Bessant Drive, Kew
Welcome
Thank you for coming today
Today’s event is about the construction delivery for our forthcoming
development of high-quality homes and GP surgery off
Bessant Drive, Kew.
This is your chance to find out more about the various phases of
construction, our projected development timetable and the steps
we are taking to keep disruption to our neighbours to a minimum.
We are also here to listen to your views and comments and to answer any
Key Facts
170 new homes including 27 affordable homes.
188 secure basement parking spaces for residents and visitors.
Space for an 896 sq m doctor’s surgery.
Extensive new landscaped amenity areas and central
courtyard space.
About our development
www.taylorwimpey.co.uk/bessant-drive
Our proposals for
Bessant Drive, Kew
With extensive involvement from the community, our designs
have been developed to maximise the amount of air and light
throughout the project. The new buildings will be set amongst
extensive green surroundings, with a landscaped courtyard at
the centre for community use, a new gateway entrance from
Bessant Drive will be provided along with a wider redesigned
boundary to Strand Drive, creating an open, green street,
opposite the existing river frontage buildings.
Strand Drive street elevation
Proposed master plan
Bessant Drive, Kew
Estimated construction milestones
Build Stage
Frame erection
Start
Finish
November – 2015
March – 2017
Piling and excavating
Building envelope
August – 2015
December – 2015
July – 2016
September – 2017
About our development
www.taylorwimpey.co.uk/bessant-drive
Groundworks and
frame construction
(1 of 5)
Week 1
• Site set up.
• Site clearance.
• Prepare piling mat for perimeter sheet piling.
Week 7
• Sheet piling almost complete.
• Capping beam progressing.
• Bulk excavation commences.
About our development
www.taylorwimpey.co.uk/bessant-drive
Groundworks and
frame construction
(2 of 5)
Week 13
• Bulk excavation almost complete.
• Piling mat and piling continuing.
• TC 2 base complete.
Week 19
• Piling complete.
• Pile caps and core pile caps complete to Blocks A and B.
• Underslab drainage continuing.
• TC 1 and TC 2 operational.
• Substation complete.
About our development
www.taylorwimpey.co.uk/bessant-drive
Groundworks and
frame construction
(3 of 5)
Week 25
• Pile caps almost complete.
• Basement slab complete to Blocks A and B.
• Columns, walls and ground floor decking to Block A.
• Basement ramp relocated.
Week 31
• Basement slab almost complete.
• Ground floor slab progressing to Block C.
• Block A – 1st floor slab underway.
About our development
www.taylorwimpey.co.uk/bessant-drive
Groundworks and
frame construction
(4 of 5)
Week 39
• Central podium almost complete.
• Block D – Ground Floor slab complete.
• Block A – 3rd Floor slab complete.
• Block B – 2nd Floor slab progressing.
Week 45
• Block A – complete.
• Block B – 4th Floor complete.
• Block C – 2nd Floor complete.
• Block D – columns and walls from Ground to 1st Floor underway.
• Permavoid drainage layer progressing.
About our development
www.taylorwimpey.co.uk/bessant-drive
Groundworks and
frame construction
(5 of 5)
Week 51
• Blocks A, B and C complete.
• Block D – 2nd Floor complete.
• Block D – columns, walls and slab to 3rd Floor progressing.
• Podium permavoid and tarmac protection progressing.
Week 60
Key Facts
Noise, dust and vibration monitors are already in place at the
Bessant Drive site and will remain in place throughout groundworks
and frame construction.
Works on site restricted to 8am-6pm, Monday to Friday,
and 8am-1pm on Saturdays.
The monitors are located closer to the works than is recommended
by the EHO – so our measures to restrict noise, dust and vibration
are more stringent.
Continuous flight auger (CFA) and hydraulic pressed-in sheet piling
will be used as opposed to a driven system.
Dust to be suppressed by covering skips and loads. Water
suppressants to be used during site activities.
Piling and excavation will take place in the second half of 2015.
About our development
www.taylorwimpey.co.uk/bessant-drive
Steps we are taking
to limit disruption
Noise, dust and vibration monitoring
We contacted the Environmental Health Officer (EHO) and requested he attend
site to discuss the options available to the development to help reduce
the impact of noise, dust and vibration on our neighbours. Further to these
discussions we decided to provide three types of monitors. Instead of placing
them at our neighbours boundaries we have positioned them within the site
closer to the source. By doing this, we are placing more stringent measures
on our site contractors than the recommendations of the EHO.
In the unlikely event that monitors are triggered at any time, we will receive
an alert. We will then contact the site contractor requesting confirmation of what
set off the alert and ask that they change the way in which they are working to
alleviate the problem.
Dust will be mitigated by the following measures:
• Covering skips when not in use
• All loads leaving site to be covered
• Water dust suppressant to be used during site activities
• Cutting equipment to use water suppressant
Noise and vibration will be mitigated by the following measures:
• Works on site will not be carried out outside the hours 8am–6pm,
Monday to Friday (excluding bank holidays)
• Works on site will not be carried out outside the hours 8am–1pm on Saturdays
and this will be avoided
where possible.
• Hand-held and portable equipment will be electrically powered
where practicable
• Activities producing significant noise levels will be carried out at times
which are less likely to cause disturbance where possible
• Utilising alternative piling methods
Piling
The standard most cost-effective form of piling within our industry is driven,
however this form of construction can create elevated levels of noise,
dust, and vibration. Given the concern within the local community over noise,
dust and vibration we have changed our method for carrying out these works.
Instead we shall now be piling using Continuous Flight Auger (CFA) piling and
hydraulic pressed-in sheet piling methods.
The pressed-in sheet piling method will be undertaken first. This piling method
involves a rig hydraulically pressing steel sheets into the ground, with water jetting
used to get past hard spots to reduce vibration and noise. See below pictures of
the two methods of construction.
A capping beam will follow the sheet piles. During this time bulk excavation
will start, programmed for circa 30-40 loads a day to be removed from site.
The CFA piling method will follow this, and will involve a rig drilling into
the ground and pumping concrete into the ground as the drill retracts.
The piling and excavation process is scheduled to take place throughout the
second half of 2015. Movement of heavy equipment on and off site will be
undertaken under police escort. You will be notified of these movements by
letter in advance.
Key Facts
The rate of surface water run-off from the old Inland Revenue site
was 96.4 litres per second for the 1 in 1 year storm.
Through use of a storage tank and permeable paving, the actual
run-off rate for the new development will be only 5 litres
per second.
We are required to halve this to 48.2 litres per second by the
London Plan.
The storage capacity for water run-off is 448,000 litres of water.
About our development
www.taylorwimpey.co.uk/bessant-drive
Drainage and
flood prevention
4.5 4.5 6.4 5.6 5.6 3.349 2.059 5.947 1.712 1.822 2.958 2.911 7.486 3 2 4 5 9 1 BESSANT DRIVE STRAND DRIVE K R A P E DI S R E VI R W E KKEW RIVERSIDE PARK
KEW RETAIL PARK
CAR PARK CAR PARK CAR PARK 100 CONCRETE SLAB 3.75 4.23 4.15 3.93 3.45 3.27 3.16 3.04 3.06 3.20 CL: 4.310 IL: 1.680 CL: 4.520 IL: 2.256 FW & SW fixed to inside of vent wall
3 2 4 5 1 Existing SW pump station to be replaced with new package pump discharging at 5l/s. CL: 4.520 IL: 3.520 CL: 4.260 IL: 2.210 31: 1 1:13
Expansion Joint - For details see ground floor G.A Outlet - 2l/s orifice plate
See drawing C82887-D-010
Outlet - 2l/s orifice plate see drawing S82887-D-010 150mm Upstand
150mm Upstand
150mm Upstand
Marshalls Mono Slot Drain
Sheet pile retaining wall zone
Vent Well
For sheet pile line - See foundation drawing Vent Well
Vent Well
Vent Well
Vent Well Outlet to podium storage
from under ground pump with access cover
For Ramp Details See D-007
5.910
5.910
5.910
5.910
5.910
5.910
5.910
4.780
5.910
Suspended drainage shown is indicative. For details see Vector drawings. Foul rising main frombasement.
Existing foul outfall to be abandoned
D
Tender
A 19/12/14 Issued for Information. JP CGC B 15/01/15 Updated following latest comments. JP CGC C 20/01/15 Updated following latest comments. JP CGC D 23/01/15 Amended following Tech Check. Issued forTender. CGC .
Drawing No. Job
Title Client Status
Rev. Date Amendment By Chk.
QA Ref: QD0190 Rev B
Rev.
Health and Safety Note:
The details on this drawing have been prepared on the assumption that a competent contractor will be carrying out the works. If the contractor(s) considers that there is insufficient Health and Safety information on this drawing, this should immediately be brought to the attention of the designer.
Notes:-1. Where this drawing has been issued in electronic .dwg format it has been done so in good faith. jnpgroup do not take any responsibility for any inaccuracies in the electronic data, which should be checked against the paper (or .pdf) drawing issue. Any apparent discrepancies should be immediately reported to jnpgroup. The electronic .dwg file should not be assumed to be to scale and should not be used for 'overlaying', setting out or checking of any third party information. All dimensions should be taken from the paper (or .pdf) version of the drawing. Electronic drawings may contain third party information. jnpgroup take no responsibility for this information, which should be checked against the originators paper drawing(s).
2. All working dimensions to be checked on site. 3. Do not scale.
4. Any discrepancies between drawings of different scales, and between drawings and specification where appropriate to be notified to The Engineer for decision.
5. Copyright reserved. This drawing may only be used for The Client and location specified in the title block. It may not be copied or disclosed to any third party without the prior written consent of jnpgroup.
6. This drawing should only be used for construction if the drawing status is "Construction". jnpgroup take no responsibility for construction works undertaken to drawings which are not marked with this status.
C82887-D-002
Tech. Check Eng. Check Drawn By Date Scale @ A1Taylor Wimpey West London
Bessant Drive
Kew
Job No. 20657
Private Drainage
Ground Floor
JP November 2014 CGC 1:250HAZARD IDENTIFICATION BOX This table is provided to assist the Principal Contractor to
fulfil their obligations under the CDM Regulations 2007 Construction Hazard Cleaning HazardMaintenance / Demolition / AdaptionHazard
jnpgroup
New foul water drain, 100Ø PVC-U pipework laid at 1:100 UNO.
New Type 4 foul inspection chamber 225 mm Ø polypropylene or vitrified clay up to 600 mm deep. New Type 3 foul inspection chamber 450 mm Ø polypropylene up to 3000 mm deep (non man access).
New internal foul outlet. SVP
Existing foul water sewer. (Dimensions are approx. internal sizes).
Surface Water Drainage Legend
RWP
RE
(Dimensions are approx. internal sizes).
Foul Water Drainage Legend
Existing surface water sewer. New surface water drain, 100Ø PVC-U pipework laid at 1:100 UNO.
New Type 3 surface water inspection chamber. 450 mm dia polypropylene up to 3000 mm deep (non man access for depths greater than 1.2m) New SW rodding eye
New rain water pipe Marshalls Mono Slot Drain New Yard Gully New Highway Gully New Linear Theshold Drain Orifice Plate
150mm Permavoid Attenuation System New Type 4 foul inspection chamber 225 mm Ø polypropylene or vitrified clay up to 600 mm deep.
Note:
Pipes laid at 1:100 unless otherwise noted New S106 surface water sewer.
New S106 foul water sewer.
SW Ground Floor Manhole Schedule
MH Ref Cover Level Invert Level Depth Diameter/Type Cover Classification SWMH14 4.260m 2.210m 2.050m 1200mm/Type 3 Standard SWMH15 4.520m 3.520m 1.000m 1200mm/Type E Standard FW Ground Floor Manhole Schedule
MH Ref Cover Level Invert Level Depth Diameter/Type Cover Classification FWMH10 4.310m 1.680m 2.630m 1200mm/Type 3 Standard FWMH11 4.520m 2.256m 2.264m 1200mm/Type B Standard FWMH12 3.750m 3.366m 0.384m PPIC Standard
Preliminary design for SUDS
In its former use as an Inland Revenue
building, 60% of the Bessant Drive site was
impermeable to surface water run-off.
The rate of surface water discharge to the
local drainage network was calculated as
follows for the former Inland Revenue site:
• 1 in 1 year storm – 96.4 litres per second (l/s)
• 1 in 30 year storm – 227.6 l/s
• 1 in 100 year storm – 288.8 l/s
The London Plan asks that our development
reduces the rate of surface water discharge
to 50% of the rate of the site’s previous use
for the 1 in 1 year storm event. This works
out to 48.2 litres per second.
The area highlighted blue in the image
shown is the storage area on our podium
which will be created for surface water
run-off. This area will be covered by
permeable paving allowing the water from
our roofs and landing on the podium to
absorb through to these storage tanks.
The surface water from the storage tanks
then discharges to the local drainage
network at a rate of 5 litres per second. By building to these proposals we are exceeding
the requirements of the London Plan by 43.2 litres per second, significantly reducing the
impact on the surrounding area from the previous site use.
About our development
www.taylorwimpey.co.uk/bessant-drive
Transport
and access
Construction management plan
Construction traffic will enter from
Bessant Drive and the A205. All supplies
and contractors will be briefed with the
construction logistics plan prior to arriving
on site.
The plan depicts no access to Strand
Drive or beyond the new location of
the gates to The National Archives
once relocated.
A jet wash will be operated on site to
reduce the amount of mud dropped on
the public highways, along with a road
sweeper during the groundworks and
frame erection on Bessant Drive.
Waste from site will be segregated and
recycled as appropriate in line with our
site waste management plan.
Key Facts
Construction traffic will access the site from Bessant Drive
and the A205.
A road sweeper will be in operation on Bessant Drive during
groundworks and frame erection.
No access to Strand Drive or beyond the new location of the
About our development
www.taylorwimpey.co.uk/bessant-drive
Transport
and access
Transport package
We have prepared a package of transport proposals as part of our scheme
which takes into account the feedback we received from the local community
during previous public consultations.
This includes:
• Car parking provided to meet maximum standard plus visitor parking.
• A drop-off facility for the proposed GP surgery alongside parking within
the basement for appointments.
• Provision of a dedicated space for a car club vehicle.
• Moving the keep clear sign on the Bessant Drive/Retail Park Access T-junction.
This will minimise ‘blocking back’ occurring, making it easier for vehicles to exit
Bessant Drive (from Strand Drive) onto the first section of Bessant Drive, which
connects to Mortlake Road.
• Extension of the northbound right turn lane towards the Mortlake Road/
Bessant Drive signal junction. The right turn lane back from the signal junction
will be extended from 50m to 150m. The purpose of the longer lane is to allow
traffic to exit out of any queuing traffic along Mortlake Road at an earlier point,
to turn right into West Park Avenue and Bessant Drive. This will also benefit
bus service R68 which can be delayed by traffic travelling northbound along
Mortlake Road.
• A Travel Plan to survey, monitor and encourage residents and staff at the
GP surgery (if staff levels are greater than 20) to travel by more sustainable
means, by the implementation of measures such as: provision of information
on travel choices, events to raise awareness of the choice and health benefits,
car clubs, etc.
• Agreed developer contributions to the London Borough of Richmond upon
Thames for sustainable access improvements.
Reconfigure white lining to create extended
right turn lane toward signal junction
Relocate keep clear markings to a
more suitable location
© P e t e r B r e t t A s s o c i a t e s L L P w w w . p e t e r b r e t t . c o m Offices throughout the UK & Europe
R E A DI N G T el : 0 11 8 9 5 0 0 7 61
Chkd by Drawing Issue Status
Date of Dwn by Drawing Number Revision
Drawn
Mark Revision Date Chkd
File Location: j:\29488 bessant drive, kew\transport\drawings, gis, photos and video\cad\dwgs\29488-002-004a.dwg UTILITIES NOTE: The position of any existing public or private sewers, utility services, plant or apparatus shown on this drawing is believed to be correct, but no warranty to this is expressed or implied. Other such plant or apparatus may also be present but not shown. The Contractor is therefore advised to undertake his own investigation where the presence of any existing sewers, services, plant or apparatus may affect his operations.
SCALING NOTE: Do not scale from this drawing. If in doubt, ask.
Reproduced from/based upon Ordnance Survey material with the permission of Ordnance Survey ®
on behalf of The Controller of Her Majesty's Stationery Office. ©Crown Copyright.
Unauthorised reproduction infringes Crown Copyright and may lead to prosecution or civil proceedings. Licence No. Year of Publication Owner/Purchaser of Mapping
user name: dale harvey
1st Issue Client
Former Inland Revenue Site,
Bessant Drive, Kew
Proposed Highway Improvements
F O R P L A N N I N G
29488-002-004
A
21-03-14 1:1000 DH SMA Yellow Box Removed DH 01/10/14 SM
PBA
100021575 2014 A4 Scale