• No results found

Accounting System Requirements

N/A
N/A
Protected

Academic year: 2021

Share "Accounting System Requirements"

Copied!
12
0
0

Loading.... (view fulltext now)

Full text

(1)

Basic Financial Requirements for

Government Contracting

The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations

Accounting System

Requirements

(2)

Page | 3

Prior to Contract Award

Contracting Office or DCMA conducts

Preaward Survey to consider responsibility of prospective contractor

Design of the Accounting System is part of the Preaward Survey (SF 1408 Criteria) DCAA requested to evaluate design of Accounting System

Preaward Accounting System Audit

Evaluates design of Accounting System to determine if it is acceptable for prospective contract

DCAA or Buying Command will request contractor complete Preaward Accounting System Checklist

Contractor should be prepared to demonstrate how accounting system satisfies SF 1408 criteria at initial meeting

(3)

Based on SF 1408 criteria

Generally used by contractors new to government contracting that the

Government plans to award a cost type contract (cost reimbursement contracts, or for contractors that will receive progress payments based on cost)

Assesses whether the requirements for an adequate accounting system have been met

Page | 5

Preaward Accounting System Checklist

Preaward Accounting System

Compliance Requirements

Generally Accepted Accounting Practices (GAAP)

Proper Segregation of Costs Direct Costs by Contract Allocation of Indirect Costs Accumulation of Costs Under General Ledger Control Timekeeping System

Labor Distribution

Interim Determination of Costs Exclusion of Unallowables Costs by Contract Line Item Preproduction Costs

Limitation of Costs Billings

(4)

Issue report to Contracting Officer with an opinion that the accounting system is or is not suitably designed, in all material respects, for award of a prospective contract.

Includes a completed SF 1408

An opinion that the system is not suitably designed means that the contractor cannot be awarded a cost type contract of the award will be delayed until corrective action is taken and a follow-up audit can be performed

Page | 7

After the Audit is Completed

Contractors not making interim (at least monthly) determination of costs charged through routine posting to books of

account

Failure to properly segregate direct and indirect costs

Improper timekeeping

Failure to exclude unallowable costs

(5)

Page | 9

Incurred Cost Submission

Due Dates of Submissions

Incurred cost claims are due six months after completion of the contractor’s

fiscal year end

Per the Allowable Cost and Payment Clause (FAR 52.216-7(d)(2))

Allowable cost and payment clause applies to cost-reimbursement type contracts (FAR 16.307)

(6)

ICE is an excel spreadsheet

It includes all schedules required for an adequate submission per FAR 52.216-7 ICE is not a requirement but a tool to assist in preparation of an adequate incurred cost submission

The submission of an adequate proposal may expedite contract closings

Page | 11

Incurred Cost Electronically

Model (ICE)

If submissions are six months delinquent, DCAA will recommend a decrement factor and for the CO to make a unilateral

determination. (FAR 42.703-2(c)(2))

(7)

Page | 13

Provisional Billing Rates (PBRs)

Purpose of PBRs

Established to approximatethe contractor’s final year-end rates, as adjusted for any unallowable costs Used for interim purposes until settlement is reached on the final indirect rates for the contractor’s fiscal year

FAR 42.704 - Billing Rates - provides procedures and guidance for establishing PBRs

The contracting officer or auditor shall establish PBRs on the basis of information resulting from recent review, previous rate audits or experience, or similar reliable data or experience of other

(8)

Page | 15

When Should We Submit?

Prior to the beginning of the fiscal year (once budgets are complete) or when the

established billing rates are no longer

representative of final year end rates due to unforeseen circumstances.

PBRs should be submitted at least annually. Vouchers and progress payments can be returned if submitted without properly established billing rates.

Monitoring

PBRs should be monitored:

Throughout the year

Immediately after year-end

Upon submission of the final indirect rate proposal

PBRs may be adjusted by either party at any time to prevent substantial under or over payment – FAR 42.704(c).

If PBRs are adjusted, the contractor should submit adjustment vouchers accordingly.

(9)

Page | 17

Common Deficiencies

Failure to remove unallowable costs from the billing rate projections.

Failure to adjust provisional billing rates based on actual experience:

Before year end, if there are known or reasonably anticipated significant variances.

After year end once actual rates, net of unallowable expenses, are calculated.

(10)

Public Vouchers

Page | 19

Cost type contracts provide for interim payments for costs on a Standard Form (SF) 1034 public voucher. DCAA will perform voucher reviews based on risk. Fixed price contracts are subject to FAR Part 32 financing methods.

Contractor Responsibilities

Contact the cognizant DCAA office after contract award

Ensure DCAA has the necessary information to process contract billings, such as current

provisional billing rates, copy of the contract, any special contract provisions, etc.

Maintain adequate billing system internal controls Ensure adequate support is maintained for

amounts billed

Submit timely incurred cost proposals and final vouchers in accordance with FAR 52.216-7

(11)

Preparation of Vouchers

The contractor is responsible for preparing and submitting claims for reimbursement according to the terms of the contract.

Vouchers should not be submitted more than once every two weeks.

All vouchers should be submitted through WAWF unless contract terms require hard copy vouchers to be submitted.

Public voucher claims for reimbursement must be prepared on the prescribed Government forms:

First voucher on a contract is an interim voucher, as are all subsequent vouchers prior to the final voucher. Final voucher will not be submitted until all contract work is completed

Page | 21

Common Deficiencies

Math errors

Billed costs not allowed per the contract terms (e.g. overtime)

Incorrect provisional billing rates (indirect costs)

(12)

Page | 23

DCAA Internet Resources

www.dcaa.mil

Audit Process Overview – Information for Contractors Manual

DCAA Pre-award Accounting System Checklist DoD Contract Proposal Adequacy Checklist DCAA Incurred Cost Adequacy Checklist Incurred Cost Electronically (ICE) Model Links to Acquisition Regulations

Small Business Seminar Slides

Contact Information

DoD Office of Small Business Programs

www.acq.osd.mil/OSBP

DCAA

References

Related documents

In this section we introduce primitive recursive set theory with infinity (PRSω), which will be the default base theory for the rest of this thesis (occasionally exten- ded by

The choice of a transformation-based morphology model is motivated mainly by the realization that most Natural Language Processing methods treat words as basic units of language,

- Unallowable costs must be identified and excluded from any billing, claim or proposal, including indirect cost pools.. - When an unallowable cost is incurred, its

CAMRAD II calculations using wall corrections (from Ref. 1) are included in addition to the CFD results. The computations bound the measured vertical location of the vortices with

Thus, CIs not containing zero indicate the mediating variable (i.e., political interest) was a statistically significant mediator between social trust variables (i.e., trust in

As with Phillips (2002) study suggesting that parent firms tend to transfer procedures and social structures to their spinoffs, spinoff founders said that they attempted to

https://www.twobirds.com/en/news/articles/2016/global/unified-patent-court-back-on-track- again (accessed 1 February 2018).. litigation system which included EU and non-EU

Blank, Updated overall survival analysis in OCEANS, a randomized phase 3 trail of gemcitabine + carboplatin and bevacizumab or placebo followed by bevacizumab or placebo