1
Presented by
Craig Misso, Ontario-Montclair School District
Chris Lawrence, HMC GROUP
Barbara Gadbois of Gibbs, Giden, Locher & Turner, LLP
AVOIDING RISK AND SAVING
MONEY ON YOUR
MODERNIZATION PROJECT
PREFACE
The information provided in this presentation, whether written or oral, should not be relied upon as legal advise or opinion regarding any specific matter. All attendees and readers should contact professional legal counsel to obtain advice on specific projects or issues. The presenters have no liability or responsibility to any person, property, organization, whatsoever with respect to any loss or damage
3
Overview
z
Planning/Bidding Phase
z
Construction Administration Phase
z
Project Closeout Phase
4
Planning/Bidding - Overview
z
Project Launching
z
Selection of Professional Services Firms
zContract Considerations
5
Planning/Bidding Phase
z
Project Launching
– Project concept – Project budget
– Roles of district’s planning team
z
Selection of Professional Services Firms
(architect & engineer, construction manager (CM)
& inspector of record IOR)
– Qualifications & compatibility with district philosophies – Work load & project team members’ experience – Verification of required certifications and licenses
Planning/Bidding Phase
z
Professional Services Firms Contract
Considerations
– Errors and omissions and general liability
insurance
– Poor performance/plan provision
7
Planning/Bidding Phase
z
Project Document Contract
Considerations
– Liquidated damages assessment level
– Assigned owner owned “float” to address unforeseen conditions
– Termination for convenience clause – Simultaneous projects provision – Prequalification criteria
– Bonding requirements for major subcontractors – Project marketing & plans distribution
– Project superintendent qualifications and substitution
8
Planning/Bidding Phase
z
Project Document Contract
Considerations (cont.)
– Bid advertisement
– Environmental conditions
– Pre-bid conference
– Change order pricing options
– Payment applications
9
Planning/Bidding Phase
z
Risk Avoidance Techniques
– Establish unit-price bids
– Obtain final sign-off of plans
– Obtain Division of State Architect (DSA) approval
prior to bidding
– Conduct interdisciplinary plan review (IPR)
– Provide active representation throughout the
planning phase
Planning/Bidding Phase
z
Risk Avoidance Techniques (cont.)
– Allow adequate time for bid review – Investigate listed major subcontractors – Maintain open contracts with third parties
• Environmental consultants • Testing labs
11
Construction Administration
Phase
z
Role of Architect & Engineer in Reducing
Risk
– Timely response to issues regarding drawings & specifications
– Interface between owner and contractor
– Monitors adherence to the construction documents
z
Role of District in Reducing Risk
– Clear and timely decisions
– Coordination of campus operations – Timely payment to contractor
12
Construction Administration
Phase
z
Role of the Inspector of Record in
Reducing Risk
– Confirm compliance with DSA approved drawings & specifications
– Document progress of construction
– Inform contractor of non-compliant work and reviews corrections
z
Agency Prior to Bidding
– Preliminary approval
13
Construction Administration
Phase
z
Project Schedule
– Unrealistic timelines provoke the contractor to generate delay claims
– Require a network analysis schedule – Identify concurrent vs. critical path work
z
Interpretation of Contract Documents
– The architect’s role, not the contractor’s – Job site decisions can be uninformed – Fair play
Construction Administration
Phase
z
Submittals
– Require a submittal schedule – Process submittals quickly – Require complete submittals
z
Substitutions
– Minimize, minimize, minimize
– Contractor to pay for resulting changes and engineering
15
Construction Administration
Phase
z
Requests for Information (RFI)
– Quantity and timing can reveal trouble – Recognize frivolous claims or questions – Establish turn around time in the contract
documents
– Require all RFIs to be sent to the architect – Do not use RFIs to:
• Approve submittals • Approve substitutions
• Approve changes affecting contract sum or time
16
Construction Administration
Phase
z
Unforeseen Conditions
– Expect them
– “As-builts” are not always available or accurate – Have contingency funds
z
Change Orders
17
Construction Administration
Phase
z
Meeting Minutes
– Does not replace an RFI
– Records direction to the contractor – Less is less
z
Construction Managers
– Agree to be a team
– Establish roles at the inception of the project – District involvement to remain
Construction Administration
Phase
z
Dispute Resolution During
Construction
– Sooner is better – Get all the facts
– Check your ego at the door
– Establish your goals prior to meeting with the contractor
19
Construction Administration
Phase
z
Communication
– Be available to respond
– Have a written response to all correspondence – Verbal direction is only as good as the paper it is
written on
– Have complete logs
– He who has the most paper wins – Stay professional
20
Project Closeout Phase
z
Make Sure You Get What You Pay
For in Closeout of 3 Major Areas:
– Site Conditions
21
Project Closeout Phase
z
Site Conditions
– Punch list completion
– Clean-up/restoration of areas impacted
– Removal of contractor facilities
Project Closeout Phase
z
Project Specifications
– Written warranties and bonds
– Operations & maintenance manuals and training – Inspection and testing reports
– Attic stock/spare parts
– Complete record/as-built drawings
23
Project Closeout Phase
z
Contract Requirements
– Unconditional releases (Civil Code § 3262) – Releases/bonds for known stop notices – Contractor Affidavit that all bills paid – Consent of surety to final payment – Insurance certificates (monitor renewal)
– Contractor acknowledgment that final payment is a release of all claims except those reserved in writing
24
Project Closeout Phase
z
Withhold Sufficient Funds
– Retention
– Labor Enforcement Notices – Stop Notice claims
– Liquidated damages – Disputed work
25
Project Closeout Phase
z
Handling Stop Notices
– Amount to withhold
– Funds not subject to withhold – Liability for failure to withhold
– Pro rata distribution to multiple claimants – Expiration of duty to withhold
Project Closeout Phase
z
Completion/Notice of Completion
– Civil Code
§ 3086 Acceptance by Board
– Civil Code
§ 3093 Notice of Completion
27
Project Closeout Phase
z
Assess Liquidated Damages
– Government Code § 53069.85
– Contract must be clear as to commencement and completion dates
– Change orders should address time
– Written notice to contractor as soon as deadline is missed
– Quantify delay and notify contractor promptly
28
Project Closeout Phase
z
Release of Retention and
Withholding
– Public Contract Code § 7101
– Definition of completion
– Withhold disputed/release undisputed
– Penalties for wrongful withholding
29
Project Closeout Phase
z
Enforce Performance Bond Rights
– Require contractors to use district’s bond forms (Cates decision)
– Investigate surety
– Notify surety of all contractor defaults and delays and stop notice claims
– Secure surety consent to final payment
– Surety will investigate claim and/or complete the project if default
– Do not “release” the bond
Project Closeout Phase
z
Dispute Resolution
– Public Contract Code
§ 20104
– Alternative dispute resolution
– Utilize documentation prepared during
contract administration
31
Internet Sites
z
State Contractor License Board: www.2.cslb.ca.govz
Division of the StateArchitect
www.dsa.ca.gov