23/17 8/31/17 Fair View ES 6/23/17 6/23/17 8/31/17 Forest Glen EEC 6/26/17 6/26/17 8/31/17 Franklin ES 6/26/17 6/28/17 8/31/17 Berkeley ES 6/28/17 6/30/17 8/31/17
Oak View ES 7/3/17 7/5/17 8/31/17
Bloomfield MS 7/5/17 7/7/17 8/31/17
Brookdale ES 7/7/17 8/31/17 TBD
Substantial Completion Date: 7/12/17 Percent Complete: 100%
ID Task Name Start Finish
1
Lighting Upgrades
Mon 9/11/17 Fri 9/22/17
2
Watsessing Elementary
Mon 9/11/17 Fri 9/22/17
3
Carteret Elementary
Mon 9/11/17 Fri 9/15/17
4
5
ECM-2 Schedule - Boiler Replacement
Mon 9/11/17 Fri 9/22/17
6
Franklin Elementary
Mon 9/11/17 Fri 9/22/17
7
Forest Glen
Mon 9/11/17 Fri 9/22/17
8
9
ECM - 3 BMS Upgrades
Mon 9/11/17 Fri 9/22/17
10
Demarest Elementary
Mon 9/11/17 Fri 9/22/17
11
High School Upgrades
Mon 9/11/17 Fri 9/22/17
12
13
ECM - 1 Transformers Upgrade
Sat 9/9/17
Sat 9/9/17
14
High School
Sat 9/9/17
Sat 9/9/17
Watsessing Elementary Carteret Elementary Franklin Elementary Forest Glen Demarest Elementary High School Upgrades High School
W T F S Sep 10, '17S M T W T F S Sep 17, '17S M T W T F S Sep 24, '17S
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only
Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: Bloomfield Date: Fri 9/8/17