SAO-SYS-PR-00002-A
PROCEDURE
CHANGES, DEVIATIONS &
WAIVERS PROCESSES
This document is stored electronically. Printed version might not be the latest.
SAOCOM PROJECT
COMISION NACIONAL DE ACTIVIDADES ESPACIALES
Number
SAO-SYS-PR-00002-A
Title
CHANGES, DEVIATIONS AND WAIVERS PROCESSES
Summary
Procedure that defines the processes to employ for changes, deviations and
waivers of configuration baseline.
Secondary Reference
Circulation Level
1
This document is digitally signed
Workflow Summary
State
Assignee
Action
Completed Date
Review
mpetruccioli
Approved
11-may-2012
Review
hmartirena
Approved
27-mar-2012
Approve
jmedina
Approved
11-may-2012
Changes Record
Issue Date Author PARA Description
A 12/03/2012 P. QUINTELA ALL CREATION
Comisión Nacional de Actividades Espaciales (CONAE) from Argentina owns the copyright of this document which is supplied in confidence and which shall not be used for any purpose other than that for which it is supplied and shall be only reproduced, copied or communicated, in whole or in part, for internal use of CONAE, directly or by third parties holding confidentiality agreements with CONAE. Any person other than the authorised holder obtaining possession of this document by finding or otherwise, should send it, together with his name and address, in a sealed envelope to:
Comisión Nacional de Actividades Espaciales (CONAE) – SAOCOM Project Av. Paseo Colón 751
(C1063ACH) Capital Federal ARGENTINA
INDEX
INDEX ... 3
1. OBJECTIVE ... 4
2. SCOPE ... 4
3. APPLICABLE AND REFERENCE DOCUMENTS ... 4
3.1. APPLICABLE DOCUMENTS ... 4
3.2. REFERENCE DOCUMENTS ... 4
4. DEFINITIONS AND ABBREVIATIONS ... 4
4.1. DEFINITIONS ... 4
4.2. ABBREVIATIONS AND ACRONYMS ... 5
5. ROLES AND RESPONSABILITIES ... 5
6. ENGINEERING CHANGE PROCESS ... 6
7. DEVIATIONS AND WAIVER PROCESS ... 8
1. OBJECTIVE
The purpose of this document is to define the processes to manage changes, deviations and
waivers of configuration baseline in SAOCOM project.
2. SCOPE
This procedure applies to configuration items and released baseline documentation, and shall be
employed by internal (CONAE) and external (Suppliers) personnel working in SAOCOM project to
manage changes and/or deviations/waivers of agreed baseline.
3. APPLICABLE AND REFERENCE DOCUMENTS
3.1.
APPLICABLE DOCUMENTS
SAO-SYS-PR-00001
Information/Document Management System
3.2.
REFERENCE DOCUMENTS
SAO-SYS-PL-00001
CONFIGURATION AND DOCUMENTATION MANAGEMENT PLAN
SAO-PAS-PR-00001
Non Conformances Management System
4. DEFINITIONS AND ABBREVIATIONS
4.1.
DEFINITIONS
Engineering Changes:
An engineering change is a modification or evolution of the product that have his configuration,
and therefore their specifications of design, approved or "frozen".
An engineering change supposes re-work in the design documentation and could concern
parameters like period, costs and quality.
Engineering changes can take place in any stage of the life-cycle of the product.
There are two ways to request and engineering change:
Engineering Change Request or Change Request (ECR/CR):
When the process
of change is initiated in CONAE or from CONAE towards their suppliers.
Engineering Change Proposal or Change Proposal (ECP/CP):
When the need of
the change is detected by a supplier and submits a proposal to approval for
CONAE.
Departures:
A departure is an impossibility of a product to reach its functional performance or fulfill with its
technical requirements. Being the product next the stage of manufacture, in manufacture, or
already made.
A departure is always limited, and does not imply realizing a change in the engineering
documentation.
Planned departure, that is to say that one in which there is known in advance
the inability to fulfill with the requirements. It is requested by a
Request for
Deviation (RFD)
Unexpected departure, that is to say that one that knows itself once produced
the departure. It is requested by a
Request for Waiver (RFW)
SAOCOM PLM Software:
Is a data base contained in a Product Life-cycle Management software that employ the
SAOCOM project to manage all project related information.
4.2.
ABBREVIATIONS AND ACRONYMS
Explanation of abbreviations and acronyms are self-contained in the text of document.
5. ROLES AND RESPONSABILITIES
Internal personnel and suppliers of SAOCOM project shall request Engineering Changes
and Request for Waiver/Deviation that explains the paragraphs 7 and 8 of this procedure.
Suppliers shall replicate this procedure to their subcontractors.
Processing of changes and departures on subassemblies and components of the project
SAOCOM is on the responsibility of the
Configuration Control Board (CCB).
This board
has as purpose:
·
To process the Change Request / Proposal and the Request for Waiver /
Deviation
·
To verify its integrity in terms of information and documentation of
reference
·
To evaluate and dispose (to approve or to reject) each of them
·
To authorize the use of configuration documents.
CCB is compound by:
·
The project manager
·
The configuration management responsible
·
The project planning responsible
·
The system manager
·
The contract representantive (
who processes contractual impacts
)
·
The product assurance manager
·
Additional members can participate, according requirement.
CONAE and Suppliers shall assure the integrity of project information after changes and
departures dispositions:
o
Configuration baselines shall be updated in conformance with the disposition of
approved changes and deviations. Configuration
‐
controlled documents shall be
revised to incorporate approved changes.
CONAE and Suppliers shall record the status of interface definition data and shall ensure
that all data is consistent with its product configuration.
Suppliers shall identify and control the internal interfaces of its product and those interfaces
for which he has received delegated authority.
6. ENGINEERING CHANGE PROCESS
CHANGE REQUEST
Process Flow
Explanation
The configuration state of the product can evolve due the need of a change detected by CONAE's engineering. The change can be motivated by: · a modification in the necessity · imperfect translation of the necessity · insufficiency of the product or function against the expressed necessity
· an improvement or optimization of product
· a technical problem or anomaly · a fall in disuse
· experience feedback
The engineer who detects the need of the change, initiates a Change Request in the SAOCOM PLM Software.
Control of Configuration transfers the change request towards the technical responsible according to the application area.
The technical responsible incorporates technical specialists to evaluate the impact of the change and to generate the analyses and necessary reports. The CCB dispose the acceptance or rejection of change.
Control of Configuration closes the Change Request and assures the baseline update.
If it is necessary the issue the alert to the affected suppliers in order that they issue a Change Proposal in response to the approved Change Request.
Change Request
CONAE
Transfer to Tech. Resp.
Configuration Control Implement Change Disposition
CCB
Reject ChangeImpact Evaluation
Technical responsibleAnalysis
Technical specialistCHANGE PROPOSAL
Process Flow
Explanation
The configuration state of the product can evolve due a change requested by CONAE or a change proposed by the supplier.
Any change to a configuration item, in relation with a baseline of approved configuration, will be described, well-justified and pre-classified by the supplier before sending the request for review and disposition.
The supplier initiates the process sending a change proposal employing the SAOCOM PLM Software.
Control of Configuration transfers the change request towards the technical responsible according to the application area.
The technical responsible incorporates technical specialists to evaluate the impact of the change and to generate the analyses and necessary reports that allow classify the proposal.
If the Change Proposal is classified as Minor and is based in a Change Request of CONAE the technical responsible implement the change.
If the change proposal is classified as Major or is not an answer of a CR, the technical responsible involves the CCB to define the disposition.
The CCB dispose the acceptance or rejection of change.
Control of Configuration closes the Change Proposal and assures the baseline update.
Change Proposal
Supplier
Transfer to Tech. Resp.
Configuration Control Classification Technical responsible Implement Change Disposition
CCB
Reject ChangeImpact Evaluation
Technical responsibleAnalysis
Technical specialist Not based on a CR Or Major Based on a CR And Minor7.
DEVIATIONS AND WAIVER PROCESS
REQUEST FOR DEVIATION
Process Flow
Explanation
When is detected that an item will not fulfill with the requirements or the configuration baseline of the product, there begins a Request for Deviation, being this departure planned on having be detected before its occurrence. Any departure in relation with a baseline of approved configuration, will be
described, well-justified and
pre-classified for the supplier, before sending the request for review and disposition.
The supplier initiates the process sending a Request for Deviation employing the SAOCOM PLM Software. Control of Configuration transfers the Request for Deviation towards the technical responsible according to the application area.
The technical responsible incorporates technical specialists to evaluate the deviation and define if continue or not with the process.
The technical responsible decides if the request for deviation is acceptable giving place to the definition by the CCB.
In case of be considering as
unacceptable, the RFD is rejected in this step.
The CCB dispose the acceptance or rejection of change.
Control of Configuration closes the Request for Deviation and assures the baseline update.
Request for
Deviation
Supplier
Transfer to Tech. Resp.
Configuration Control Acceptable Technical responsible RFD Rejected Disposition
CCB
RFD ApprovedImpact Evaluation
Technical responsibleAnalysis
Technical specialistYes
No
REQUEST FOR WAIVER
Process Flow
Explanation
When is detected that an item does not fulfill with the requirements or the configuration baseline of the product, there begins a Request for Waiver, being this unexpected departure on having be detected after its occurrence.
Any departure in relation with a baseline of approved configuration, will be
described, well-justified and
pre-classified for the supplier, before sending the request for review and disposition.
The supplier initiates the process sending a Request for Deviation employing the SAOCOM PLM Software. Control of Configuration transfers the Request for Waiver towards the technical responsible according to the application area.
The technical responsible incorporates technical specialists to evaluate the deviation and define if continue or not with the process.
The technical responsible decides if the request for deviation is acceptable giving place to the definition by the CCB.
In case of be considering as
unacceptable, the RFW is rejected in this step.
The CCB dispose the acceptance or rejection of change. It involves the NRB depending on the disposition of the associate Nonconformance Report.
Control of Configuration closes the Request for Waiver and assures the baseline update.
Request for
Waiver
Supplier
Transfer to Tech. Resp.
Configuration Control Acceptable Technical responsible RFW Rejected Disposition