COMMITMENT &INTEGRITY DRIVE RESULTS
Sewer Authority Mid-Coastside
Wet Weather Flow Alternatives
July 27, 2020 Presented by: Tony Valdivia, P.E.
Introductions & Acknowledgements
Introductions & Acknowledgements
Woodard & Curran Team Project Manager: Jim Graydon, P.E.
Technical Manager: Tony Valdivia, P.E.
Project Engineer: Athena Pervissian, P.E.
Woodard & Curran would like to acknowledge the contributions of all previous engineering consultants and SAM staff. SRT Consultants Carollo Engineers
Whitley Burchett (West Yost Associates)
Wastewater Management Services, LLC
Project Objective
Project Objective
Evaluate four potential projects for handling projected wet weather flows in the SAM Intertie Pipeline System (IPS)3 No Project (Status Quo) 200,000 Gallons of Storage 400,000 Gallons of Storage Portola Pump Station Improvements
Basic Evaluation Criteria
Basic Evaluation Criteria
Capital and Operating Costs (Life Cycle Cost)
Mitigation of Future Risk (spills; fines; reputation)COST
Project Flow Criteria
Project Flow Criteria
SAM policy regarding design storm capacity in the IPS: 10-year, 6-hour stormProject Objectives/Limitations: Non-Pump Station
Project Objectives/Limitations: Non-Pump Station
Rely on prior studies (by others) to define project and technical details
Develop capital costs based on recent bids (storage projects)
Develop O&M costs based on current SAM practices
No independent validation of design storm flows or project capacity No Project (Status Quo) 200,000 Gallons of Storage 400,000 Gallons of StorageProject Approach: Portola Pump Station
Project Approach: Portola Pump Station
Develop project technical details and costs to support direct comparison to the other three alternatives: Mechanical and electrical systems evaluation
New equipment selection and operational analysis
Reasonable allowances for items beyond technical scope (e.g. structures) Full capital and operating costs estimate
Portola Pump Station Improvements
Project Approach: Limitations
Project Approach: Limitations
No analysis of treatment plant impacts
No detailed analysis of permitting requirements
No structural evaluation, though impacts may be significant Portola Pump StationPortola Pump Station Improvements
Portola Pump Station Improvements
Previous studies evaluated improvingthe Portola Pump Station, but only assuming a costly parallel Granada Force Main.
Granada Force Main
Granada Force Main Improvements
Granada Force Main Improvements
Much of the Granada Force Main has now been repaired or replaced. Has the Pump Station Improvement
System Curve by SRT Consultants, 2019
System Hydraulics
System Hydraulics
Approx. 2020 Capacity w/ Two New 60 Hp Pumps 3,000 gpm Improvement Project Capacity 5,000 gpm* 67% Increase in Flow 91% Increase in HeadSystem Hydraulics
System Hydraulics
System Curve by SRT Consultants, 2019
At 5,000 gpm, force main velocity is over 10 feet per second. This is very fast for raw wastewater and may result in long-term damage.
Design standard velocities are typically 2 to 7 feet per second under all operating conditions.
Head loss in pipes increases exponentially with rising velocity. Pump and motor size increase with head loss.
System Hydraulics
System Hydraulics
System Curve by SRT Consultants, 2019
The Granada Force Main is too small for 5,000 gpm. A larger or parallel force main is still required.
Pump Selection @ 5,000 gpm
Pump Selection @ 5,000 gpm
Alternative 1 SAM-Owned 60 Hp Pumps New Wet Weather Pumps 5,000 gpm 5,000 gpm Standby 1,500 gpm 1,500 gpm Alternative 3 1,667 gpm 1,667 gpm 1,667 gpm 1,667 gpm Standby 250 Hp Alternative 2 2,500 gpm Standby 2,500 gpm 2,500 gpm 1,500 gpm 250 Hp 350 HpFour Pumps is the Limit
Four Pumps is the Limit
The Smaller (60 Hp) Pumps are Important
The Smaller (60 Hp) Pumps are Important
60 Hp pumps more efficiently convey low flows when driven by variable frequency drives (VFDs).
Wet weather pumps are sized for very high flows and head. They
cannot get close to ADWF.
Average Dry Weather Flow (ADWF): 350 gpm
Pump Selection @ 5,000 gpm
Pump Selection @ 5,000 gpm
Alternative 1 SAM-Owned 60 Hp Pumps New Wet Weather Pumps Alternative 2 Alternative 3 5,000 gpm 5,000 gpm Standby 2,500 gpm Standby 2,500 gpm 2,500 gpm 1,667 gpm 1,667 gpm 1,667 gpm 1,667 gpm Standby 1,500 gpm 1,500 gpm 1,500 gpm 250 Hp 250 Hp 350 Hp No Small PumpsPump Selection @ 5,000 gpm
Pump Selection @ 5,000 gpm
Alternative 1 SAM-Owned 60 Hp Pumps New Wet Weather Pumps Alternative 2 Alternative 3 5,000 gpm 5,000 gpm Standby 2,500 gpm Standby 2,500 gpm 2,500 gpm 1,667 gpm 1,667 gpm 1,667 gpm 1,667 gpm Standby 1,500 gpm 1,500 gpm 1,500 gpm 250 Hp 250 Hp 350 HpPump Station Electrical Improvements
Pump Station Electrical Improvements
New Standby Generator (outside enclosure)
New Main Distribution and Switchboard
New VFDs (all pumps)
New MCC (ancillary loads)
New HVAC (heat loads)
New Room Configuration
New Utility Service
New ConductorsThe increase in station
horsepower is significant and is anticipated to require an overhaul of most electrical gear.
Additional Assumptions
Additional Assumptions
New surge tank (higher velocities = high surge potential)
Structural retrofit to current code is likely
Retrofit of force main air valves (surge capacity)Portola Pump Station Costs
Portola Pump Station Costs
Construction Cost:$3.4 Million*
Excludes 25% soft costs Assumes existing force main
Annual Operating Costs:$110,000
Includes labor, power,
maintenance/parts
20-Year Net Present Value: $4.9 MillionPortola Pump Station Risk
Portola Pump Station Risk
•
Risk of damage to existing force main•
Redundancy in pumping provides firm capacity equal to design flows•
Multi-year schedule for implementation (schedule risk)•
Permitting will be complicated (CEQA, Coastal Commission) andNo Project Alternative Costs
No Project Alternative Costs
Initial Cost: $300,000 (Settlement payment)
Annual Cost: $192,000
$97,000 Portola Pump Station (existing)
$95,000 labor, equipment rental/maintenance for high flow
management (unverified)
20-Year Net Present Value:
No Project Alternative Risk
No Project Alternative Risk
•
Labor and maintenance intensive approach•
Failure to complete a capacity improvement project per the Settlement is likely to place SAM under additional scrutiny and increased risk of larger fines or legal action in the event of a future spill.200,000 Gallons of Storage Costs
200,000 Gallons of Storage Costs
Construction Cost: $1.4 Million Excludes 5% soft costs, “shovel ready”
Settlement Credit: ($300,000)
Net Construction Cost: $1.1 Million
Annual Operating Costs: $97,000 (Portola Pump Station)200,000 Gallons of Storage Risk
200,000 Gallons of Storage Risk
•
Passive overflow not dependent on mechanical systems•
SAM experience indicates low cost to maintain (high availability)400,000 Gallons of Storage Costs
400,000 Gallons of Storage Costs
Construction Cost: $2.9 Million Excludes 25% Soft Costs
Settlement Credit: ($300,000)
Net Construction Cost: $2.6 Million
Annual Operating Costs: $97,000 (Portola Pump Station)400,000 Gallons of Storage Risk
400,000 Gallons of Storage Risk
•
Passive overflow not dependent on mechanical systems•
SAM experience indicates low cost to maintain (high availability)Summary of Alternatives
Summary of Alternatives
Pump Station Improvements No Project 200,000 Gallons Storage1 400,000 Gallons Storage1 Construction/Initial Cost $3.4 Million $300,000 $1.1 Million (Net) $2.6 Million (Net)Net Present Value $4.9 Million $2.9 Million $2.4 Million (Net) $3.9 Million (Net)
Risk Assessment MODERATE HIGH MODERATE LOW
Recommended Project
Recommended Project
400,000 Gallons of Storage is the Recommended ProjectNo Project (Status Quo) 200,000 Gallons of Storage 400,000 Gallons of Storage Portola Pump Station Improvements
Additional Considerations
Additional Considerations
Storage can be phased for capital expenditure planning Two 200,000-gallon projects will cost marginally more than a single
400,000-gallon project due economy of scale
It is the Granada Force Main limitations that drive the recommendation away from the Pump Station Improvements With a parallel force main, the Portola Pump Station alternative would be much
more compelling, and the risk of a force main break would also be largely mitigated
COMMITMENT &INTEGRITY DRIVE RESULTS
Sewer Authority Mid-Coastside
Wet Weather Flow Alternatives
July 27, 2020 Presented by: Tony Valdivia, P.E.
Thank You!
Questions?
BACKUP SLIDES
BACKUP SLIDES
Summary of Alternatives
Summary of Alternatives
Pump Station Improvements No Project 200,000 Gallons Storage1 400,000 Gallons Storage1Construction/Initial Cost $3.4 Million $300,000 $1.4 Million
$1.1 Million (Net)1
$2.9 Million $2.6 Million (Net)1
Net Present Value $4.9 Million $2.9 Million $2.7 Million
$2.4 Million (Net)1
$4.2 Million
$3.9 Million (Net)1
Risk Assessment MODERATE HIGH MODERATE LOW