Dulles Corridor Metrorail Project

MONTHLY COST AND SCHEDULE UPDATE FOR

PHASE 2 AS OF JULY 31, 2015

(2)

July Expenditures

$

19.2 Million

Total Expenditures

$

508.7 Million

Total Budget

$

2.778 Billion

Total Forecast

$

2.778 Billion

(3)

Phase 2 Contingency Utilization

Total Contingency

$ 551.5 Million

Contingency Utilized through June 2015

$ 46.8 Million

Contingency Utilized in July 2015

$ 1.0 Million

Total Contingency Utilized through July 2015

$ 47.8 Million

(4)

Total Contingency Utilized in July 2015

$ 1.0 Million

• WMATA Open Office Space Build-out - Design $ 0.2 Million • Voice Over Internet Protocol (VOIP) Telephones - Design

and Construction

$ 0.2 Million • Building Automation System Modification - Design $ 0.1 Million • Proposed Contact Rail Heater Controller - Design $ 0.1 Million • Miscellaneous (Items less than 0.1 million) $ 0.4 Million

Phase 2

(5)

Phase 2 Guideway & Stations

Design-Build Activities

Current

• Advancement of Design Packages – 88% Complete • Advancement of Building Permits for Design Packages:

̶ DP018.1 – Reston Town Center Station Foundations (July 17, 2015) ̶ DP019 – Herndon Station (July 23, 2015)

̶ DP022 – Loudoun Gateway station (July 10, 2015)

̶ DP012.2 – Civil West Storm Water Management (July 16, 2015) ̶ DP026.4 – Traction Power Substation #20 (July 8, 2015)

̶ DP026.1 – Te Breaker Station #8 (July 6, 2015)

̶ DP026.3 – Traction Power Substation #19 (July 6, 2015)

̶ DP042 – Reston Town Center Parkway Track Support (August 24, 2015) ̶ 10 Design Change Permit Revisions (July-August 2015)

̶ 25 Design Packages and Changes Issued for Construction (July-August 2015) ̶ 106 Supplier Documents (“Shop Drawings”) Processed (July-August 2015)

(6)

Phase 2 Guideway & Stations

Design-Build Activities

(7)

Phase 2 Guideway & Stations

Design-Build Activities

(8)

Phase 2 Guideway & Stations

Design-Build Activities

Excavation for Dulles Station

(9)

Phase 2 Guideway & Stations

Design-Build Activities

(10)

Phase 2 Guideway & Stations

Design-Build Activities

Innovation Station

(11)

Phase 2 Guideway & Stations

Design-Build Activities

(12)

Phase 2 Guideway & Stations

Design-Build Activities

Aerial Guideway Columns approaching the Future Maintenance Yard

(13)

Phase 2 Guideway & Stations

Design-Build Activities

(14)

Phase 2 Guideway & Stations

Design-Build Activities

Aerial Guideway

(15)

Phase 2 Guideway & Stations

Design-Build Activities

(16)

Phase 2 Guideway & Stations

Design-Build Activities

(17)

Phase 2 Guideway & Stations

Design-Build Activities

Current

• Herndon Station – Hand tunneling for utilities, and installation of 34.5 KV duct bank

• Innovation Center Station – Concrete foundations and directional drilling for sanitary line • Innovation Station segment - DIAAH median (West of Horsepen Run bridge) –

Cast-in-place track wall/retaining wall and storm drainage

• Airport Station – Mass excavation and force main sewer line installation

• Airport Station segment – S1 guideway at entrance to Airport abutment A foundation • Reston Town Center Station segment- DIAAH median work for lane shifts and pits for

utility crossing operations

• Aerial Guideway – Pour drilled shafts, columns, and pier caps (Airport and Yard Leads) • 34.5 KV duct bank and manhole installation along DIAAH and Autopilot

(18)

Phase 2 Guideway & Stations

Design-Build Activities

Current

• Airport Segment/Autopilot Drive – 34.5 KV duct bank installation

• Greenway/Yard Leads Segment – Widening for aerial guideway abutment installation • Centerville Road bridge – Piles installation at the abutments

• Broad Run bridge – Center piers completed, abutment construction to follow Centerville Bridge work

(19)

Phase 2 Guideway & Stations

Design-Build Activities

Upcoming

• Reston Station – Lane Shifts; Utility tunnels under DIAAH and Toll Road

• Herndon Station – Continue Lane Shifts; Small utility tunnels for Storm drainage • Innovation Station – Hand tunnels for utilities and station foundation work

• Dulles Station – Mass excavation

• Aerial Guideway – Pour drilled shafts, columns, and pier caps (on Airport and Yard Leads). Erect precast girders along Autopilot starting with Span 64.

(20)

New Girder Design

• Travel (cable) strands used to strengthen beam for transport have been relocated • Travel strands stress lowered from 44,000 lbs to 25,000 lbs

• Girder rebar relocated closer to outside edge of flange

• MWAA independent engineer, PB/AECOM finite element analysis confirms stress lowered to within allowables

• CRC given green light to resume installing 84” high girders which have the new design details

(21)
(22)

Phase 2

WMATA Rail Yard & Maintenance Facility

Design-Build Activities

Current

• Project wide buildings 60% comments resolution meetings • Early Civil Sitework (IPP #1) Submitted to AHJ for permit

• Final Grading/Utilities/Yard layout design (IPP #2) 90% comments resolution meetings • Construction activities within limits of IPP #0 Permit

(23)

Phase 2

WMATA Rail Yard & Maintenance Facility

Design-Build Activities

Upcoming

• Project wide 90% design submission

• Structures and Long Lead (IPP #3) 100% design submission

(24)

Phase 2

WMATA Rail Yard & Maintenance Facility

Design-Build Activities

(25)

Ronald Reagan Washington National Airport Dulles Corridor Metrorail Project

Washington Dulles International Airport Dulles Toll Road

(26)

Description Budget Total Contract Contract Amount1 Forecast2 Amount Total NTP Substantial

Percent

b c c/b

DULLES CORRIDOR METRORAIL PROJECT - PHASE 2

DESIGN-BUILD Package A 1,193,777,000 1,248,825,459 271,403,594 22% 8-Jul-13 7-Aug-19 DESIGN-BUILD Package B + S 273,280,530 263,570,297 26,540,402 10% 18-Nov-13 29-Jun-18

ROW 58,600,000 58,600,000 4,784,548 8% 8-Jul-13 30-Sep-17

WMATA 305,324,718 305,324,718 45,085,228 15% N/A 3-Feb-20

PRELIMINARY ENGINEERING 75,000,000 75,000,000 71,107,066 95% 15-Jul-09 30-Dec-13 PROJECT MANAGEMENT 320,802,137 323,231,409 89,763,314 28% N/A 2-Jan-19 CONTINGENCY 551,451,179 503,683,681

TOTAL FOR DCMP 2,778,235,564 2,778,235,564 508,684,152

Notes: 1 2

3 Budget Amount includes commodity escalation of $20 million for Package A & B+S. 4 Package A Contract Substantial Completion date changed from 7-Jul-2018 to 7-Aug-2019

Total Forecast includes funded changes. It does not include finance costs.

As of July 31, 2015

Expenditures to Date

(27)

Description Amount in million

($) DULLES CORRIDOR METRORAIL PROJECT - PHASE 2

551.5 $

46.8 $ Expended Contingency in July 2015* $ 1.0 Total Contingency Utilized through July 2015 $ 47.8

Remaining Contingency $ 503.7

WMATA Open Office Space Build-out - Design $ 0.2 Voice Over Internet Protocol (VOIP) Telephones - Design and Construction $ 0.2 Building Automation System Modification - Design $ 0.1 Proposed Contact Rail Heater Controller - Design $ 0.1 Miscellaneous (Items less than 0.1 million) $ 0.4 TOTAL $ 1.0 Total Contingency

Contingency Utilized through June 2015

*See table below for details