• No results found

vd calculation

N/A
N/A
Protected

Academic year: 2021

Share "vd calculation"

Copied!
75
0
0

Loading.... (view fulltext now)

Full text

(1)

SECTION-9

(2)

1.0 Formula Used:

1.1 Working Load in kVA = L. F.

1.2 System P. F. = P. F. D. F. Effi. 2.0 Unit Total (kW) Unit Total (kW) 2.1 280 0.946 0.85 0.9 1 3 840 2 504 Total Load 840 504 3.0 = 752.15 kVA 4.0 = 0.8041 5.0 5.1 = 1250 kVA 5.2 = 5 % 5.3 = 280 KW 5.4 = 3.3 kV 5.5 = 0.85 5.6 = 0.946 5.9 = 348.2153961 kVA 5.10 = 2089.292377 kVA 5.11 = 696.4307922 kVA 5.14 = 25000 kVA (within 10%) S.C capacity of transformer

The selected rating of transformer is 1250 kVA 5.16 Voltage drop at transformer terminal when largest

motor start with Star Delta starting = 4.2 %

[Motor Starting kVA (S/D) + Base Load kVA] x 100

S.C capacity of transformer 1.7321 x kV x I SC

5.15 Voltage drop at transformer terminal when largest

motor start with DOL starting = 9.750031091 %

[Motor Starting kVA (DOL) + Base Load kVA] x 100

(within 10%) S.C capacity of transformer

5.13 Fault current of transformer secondary side (ISC) = 4.373741456 kA

Fault Level in MVA 1.7321 x kV

5.12 Fault Level at transformer secondary side = 25 MVA Rating of transformer in MVA x 100

Impedance of transformer in % Base load on transformer before starting Second

largest motor (Considering only one motor is working and the Second motor is started)

Motor starting Kva with DOL start = 6 x 1.7321 x kV x I FLC

Motor starting Kva with Star Delta start = 3 x 1.7321 x kV x I FLC

5.8 Rating of largest size motor in kVA = 348.2153961 kVA kW

P.F x Efficiency

5.7 FLC of motor = 60.92016454 A kW x 1000

1.7321 x V x p.f x efficiency

Supply voltage System voltage

P.F of largest size motor From the above table

Efficiency of largest size motor From the above table

Calculation to check the starting of largest size motor

Rating of transformer assumed Nearest standard size (Confg. 33/3.3KV,Dyn11,Delta-star)

% impedance of transformer assumed From IS 2026

Rating of the largest size motor From the above table

626.79

Considering 20% contingency System P. F.

D. F.

Connected Load Working Load

Working Load (kVA)

Pump 626.79

Sr.

No. Item Description

Rating in

kW Effi. P. F. L. F.

= Motor Efficiency Input Data and Calculations:

TRANSFORMER SIZING FOR CWPS PLANT

[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ] = Load Factor Total Working Load (kW) / Total Working Load (kVA) = Motor Power Factor

(3)

CAPACITOR BANK SIZING ACROSS MOTOR TERMINAL

1

Motor rating (kW)

280

2

Motor rating after 90% load factor (kW)

252

To be considered for further calculations

3

Supply Voltage (V)

3300

4

Motor Power Factor (p.f

1

)

0.85

Based on actual Values given by jyoti

5

Motor efficiency (Effi.)

0.946

Based on actual Values given by jyoti

6

Power Factor to be improved (p.f

2)

0.98

7

No load p.f. (p.f

NL

)

0.1

Assumption

8

Motor Full Load Current in amp.(FLC)

54.828

= (kW x 1000) / (1.7321 x V x cos(p.f

1

) x Effi.)

9

No load current in amp. (I

NLC

)

19.190

35% of FLC

10 Motor magnetising current in amp.

19.094

= [ I

NLC

x sin(cos

-1

p.f

NL

) ]

11 Capacitor current (Ic)

17.184

Shall be 90% of motor magnetising current

12

Max. kVAR that can be connected across motor

terminal

98.22

= (1.7321 x V x Ic) / 1000

13

Total kVAR to be connected across the motor

terminal

105.00

= kW[ tan(cos

-1

p.f

1

) - tan(cos

-1

p.f

2

) ]

14

Excess kVAR to be connected across the

switchgear bus bars (13 - 12)

6.79

Negative value indicates capacitor bank is not

required across the bus.

(4)

1.0 Formula Used:

1.1 Working Load in kVA = L. F.

1.2 System P. F. = P. F. D. F. Effi. 2.0 Unit Total (kW) Unit Total (kW) a EOT crane 15 0.87 0.82 1 2 1 15 1 7.5 b Exhaust fan 0.5 0.67 0.82 1 1 8 4 8 4 c 15 0.8 0.8 1 1.5 Lumpsum 15 Lumpsum 10 d 1.5 0.79 0.81 0.9 1 2 3 2 2.7 e 7.5 0.87 0.82 0.9 1 2 15 2 13.5 f 160 0.962 0.86 0.9 2 2 320 1 72 g 37 0.935 0.86 0.9 2 2 74 1 16.65 h 1.1 0.79 0.81 0.9 2 2 2.2 1 0.495 i 1.1 0.77 0.81 0.9 1 2 2.2 1 0.99 j 3.7 0.77 0.82 0.9 1 2 7.4 1 3.33 k 1.5 0.79 0.81 1 2 3 4.5 3 2.25 l 1.5 0.79 0.81 1 2 3 4.5 3 2.25 m 1.5 0.79 0.81 1 2 3 4.5 3 2.25 n 1.5 0.79 0.81 1 1 2 3 1 1.5 o 1.5 0.79 0.81 1 1 2 3 1 1.5 p 1.5 0.79 0.81 1 1 2 3 1 1.5 q 0.5 0.67 0.82 0.9 2 30 15 30 6.75 r 7.5 0.87 0.82 0.9 1 1 7.5 1 6.75 s 40 0.902 0.81 1 1.5 Lumpsum 40 Lumpsum 26.666667 Total Load 542.8 182.58167 3.0 = 297.31 kVA 4.0 = 0.7369 5.0 5.1 = 315 kVA 5.2 = 4.5 % 5.3 = 160 KW 5.4 = 0.415 kV 5.5 = 0.86 5.6 = 0.962 5.9 = 121.6044578 kVA 5.10 = 1160.373253 kVA 5.11 = 386.7910845 kVA 5.14 = 7000 kVA = Motor Efficiency Input Data and Calculations:

D. F.

Connected Load Working Load

Working Load (kVA) TRANSFORMER SIZING FOR CWPS PLANT

[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ] = Load Factor Total Working Load (kW) / Total Working Load (kVA) = Motor Power Factor

= Diversity Factor

Sr.

No. Item Description

Rating in kW Effi. P. F. L. F. 247.76 Considering 20% contingency 10.51 7.28 Flash mixture 4.22 Lighting (CWPS) 15.63 System P. F.

Calculation to check the starting of largest size motor

Rating of transformer assumed Nearest staanddard size (Confg. 33/0.433KV,Dyn11,Delta-star)

% impedance of transformer assumed From IS 2026

Rating of the largest size motor From the above table

Supply voltage System voltage

P.F of largest size motor From the above table

Efficiency of largest size motor From the above table

5.7 FLC of motor = 269.0452946 A kW x 1000

1.7321 x V x p.f x efficiency

5.8 Rating of largest size motor in kVA = 193.3955422 kVA kW

P.F x Efficiency Base load on transformer before starting fourth

largest motor (Rating in kVA of transformer assumed - Largest motor KVA)

Motor starting Kva with DOL start = 6 x 1.7321 x kV x I FLC

Motor starting Kva with Star Delta start = 3 x 1.7321 x kV x I FLC

5.12 Fault Level at transformer secondary side = 7 MVA Rating of transformer in MVA x 100

Impedance of transformer in % 5.13 Fault current of transformer secondary side (ISC) = 9.738161699 kA Fault Level in MVA

1.7321 x kV

S.C capacity of transformer 1.7321 x kV x I SC

5.15 Voltage drop at transformer terminal when largest

motor start with DOL starting = 18.3139673 %

[Motor Starting kVA (DOL) + Base Load kVA] x 100

(within 10%) S.C capacity of transformer

(within 10%) S.C capacity of transformer

The selected rating of transformer is 400 kVA 5.16 Voltage drop at transformer terminal when largest

motor start with Star Delta starting = 7.3 %

[Motor Starting kVA (S/D) + Base Load kVA] x 100

Clarifloculator mechanism phase-1 18.92

backwash pumps 87.03

Air blower 20.71

Chlorine booster pumps for prechlorination 0.77

Chlorine booster pumps for postchlorination 1.59

Service water pumps 5.27

Agitator for Alum dosing pump 3.52

Agitaotor for Lime dosing pump 3.52

Agitator for polyelectrolyte dosing tank 3.52

Dosing pump for alum 2.34

Dosing pump for lime 2.34

Dosing pump for polyelectrolyte 2.34

EOT crane 9.46

Lighting (chemical,Filter,pump,outdoor) 36.50

(5)

CAPACITOR BANK SIZING ACROSS BUS

Intermediate Pumping Station

1 Average Power factor (pf1)

0.737

2 Total Working load in IPS

210

kW

3 Power factor To be improved (pf2)

0.98

Total kVAR to be connected across Bus

4 Total kVAR to be connected across Bus

150

KVAR

(6)

Short circuit calculation CWPS main Pump Assumptions

1 Fault level at 220kV bus 20000 MVA (as per IS :2026)

2 Base MVA 2000

Ratio = 220kV / 132kV Capacity = 100.00 MVA

Z= 9.27%

Qty 1 Nos

Considering negative tolerance Z = 8.34% Net Z for transformers single transformer= 8.34% 3

Ratio = 132kV / 33kV

Capacity = 40.00 MVA

Z= 10.18%

Qty 1 Nos

Considering negative tolerance Z = 9.16% Net Z for transformers single transformer= 9.16% 4

Line length = 15 kM

Conductor Type = DOG Assumed

Conductor Resiatance = 0.2733 ohm/kM Z,Considering Reactance Negligible = 4.0995 ohm 5

Ratio = 33kV / 3.3kV

Capacity = 1.25 MVA

Z= 5.0%

Qty 1 Nos

Considering negative tolerance Z = 4.5% Net Z for transformers single transformer= 4.5%

6 K' Constant for XLPE AL cable= 94

K' Constant for PVC AL cable= 75 K' Constant for PVC CU cable= 112

7 Fault clearing time for 33kV Breaker (t) = 1 Sec

Fault clearing time for 3.3kV Breaker (t) = 1 Sec

10 Starting Voltage dip = 15%

11 Starting current for DOL= 6 times

12 Starting current for Y-D= 2 times

13 Starting current for FCMA softstarter= 2.5 times

Transformer Details at Chandaka220KV/132KV

Transformer Details at Chandaka 132KV/33KV

33kV Over head line from Chandaka to CWPS

(7)

Calculation

a chandaka Grid Substation

220KV Bus 0.1 20000 52 220KV/132KV,100MVA transformer 1.7 1 132kV Bus 1.8 1130.8 5 2 132kV/33kV,40MVA transformer 4.6 3 33kV Bus 6.3 315.0 5.51 58.6 b CWPS

1 15 kM 33kV O/H line from Chandaka Substation to CWPS 7.53

2 33kV Bus 13.88 144.1 2.52 26.8

3

33kV , XLPE, cable 3core x 95sqmm cable from 6 Pole

structure to 33KV panel 0.03950

4 33kV panel 13.92 143.7 2.51 26.7

5

33kV , XLPE, cable 3core x 95sqmm cable from 33KV panel

to transformer 0.000987

6 33kV/3.3kV, 1.25MVA transformer 72.00

7 3.3kV side of 1.25MVA transformer 86.02 23.3 4.07 43.3

(XLPE,AL,3.3 kV) 8

3.3kV , XLPE, cable 3core x 300sqmm cable from

transformer secondary to CWPS PMCC 1.91 9 3.3kV CWPS PMCC Bus 87.83 22.8 3.98 42.4 (,AL,3.3 kV) Sr No Description Impedance " Z" Fault level "MVA" Fault Current "kA" Minimum Cable size "SQMM"

(8)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 1250

2 VOLTAGE (V) = 3.3

3 PF = 0.8

4 FAULT CURRENT Ish = 4.07

5 FAULT CLEARING TIME t = 1

6 CONSTANT K = 94

7 LENGTH = 70

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 43.2978723

2 CABLE SIZE CHOSEN = 50 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable laid ground (3 cables touching)

RATING FACTOR = 0.69

3 OVERALL DERATING FACTOR = 0.6555

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE

= 218.70

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

333.64

3 Current carring capacity of 3C x300 Sqmm AL XLPE cable is = 360

4 No of cable required = 0.93

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3C x300 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 300SQmm AL XLPE Cable) = 0.13 3 X AT CONDUCTOR TEMP. (3C x 300SQmm AL XLPE Cable) = 0.072

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 0.11827365

CABLE SIZE CHOSEN = 3CX300 sq.mm Al XLPE Cable

! " #$#

%&" '(

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(9)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 349

2 VOLTAGE (V) = 3.3

3 PF = 0.8

4 FAULT CURRENT Ish = 3.98

5 FAULT CLEARING TIME t = 1

6 CONSTANT K = 94

7 LENGTH = 40

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 42.34042553

2 CABLE SIZE CHOSEN = 50 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable laid in trench (9 cables touching)

RATING FACTOR = 0.76

3 OVERALL DERATING FACTOR = 0.722

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732

= 35.25

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

48.83

3 Current carring capacity of 3.5C x50 Sqmm AL XLPE cable is = 120

4 No of cable required = 0.41

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3C x50 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 50 SQmm AL XLPE Cable) = 0.82 3 X AT CONDUCTOR TEMP. (3C x 50 Qmm AL XLPE Cable) = 0.086

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 0.052371797

CABLE SIZE CHOSEN = 3.5CX50 sq.mm Al XLPE Cable

#$#

%&" '(

"

)

* + "

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(10)

Short circuit calculation CWPS Auxilary WTP load Assumptions

1 Fault level at 220kV bus 20000 MVA (as per IS :2026)

2 Base MVA 2000

Ratio = 220kV / 132kV Capacity = 100.00 MVA

Z= 9.27%

Qty 1 Nos

Considering negative tolerance Z = 8.34% Net Z for transformers single transformer= 8.34% 3

Ratio = 132kV / 33kV

Capacity = 40.00 MVA

Z= 10.18%

Qty 1 Nos

Considering negative tolerance Z = 9.16% Net Z for transformers single transformer= 9.16% 4

Line length = 15 kM

Conductor Type = DOG Assumed

Conductor Resiatance = 0.2733 ohm/kM Z,Considering Reactance Negligible = 4.0995 ohm 5

Ratio = 33kV / 0.415kV

Capacity = 0.32 MVA

Z= 4.5%

Qty 1 Nos

Considering negative tolerance Z = 4.1% Net Z for transformers single transformer= 4.1%

6 K' Constant for XLPE AL cable= 94

K' Constant for PVC AL cable= 75 K' Constant for PVC CU cable= 112

7 Fault clearing time for 33kV Breaker (t) = 1 Sec

Fault clearing time for 0.415kV ACB Breaker (t) = 0.08 Sec Fault clearing time for 0.415kV MCCB Breaker (t) = 0.04 Sec

10 Starting Voltage dip = 15%

11 Starting current for DOL= 6 times

12 Starting current for Y-D= 3.5 times

13 Starting current for FCMA softstarter= 2.5 times

Formula used 1

2

3 Zline =

Transformer Details at Chandaka220KV/132KV

Transformer Details at Chandaka 132KV/33KV

33kV Over head line from Chandaka to CWPS

Transformer at CWPS

Zsource = Base MVA

Fault level at 132kV bus

Ztransformer = Base MVA X tranformer Z%

Transformer capacity in MVA Base MVA

X Line Z kV2

(11)

Calculation

a chandaka Grid Substation

1 220KV Bus 0.1 20000 52 2 220KV/132KV,100MVA transformer 1.7 3 132kV Bus 1.8 1130.8 5 4 132kV/33kV,40MVA transformer 4.6 5 33kV Bus 6.3 315.0 5.51 b CWPS

1 15 kM 33kV O/H line from Chandaka Substation to CWPS 7.53

2 33kV Bus 13.88 144.1 2.52 26.8

4 33kV/0.415kV, 315KVA transformer 257.14

5 0.415kV side of 315KVA transformer 271.02 7.4 10.27 30.9

(XLPE,AL,0.415kV) 6

0.415kV , XLPE, cable 2 X 3.5c x 240.sqmm cable from

transformer secondary to CWPS PMCC 40.66

7 0.415kV CWPS AUXILARY MCC 311.68 6.4 8.93 26.9

(,AL,0.415 kV) 8

0.415kV , XLPE, cable 2 x 3.5core x 120sqmm cable from

CWPS PMCC to Motor (160KW) 81.31

9 0.415kV 160KW motor (194) 392.99 5.1 7.08 15.1

(,AL,0.415 kV) 10

0.415kV , XLPE, cable 3.5C x 240sqmm cable from CWPS

PMCC to WTP & Chemical 508.19 11 0.415kV WTP & Chemical 819.87 2.4 3.39 7.2 (,AL,0.415 kV) Sr No Description Impedance " Z" Fault level "MVA" Fault Current "kA" Minimum Cable size "SQMM"

(12)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 315

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 10.27

5 FAULT CLEARING TIME t = 0.08

6 CONSTANT K = 94

7 LENGTH = 40

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 30.90207082

2 CABLE SIZE CHOSEN = 35 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION) C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable directly burried (3 cables touching)

RATING FACTOR = 0.69

3 OVERALL DERATING FACTOR = 0.6555

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE

= 438.24

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

668.56

3 Current carring capacity of 3.5C x240 Sqmm AL XLPE cable is = 326

4 No of cable required = 2.05

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3.5C x240 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3.5C x 240 SQmm AL XLPE Cable) = 0.16

3 X AT CONDUCTOR TEMP. (3.5C x 240 Qmm AL XLPE Cable) = 0.071

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 2

% VOLTAGE DROP =

7 % VOLTAGE DROP = 0.624055741

CABLE SIZE CHOSEN = 2X3.5CX240 sq.mm Al XLPE Cable

" " *, - +

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(13)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 194

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 8.93

5 FAULT CLEARING TIME t = 0.04

6 CONSTANT K = 94

7 LENGTH = 40

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 19

2 CABLE SIZE CHOSEN = 25 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable laid in trench (9 cables touching)

RATING FACTOR = 0.66

3 OVERALL DERATING FACTOR = 0.627

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732

= 155.83

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

248.54

3 Current carring capacity of 3C x120 Sqmm AL XLPE cable is = 257

4 No of cable required = 0.97

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3C x120 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 120SQmm AL XLPE Cable) = 0.324 3 X AT CONDUCTOR TEMP. (3C x 120 Qmm AL XLPE Cable) = 0.0712

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 0.785433685

CABLE SIZE CHOSEN = 2X3CX120 sq.mm Al XLPE Cable

*,

- +

"

.

*

"

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(14)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 46

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 8.93

5 FAULT CLEARING TIME t = 0.04

6 CONSTANT K = 94

7 LENGTH = 40

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 19

2 CABLE SIZE CHOSEN = 25 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION) C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable laid in trench (9 cables touching)

RATING FACTOR = 0.66

3 OVERALL DERATING FACTOR = 0.627

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732

= 36.95

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

58.93

3 Current carring capacity of 3C x25 Sqmm AL XLPE cable is = 96

4 No of cable required = 0.61

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3C x25 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 25SQmm AL XLPE Cable) = 1.54

3 X AT CONDUCTOR TEMP. (3C x 25 Qmm AL XLPE Cable) = 0.0805

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 0.789742459

CABLE SIZE CHOSEN = 2X3CX25 sq.mm Al XLPE Cable

*, - + " #/ * "

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(15)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 91

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 8.93

5 FAULT CLEARING TIME t = 0.04

6 CONSTANT K = 94

7 LENGTH = 250

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 19

2 CABLE SIZE CHOSEN = 25 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable directly burried (3 cables touching)

RATING FACTOR = 0.69

3 OVERALL DERATING FACTOR = 0.6555

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE

= 126.60

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

193.14

3 Current carring capacity of 3.5C x240 Sqmm AL XLPE cable is = 367

4 No of cable required = 0.53

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3.5C x240 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3.5C x 300 SQmm AL XLPE Cable) = 0.128 3 X AT CONDUCTOR TEMP. (3.5C x 300Qmm AL XLPE Cable) = 0.0705

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 1.911409493

CABLE SIZE CHOSEN = 3.5CX300 sq.mm Al XLPE Cable

+ *,

- +

" * ,

+

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(16)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 20

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 3.39

5 FAULT CLEARING TIME t = 0.04

6 CONSTANT K = 94

7 LENGTH = 120

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 7.212765957

2 CABLE SIZE CHOSEN = 10 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable directly burried (6 cables touching)

RATING FACTOR = 0.54

3 OVERALL DERATING FACTOR = 0.513

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE

= 27.82

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

54.24

3 Current carring capacity of 3.5C x35 Sqmm AL XLPE cable is = 113

4 No of cable required = 0.48

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3.5C x35 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3.5C x 35 SQmm AL XLPE Cable) = 1.11 3 X AT CONDUCTOR TEMP. (3.5C x 35 Qmm AL XLPE Cable) = 0.0783

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 1.302918856

CABLE SIZE CHOSEN = 3.5CX35 sq.mm Al XLPE Cable

* ,

'

&

0 +

"

,1

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(17)

A) FEEDER DATA

1 WORKING LOAD (KW)

5.6

2 WORKING LOAD (KVA)

=

7

2 VOLTAGE (V)

=

0.415

3 PF

=

0.8

4 FAULT CURRENT

Ish

=

3.39

5 FAULT CLEARING TIME

t

=

0.04

6 CONSTANT

K

=

94

7 LENGTH

=

120

B)

1 AREA OF CONDUCTOR

=

Ish* t/K

=

7.212765957

2 CABLE SIZE CHOSEN

=

10 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable directly burried (6 cables touching)

RATING FACTOR

=

0.54

3 OVERALL DERATING FACTOR

=

0.513

D)

1 FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

9.74

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

18.98

3 Current carring capacity of 4C x16 Sqmm AL XLPE cable is

=

67

4 No of cable required

=

0.28

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

4C x16 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (4C x16 SQmm AL XLPE Cable) =

2.44

3 X AT CONDUCTOR TEMP. (4C x16 Qmm AL XLPE Cable) =

0.0837

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

0.976550907

CABLE SIZE CHOSEN

=

4CX16

sq.mm Al XLPE Cable

* ,

'

&

0 +

"

,1

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(18)

A) FEEDER DATA

1 WORKING LOAD (KW) 12

2 WORKING LOAD (KVA) = 15

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 3.39

5 FAULT CLEARING TIME t = 0.04

6 CONSTANT K = 94

7 LENGTH = 105

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 7.212765957

2 CABLE SIZE CHOSEN = 10 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable directly burried (6 cables touching)

RATING FACTOR = 0.54

3 OVERALL DERATING FACTOR = 0.513

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE

= 20.87

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

40.68

3 Current carring capacity of 4C x16 Sqmm AL XLPE cable is = 67

4 No of cable required = 0.61

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 4C x16 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (4C x16 SQmm AL XLPE Cable) = 2.44 3 X AT CONDUCTOR TEMP. (4C x16 Qmm AL XLPE Cable) = 0.0837

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 1.831032951

CABLE SIZE CHOSEN = 4CX16 sq.mm Al XLPE Cable

* ,

'

&

0 +

"

,1#

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(19)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 75

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 8.93

5 FAULT CLEARING TIME t = 0.04

6 CONSTANT K = 94

7 LENGTH = 25

B)

1 AREA OF CONDUCTOR = Ish* t/K

= 19

2 CABLE SIZE CHOSEN = 25 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable laid in trench (9 cables touching)

RATING FACTOR = 0.66

3 OVERALL DERATING FACTOR = 0.627

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE

= 104.34

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR

166.42

Considering 35% extra current 224.66

3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is = 257

4 No of cable required = 0.87

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3.5C x120 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable) = 0.264 3 X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable) = 0.0716

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 0.276701989

CABLE SIZE CHOSEN = 3.5CX120 sq.mm Al XLPE Cable

*,

23&0 ! +

" /

4

&"

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

(20)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

100

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

3.09

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

25

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

9.297701931

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in ground (3 cables touching)

RATING FACTOR

=

0.69

3

OVERALL DERATING FACTOR

=

0.6555

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

139.12

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

212.24

3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is

=

223

4

No of cable required

=

0.95

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

3.5C x120 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable)

=

0.324

3 X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable)

=

0.0712

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

0.438263899

CABLE SIZE CHOSEN

=

3.5CX120

sq.mm Al XLPE Cable

!"

#

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(21)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

29

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

45

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

40.35

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

64.35

3 Current carring capacity of 3C x16 Sqmm AL XLPE cable is

=

70

4

No of cable required

=

0.92

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

3C x16Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE Cable)

=

2.44

3 X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE Cable)

=

0.0808

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

1.515823138

CABLE SIZE CHOSEN

=

2X3CX16

sq.mm Al XLPE Cable

$

!"

#

%% &

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(22)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

16

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

55

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

=

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

22.26

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

35.50

3 Current carring capacity of 3C x10 Sqmm AL XLPE cable is

=

67

4

No of cable required

=

0.53

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

3C x10 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 10 SQmm AL XLPE Cable)

=

3.94

3 X AT CONDUCTOR TEMP. (3C x 10 Qmm AL XLPE Cable)

=

0.0837

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

1.636204732

CABLE SIZE CHOSEN

=

2X3CX10

sq.mm Al XLPE Cable

$

!"

#

&

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(23)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

20

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

35

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

=

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

27.82

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

44.38

Considering 35% extra current

59.91

3 Current carring capacity of 4C x10 Sqmm AL XLPE cable is

=

67

4

No of cable required

=

0.89

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

4C x10 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE Cable)

=

3.94

3 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE Cable)

=

0.0837

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

1.301526492

CABLE SIZE CHOSEN

=

4CX10

sq.mm Al XLPE Cable

$

!"

#

%

'

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(24)

A) FEEDER DATA

1

WORKING LOAD (KW)

10

2

WORKING LOAD (KVA)

=

12.5

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

30

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

=

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

17.39

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

27.74

3 Current carring capacity of 4C x10 Sqmm AL XLPE cable is

=

67

4

No of cable required

=

0.41

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

4C x10 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE Cable)

=

3.94

3 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE Cable)

=

0.0837

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

0.697246335

CABLE SIZE CHOSEN

=

4CX10

sq.mm Al XLPE Cable

$

!"

#

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(25)

1.0 Formula Used:

1.1 Working Load in kVA = L. F.

1.2 System P. F. = P. F. D. F. Effi. 2.0 Unit Total (kW) Unit Total (kW) 2.1 22 0.917 0.83 0.9 1 2 44 1 19.8 2.2 11 0.892 0.81 0.9 1 2 22 2 19.8 2.3 2 0.83 0.82 1 2 1 2 1 1 2.4 0.5 0.67 0.82 1 1 6 3 6 3 2.5 10 0.8 0.8 1 1.5 Lumpsum 10 Lumpsum 6.6666667 81 50.266667 3.0 = 84.92 kVA 4.0 = 0.71 5.0 5.1 = 100 kVA 5.2 = 4.5 % 5.3 = 22 KW 5.4 = 0.415 kV 5.5 = 0.83 5.6 = 0.917 5.9 = 71.095 kVA 5.10 = 173.43 kVA 5.11 = 101.17 kVA 5.14 = 2222.2 kVA

TRANSFORMER SIZING FOR JATNI (KAJU PLANTATION) PUMPING STATION

[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ] = Load Factor

Lighting 10.42

5.46 1.47

Sr.

No. L. F. D. F.

Total Working Load (kW) / Total Working Load (kVA) = Motor Power Factor

Rating of the largest size motor From the above table

Considering 20% contingency System P. F.

= Diversity Factor = Motor Efficiency

Item Description Rating in kW Effi.

Working Load (kVA) Connected Load Working Load

Input Data and Calculations:

P. F. Total Load Chain pully Exhaust Fan 70.77 Pump-1 26.01 Pump-2 27.40

Supply voltage System voltage

Calculation to check the starting of largest size motor

Rating of transformer assumed Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star)

% impedance of transformer assumed From IS 2026

P.F of largest size motor From the above table

Efficiency of largest size motor From the above table

5.7 FLC of motor = 40.212 A kW x 1000

1.7321 x V x p.f x efficiency

Motor starting Kva with Star-Delta start = 3 x 1.7321 x kV x I FLC

5.8 Rating of largest size motor in kVA = 28.905 kVA kW

P.F x Efficiency Base load on transformer before starting fourth

largest motor (Rating in kVA of transformer assumed - Largest motor KVA)

Motor starting Kva with DOL start = 6 x 1.7321 x kV x I FLC

5.13 Fault current of transformer secondary side (ISC) = 3.0915

5.12 Fault Level at transformer secondary side = 2.2222

S.C capacity of transformer

MVA Rating of transformer in MVA x 100

Impedance of transformer in %

kA Fault Level in MVA

1.7321 x kV

S.C capacity of transformer 1.7321 x kV x I SC

5.15 Voltage drop at transformer terminal when largest

motor start with DOL starting = 11.004 %

[Motor Starting kVA (DOL) + Base Load kVA] x 100

(within 10%)

The selected rating of transformer is 100 kVA

% [Motor Starting kVA (S/D) + Base Load kVA] x 100 (within 10%)

S.C capacity of transformer

5.16 Voltage drop at transformer terminal when largest

(26)

CAPACITOR BANK SIZING ACROSS BUS

1 Average Power factor (pf1)

0.710

2 Total Working load

50

kW

3 Power factor To be improved (pf2)

0.98

Total kVAR to be connected across Bus

4 Total kVAR to be connected across Bus

40

KVAR

(27)

1.0 Formula Used:

1.1 Working Load in kVA = L. F.

1.2 System P. F. = P. F. D. F. Effi. 2.0 Unit Total (kW) Unit Total (kW) 2.1 22 0.917 0.83 0.9 1 2 44 1 19.8 2.2 11 0.892 0.81 0.9 1 2 22 2 19.8 2.3 2 0.83 0.82 1 2 1 2 1 1 2.4 0.5 0.67 0.82 1 1 6 3 6 3 2.5 10 0.8 0.8 1 1.5 Lumpsum 10 Lumpsum 6.6666667 81 50.266667 3.0 = 84.92 kVA 4.0 = 0.71 5.0 5.1 = 100 kVA 5.2 = 4.5 % 5.3 = 22 KW 5.4 = 0.415 kV 5.5 = 0.83 5.6 = 0.917 5.9 = 71.095 kVA 5.10 = 173.43 kVA 5.11 = 101.17 kVA 5.14 = 2222.2 kVA

TRANSFORMER SIZING FOR JATNI (KAJU PLANTATION) PUMPING STATION

[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ] = Load Factor

Lighting 10.42

5.46 1.47

Sr.

No. L. F. D. F.

Total Working Load (kW) / Total Working Load (kVA) = Motor Power Factor

Rating of the largest size motor From the above table

Considering 20% contingency System P. F.

= Diversity Factor = Motor Efficiency

Item Description Rating in kW Effi.

Working Load (kVA) Connected Load Working Load

Input Data and Calculations:

P. F. Total Load Chain pully Exhaust Fan 70.77 Pump-1 26.01 Pump-2 27.40

Supply voltage System voltage

Calculation to check the starting of largest size motor

Rating of transformer assumed Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star)

% impedance of transformer assumed From IS 2026

P.F of largest size motor From the above table

Efficiency of largest size motor From the above table

5.7 FLC of motor = 40.212 A kW x 1000

1.7321 x V x p.f x efficiency

Motor starting Kva with Star-Delta start = 3 x 1.7321 x kV x I FLC

5.8 Rating of largest size motor in kVA = 28.905 kVA kW

P.F x Efficiency Base load on transformer before starting fourth

largest motor (Rating in kVA of transformer assumed - Largest motor KVA)

Motor starting Kva with DOL start = 6 x 1.7321 x kV x I FLC

5.13 Fault current of transformer secondary side (ISC) = 3.0915

5.12 Fault Level at transformer secondary side = 2.2222

S.C capacity of transformer

MVA Rating of transformer in MVA x 100

Impedance of transformer in %

kA Fault Level in MVA

1.7321 x kV

S.C capacity of transformer 1.7321 x kV x I SC

5.15 Voltage drop at transformer terminal when largest

motor start with DOL starting = 11.004 %

[Motor Starting kVA (DOL) + Base Load kVA] x 100

(within 10%)

The selected rating of transformer is 100 kVA

% [Motor Starting kVA (S/D) + Base Load kVA] x 100 (within 10%)

S.C capacity of transformer

5.16 Voltage drop at transformer terminal when largest

(28)

CAPACITOR BANK SIZING ACROSS BUS

1 Average Power factor (pf1)

0.710

2 Total Working load

50

kW

3 Power factor To be improved (pf2)

0.98

Total kVAR to be connected across Bus

4 Total kVAR to be connected across Bus

40

KVAR

(29)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

100

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

3.09

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

25

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

9.297701931

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in ground (3 cables touching)

RATING FACTOR

=

0.69

3

OVERALL DERATING FACTOR

=

0.6555

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

139.12

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

212.24

3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is

=

223

4

No of cable required

=

0.95

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

3.5C x120 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable)

=

0.324

3 X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable)

=

0.0712

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

0.438263899

CABLE SIZE CHOSEN

=

3.5CX120

sq.mm Al XLPE Cable

!"

#

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(30)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

29

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

45

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

40.35

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

64.35

3 Current carring capacity of 3C x16 Sqmm AL XLPE cable is

=

70

4

No of cable required

=

0.92

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

3C x16Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE Cable)

=

2.44

3 X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE Cable)

=

0.0808

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

1.515823138

CABLE SIZE CHOSEN

=

2X3CX16

sq.mm Al XLPE Cable

$

!"

#

%% &

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(31)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

16

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

55

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

=

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

22.26

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

35.50

3 Current carring capacity of 3C x10 Sqmm AL XLPE cable is

=

67

4

No of cable required

=

0.53

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

3C x10 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3C x 10 SQmm AL XLPE Cable)

=

3.94

3 X AT CONDUCTOR TEMP. (3C x 10 Qmm AL XLPE Cable)

=

0.0837

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

1.636204732

$

!"

#

&

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(32)

A) FEEDER DATA

1

WORKING LOAD (KW)

2

WORKING LOAD (KVA)

=

20

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

35

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

=

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

27.82

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

44.38

Considering 35% extra current

59.91

3 Current carring capacity of 4C x10 Sqmm AL XLPE cable is

=

67

4

No of cable required

=

0.89

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

4C x10 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE Cable)

=

3.94

3 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE Cable)

=

0.0837

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

1.301526492

CABLE SIZE CHOSEN

=

4CX10

sq.mm Al XLPE Cable

$

!"

#

%

'

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(33)

A) FEEDER DATA

1

WORKING LOAD (KW)

10

2

WORKING LOAD (KVA)

=

12.5

2

VOLTAGE (V)

=

0.415

3

PF

=

0.8

4

FAULT CURRENT

Ish

=

2.64

5

FAULT CLEARING TIME

t

=

0.08

6

CONSTANT

K

=

94

7

LENGTH

=

30

B)

1

AREA OF CONDUCTOR

=

Ish* t/K

=

7.943667669

2

CABLE SIZE CHOSEN

=

10

SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1

AMBIENT AIR TEMPERATURE

=

45

RATING FACTOR

=

0.95

2 GROUPING/SPACING WITH OTHER CABLES

=

Cable laid in trench (9 cables touching)

RATING FACTOR

=

0.66

3

OVERALL DERATING FACTOR

=

0.627

D)

1

FULL LOAD CURRENT

Ifl

=

WORLING LOAD (KVA)/1.732 x VOLTAGE

=

17.39

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING

=

FULL LOAD CURRENT/DERATING FACTOR

27.74

3 Current carring capacity of 4C x10 Sqmm AL XLPE cable is

=

67

4

No of cable required

=

0.41

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE

=

4C x10 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE Cable)

=

3.94

3 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE Cable)

=

0.0837

4 COSø

=

0.8

5 SINø

=

0.6

6 No of runs:

=

1

% VOLTAGE DROP

=

7 % VOLTAGE DROP

=

0.697246335

CABLE SIZE CHOSEN

=

4CX10

sq.mm Al XLPE Cable

$

!"

#

(FULL LOAD CURRENT X LENGTH X

IMPEDENCE)/NO OF RUNS X VOLTAGE

(34)

1.0 Formula Used:

1.1 Working Load in kVA = L. F.

1.2 System P. F. = P. F. D. F. Effi. 2.0 Unit Total (kW) Unit Total (kW) 2.1 45 0.936 0.86 0.9 1 2 90 1 40.5 2.2 2.5 0.83 0.82 1 1 1 2.5 1 2.5 2.3 8 0.8 0.8 1 1.3 Lumpsum 8 Lumpsum 6.1538462 2.4 0.5 0.67 0.82 1 1 6 3 6 3 103.5 52.153846 3.0 = 82.87 kVA 4.0 = 0.76 5.0 5.1 = 100 kVA 5.2 = 4.5 % 5.3 = 45 KW 5.4 = 0.415 kV 5.5 = 0.86 5.6 = 0.936 5.9 = 44.097 kVA 5.10 = 335.42 kVA 5.11 = 111.81 kVA 5.14 = 2222.2 kVA

The selected rating of transformer is 100 kVA

% [Motor Starting kVA (S/D) + Base Load kVA] x 100 (within 10%)

S.C capacity of transformer 5.16 Voltage drop at transformer terminal when largest

motor start with Star-Delta starting = 7.0

S.C capacity of transformer 1.7321 x kV x I SC

5.15 Voltage drop at transformer terminal when largest

motor start with DOL starting = 17.078 %

[Motor Starting kVA (DOL) + Base Load kVA] x 100

(within 10%) 2.2222

S.C capacity of transformer

MVA Rating of transformer in MVA x 100

Impedance of transformer in %

kA Fault Level in MVA

1.7321 x kV

(Rating in kVA of transformer assumed - Largest motor KVA)

Motor starting Kva with DOL start = 6 x 1.7321 x kV x I FLC

5.13 Fault current of transformer secondary side (ISC) = 3.0915

5.12 Fault Level at transformer secondary side =

Motor starting Kva with Star-Delta start = 3 x 1.7321 x kV x I FLC

5.8 Rating of largest size motor in kVA = 55.903 kVA kW

P.F x Efficiency Base load on transformer before starting fourth

largest motor

5.7 FLC of motor = 77.771 A kW x 1000

1.7321 x V x p.f x efficiency

Rating of the largest size motor From the above table

P.F of largest size motor From the above table

Efficiency of largest size motor From the above table

9.62 Pump (existing)

Supply voltage System voltage

Calculation to check the starting of largest size motor

Rating of transformer assumed Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star)

% impedance of transformer assumed From IS 2026

System P. F.

= Diversity Factor = Motor Efficiency

Item Description Rating in kW Effi.

Working Load (kVA) Connected Load Working Load

Input Data and Calculations:

D. F.

Total Working Load (kW) / Total Working Load (kVA) = Motor Power Factor

P. F.

Considering 20% contingency

Total Load 69.06

Lighting

TRANSFORMER SIZING FOR JATNI (PHED Transmission) PUMPING STATION

[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ] = Load Factor

5.46 Exhaust Fan (existing)

3.67 Chain pully (existing)

50.31

Sr.

(35)

CAPACITOR BANK SIZING ACROSS BUS

1 Average Power factor (pf1)

0.755

2 Total Working load

52

kW

3 Power factor To be improved (pf2)

0.98

Total kVAR to be connected across Bus

4 Total kVAR to be connected across Bus

35

KVAR

(36)

A) FEEDER DATA 1 WORKING LOAD (KW)

2 WORKING LOAD (KVA) = 100

2 VOLTAGE (V) = 0.415

3 PF = 0.8

4 FAULT CURRENT Ish = 3.09

5 FAULT CLEARING TIME t = 0.08

6 CONSTANT K = 94

7 LENGTH = 60

B)

1 AREA OF CONDUCTOR = Ish* t/K = 9.297701931

2 CABLE SIZE CHOSEN = 10 SQ.MM AL

(AS PER SHORT CIRCUIT CALCULATION)

C) LAYING CONDITIONS

1 AMBIENT AIR TEMPERATURE = 45

RATING FACTOR = 0.95

2 GROUPING/SPACING WITH OTHER CABLES = Cable laid in ground (3 cables touching)

RATING FACTOR = 0.69

3 OVERALL DERATING FACTOR = 0.6555

D)

1 FULL LOAD CURRENT Ifl = WORLING LOAD (KVA)/1.732 x VOLTAGE

= 139.12

2 CURRENT RATING REQ.AFTER CONSIDERING DERATING = FULL LOAD CURRENT/DERATING FACTOR 212.24

3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is = 223

4 No of cable required = 0.95

E) CHECK FOR VOLTAGE DROP

1 CABLE SIZE = 3.5C x120 Sqmm AL XLPE cable

2 R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable) = 0.324 3 X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable) = 0.0712

4 COSø = 0.8

5 SINø = 0.6

6 No of runs: = 1

% VOLTAGE DROP =

7 % VOLTAGE DROP = 1.051833358

CABLE SIZE CHOSEN = 3.5CX120 sq.mm Al XLPE Cable

!"# $

(FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE

References

Related documents

facilitate experimentation on hybrid IP/SDN networks at large scale. The Google B4 WAN [21] is an integrated hybrid IP SDN solution, and it has likely been the first application

BASE: From Front Bird bend knees, turn toes out to place hands on flyer's hips. Place index and middle finger on belly, ring and pinkie finger around outer hip, flyer's

In the long term variable interest rates have a significant and negative effect on the exchange rate of Rp / Yen, the inflation difference variable has

If the current disposable income of college students increases, there would be higher consumption expenditures regarding classes 9, 3 and 5 (Recreation and culture; Clothing

In order to answer these questions, I mainly rely on survey data from the The Programme for the International Assessment of Adult Competencies (PIAAC) which covers tens

The results for ∆GDIGDP are mixed and non-significant while there are significant differences for ∆GAGRVA indicating a higher rate of growth in agricultural value added in groups

Reade (2013) is attempting to detect corruption by forecasting soccer games based on a bookmaker model with odds corrected for FLB bias.. He did not mention the other

The study was undertaken as an exploratory investigation to examine how Hispanic students of Mexican descent perceive intergroup conflict, its impact on their exchanges with