WORK

BREAKDOWN

STRUCTURE

FOR

A

TYPICAL

MINE

LEGEND

[GeoMine] = Technology Sites

[Exploration-Geology-Reserves] = Edumine Courses

(2)

1 E

XPLORATION

[GEOMINE]

[E

XPLORATION

-G

EOLOGY

-R

ESERVES

]

1.1 Claim Staking 1.2 Land Title

1.3 Drilling & Sampling

1.3.1 Permits

1.3.2 Health & Safety

1.3.3 Quality 1.3.4 Access 1.3.5 Accommodation 1.3.6 Supplies 1.3.7 Drilling 1.3.8 Sampling 1.3.9 Reporting 1.4 Testing 1.5 Geology 1.6 Geochemistry [GEOCHEMISTRY]

2 E

NVIRONMENTAL

[ENVIROMINE]

[E

NVIRONMENT

–H

EALTH

-S

AFETY

]

2.1 Site Characterization

(3)

2.1.1 Topography 2.1.2 Climate 2.1.2.1 Temperature 2.1.2.2 Wind 2.1.2.3 Air Quality 2.1.2.4 Precipitation

2.1.3 Soil & Rock

2.1.3.1 Geology 2.1.3.2 Soils 2.1.3.3 Geochemistry [GEOCHEMISTRY] 2.1.4 Flora 2.1.5 Fauna 2.1.6 Water 2.1.6.1 Surface Water 2.1.6.2 Groundwater 2.1.6.3 Marine Waters

2.2 Data Management [GPS] [GIS]

[DIGITAL MAPPING]

2.2.1 Surveying

2.2.2 GIS

(4)

2.3 Reporting

2.3.1 Environmental Impact Assessment

2.3.2 Regulatory Interaction

2.3.3 Community Relations

2.3.4 Permits

3

E

NGINEERING

&

T

ECHNICAL

[GEOTECHMINE & HYDROMINE]

[Geotechnics-Rock Mechanics]

(5)

3.1 Surveying [GPS] [GIS]

[DIGITAL MAPPING] 3.2 Geotechnical [GeotechMine] 3.3 Geologic [GeoMine] 3.4 Site Water Balance [HydroMine]

[WATER BALANCE] 3.5 Groundwater [HydroMine]

3.6 Surface Water [HydroMine]

3.7 Geochemistry [GEOCHEMISTRY] 3.8 Biological 3.9 Vegetation 3.10 Data Management 3.10.1 GPS [GPS] 3.10.2 GIS [GIS] 3.10.3 CADD

4 F

ACILITIES

[T

AILINGSMINE] 4.1 Tailings [TAILINGS] 4.1.1 Site Selection

4.1.1.1 Alternative Site Identification 4.1.1.2 Site Comparison

4.1.1.3 Site Assessment 4.1.1.4 Report Preparation

(6)

4.1.2 Site Characterization

4.1.3 Design

4.1.3.1 Layout [EROSION]

4.1.3.2 Foundations

4.1.3.3 Liner [FACILITY LINERS

4.1.3.4 Embankments

4.1.3.5 Surface Water Management Facilities 4.1.3.6 Supply & Discharge Lines

4.1.3.7 Placement Procedures

4.1.3.8 Cover [COVERS] [EROSION]

4.1.3.9 Monitoring & Instrumentation

4.1.3.10 Closure Works [DESIGN FOR CLOSURE] 4.1.3.11 Design Documentation

4.1.3.11.1 R eport 4.1.3.11.2 Drawings 4.1.3.11.3 Calculations 4.1.3.11.4 Cost Estim ates

(7)

4.1.4 Construction

4.1.5 Operation

4.1.6 Closure

4.1.7 Post-Closure Surveillance and Maintenance

4.2 Waste Rock [ROCK WASTE]

4.2.1 Site Selection

4.2.1.1 Alternative Site Identification 4.2.1.2 Site Comparison 4.2.1.3 Site Assessment 4.2.1.4 Report Preparation 4.2.2 Site Characterization 4.2.3 Design 4.2.3.1 Layout [EROSION] 4.2.3.2 Foundations

4.2.3.3 Liner [FACILITY LINERS

4.2.3.4 Embankments

4.2.3.5 Surface Water Management Facilities 4.2.3.6 Supply & Discharge Lines

4.2.3.7 Placement Procedures

4.2.3.8 Cover [COVERS] [EROSION]

4.2.3.9 Monitoring & Instrumentation

4.2.3.10 Closure Works [DESIGN FOR CLOSURE] 4.2.3.11 Design Documentation

4.2.3.11.1 R eport 4.2.3.11.2 Drawings 4.2.3.11.3 Calculations 4.2.3.11.4 Cost Estim ates

(8)

4.2.4 Construction

4.2.5 Operation

4.2.6 Closure

4.2.7 Post-Closure Surveillance and Maintenance

4.3 Heap Leach

4.3.1 Site Selection

4.3.1.1 Alternative Site Identification 4.3.1.2 Site Comparison 4.3.1.3 Site Assessment 4.3.1.4 Report Preparation 4.3.2 Site Characterization 4.3.3 Design 4.3.3.1 Layout [EROSION] 4.3.3.2 Foundations

4.3.3.3 Liner [FACILITY LINERS

4.3.3.4 Embankments

4.3.3.5 Surface Water Management Facilities 4.3.3.6 Supply & Discharge Lines

4.3.3.7 Placement Procedures

4.3.3.8 Cover [COVERS] [EROSION]

4.3.3.9 Monitoring & Instrumentation

4.3.3.10 Closure Works [DESIGN FOR CLOSURE] 4.3.3.11 Design Documentation

4.3.3.11.1 R eport 4.3.3.11.2 Drawings 4.3.3.11.3 Calculations 4.3.3.11.4 Cost Estim ates

(9)

4.3.4 Construction

4.3.5 Operation

4.3.6 Closure

4.3.7 Post-Closure Surveillance and Maintenance

4.4 Dams

4.4.1 Sediment Ponds [SEDIMENT PONDS]

4.4.2 Water Retention Dams

4.5 Access Facilities

4.5.1 Roads [MINE ROADS]

4.5.2 Bridges 4.5.3 Air Strips 4.6 Power Facilities 4.6.1 Power Lines 4.6.2 Generators 4.7 Domestic Water

4.7.1 Water Supply Systems

4.7.2 Waste Water 4.8 Buildings 4.8.1 Accommodation Facilities 4.8.2 Offices 4.8.3 Plant Structures 4.8.4 Security Structures 4.8.5 Communications Facilities

(10)

5 M

INING

[Mining Methods—Mine

Planning]

5.1 Surface Mine [OpenPitMine]

5.1.1 Pit Layout & Design

5.1.2 Slope Stability [ROCK SLOPE STABILITY

5.1.3 Roads [MINE ROADS]

5.1.4 Equipment 5.1.4.1 Trucks 5.1.4.2 Loaders 5.1.4.3 Conveyors 5.1.5 Overburden Removal 5.1.5.1 Drilling 5.1.5.2 Blasting [BLASTING] 5.1.5.3 Loading 5.1.5.4 Transport 5.1.5.5 Disposal 5.1.6 Ore Removal

(11)

5.2 Underground Mine [UndergroundMine] 5.2.1 Shafts 5.2.2 Portals 5.2.3 Ventilation 5.2.4 Drilling 5.2.5 Blasting [BLASTING]

5.2.6 Rock Support [SUBSIDENCE]

5.2.7 Waste Removal 5.2.8 Ore Removal

6 P

ROCESSING

[METMINE]

[Mineralogy—Mineral

Processing]

(12)

6.1 Crushing 6.2 Grinding 6.3 Flotation 6.4 Metallurgical 6.5 Chemical [CYANIDE] 6.6 Concentration 6.7 Pyrometallurgical 6.8 Bio-metallurgical [BIOTECHNOLOGY]

7 P

EOPLE

[PEOPLEMINE]

7.1 Human Resources [MINING CAREERS] 7.2 Health and Safety [HEALTH & SAFETY]

7.3 Emergency Response [EMERGENCY RESPONSE] 7.4 Community Relations [RESPONSIBLE MINING]

7.4.1 Press Relations

7.4.2 Community Outreach [COMMUNITY RELATIONS]

7.4.3 Community Education 7.4.4 Visitor Facilities 7.4.5 Charity 7.5 Continuing Education 7.5.1 On-Line Learning 7.5.2 Academic Attendance 7.5.3 Conferences

(13)

8 M

ANAGEMENT

[LAWMINE]

[Management-Risk-Financial]

8.1 Management [DECISION MAKING]

8.2 Cost & Schedule [MINE COSTS]

[PROJECT MANAGEMENT] 8.3 Accounting [VALUATION] 8.4 Legal [LAW] 8.5 Procurement 8.6 Sales 8.7 Quality [QUALITY] 8.8 Security

References

Related documents

Attendees include the winning Contractor, the Sub-Contractor for ITS work, Bureau of ITS Engineering, Bureau of Traffic Operations, Regional Construction and other key

The purpose of this study was to compare the teaching practices and efficacy beliefs of traditional middle school teachers and International Baccalaureate Middle Years

As a consequence of the above theorem, we can apply to any weak- assortative matrix, directly from its central strip our previous results for assortative matrices, that is, the

In private regulation, private actors make, implement, and enforce rules that serve traditional public goals. While private safety standards have a long history, private social

Reject cookies help don open in office letters clue play store the user that appear on our pages a lot of times a visitor on this daily crossword today!. Number of amateur don t open

A tool that allows users to check and correct spelling, hear words read and spelled aloud; find definitions, synonyms, grammar; help save words and messages for communication

Assessment of functional status Stimulated chart recall, standardized patient examination, oral examination Communication skills Standardized patient examination,..

understanding how individual college students develop the social identity of being collaborative, relational leaders interdependently engaging in leadership as a group