• No results found

Thank you for coming today

N/A
N/A
Protected

Academic year: 2021

Share "Thank you for coming today"

Copied!
12
0
0

Loading.... (view fulltext now)

Full text

(1)

Bessant Drive, Kew

Welcome

Thank you for coming today

Today’s event is about the construction delivery for our forthcoming

development of high-quality homes and GP surgery off

Bessant Drive, Kew.

This is your chance to find out more about the various phases of

construction, our projected development timetable and the steps

we are taking to keep disruption to our neighbours to a minimum.

We are also here to listen to your views and comments and to answer any

(2)

Key Facts

170 new homes including 27 affordable homes.

188 secure basement parking spaces for residents and visitors.

Space for an 896 sq m doctor’s surgery.

Extensive new landscaped amenity areas and central

courtyard space.

About our development

www.taylorwimpey.co.uk/bessant-drive

Our proposals for

Bessant Drive, Kew

With extensive involvement from the community, our designs

have been developed to maximise the amount of air and light

throughout the project. The new buildings will be set amongst

extensive green surroundings, with a landscaped courtyard at

the centre for community use, a new gateway entrance from

Bessant Drive will be provided along with a wider redesigned

boundary to Strand Drive, creating an open, green street,

opposite the existing river frontage buildings.

Strand Drive street elevation

Proposed master plan

(3)

Bessant Drive, Kew

Estimated construction milestones

Build Stage

Frame erection

Start

Finish

November – 2015

March – 2017

Piling and excavating

Building envelope

August – 2015

December – 2015

July – 2016

September – 2017

(4)

About our development

www.taylorwimpey.co.uk/bessant-drive

Groundworks and

frame construction

(1 of 5)

Week 1

• Site set up.

• Site clearance.

• Prepare piling mat for perimeter sheet piling.

Week 7

• Sheet piling almost complete.

• Capping beam progressing.

• Bulk excavation commences.

(5)

About our development

www.taylorwimpey.co.uk/bessant-drive

Groundworks and

frame construction

(2 of 5)

Week 13

• Bulk excavation almost complete.

• Piling mat and piling continuing.

• TC 2 base complete.

Week 19

• Piling complete.

• Pile caps and core pile caps complete to Blocks A and B.

• Underslab drainage continuing.

• TC 1 and TC 2 operational.

• Substation complete.

(6)

About our development

www.taylorwimpey.co.uk/bessant-drive

Groundworks and

frame construction

(3 of 5)

Week 25

• Pile caps almost complete.

• Basement slab complete to Blocks A and B.

• Columns, walls and ground floor decking to Block A.

• Basement ramp relocated.

Week 31

• Basement slab almost complete.

• Ground floor slab progressing to Block C.

• Block A – 1st floor slab underway.

(7)

About our development

www.taylorwimpey.co.uk/bessant-drive

Groundworks and

frame construction

(4 of 5)

Week 39

• Central podium almost complete.

• Block D – Ground Floor slab complete.

• Block A – 3rd Floor slab complete.

• Block B – 2nd Floor slab progressing.

Week 45

• Block A – complete.

• Block B – 4th Floor complete.

• Block C – 2nd Floor complete.

• Block D – columns and walls from Ground to 1st Floor underway.

• Permavoid drainage layer progressing.

(8)

About our development

www.taylorwimpey.co.uk/bessant-drive

Groundworks and

frame construction

(5 of 5)

Week 51

• Blocks A, B and C complete.

• Block D – 2nd Floor complete.

• Block D – columns, walls and slab to 3rd Floor progressing.

• Podium permavoid and tarmac protection progressing.

Week 60

(9)

Key Facts

Noise, dust and vibration monitors are already in place at the

Bessant Drive site and will remain in place throughout groundworks

and frame construction.

Works on site restricted to 8am-6pm, Monday to Friday,

and 8am-1pm on Saturdays.

The monitors are located closer to the works than is recommended

by the EHO – so our measures to restrict noise, dust and vibration

are more stringent.

Continuous flight auger (CFA) and hydraulic pressed-in sheet piling

will be used as opposed to a driven system.

Dust to be suppressed by covering skips and loads. Water

suppressants to be used during site activities.

Piling and excavation will take place in the second half of 2015.

About our development

www.taylorwimpey.co.uk/bessant-drive

Steps we are taking

to limit disruption

Noise, dust and vibration monitoring

We contacted the Environmental Health Officer (EHO) and requested he attend

site to discuss the options available to the development to help reduce

the impact of noise, dust and vibration on our neighbours. Further to these

discussions we decided to provide three types of monitors. Instead of placing

them at our neighbours boundaries we have positioned them within the site

closer to the source. By doing this, we are placing more stringent measures

on our site contractors than the recommendations of the EHO.

In the unlikely event that monitors are triggered at any time, we will receive

an alert. We will then contact the site contractor requesting confirmation of what

set off the alert and ask that they change the way in which they are working to

alleviate the problem.

Dust will be mitigated by the following measures:

• Covering skips when not in use

• All loads leaving site to be covered

• Water dust suppressant to be used during site activities

• Cutting equipment to use water suppressant

Noise and vibration will be mitigated by the following measures:

• Works on site will not be carried out outside the hours 8am–6pm,

Monday to Friday (excluding bank holidays)

• Works on site will not be carried out outside the hours 8am–1pm on Saturdays

and this will be avoided

where possible.

• Hand-held and portable equipment will be electrically powered

where practicable

• Activities producing significant noise levels will be carried out at times

which are less likely to cause disturbance where possible

• Utilising alternative piling methods

Piling

The standard most cost-effective form of piling within our industry is driven,

however this form of construction can create elevated levels of noise,

dust, and vibration. Given the concern within the local community over noise,

dust and vibration we have changed our method for carrying out these works.

Instead we shall now be piling using Continuous Flight Auger (CFA) piling and

hydraulic pressed-in sheet piling methods.

The pressed-in sheet piling method will be undertaken first. This piling method

involves a rig hydraulically pressing steel sheets into the ground, with water jetting

used to get past hard spots to reduce vibration and noise. See below pictures of

the two methods of construction.

A capping beam will follow the sheet piles. During this time bulk excavation

will start, programmed for circa 30-40 loads a day to be removed from site.

The CFA piling method will follow this, and will involve a rig drilling into

the ground and pumping concrete into the ground as the drill retracts.

The piling and excavation process is scheduled to take place throughout the

second half of 2015. Movement of heavy equipment on and off site will be

undertaken under police escort. You will be notified of these movements by

letter in advance.

(10)

Key Facts

The rate of surface water run-off from the old Inland Revenue site

was 96.4 litres per second for the 1 in 1 year storm.

Through use of a storage tank and permeable paving, the actual

run-off rate for the new development will be only 5 litres

per second.

We are required to halve this to 48.2 litres per second by the

London Plan.

The storage capacity for water run-off is 448,000 litres of water.

About our development

www.taylorwimpey.co.uk/bessant-drive

Drainage and

flood prevention

4.5 4.5 6.4 5.6 5.6 3.349 2.059 5.947 1.712 1.822 2.958 2.911 7.486 3 2 4 5 9 1 BESSANT DRIVE STRAND DRIVE K R A P E DI S R E VI R W E K

KEW RIVERSIDE PARK

KEW RETAIL PARK

CAR PARK CAR PARK CAR PARK 100 CONCRETE SLAB 3.75 4.23 4.15 3.93 3.45 3.27 3.16 3.04 3.06 3.20 CL: 4.310 IL: 1.680 CL: 4.520 IL: 2.256 FW & SW fixed to inside of vent wall

3 2 4 5 1 Existing SW pump station to be replaced with new package pump discharging at 5l/s. CL: 4.520 IL: 3.520 CL: 4.260 IL: 2.210 31: 1 1:13

Expansion Joint - For details see ground floor G.A Outlet - 2l/s orifice plate

See drawing C82887-D-010

Outlet - 2l/s orifice plate see drawing S82887-D-010 150mm Upstand

150mm Upstand

150mm Upstand

Marshalls Mono Slot Drain

Sheet pile retaining wall zone

Vent Well

For sheet pile line - See foundation drawing Vent Well

Vent Well

Vent Well

Vent Well Outlet to podium storage

from under ground pump with access cover

For Ramp Details See D-007

5.910

5.910

5.910

5.910

5.910

5.910

5.910

4.780

5.910

Suspended drainage shown is indicative. For details see Vector drawings. Foul rising main from

basement.

Existing foul outfall to be abandoned

D

Tender

A 19/12/14 Issued for Information. JP CGC B 15/01/15 Updated following latest comments. JP CGC C 20/01/15 Updated following latest comments. JP CGC D 23/01/15 Amended following Tech Check. Issued forTender. CGC .

Drawing No. Job

Title Client Status

Rev. Date Amendment By Chk.

QA Ref: QD0190 Rev B

Rev.

Health and Safety Note:

The details on this drawing have been prepared on the assumption that a competent contractor will be carrying out the works. If the contractor(s) considers that there is insufficient Health and Safety information on this drawing, this should immediately be brought to the attention of the designer.

Notes:-1. Where this drawing has been issued in electronic .dwg format it has been done so in good faith. jnpgroup do not take any responsibility for any inaccuracies in the electronic data, which should be checked against the paper (or .pdf) drawing issue. Any apparent discrepancies should be immediately reported to jnpgroup. The electronic .dwg file should not be assumed to be to scale and should not be used for 'overlaying', setting out or checking of any third party information. All dimensions should be taken from the paper (or .pdf) version of the drawing. Electronic drawings may contain third party information. jnpgroup take no responsibility for this information, which should be checked against the originators paper drawing(s).

2. All working dimensions to be checked on site. 3. Do not scale.

4. Any discrepancies between drawings of different scales, and between drawings and specification where appropriate to be notified to The Engineer for decision.

5. Copyright reserved. This drawing may only be used for The Client and location specified in the title block. It may not be copied or disclosed to any third party without the prior written consent of jnpgroup.

6. This drawing should only be used for construction if the drawing status is "Construction". jnpgroup take no responsibility for construction works undertaken to drawings which are not marked with this status.

C82887-D-002

Tech. Check Eng. Check Drawn By Date Scale @ A1

Taylor Wimpey West London

Bessant Drive

Kew

Job No. 20657

Private Drainage

Ground Floor

JP November 2014 CGC 1:250

HAZARD IDENTIFICATION BOX This table is provided to assist the Principal Contractor to

fulfil their obligations under the CDM Regulations 2007 Construction Hazard Cleaning HazardMaintenance / Demolition / AdaptionHazard

jnpgroup

New foul water drain, 100Ø PVC-U pipework laid at 1:100 UNO.

New Type 4 foul inspection chamber 225 mm Ø polypropylene or vitrified clay up to 600 mm deep. New Type 3 foul inspection chamber 450 mm Ø polypropylene up to 3000 mm deep (non man access).

New internal foul outlet. SVP

Existing foul water sewer. (Dimensions are approx. internal sizes).

Surface Water Drainage Legend

RWP

RE

(Dimensions are approx. internal sizes).

Foul Water Drainage Legend

Existing surface water sewer. New surface water drain, 100Ø PVC-U pipework laid at 1:100 UNO.

New Type 3 surface water inspection chamber. 450 mm dia polypropylene up to 3000 mm deep (non man access for depths greater than 1.2m) New SW rodding eye

New rain water pipe Marshalls Mono Slot Drain New Yard Gully New Highway Gully New Linear Theshold Drain Orifice Plate

150mm Permavoid Attenuation System New Type 4 foul inspection chamber 225 mm Ø polypropylene or vitrified clay up to 600 mm deep.

Note:

Pipes laid at 1:100 unless otherwise noted New S106 surface water sewer.

New S106 foul water sewer.

SW Ground Floor Manhole Schedule

MH Ref Cover Level Invert Level Depth Diameter/Type Cover Classification SWMH14 4.260m 2.210m 2.050m 1200mm/Type 3 Standard SWMH15 4.520m 3.520m 1.000m 1200mm/Type E Standard FW Ground Floor Manhole Schedule

MH Ref Cover Level Invert Level Depth Diameter/Type Cover Classification FWMH10 4.310m 1.680m 2.630m 1200mm/Type 3 Standard FWMH11 4.520m 2.256m 2.264m 1200mm/Type B Standard FWMH12 3.750m 3.366m 0.384m PPIC Standard

Preliminary design for SUDS

In its former use as an Inland Revenue

building, 60% of the Bessant Drive site was

impermeable to surface water run-off.

The rate of surface water discharge to the

local drainage network was calculated as

follows for the former Inland Revenue site:

• 1 in 1 year storm – 96.4 litres per second (l/s)

• 1 in 30 year storm – 227.6 l/s

• 1 in 100 year storm – 288.8 l/s

The London Plan asks that our development

reduces the rate of surface water discharge

to 50% of the rate of the site’s previous use

for the 1 in 1 year storm event. This works

out to 48.2 litres per second.

The area highlighted blue in the image

shown is the storage area on our podium

which will be created for surface water

run-off. This area will be covered by

permeable paving allowing the water from

our roofs and landing on the podium to

absorb through to these storage tanks.

The surface water from the storage tanks

then discharges to the local drainage

network at a rate of 5 litres per second. By building to these proposals we are exceeding

the requirements of the London Plan by 43.2 litres per second, significantly reducing the

impact on the surrounding area from the previous site use.

(11)

About our development

www.taylorwimpey.co.uk/bessant-drive

Transport

and access

Construction management plan

Construction traffic will enter from

Bessant Drive and the A205. All supplies

and contractors will be briefed with the

construction logistics plan prior to arriving

on site.

The plan depicts no access to Strand

Drive or beyond the new location of

the gates to The National Archives

once relocated.

A jet wash will be operated on site to

reduce the amount of mud dropped on

the public highways, along with a road

sweeper during the groundworks and

frame erection on Bessant Drive.

Waste from site will be segregated and

recycled as appropriate in line with our

site waste management plan.

Key Facts

Construction traffic will access the site from Bessant Drive

and the A205.

A road sweeper will be in operation on Bessant Drive during

groundworks and frame erection.

No access to Strand Drive or beyond the new location of the

(12)

About our development

www.taylorwimpey.co.uk/bessant-drive

Transport

and access

Transport package

We have prepared a package of transport proposals as part of our scheme

which takes into account the feedback we received from the local community

during previous public consultations.

This includes:

• Car parking provided to meet maximum standard plus visitor parking.

• A drop-off facility for the proposed GP surgery alongside parking within

the basement for appointments.

• Provision of a dedicated space for a car club vehicle.

• Moving the keep clear sign on the Bessant Drive/Retail Park Access T-junction.

This will minimise ‘blocking back’ occurring, making it easier for vehicles to exit

Bessant Drive (from Strand Drive) onto the first section of Bessant Drive, which

connects to Mortlake Road.

• Extension of the northbound right turn lane towards the Mortlake Road/

Bessant Drive signal junction. The right turn lane back from the signal junction

will be extended from 50m to 150m. The purpose of the longer lane is to allow

traffic to exit out of any queuing traffic along Mortlake Road at an earlier point,

to turn right into West Park Avenue and Bessant Drive. This will also benefit

bus service R68 which can be delayed by traffic travelling northbound along

Mortlake Road.

• A Travel Plan to survey, monitor and encourage residents and staff at the

GP surgery (if staff levels are greater than 20) to travel by more sustainable

means, by the implementation of measures such as: provision of information

on travel choices, events to raise awareness of the choice and health benefits,

car clubs, etc.

• Agreed developer contributions to the London Borough of Richmond upon

Thames for sustainable access improvements.

Reconfigure white lining to create extended

right turn lane toward signal junction

Relocate keep clear markings to a

more suitable location

© P e t e r B r e t t A s s o c i a t e s L L P w w w . p e t e r b r e t t . c o m Offices throughout the UK & Europe

R E A DI N G T el : 0 11 8 9 5 0 0 7 61

Chkd by Drawing Issue Status

Date of Dwn by Drawing Number Revision

Drawn

Mark Revision Date Chkd

File Location: j:\29488 bessant drive, kew\transport\drawings, gis, photos and video\cad\dwgs\29488-002-004a.dwg UTILITIES NOTE: The position of any existing public or private sewers, utility services, plant or apparatus shown on this drawing is believed to be correct, but no warranty to this is expressed or implied. Other such plant or apparatus may also be present but not shown. The Contractor is therefore advised to undertake his own investigation where the presence of any existing sewers, services, plant or apparatus may affect his operations.

SCALING NOTE: Do not scale from this drawing. If in doubt, ask.

Reproduced from/based upon Ordnance Survey material with the permission of Ordnance Survey ®

on behalf of The Controller of Her Majesty's Stationery Office. ©Crown Copyright.

Unauthorised reproduction infringes Crown Copyright and may lead to prosecution or civil proceedings. Licence No. Year of Publication Owner/Purchaser of Mapping

user name: dale harvey

1st Issue Client

Former Inland Revenue Site,

Bessant Drive, Kew

Proposed Highway Improvements

F O R P L A N N I N G

29488-002-004

A

21-03-14 1:1000 DH SM

A Yellow Box Removed DH 01/10/14 SM

PBA

100021575 2014 A4 Scale

Key Facts

Car parking for the development will meet maximum local authority

standards.

Off-site highways improvements to Bessant Drive and

Mortlake Road to aid the flow of traffic.

Enhancement to the existing highways on Bessant Drive

and Mortlake Road

Agreed developer contributions towards sustainable access

improvements for the London Borough of Richmond.

References

Related documents

Keywords: national policy, dual citizenship, naturalisation, minority policy Tibor Toró: The Hungarian Communities from the Neighbouring Countries after the Law of

NDMA formation from the most reactive tertiary amines (e.g. dimethylaminomethylfurfuryl alcohol or DMP30) was enhanced in the presence of bromide due to the formation of

Moreover, consumers between the ages of 19 and 24 made relatively many contactless payments compared to the average consumer, followed by consumers between 25 and 34 years

Applications of Fourier transform ion cyclotron resonance (FT-ICR) and orbitrap based high resolution mass spectrometry in metabolomics and lipidomics. LC–MS-based holistic metabolic

In addition, the course provides students the opportunity to engage in content literacy strategies, with emphases on comprehension, vocabulary development, and writing. FOUNDATIONS

Respondent’s challenge is made on the sole ground that Respondent’s counsel had, in the past 2 years, worked closely in other cases with a different lawyer from the same law firm as

Kožený poťah sedadiel Torino - v čiernej farbe Charcoal Black + elektricky vyhrievané predné sedadlá s funkciou regulácie teploty, elektricky nastaviteľné sedadlo vodiča

Based on the assumption that an ontology, like any other knowledge model, is more effective when it integrates into its design the information requirements of end users, the study