• No results found

18.pdf

N/A
N/A
Protected

Academic year: 2021

Share "18.pdf"

Copied!
33
0
0

Loading.... (view fulltext now)

Full text

(1)

18

18

Student: ___________________________________________________________________________ Student: ___________________________________________________________________________

1.

1. The The finafinanciancial l manamanager'ger's s respresponsionsibilibility ty invoinvolveslves A.

A. increasing the per share price of the company's stock at any cost and by any means, ways and fashionincreasing the per share price of the company's stock at any cost and by any means, ways and fashion that is possible.

that is possible.

B. the shareholder wealth maximization. B. the shareholder wealth maximization. C. which capital projects to select.

C. which capital projects to select. D. both b and c

D. both b and c 2.

2. PerPerhaps thhaps the most ime most importportant decant decisioisions that cns that confronfront thont the finane financial mcial managanager areer are A. which capital projects to select.

A. which capital projects to select.

B. the correct capital structure for the firm. B. the correct capital structure for the firm. C. the correct capital structure for projects. C. the correct capital structure for projects. D. none of the above

D. none of the above 3.

3. CapiCapital tal budgbudgetineting ang analysalysis iis is vers very imy importportant, ant, becabecause use itit

A. involves, usually expensive, investments in capital assets. A. involves, usually expensive, investments in capital assets. B. has to do with the productive capacity of a firm.

B. has to do with the productive capacity of a firm.

C. will determine how competitive and profitable a firm will be. C. will determine how competitive and profitable a firm will be. D. all of the above

D. all of the above

Tiger Towers, Inc. is considering an expansion of their existing business, student apartments. The new Tiger Towers, Inc. is considering an expansion of their existing business, student apartments. The new project will be built on some vacant land that the firm has just contracted to buy. The land cost $1,000,000 project will be built on some vacant land that the firm has just contracted to buy. The land cost $1,000,000 and the payment is due today. Construction of a 20-unit office building will cost $3 million; this expense and the payment is due today. Construction of a 20-unit office building will cost $3 million; this expense will be depreciated straight-line over 30 years to zero salvage value; the pretax value of the land and will be depreciated straight-line over 30 years to zero salvage value; the pretax value of the land and building in year 30 will be $18,000,000. The $3,000,000 construction cost is to be paid today. The project building in year 30 will be $18,000,000. The $3,000,000 construction cost is to be paid today. The project will not change the risk level of the firm. The firm will lease 20 offices suites at $20,000 per suite per will not change the risk level of the firm. The firm will lease 20 offices suites at $20,000 per suite per year; payment is due at the start of the year; occupancy will begin in one year. Variable cost is $3,500 per year; payment is due at the start of the year; occupancy will begin in one year. Variable cost is $3,500 per suite. Fixed costs, excluding depreciation, are $75,000 per year. The project will require a $10,000

suite. Fixed costs, excluding depreciation, are $75,000 per year. The project will require a $10,000 investment in net working capital.

investment in net working capital.

4

4.. WWhhaat t iis s tthhee ununlevered after-tax incremental cash flow for year 0?levered after-tax incremental cash flow for year 0? A. -$3,660,000 A. -$3,660,000 B. -$5,100,000 B. -$5,100,000 C. -$4,000,000 C. -$4,000,000 D. -$4,010,000 D. -$4,010,000

E. None of the above E. None of the above 5

5.. WWhhaat t iis s tthhee ununlevered after-tax incremental cash flow for year 2?levered after-tax incremental cash flow for year 2? A. -$4,610 A. -$4,610 B. $102,300 B. $102,300 C. $202,300 C. $202,300 D. $255,000 D. $255,000

E. None of the above E. None of the above

(2)

6

6.. WWhhaat t iis s tthhee ununlevered after-tax incremental cash flow for year 30?levered after-tax incremental cash flow for year 30? A. $12,432,300 A. $12,432,300 B. $12,225,390 B. $12,225,390 C. $12,332,300 C. $12,332,300 D. $12,485,000 D. $12,485,000 E. None of the above E. None of the above

Assume that the firm will partially finance the project with a $3,000,000 interest-only 30-year loan at Assume that the firm will partially finance the project with a $3,000,000 interest-only 30-year loan at 10.0 percent APR with annual payments.

10.0 percent APR with annual payments. 7.

7. What What is this the leve levered aered afterfter-tax i-tax increncrementmental casal cash floh flow for yw for year 0ear 0?? A. -$1,010,000 A. -$1,010,000 B. -$1,000,000 B. -$1,000,000 C. -$660,000 C. -$660,000 D. -$2,100,000 D. -$2,100,000

E. None of the above E. None of the above 8.

8. What What is this the leve levered aered afterfter-tax i-tax increncrementmental casal cash floh flow for yw for year 1ear 1?? A. $4,300 A. $4,300 B. -$202,610 B. -$202,610 C. -$95,700 C. -$95,700 D. $57,000 D. $57,000

E. None of the above E. None of the above 9.

9. What What is this the leve levered aered afterfter-tax i-tax increncrementmental casal cash floh flow for yw for year 3ear 30?0? A. $9,027,390 A. $9,027,390 B. $9,234,300 B. $9,234,300 C. $9,134,300 C. $9,134,300 D. $9,287,000 D. $9,287,000

E. None of the above E. None of the above 10.

10. Assume that the firAssume that the firm will partialm will partially finance the project wly finance the project with a subsidized $3,0ith a subsidized $3,000,000 intere00,000 interest only 30-yearst only 30-year loan at

loan at8.8.0 percent APR with annual payments. Note that eight percent is less than the 10 percent that0 percent APR with annual payments. Note that eight percent is less than the 10 percent that

they normally borrow at. What is the NPV of the loan? they normally borrow at. What is the NPV of the loan? A. $198,469 A. $198,469 B. $53,979.83 B. $53,979.83 C. $102,727.55 C. $102,727.55 D. $1,334,851.09 D. $1,334,851.09 E. None of the above E. None of the above 11.

11. The firm'The firm's tax rate is 34%. s tax rate is 34%. The firm'The firm's pre-tax cost of ds pre-tax cost of debt is 8%; the fiebt is 8%; the firm's debt-trm's debt-to-equity rato-equity ratio is 3; theio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is the firm's cost of equity capital?

the firm's cost of equity capital? A. 33.33% A. 33.33% B. 10.85% B. 10.85% C. 13.12% C. 13.12% D. 16.5% D. 16.5%

E. None of the above E. None of the above 12.

12. The firm'The firm's tax rate is 34%. s tax rate is 34%. The firm'The firm's pre-tax cost of ds pre-tax cost of debt is 8%; the fiebt is 8%; the firm's debt-trm's debt-to-equity rato-equity ratio is 3; theio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is the required return on assets?

the required return on assets? A. 33.33% A. 33.33% B. 10.85% B. 10.85% C. 13.12% C. 13.12% D. 16.5% D. 16.5%

E. None of the above E. None of the above

(3)

6

6.. WWhhaat t iis s tthhee ununlevered after-tax incremental cash flow for year 30?levered after-tax incremental cash flow for year 30? A. $12,432,300 A. $12,432,300 B. $12,225,390 B. $12,225,390 C. $12,332,300 C. $12,332,300 D. $12,485,000 D. $12,485,000 E. None of the above E. None of the above

Assume that the firm will partially finance the project with a $3,000,000 interest-only 30-year loan at Assume that the firm will partially finance the project with a $3,000,000 interest-only 30-year loan at 10.0 percent APR with annual payments.

10.0 percent APR with annual payments. 7.

7. What What is this the leve levered aered afterfter-tax i-tax increncrementmental casal cash floh flow for yw for year 0ear 0?? A. -$1,010,000 A. -$1,010,000 B. -$1,000,000 B. -$1,000,000 C. -$660,000 C. -$660,000 D. -$2,100,000 D. -$2,100,000

E. None of the above E. None of the above 8.

8. What What is this the leve levered aered afterfter-tax i-tax increncrementmental casal cash floh flow for yw for year 1ear 1?? A. $4,300 A. $4,300 B. -$202,610 B. -$202,610 C. -$95,700 C. -$95,700 D. $57,000 D. $57,000

E. None of the above E. None of the above 9.

9. What What is this the leve levered aered afterfter-tax i-tax increncrementmental casal cash floh flow for yw for year 3ear 30?0? A. $9,027,390 A. $9,027,390 B. $9,234,300 B. $9,234,300 C. $9,134,300 C. $9,134,300 D. $9,287,000 D. $9,287,000

E. None of the above E. None of the above 10.

10. Assume that the firAssume that the firm will partialm will partially finance the project wly finance the project with a subsidized $3,0ith a subsidized $3,000,000 intere00,000 interest only 30-yearst only 30-year loan at

loan at8.8.0 percent APR with annual payments. Note that eight percent is less than the 10 percent that0 percent APR with annual payments. Note that eight percent is less than the 10 percent that

they normally borrow at. What is the NPV of the loan? they normally borrow at. What is the NPV of the loan? A. $198,469 A. $198,469 B. $53,979.83 B. $53,979.83 C. $102,727.55 C. $102,727.55 D. $1,334,851.09 D. $1,334,851.09 E. None of the above E. None of the above 11.

11. The firm'The firm's tax rate is 34%. s tax rate is 34%. The firm'The firm's pre-tax cost of ds pre-tax cost of debt is 8%; the fiebt is 8%; the firm's debt-trm's debt-to-equity rato-equity ratio is 3; theio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is the firm's cost of equity capital?

the firm's cost of equity capital? A. 33.33% A. 33.33% B. 10.85% B. 10.85% C. 13.12% C. 13.12% D. 16.5% D. 16.5%

E. None of the above E. None of the above 12.

12. The firm'The firm's tax rate is 34%. s tax rate is 34%. The firm'The firm's pre-tax cost of ds pre-tax cost of debt is 8%; the fiebt is 8%; the firm's debt-trm's debt-to-equity rato-equity ratio is 3; theio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is the required return on assets?

the required return on assets? A. 33.33% A. 33.33% B. 10.85% B. 10.85% C. 13.12% C. 13.12% D. 16.5% D. 16.5%

E. None of the above E. None of the above

(4)

The 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will contribute The 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will contribute $20,000 cash and borrow $80,000 at 6% with an interest-only loan with a maturity of 5 years and annual $20,000 cash and borrow $80,000 at 6% with an interest-only loan with a maturity of 5 years and annual interest payments. The equipment will be depreciated straight-line to zero over the 5-year life of the interest payments. The equipment will be depreciated straight-line to zero over the 5-year life of the project. There will be a pre-tax salvage value of $5,000. There are no other start-up costs at year 0. project. There will be a pre-tax salvage value of $5,000. There are no other start-up costs at year 0. During years 1 through 5, the firm will sell 25,000 units of product at $5; variable costs are $3; there are During years 1 through 5, the firm will sell 25,000 units of product at $5; variable costs are $3; there are no fixed costs.

no fixed costs. 13.

13. What is thWhat is the NPV oe NPV of the projef the project using thct using the WACC e WACC methodolomethodology?gy? A. $49,613.03 A. $49,613.03 B. $58,028.68 B. $58,028.68 C. $102s,727.55 C. $102s,727.55 D. $315,666.16 D. $315,666.16 E. None of the above E. None of the above 14.

14. What is thWhat is the NPV oe NPV of the projef the project using thct using the APV me APV methodologyethodology?? A. $49,613.03 A. $49,613.03 B. $198,469 B. $198,469 C. $102,727.55 C. $102,727.55 D. $149,580.12 D. $149,580.12 E. None of the above E. None of the above

The 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will contribute The 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will contribute $25,000 cash and borrow $75,000 with an interest-only loan with a maturity of 5 years and annual interest $25,000 cash and borrow $75,000 with an interest-only loan with a maturity of 5 years and annual interest payments. The equipment will be depreciated straight-line to zero over the 5-year life of the project.

payments. The equipment will be depreciated straight-line to zero over the 5-year life of the project.

There will be a pre-tax salvage value of $5,000. There are no other start-up costs at year 0. During years 1 There will be a pre-tax salvage value of $5,000. There are no other start-up costs at year 0. During years 1 through 5, the firm will sell 25,000 units of product at $5; variable costs are $3; there are no fixed costs. through 5, the firm will sell 25,000 units of product at $5; variable costs are $3; there are no fixed costs. 15.

15. What is thWhat is the NPV oe NPV of the projef the project using thct using the WACC e WACC methodolomethodology?gy? A. $58,028.68 A. $58,028.68 B. $49,613.03 B. $49,613.03 C. $48,300.47 C. $48,300.47 D. $102,727.55 D. $102,727.55 E. None of the above E. None of the above 16.

16. When using the AWhen using the APV methoPV methodology, whdology, what is the NPV oat is the NPV of the depreciaf the depreciation tax shieldtion tax shield?? A. $32,051.52 A. $32,051.52 B. $25,777.35 B. $25,777.35 C. $22,794.65 C. $22,794.65 D. $97,152.98 D. $97,152.98

E. None of the above E. None of the above 17.

17. When using the AWhen using the APV methoPV methodology, whdology, what is the NPV oat is the NPV of the interest tf the interest tax shield?ax shield? A. $9,666.51 A. $9,666.51 B. $12,019.32 B. $12,019.32 C. $9,377.31 C. $9,377.31 D. $7,000.73 D. $7,000.73

E. None of the above E. None of the above

(5)

18. Today is January 1, 2009. The state of Iowa has offered your firm a subsidized loan. It will be in the amount of $10,000,000 at an interest rate of 5% and have ANNUAL (amortizing) payments over 3 years. The first payment is due today and your taxes are due January 1 of each year on the previous year's

income. The yield to maturity on your firm's existing debt is 8%. What is the APV of this subsidized loan? If you rounded in your intermediate steps, the answer may be slightly different from what you got. Choose the closest.

A. -$3,497,224.43 B. $417,201.05 C. $840,797

D. None of the above

19. Today is January 1, 2009. The state of Iowa has offered your firm a subsidized loan. It will be in the amount of $10,000,000 at an interest rate of 5% and have ANNUAL (amortizing) payments over 3 years. The first payment is due December 31, 2009 and your taxes are due January 1 of each year on the previous year's income. The yield to maturity on your firm's existing debt is 8%. What is the APV of this subsidized loan?

Note that I did not round my intermediate steps. If you did, your answer may be off by a bit. Select the answer closest to yours.

A. -$3,497,224.43 B. $417,201.05 C. $840,797

D. None of the above

20. The required return on assets is 18%. The firm can borrow at 12.5%; firm's target debt to value ratio is 3/  5. The corporate tax rate is 34%, and the risk-free rate is 4% and the market risk premium is 9.2 percent. What is the weighted average cost of capital?

A. 12.15% B. 13.02% C. 14.33% D. 23.45%

E. None of the above

21. Your firm is in the 34% tax bracket. The yield to maturity on your existing bonds is 8%. The state of Georgia offers to loan your firm $1,000,000 with a TWO year AMORTIZING loan at a 5% rate of interest and ANNUAL payments due at the END OF THE YEAR.

The interest will be deductible at the time that you pay. What is the APV of this below-market loan to your firm? I did not round any of my intermediate steps. You might be a little bit off. Pick the answer closest to yours.

A. $64,157.38 B. $417,201.05 C. $840,797

D. None of the above

22. The firm's tax rate is 34%. The firm's pre-tax cost of debt is 8%; the firm's debt-to-equity ratio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. Calculate the weighted average cost of capital.

A. 33.33% B. 8.09% C. 9.02% D. 16.5%

(6)

Consider a project of the Cornell Haul Moving Company, the timing and size of the incremental after-tax cash flows (for an all-equity firm) are shown below in millions:

The firm's tax rate is 34%; the firm's bonds trade with a yield to maturity of 8%; the current and target debt-equity ratio is 2; if the firm were financed entirely with equity, the required return would be 10% 23. Using the weighted average cost of capital methodology, what is the NPV? I didn't round my

intermediate steps. If you do, you're not going to get the right answer. A. -$1,406,301.25

B. $12,494,643.75 C. $36,580,767.55 D. $108,994.618.20 E. $59,459,301.03

24. What is the levered after-tax incremental cash flow for year 2? A. $185,796,000

B. $215,152,000 C. $267,952,000 D. $284,848,000 E. None of the above

25. What is the levered after-tax incremental cash flow for year 4? A. $281,704,000

B. $465,152,000 C. -$194,848,000 D. $460,796,000 E. None of the above

26. Using the flow to equity methodology, what is the value of the equity claim? A. -$1,540,000

B. $446,570,866.00 C. $36,580,767.55 D. $470,953,393.70 E. $30,716,236.13

27. Using the APV method, what is the value of this project to an all-equity firm? A. -$46,502,288.10

B. $12,494,643.75 C. $36,580,767.55 D. -$67,163,445.12 E. $59,459,301.03

28. Using the APV method, what is the value of the debt side effects? A. $239,072,652.70

B. $66,891,713.66 C. $59,459,301.03 D. $660,000,000 E. None of the above

(7)

Consider a project of the Cornell Haul Moving Company, the timing and size of the incremental after-tax cash flows (for an all-equity firm) are shown below in millions:

The firm's tax rate is 34%; the firm's bonds trade with a yield to maturity of 8%; the current and target debt-equity ratio is 3; if the firm were financed entirely with equity, the required return would be 10% 29. Using the weighted average cost of capital methodology, what is the NPV? I didn't round my

intermediate steps. If you do, you're not going to get the right answer. A. -$1,406,301.25

B. $12,494,643.75 C. $36,580,767.55 D. $108,994.618.20 E. $59,459,301.03

30. What is the levered after-tax incremental cash flow for year 2? A. $185,796,000

B. $215,152,000 C. $267,952,000 D. $284,848,000 E. None of the above

31. What is the levered after-tax incremental cash flow for year 4? A. -$281,704,000

B. $465,152,000 C. -$194,848,000 D. $460,796,000 E. None of the above

32. Using the flow to equity methodology, what is the value of the equity claim? A. -$1,540,000

B. $446,570,866.00 C. $36,580,767.55 D. $470,953,393.70 E. $30,716,236.13

33. Using the APV method, what is the value of this project to an all-equity firm? A. -$46,502,288.10

B. $12,494,643.75 C. $36,580,767.55 D. -$67,163,445.12 E. $59,459,301.03

34. Using the APV method, what is the value of the debt side effects? A. $239,072,652.70

B. $66,891,713.66 C. $59,459,301.03 D. $660,000,000 E. None of the above 35. In the APV model

A. interest tax shields are discounted ati.

B. operating cash flows are discounted atK u.

C. depreciation tax shields are discounted ati.

(8)

36. Your firm's existing bonds trade with a yield to maturity of eight percent. The state of Missouri has offered to loan your firm $10,000,000 at zero percent for five years. Repayment will be of the form of $2,000,000 per year for five years the first payment is due in one year. What is the value of this offer? A. $4,729,622.75

B. $2,014,579.93 C. $0

D. $196,929.88 E. None of the above

37. What proportion of the firm is financed by debt for a firm that expects a 15% return on equity, a 12% return on assets, and a 10% return on debt? The tax rate is 25%.

A. 20% B. 1/3 C. 60% D. 2/3 E. 80%

38. The required return on equity for a levered firm is 10.60%. The debt to equity ratio is ½ the tax rate is 40%, the pre-tax cost of debt is 8%. Find the cost of capital if this firm were financed entirely with equity.

A. 10% B. 12% C. 8.67%

D. None of the above

39. The required return on equity for an all-equity firm is 10.0%. They are considering a change in capital structure to a debt-to-equity ratio of ½ the tax rate is 40%, the pre-tax cost of debt is 8%. Find the new cost of capital if this firm changes capital structure.

A. 14.93% B. 8.67% C. 7.40%

D. None of the above

40. The required return on equity for an all-equity firm is 10.0%. They currently have a beta of one and the risk-free rate is 5% and the market risk premium is 5%. They are considering a change in capital structure to a debt-to-equity ratio of ½ the tax rate is 40%, the pre-tax cost of debt is 8%. Find the beta if this firm changes capital structure.

A. 1.12 B. 1 C. 7.4%

D. None of the above

41. What is the expected return on equity for a tax-free firm with a 15% expected return on assets that pays 12% on its debt, which totals 25% of assets?

A. 24% B. 15.60% C. 16% D. 20% E. 15.75%

42. What is the expected return on equity for firm in the 40% tax bracket with a 15% expected return on assets that pays 12% on its debt, which totals 25% of assets?

A. 24% B. 15.60% C. 16% D. 20% E. 15.75%

(9)

43. Assume that XYZ Corporation is a leveraged company with the following information:

Calculate the debt-to-total-market-value ratio that would result in XYZ having a weighted average cost of capital of 9.3%.

A. 35% B. 40% C. 45% D. 50%

44. Today is January 1, 2009. The state of Iowa has offered your firm a subsidized loan. It will be in the amount of $10,000,000 at an interest rate of 5% and have ANNUAL (amortizing) payments over 3 years. The first payment is due today and your taxes are due January 1 of each year on the previous year's

income. The yield to maturity on your firm's existing debt is 8%. What is the APV of this subsidized loan? Note that  I did not round my intermediate steps. If  you did, your answer may be off by a bit. Select  the answer closest to yours.

A. $406,023.10 B. $840,797 C. $64,157.38 D. $20,659.77

E. None of the other answers are within $100 of my answer

45. What is the €-denominated NPV of this project? I did not round my intermediate steps, if you did, select

the answer closest to yours. A. €5,563.23

B. €2,270.79 C. €7,223.14 D. €3,554.29

E. There is not enough information (e.g. U.S. inflation) to do this problem.

46. The spot exchange rate is ¥125 = $1. The U.S. discount rate is 10%; inflation over the next three years is 3% per year in the U.S. and 2% per year in Japan. Calculate the dollar NPV of this project.

I did not round my intermediate steps, if you did, select the answer closest to yours. A. $267,181.87

B. $14,176.67 C. $2,536.49 D. $2,137.46

(10)

47. Some of the factors (with selected explanations) used in calculating the basic "net present value" and the "incremental" cash flows of a capital project are:

(i) - expected after-tax terminal value, including recapture of working capital (ii) - net income, which belongs to the equity holders of the firm

(iii) - initial investment at inception

(iv) - depreciation, and the fact that depreciation is a noncash expense (i.e. it is removed from the calculation of net income, for tax purposes, but added back because it did not actually flow out of the firm)

(v) - weighted-average cost of capital

(vi) - the firm's after-tax payment of interest to debtholders (vii) - economic life of the capital project in years

The "net present value" of a capital project is calculated by using: A. (i), (ii), and (iii)

B. (ii), (iv), and (vi) C. (i), (iii), (v), and (vii) D. (iv), (v), (vi), and (vii)

48. Some of the factors (with selected explanations) used in calculating the basic "net present value" and the "incremental" cash flows of a capital project are:

(i) - expected after-tax terminal value, including recapture of working capital (ii) - net income, which belongs to the equity holders of the firm

(iii) - initial investment at inception

(iv) - depreciation, and the fact that depreciation is a noncash expense (i.e. it is removed from the calculation of net income, for tax purposes, but added back because it did not actually flow out of the firm)

(v) - weighted-average cost of capital

(vi) - the firm's after-tax payment of interest to debtholders (vii) - economic life of the capital project in years

The "incremental" cash flows of a capital project is calculated by using: A. (i), (ii), and (iii)

B. (ii), (iv), and (vi) C. (i), (iii), (v), and (vii) D. (iv), (v), (vi), and (vii)

49. In the context of the capital budgeting analysis of an MNC that has strong foreign competitors, "lost sales" refers to

A. the cannibalization of existing projects by new projects.

B.the entire sales revenue of a new foreign manufacturing facility representing the incremental sales revenue of the new project.

C. both a and b

D. none of the above

50. Which of the following statements is false about "borrowing capacity"? A

.

it is an especially important point in international capital budgeting analysis because of the frequency of large concessionary loans.

B. it creates tax shields for APV analysis regardless of how the project is actually financed. C. is synonymous to the "project debt".

(11)

51. The adjusted present value (APV) model that is suitable for an MNC is the basic net present value (NPV) model expanded to

A. distinguish between the market value of a levered firm and the market value of an unlevered firm. B. discern the blocking of certain cash flows by the host country from being legally remitted to the

parent.

C. consider foreign currency fluctuations or extra taxes imposed by the host country on foreign exchange remittances.

D. all of the above

52. Sensitivity analysis in the calculation of the adjusted present value (APV) allows the financial manager to

A. analyze all of the risks (business, economic, exchange rate uncertainty, political, etc.) inherent in the investment.

B. more fully understand the implications of planned capital expenditures.

C. consider in advance actions that can be taken should an investment not develop as anticipated. D. all of the above

53. The ABC Company, a U.S.-based MNC, plans to establish a subsidiary in Spain to manufacture and sell water pumps. ABC has total assets of $80 million, of which $60 million is equity financed. The remainder is financed with debt. ABC considers its current capital structure optimal. The construction cost of the facility in Spain is estimated to be €8,500 million, of which €6,500 million is to be financed at

a below-market rate of interest arranged by the Spanish government. The proposed project will increase the borrowing capacity by

A. €1,215 million. B. €2,215 million. C. €3,215 million. D. €4,215 million.

54. Given the following information for a levered and unlevered firm, calculate the difference in the cash flow available to investors. Assume the corporate tax rate is 40%.

(Hint: Calculate the tax savings arising form the tax deductibility of interest  payments).

A. $8 B. $18 C. $78 D. $90

55. As of today, the spot exchange rate is €1.00 = $1.25 and the rates of inflation expected to prevail for

the next year in the U.S. is 2% and 3% in the euro zone. What is the one-year forward rate that should prevail?

A. €1.00 = $1.2379 B. €1.00 = $1.2139 C. €1.00 = $0.9903 D. $1.00 = €1.2623

(12)

56. As of today, the spot exchange rate is €1.00 = $1.50 and the rates of inflation expected to prevail for

the next year in the U.S. is 2% and 3% in the euro zone. What is the one-year forward rate that should prevail?

A. €1.00 = $1.5147 B. €1.00 = $1.4854 C. €1.00 = $0.6602 D. $1.00 = €0.6602

57. As of today, the spot exchange rate is €1.00 = $1.25 and the rates of inflation expected to prevail for the

next three years in the U.S. is 2% and 3% in the euro zone. What spot exchange rate should prevail three years from now?

A. €1.00 = $1.2379 B. €1.00 = $1.2139 C. €1.00 = $0.9903 D. $1.00 = €1.2623

58. An Italian firm is considering selling its line of coin-operated cappuccino machines in the U.K. The business risk will be identical to the firm's existing line of business in the euro zone, the cost of capital in the euro zone isi € = 10%. The expected inflation rate over the next two years in the U.K. is 3% per year

and 2% per year in the euro zone. The spot exchange rates are $1.80 = £1.00 and $1.15 = €1.00

The pound sterling denominated cash flows are as follows:

Your firm is based in southern Ireland (and thereby operates in euro, not pounds) and is considering an investment in the United States.

The project involves selling widgets: you project a sales volume of 50,000 widgets per year, sales price of $20 per widget with a contribution margin of $15 per widget.

The project will last for 5 years, require an investment of $1,000,000 at time zero (which will be

depreciated straight-line to $10,000 over the 5 years). Salvage value for the equipment is projected to be $10,000. The project will operate in rented quarters: $300,000 rent is due at the start of each year.

The corporate tax rate is 12½% in Ireland and 40% in the U.S.

For simplicity, assume that taxes are paid like sales taxes: immediately.

The spot exchange rate is $1.50 = €1.00. The cost of capital to the Irish firm for a domestic project of this

risk is 8%. The U.S. risk-free rate is 3%; the Irish risk-free rate is 2%. 59. What is CF0 in dollars?

(13)

60. What is CF1 in dollars?

61. What is CF5 in dollars?

62. What is the NPV of the U.S.-based project to the Irish firm?

63. What is the dollar-denominated IRR?

64. What is the euro-denominated IRR?

(14)

66. Repeat the above project analysis assuming that the Irish firm could replicate the project in Ireland. (i.e. cash flow out the project in Ireland and find break-even price (in €), quantity, NPV, IRR (in euro not

dollars).

Consider the following international investment opportunity. It involves a gold mine that can be opened at a cost, then produces a positive cash flow, but then requires environmental clean-up:

The current exchange rate is $1.60 = €1.00. The inflation rate in the U.S. is 6 percent and in the euro

zone 2 percent. The appropriate cost of capital to a U.S.-based firm for a domestic project of this risk is 8 percent.

67. Find the euro-zone cost of capital to compute is the dollar-denominated NPV of this project.

68. Find the dollar cash flows to compute the dollar-denominated NPV of this project.

Please note that your answer is worth ZERO POINTS if it does not contain currency symbols.

69. What is the dollar-denominated IRR of this project?

(15)

Consider the following international investment opportunity. It involves a gold mine that can be opened at a cost, then produces a positive cash flow, but then requires environmental clean-up:

The current exchange rate is $1.55 = €1.00. The inflation rate in the U.S. is 6 percent and in the euro

zone 2 percent. The appropriate cost of capital to a U.S.-based firm for a domestic project of this risk is 8 percent.

71. Find the euro-zone cost of capital to compute is the dollar-denominated NPV of this project.

72. Find the dollar cash flows to compute the dollar-denominated NPV of this project.

Your answer is worth ZERO POINTS if it does not contain currency symbols such as $, £, €, ¥!

73. What is the dollar-denominated IRR of this project?

74. What is the euro-denominated IRR of this project?

Consider the following international investment opportunity:

The current exchange rate is $1.60 = €1.00. The inflation rate in the U.S. is 3 percent and in the euro

zone 2 percent. The appropriate cost of capital to a U.S.-based firm for a domestic project of this risk is 8 percent.

(16)

75. Find the euro-zone cost of capital to compute is the dollar-denominated NPV of this project.

76. Find the dollar cash flows to compute the dollar-denominated NPV of this project.

77. What is the dollar-denominated IRR of this project?

78. What is the euro-denominated IRR of this project?

A French firm is considering a one-year investment in the United Kingdom with a pound-denominated rate of return ofi£ = 15%. The firm's local cost of capital is i € = 10%

The project costs £1,000 and will return £1,150 at the end of one year. The current exchange rate is €2.00 = £1.00

Suppose that the bank of England is considering either tightening or loosening its monetary policy. It is widely believed that in one year there are only two possibilities:

Following revaluation, the exchange rate is expected to remain steady for at least another year

79. Find the ex post  IRR in euro for the French firm if they undertake the project today and then the exchange rate falls to S1( €|£) = €1.80 per £.

(17)

80. Find the ex post  IRR in euro for the French firm if they undertake the project today and then the exchange rate rises to S1( €|£) = €2.20 per £.

81. Find the IRR in euro for the French firm if they wait one year to undertake the project after the exchange rate rises to S1( €|£) = €2.20 per £.

82. Find the NPV in euro for the French firm if they wait one year to undertake the project after the exchange rate rises to S1( €|£) = €2.20 per £.

83. Find the IRR in euro for the French firm if they wait one year to undertake the project after the exchange rate falls to S1( €|£) = €1.80 per £.

84. Find the NPV in euro for the French firm if they wait one year to undertake the project after the exchange rate falls to S1( €|£) = €1.80 per £.

(18)

85. The CFO who has a CFA notices the optionality in starting this project today. He asks you to comment and outline your valuation strategy.

86. Your banker quotes the euro-zone risk-free rate ati € = 6% and the British risk free rate at i£ = 6%. Find

the value of the option and thereby the project.

87. Using your results to the last question, make a recommendation vis-à-vis when to undertake the project.

88. Using the notion of a hedge ratio, make a recommendation vis-à-vis how to undertake the project today without "buying" the option.

An American Hedge Fund is considering a one-year investment in an Italian government bond with a one-year maturity and a euro-denominated rate of return ofi € = 5%. The bond costs €1,000 today

and will return €1,050 at the end of one year without risk. The current exchange rate is €1.00 = $1.50.

U.S. dollar-denominated government bonds currently have a yield to maturity of 4%. Suppose that the European Central Bank is considering either tightening or loosening its monetary policy. It is widely believed that in one year there are only two possibilities:

(19)

89. Find the ex post  IRR in euro for the American firm if they buy the bond today and then the exchange rate falls to S1($| €) = $1.40 per €.

90. Find the ex post  IRR in euro for the American firm if they buy the bond today and then the exchange rate rises to S1($| €) = $1.80 per €.

91. Find the IRR in dollars for the American firm if they wait one year to buy the bond after the exchange rate rises to S1($| €) = $1.80 per €. Assume thati € doesn't change.

92. Find the NPV in dollars for the American firm if they wait one year to buy the bond after the exchange rate rises to S1($| €) = $1.80 per €. Assume thati € doesn't change.

93. Find the IRR in dollars for the American firm if they wait one year to buy the bond after the exchange rate falls to S1($| €) = $1.40 per €. Assume thati € doesn't change.

(20)

94. Find the NPV in euro for the American firm if they wait one year to undertake the project after the exchange rate falls to S1($| €) = $1.40 per €. Assume that i € doesn't change.

95. The hedge fund manager notices the optionality in starting this project today. He asks you to comment

and outline your valuation strategy.

96. Your banker quotes the euro-zone risk-free rate ati € = 5% and the U.S. risk free rate at i$ = 4%. Find the

value of the option and thereby the correct value of the bond to a U.S. investor.

(21)

98. Using the notion of hedging, make a recommendation vis-à-vis how to undertake the project today without "buying" the option.

The Strik-it-Rich Gold Mining Company is contemplating expanding its operations. To do so it will need to purchase land that its geologists believe is rich in gold. Strik-it-Rich's management believes that the expansion will allow it to mine and sell an additional 2,000 troy ounces of gold per year. The expansion, including the cost of the land, will cost $500,000. The current price of gold bullion is $425 per ounce and one-year gold futures are trading at $450.50 = $425 × (1.06). Extraction costs are $375 per ounce. The firm's cost of capital is 10 percent.

Strik-it-Rich's management is, however, concerned with the possibility that large sales of gold reserves by Russia and the United Kingdom will drive the price of gold down to $390 for the foreseeable future. On the other hand, management believes there is some possibility that the world will soon return to a gold reserve international monetary system. In the latter event, the price of gold would increase to at least $460 per ounce. The course of the future price of gold bullion should become clear within a year. Strik-it-Rich can postpone the expansion for a year by buying a purchase option on the land for $25,000.

99. Compute the NPV at the current price of gold. Hint: think of the gold mine as a perpetuity

100.Compute the NPV at the two possible prices of gold.

101.Estimate the value of the option on the land to the management of the mine.

(22)
(23)

18 Key

1. The financial manager's responsibility involves

A. increasing the per share price of the company's stock at any cost and by any means, ways and fashion that is possible.

B. the shareholder wealth maximization. C. which capital projects to select.

D. both b and c

 Eun - Chapter 18 #1 Topic: Review of Domestic Capital Budgeting

2. Perhaps the most important decisions that confront the financial manager are

A. which capital projects to select.

B. the correct capital structure for the firm. C. the correct capital structure for projects. D. none of the above

 Eun - Chapter 18 #2 Topic: Review of Domestic Capital Budgeting

3. Capital budgeting analysis is very important, because it A. involves, usually expensive, investments in capital assets. B. has to do with the productive capacity of a firm.

C. will determine how competitive and profitable a firm will be.

D. all of the above

 Eun - Chapter 18 #3 Topic: Review of Domestic Capital Budgeting

Tiger Towers, Inc. is considering an expansion of their existing business, student apartments. The new project will be built on some vacant land that the firm has just contracted to buy. The land cost

$1,000,000 and the payment is due today. Construction of a 20-unit office building will cost $3 million; this expense will be depreciated straight-line over 30 years to zero salvage value; the pretax value of the land and building in year 30 will be $18,000,000. The $3,000,000 construction cost is to be paid today. The project will not change the risk level of the firm. The firm will lease 20 offices suites at $20,000 per suite per year; payment is due at the start of the year; occupancy will begin in one year. Variable cost is $3,500 per suite. Fixed costs, excluding depreciation, are $75,000 per year. The project will require a $10,000 investment in net working capital.

 Eun - Chapter 18 

4. What is theunlevered after-tax incremental cash flow for year 0? A.  -$3,660,000

B.  -$5,100,000 C.  -$4,000,000

D. -$4,010,000

E. None of the above

 Eun - Chapter 18 #4 Topic: Review of Domestic Capital Budgeting

5. What is theunlevered after-tax incremental cash flow for year 2? A. -$4,610

B.  $102,300

C. $202,300

D. $255,000

E. None of the above

 Eun - Chapter 18 #5 Topic: Review of Domestic Capital Budgeting

(24)

6. What is theunlevered after-tax incremental cash flow for year 30? A.  $12,432,300

B.  $12,225,390

C. $12,332,300

D.  $12,485,000

E. None of the above

 Eun - Chapter 18 #6  Topic: Review of Domestic Capital Budgeting

Assume that the firm will partially finance the project with a $3,000,000 interest-only 30-year loan at 10.0 percent APR with annual payments.

 Eun - Chapter 18 

7. What is the levered after-tax incremental cash flow for year 0?

A. -$1,010,000

B.  -$1,000,000 C.  -$660,000 D.  -$2,100,000

E. None of the above

 Eun - Chapter 18 #7  Topic: The Adjusted Present Value Model

8. What is the levered after-tax incremental cash flow for year 1?

A. $4,300

B.  -$202,610 C.  -$95,700 D. $57,000

E. None of the above

 Eun - Chapter 18 #8  Topic: The Adjusted Present Value Model

9. What is the levered after-tax incremental cash flow for year 30? A.  $9,027,390

B. $9,234,300

C.  $9,134,300 D.  $9,287,000

E. None of the above

 Eun - Chapter 18 #9 Topic: The Adjusted Present Value Model

10. Assume that the firm will partially finance the project with a subsidized $3,000,000 interest only 30-year loan at8.0 percent APR with annual payments. Note that eight percent is less than the 10 percent

that they normally borrow at. What is the NPV of the loan? A. $198,469

B.  $53,979.83 C.  $102,727.55

D. $1,334,851.09

E. None of the above

 Eun - Chapter 18 #10 Topic: The Adjusted Present Value Model

11. The firm's tax rate is 34%. The firm's pre-tax cost of debt is 8%; the firm's debt-to-equity ratio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is the firm's cost of equity capital?

A. 33.33% B.  10.85% C.  13.12%

D. 16.5%

E. None of the above

 Eun - Chapter 18 #11 Topic: The Adjusted Present Value Model

(25)

12. The firm's tax rate is 34%. The firm's pre-tax cost of debt is 8%; the firm's debt-to-equity ratio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. What is the required return on assets?

A. 33.33%

B. 10.85%

C.  13.12% D. 16.5%

E. None of the above

 Eun - Chapter 18 #12 Topic: The Adjusted Present Value Model

The 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will contribute $20,000 cash and borrow $80,000 at 6% with an interest-only loan with a maturity of 5 years and annual interest payments. The equipment will be depreciated straight-line to zero over the 5-year life of the project. There will be a pre-tax salvage value of $5,000. There are no other

start-up costs at year 0. During years 1 through 5, the firm will sell 25,000 units of product at $5; variable costs are $3; there are no fixed costs.

 Eun - Chapter 18 

13. What is the NPV of the project using the WACC methodology? A.  $49,613.03

B. $58,028.68

C.  $102s,727.55 D.  $315,666.16

E. None of the above

 Eun - Chapter 18 #13 Topic: The Adjusted Present Value Model

14. What is the NPV of the project using the APV methodology? A.  $49,613.03

B.  $198,469 C.  $102,727.55

D. $149,580.12

E. None of the above

 Eun - Chapter 18 #14 Topic: The Adjusted Present Value Model

The 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will

contribute $25,000 cash and borrow $75,000 with an interest-only loan with a maturity of 5 years and annual interest payments. The equipment will be depreciated straight-line to zero over the 5-year life of the project. There will be a pre-tax salvage value of $5,000. There are no other start-up costs at year 0. During years 1 through 5, the firm will sell 25,000 units of product at $5; variable costs are $3; there are no fixed costs.

(26)

15. What is the NPV of the project using the WACC methodology? A.  $58,028.68

B.  $49,613.03

C. $48,300.47

D.  $102,727.55

E. None of the above

Using the cash flow menu of a financial calculator: CF0 = -$100,000; C01 = $39,800; F01 = 4; C02 = $43,100; I =r WACC = 11.20; NPV = $48,300.47

 Eun - Chapter 18 #15 Topic: The Adjusted Present Value Model

16. When using the APV methodology, what is the NPV of the depreciation tax shield? A.  $32,051.52

B. $25,777.35

C.  $22,794.65 D.  $97,152.98

E. None of the above

 Eun - Chapter 18 #16  Topic: The Adjusted Present Value Model

17. When using the APV methodology, what is the NPV of the interest tax shield?

A. $9,666.51

B.  $12,019.32 C.  $9,377.31 D. $7,000.73

E. None of the above

 Eun - Chapter 18 #17  Topic: The Adjusted Present Value Model

18. Today is January 1, 2009. The state of Iowa has offered your firm a subsidized loan. It will be in the amount of $10,000,000 at an interest rate of 5% and have ANNUAL (amortizing) payments over 3 years. The first payment is due today and your taxes are due January 1 of each year on the previous year's income. The yield to maturity on your firm's existing debt is 8%. What is the APV of this subsidized loan? If you rounded in your intermediate steps, the answer may be slightly different from what you got. Choose the closest.

A.  -$3,497,224.43

B. $417,201.05

C.  $840,797

D. None of the above

 Eun - Chapter 18 #18  Topic: The Adjusted Present Value Model

19. Today is January 1, 2009. The state of Iowa has offered your firm a subsidized loan. It will be in the amount of $10,000,000 at an interest rate of 5% and have ANNUAL (amortizing) payments over 3 years. The first payment is due December 31, 2009 and your taxes are due January 1 of each year on the previous year's income. The yield to maturity on your firm's existing debt is 8%. What is the APV of this subsidized loan?

Note that I did not round my intermediate steps. If you did, your answer may be off by a bit. Select the answer closest to yours.

A.  -$3,497,224.43 B.  $417,201.05

C. $840,797

D. None of the above

 Eun - Chapter 18 #19 Topic: The Adjusted Present Value Model

(27)

20. The required return on assets is 18%. The firm can borrow at 12.5%; firm's target debt to value ratio is 3/5. The corporate tax rate is 34%, and the risk-free rate is 4% and the market risk premium is 9.2 percent. What is the weighted average cost of capital?

A. 12.15% B.  13.02%

C. 14.33%

D. 23.45%

E. None of the above

 Eun - Chapter 18 #20 Topic: The Adjusted Present Value Model

21. Your firm is in the 34% tax bracket. The yield to maturity on your existing bonds is 8%. The state of Georgia offers to loan your firm $1,000,000 with a TWO year AMORTIZING loan at a 5% rate of interest and ANNUAL payments due at the END OF THE YEAR.

The interest will be deductible at the time that you pay. What is the APV of this below-market loan to your firm? I did not round any of my intermediate steps. You might be a little bit off. Pick the answer closest to yours.

A. $64,157.38

B.  $417,201.05 C.  $840,797

D. None of the above

 Eun - Chapter 18 #21 Topic: The Adjusted Present Value Model

22. The firm's tax rate is 34%. The firm's pre-tax cost of debt is 8%; the firm's debt-to-equity ratio is 3; the risk-free rate is 3%; the beta of the firm's common stock is 1.5; the market risk premium is 9%. Calculate the weighted average cost of capital.

A. 33.33%

B. 8.09%

C.  9.02% D. 16.5%

E. None of the above

 Eun - Chapter 18 #22 Topic: The Adjusted Present Value Model

Consider a project of the Cornell Haul Moving Company, the timing and size of the incremental after-tax cash flows (for an all-equity firm) are shown below in millions:

The firm's tax rate is 34%; the firm's bonds trade with a yield to maturity of 8%; the current and target debt-equity ratio is 2; if the firm were financed entirely with equity, the required return would be 10%

 Eun - Chapter 18 

23. Using the weighted average cost of capital methodology, what is the NPV? I didn't round my intermediate steps. If you do, you're not going to get the right answer.

A.  -$1,406,301.25 B. $12,494,643.75 C.  $36,580,767.55 D.  $108,994.618.20 E.  $59,459,301.03  Eun - Chapter 18 #23 Topic: The Adjusted Present Value Model

(28)

24. What is the levered after-tax incremental cash flow for year 2? A.  $185,796,000

B. $215,152,000

C.  $267,952,000 D.  $284,848,000 E. None of the above

 Eun - Chapter 18 #24 Topic: The Adjusted Present Value Model

25. What is the levered after-tax incremental cash flow for year 4? A.  $281,704,000

B.  $465,152,000

C. -$194,848,000

D.  $460,796,000 E. None of the above

 Eun - Chapter 18 #25 Topic: The Adjusted Present Value Model

26. Using the flow to equity methodology, what is the value of the equity claim? A.  -$1,540,000 B.  $446,570,866.00 C. $36,580,767.55 D.  $470,953,393.70 E.  $30,716,236.13  Eun - Chapter 18 #26  Topic: The Adjusted Present Value Model

27. Using the APV method, what is the value of this project to an all-equity firm?

A. -$46,502,288.10 B.  $12,494,643.75 C.  $36,580,767.55 D.  -$67,163,445.12 E.  $59,459,301.03  Eun - Chapter 18 #27  Topic: The Adjusted Present Value Model

28. Using the APV method, what is the value of the debt side effects? A.  $239,072,652.70

B.  $66,891,713.66

C. $59,459,301.03

D.  $660,000,000 E. None of the above

 Eun - Chapter 18 #28  Topic: The Adjusted Present Value Model

Consider a project of the Cornell Haul Moving Company, the timing and size of the incremental after-tax cash flows (for an all-equity firm) are shown below in millions:

The firm's tax rate is 34%; the firm's bonds trade with a yield to maturity of 8%; the current and target debt-equity ratio is 3; if the firm were financed entirely with equity, the required return would be 10%

(29)

29. Using the weighted average cost of capital methodology, what is the NPV? I didn't round my intermediate steps. If you do, you're not going to get the right answer.

A. -$1,406,301.25 B.  $12,494,643.75 C.  $36,580,767.55 D.  $108,994.618.20 E.  $59,459,301.03  Eun - Chapter 18 #29 Topic: The Adjusted Present Value Model

30. What is the levered after-tax incremental cash flow for year 2?

A. $185,796,000

B.  $215,152,000 C.  $267,952,000 D.  $284,848,000 E. None of the above

 Eun - Chapter 18 #30 Topic: The Adjusted Present Value Model

31. What is the levered after-tax incremental cash flow for year 4?

A. -$281,704,000

B.  $465,152,000 C.  -$194,848,000 D.  $460,796,000 E. None of the above

 Eun - Chapter 18 #31 Topic: The Adjusted Present Value Model

32. Using the flow to equity methodology, what is the value of the equity claim? A.  -$1,540,000 B.  $446,570,866.00 C.  $36,580,767.55 D.  $470,953,393.70 E. $30,716,236.13  Eun - Chapter 18 #32 Topic: The Adjusted Present Value Model

33. Using the APV method, what is the value of this project to an all-equity firm? A.  -$46,502,288.10 B.  $12,494,643.75 C.  $36,580,767.55 D. -$67,163,445.12 E.  $59,459,301.03  Eun - Chapter 18 #33 Topic: The Adjusted Present Value Model

34. Using the APV method, what is the value of the debt side effects? A.  $239,072,652.70

B. $66,891,713.66

C.  $59,459,301.03 D.  $660,000,000 E. None of the above

 Eun - Chapter 18 #34 Topic: The Adjusted Present Value Model

35. In the APV model

A. interest tax shields are discounted ati.

B. operating cash flows are discounted atK u.

C. depreciation tax shields are discounted ati. D. all of the above

 Eun - Chapter 18 #35 Topic: The Adjusted Present Value Model

(30)

36. Your firm's existing bonds trade with a yield to maturity of eight percent. The state of Missouri has offered to loan your firm $10,000,000 at zero percent for five years. Repayment will be of the form of $2,000,000 per year for five years the first payment is due in one year. What is the value of this offer? A.  $4,729,622.75

B. $2,014,579.93

C. $0

D.  $196,929.88

E. None of the above

 Eun - Chapter 18 #36  Topic: The Adjusted Present Value Model

37. What proportion of the firm is financed by debt for a firm that expects a 15% return on equity, a 12% return on assets, and a 10% return on debt? The tax rate is 25%.

A. 20% B. 1/3 C. 60% D. 2/3 E. 80%  Eun - Chapter 18 #37  Topic: The Adjusted Present Value Model

38. The required return on equity for a levered firm is 10.60%. The debt to equity ratio is ½ the tax rate is 40%, the pre-tax cost of debt is 8%. Find the cost of capital if this firm were financed entirely with equity.

A. 10%

B. 12% C.  8.67%

D. None of the above

 Eun - Chapter 18 #38  Topic: The Adjusted Present Value Model

39. The required return on equity for an all-equity firm is 10.0%. They are considering a change in capital structure to a debt-to-equity ratio of ½ the tax rate is 40%, the pre-tax cost of debt is 8%. Find the new cost of capital if this firm changes capital structure.

A. 14.93%

B. 8.67%

C.  7.40%

D. None of the above

 Eun - Chapter 18 #39 Topic: The Adjusted Present Value Model

40. The required return on equity for an all-equity firm is 10.0%. They currently have a beta of one and the risk-free rate is 5% and the market risk premium is 5%. They are considering a change in capital structure to a debt-to-equity ratio of ½ the tax rate is 40%, the pre-tax cost of debt is 8%. Find the beta if this firm changes capital structure.

A. 1.12

B. 1

C.  7.4%

D. None of the above

 Eun - Chapter 18 #40 Topic: The Adjusted Present Value Model

41. What is the expected return on equity for a tax-free firm with a 15% expected return on assets that pays 12% on its debt, which totals 25% of assets?

A. 24% B.  15.60% C. 16% D. 20% E.  15.75%  Eun - Chapter 18 #41 Topic: The Adjusted Present Value Model

(31)

42. What is the expected return on equity for firm in the 40% tax bracket with a 15% expected return on assets that pays 12% on its debt, which totals 25% of assets?

A. 24% B. 15.60% C. 16% D. 20% E.  15.75%  Eun - Chapter 18 #42 Topic: The Adjusted Present Value Model

43. Assume that XYZ Corporation is a leveraged company with the following information:

Calculate the debt-to-total-market-value ratio that would result in XYZ having a weighted average cost of capital of 9.3%. A. 35% B. 40% C. 45% D. 50%  Eun - Chapter 18 #43 Topic: The Adjusted Present Value Model

44. Today is January 1, 2009. The state of Iowa has offered your firm a subsidized loan. It will be in the amount of $10,000,000 at an interest rate of 5% and have ANNUAL (amortizing) payments over 3 years. The first payment is due today and your taxes are due January 1 of each year on the previous year's income. The yield to maturity on your firm's existing debt is 8%. What is the APV of this subsidized loan? Note that  I did not round my intermediate steps. If  you did, your answer may be off  by a bit. Select the answer closest to yours.

A. $406,023.10

B.  $840,797 C.  $64,157.38 D.  $20,659.77

E. None of the other answers are within $100 of my answer

 Eun - Chapter 18 #44 Topic: The Adjusted Present Value Model

45. What is the €-denominated NPV of this project? I did not round my intermediate steps, if you did, select the answer closest to yours.

A.  €5,563.23

B. €2,270.79 C. €7,223.14 D. €3,554.29

E. There is not enough information (e.g. U.S. inflation) to do this problem.

 Eun - Chapter 18 #45 Topic: Capital Budgeting from the Parent Firms Perspective

(32)

46. The spot exchange rate is ¥125 = $1. The U.S. discount rate is 10%; inflation over the next three years is 3% per year in the U.S. and 2% per year in Japan. Calculate the dollar NPV of this project.

I did not round my intermediate steps, if you did, select the answer closest to yours. A.  $267,181.87

B.  $14,176.67 C.  $2,536.49

D. $2,137.46

E. None of the above

 Eun - Chapter 18 #46  Topic: Capital Budgeting from the Parent Firms Perspective

47. Some of the factors (with selected explanations) used in calculating the basic "net present value" and the "incremental" cash flows of a capital project are:

(i) - expected after-tax terminal value, including recapture of working capital (ii) - net income, which belongs to the equity holders of the firm

(iii) - initial investment at inception

(iv) - depreciation, and the fact that depreciation is a noncash expense (i.e. it is removed from the calculation of net income, for tax purposes, but added back because it did not actually flow out of the firm)

(v) - weighted-average cost of capital

(vi) - the firm's after-tax payment of interest to debtholders (vii) - economic life of the capital project in years

The "net present value" of a capital project is calculated by using: A. (i), (ii), and (iii)

B. (ii), (iv), and (vi)

C. (i), (iii), (v), and (vii)

D. (iv), (v), (vi), and (vii)

 Eun - Chapter 18 #47  Topic: Capital Budgeting from the Parent Firms Perspective

48. Some of the factors (with selected explanations) used in calculating the basic "net present value" and the "incremental" cash flows of a capital project are:

(i) - expected after-tax terminal value, including recapture of working capital (ii) - net income, which belongs to the equity holders of the firm

(iii) - initial investment at inception

(iv) - depreciation, and the fact that depreciation is a noncash expense (i.e. it is removed from the calculation of net income, for tax purposes, but added back because it did not actually flow out of the firm)

(v) - weighted-average cost of capital

(vi) - the firm's after-tax payment of interest to debtholders (vii) - economic life of the capital project in years

The "incremental" cash flows of a capital project is calculated by using: A. (i), (ii), and (iii)

B. (ii), (iv), and (vi)

C. (i), (iii), (v), and (vii) D. (iv), (v), (vi), and (vii)

 Eun - Chapter 18 #48  Topic: Capital Budgeting from the Parent Firms Perspective

(33)

18

18

Student: ___________________________________________________________________________ Student: ___________________________________________________________________________

1.

1. The The finafinanciancial l manamanager'ger's s respresponsionsibilibility ty invoinvolveslves A.

A. increasing the per share price of the company's stock at any cost and by any means, ways and fashionincreasing the per share price of the company's stock at any cost and by any means, ways and fashion that is possible.

that is possible.

B. the shareholder wealth maximization. B. the shareholder wealth maximization. C. which capital projects to select.

C. which capital projects to select. D. both b and c

D. both b and c 2.

2. PerPerhaps thhaps the most ime most importportant decant decisioisions that cns that confronfront thont the finane financial mcial managanager areer are A. which capital projects to select.

A. which capital projects to select.

B. the correct capital structure for the firm. B. the correct capital structure for the firm. C. the correct capital structure for projects. C. the correct capital structure for projects. D. none of the above

D. none of the above 3.

3. CapiCapital tal budgbudgetineting ang analysalysis iis is vers very imy importportant, ant, becabecause use itit

A. involves, usually expensive, investments in capital assets. A. involves, usually expensive, investments in capital assets. B. has to do with the productive capacity of a firm.

B. has to do with the productive capacity of a firm.

C. will determine how competitive and profitable a firm will be. C. will determine how competitive and profitable a firm will be. D. all of the above

D. all of the above

Tiger Towers, Inc. is considering an expansion of their existing business, student apartments. The new Tiger Towers, Inc. is considering an expansion of their existing business, student apartments. The new project will be built on some vacant land that the firm has just contracted to buy. The land cost $1,000,000 project will be built on some vacant land that the firm has just contracted to buy. The land cost $1,000,000 and the payment is due today. Construction of a 20-unit office building will cost $3 million; this expense and the payment is due today. Construction of a 20-unit office building will cost $3 million; this expense will be depreciated straight-line over 30 years to zero salvage value; the pretax value of the land and will be depreciated straight-line over 30 years to zero salvage value; the pretax value of the land and building in year 30 will be $18,000,000. The $3,000,000 construction cost is to be paid today. The project building in year 30 will be $18,000,000. The $3,000,000 construction cost is to be paid today. The project will not change the risk level of the firm. The firm will lease 20 offices suites at $20,000 per suite per will not change the risk level of the firm. The firm will lease 20 offices suites at $20,000 per suite per year; payment is due at the start of the year; occupancy will begin in one year. Variable cost is $3,500 per year; payment is due at the start of the year; occupancy will begin in one year. Variable cost is $3,500 per suite. Fixed costs, excluding depreciation, are $75,000 per year. The project will require a $10,000

suite. Fixed costs, excluding depreciation, are $75,000 per year. The project will require a $10,000 investment in net working capital.

investment in net working capital.

4

4.. WWhhaat t iis s tthhee ununlevered after-tax incremental cash flow for year 0?levered after-tax incremental cash flow for year 0? A. -$3,660,000 A. -$3,660,000 B. -$5,100,000 B. -$5,100,000 C. -$4,000,000 C. -$4,000,000 D. -$4,010,000 D. -$4,010,000

E. None of the above E. None of the above 5

5.. WWhhaat t iis s tthhee ununlevered after-tax incremental cash flow for year 2?levered after-tax incremental cash flow for year 2? A. -$4,610 A. -$4,610 B. $102,300 B. $102,300 C. $202,300 C. $202,300 D. $255,000 D. $255,000

E. None of the above E. None of the above

References

Related documents

The research study was directed at determining an integrated Chicken manure and inorganic fertilizer formulation that ensures: efficient Nitrogen uptake by the maize plant for

In particular, we investigate the usability of the available on-device inertial sensors to make the tracking and mapping process more resilient to rapid motions and to estimate

Stage 2 Child Care, which is available to families on welfare and with stable employment. Families may be eligible for Stage 2 Child Care for up to 24 months after they stop receiving

This paper was organized as the following structure: (a) the intro- duction of the new approach of the real-road simulation, combining the traffic and vehicle simulations; (b)

izbrojim njene krugove, svaka tadka mogla je biti ona podetna, svaki znak pridodat mno5tvu drugih znako- va mogao je biti onaj moj, ali ni5ta ne bi vredelo i da sam

Debido a este éxito, además de hablar de la música y de los artistas en sí, la revista también dará a conocer los lugares donde está presente este estilo en el

Long-term: App user monetization will lead to significantly higher margins and growth rates, likely increasing the valuation levels of myTaste to be more in line with other

multi-study report examined changes and the dose–response relationships between recovery–stress psychological states, training load (TL), heart rate (HR), heart rate recovery (HRR),