• No results found

Sewer Authority Mid-Coastside

N/A
N/A
Protected

Academic year: 2021

Share "Sewer Authority Mid-Coastside"

Copied!
34
0
0

Loading.... (view fulltext now)

Full text

(1)

COMMITMENT &INTEGRITY DRIVE RESULTS

Sewer Authority Mid-Coastside

Wet Weather Flow Alternatives

July 27, 2020 Presented by: Tony Valdivia, P.E.

(2)

Introductions & Acknowledgements

Introductions & Acknowledgements

Woodard & Curran Team

 Project Manager: Jim Graydon, P.E.

 Technical Manager: Tony Valdivia, P.E.

 Project Engineer: Athena Pervissian, P.E.

Woodard & Curran would like to acknowledge the contributions of all previous engineering consultants and SAM staff.

 SRT Consultants  Carollo Engineers

 Whitley Burchett (West Yost Associates)

 Wastewater Management Services, LLC

(3)

Project Objective

Project Objective

Evaluate four potential projects for handling projected wet weather flows in the SAM Intertie Pipeline System (IPS)

3 No Project (Status Quo) 200,000 Gallons of Storage 400,000 Gallons of Storage Portola Pump Station Improvements

(4)

Basic Evaluation Criteria

Basic Evaluation Criteria

Capital and Operating Costs (Life Cycle Cost)

Mitigation of Future Risk (spills; fines; reputation)

COST

(5)

Project Flow Criteria

Project Flow Criteria

SAM policy regarding design storm capacity in the IPS: 10-year, 6-hour storm

(6)

Project Objectives/Limitations: Non-Pump Station

Project Objectives/Limitations: Non-Pump Station

Rely on prior studies (by others) to define project and technical details

Develop capital costs based on recent bids (storage projects)

Develop O&M costs based on current SAM practices

No independent validation of design storm flows or project capacity No Project (Status Quo) 200,000 Gallons of Storage 400,000 Gallons of Storage

(7)

Project Approach: Portola Pump Station

Project Approach: Portola Pump Station

Develop project technical details and costs to support direct comparison to the other three alternatives:

 Mechanical and electrical systems evaluation

 New equipment selection and operational analysis

 Reasonable allowances for items beyond technical scope (e.g. structures)  Full capital and operating costs estimate

Portola Pump Station Improvements

(8)

Project Approach: Limitations

Project Approach: Limitations

No analysis of treatment plant impacts

No detailed analysis of permitting requirements

No structural evaluation, though impacts may be significant Portola Pump Station

(9)

Portola Pump Station Improvements

Portola Pump Station Improvements

Previous studies evaluated improving

the Portola Pump Station, but only assuming a costly parallel Granada Force Main.

Granada Force Main

(10)

Granada Force Main Improvements

Granada Force Main Improvements

Much of the Granada Force Main has now been repaired or replaced. Has the Pump Station Improvement

(11)

System Curve by SRT Consultants, 2019

System Hydraulics

System Hydraulics

Approx. 2020 Capacity w/ Two New 60 Hp Pumps 3,000 gpm Improvement Project Capacity 5,000 gpm* 67% Increase in Flow 91% Increase in Head

(12)

System Hydraulics

System Hydraulics

System Curve by SRT Consultants, 2019

At 5,000 gpm, force main velocity is over 10 feet per second. This is very fast for raw wastewater and may result in long-term damage.

Design standard velocities are typically 2 to 7 feet per second under all operating conditions.

Head loss in pipes increases exponentially with rising velocity. Pump and motor size increase with head loss.

(13)

System Hydraulics

System Hydraulics

System Curve by SRT Consultants, 2019

The Granada Force Main is too small for 5,000 gpm. A larger or parallel force main is still required.

(14)

Pump Selection @ 5,000 gpm

Pump Selection @ 5,000 gpm

Alternative 1 SAM-Owned 60 Hp Pumps New Wet Weather Pumps 5,000 gpm 5,000 gpm Standby 1,500 gpm 1,500 gpm Alternative 3 1,667 gpm 1,667 gpm 1,667 gpm 1,667 gpm Standby 250 Hp Alternative 2 2,500 gpm Standby 2,500 gpm 2,500 gpm 1,500 gpm 250 Hp 350 Hp

(15)

Four Pumps is the Limit

Four Pumps is the Limit

(16)

The Smaller (60 Hp) Pumps are Important

The Smaller (60 Hp) Pumps are Important

60 Hp pumps more efficiently convey low flows when driven by variable frequency drives (VFDs).

Wet weather pumps are sized for very high flows and head. They

cannot get close to ADWF.

Average Dry Weather Flow (ADWF): 350 gpm

(17)

Pump Selection @ 5,000 gpm

Pump Selection @ 5,000 gpm

Alternative 1 SAM-Owned 60 Hp Pumps New Wet Weather Pumps Alternative 2 Alternative 3 5,000 gpm 5,000 gpm Standby 2,500 gpm Standby 2,500 gpm 2,500 gpm 1,667 gpm 1,667 gpm 1,667 gpm 1,667 gpm Standby 1,500 gpm 1,500 gpm 1,500 gpm 250 Hp 250 Hp 350 Hp No Small Pumps

(18)

Pump Selection @ 5,000 gpm

Pump Selection @ 5,000 gpm

Alternative 1 SAM-Owned 60 Hp Pumps New Wet Weather Pumps Alternative 2 Alternative 3 5,000 gpm 5,000 gpm Standby 2,500 gpm Standby 2,500 gpm 2,500 gpm 1,667 gpm 1,667 gpm 1,667 gpm 1,667 gpm Standby 1,500 gpm 1,500 gpm 1,500 gpm 250 Hp 250 Hp 350 Hp

(19)

Pump Station Electrical Improvements

Pump Station Electrical Improvements

New Standby Generator (outside enclosure)

New Main Distribution and Switchboard

New VFDs (all pumps)

New MCC (ancillary loads)

New HVAC (heat loads)

New Room Configuration

New Utility Service

New Conductors

The increase in station

horsepower is significant and is anticipated to require an overhaul of most electrical gear.

(20)

Additional Assumptions

Additional Assumptions

New surge tank (higher velocities = high surge potential)

Structural retrofit to current code is likely

Retrofit of force main air valves (surge capacity)

(21)

Portola Pump Station Costs

Portola Pump Station Costs

Construction Cost:

$3.4 Million*

 Excludes 25% soft costs  Assumes existing force main

Annual Operating Costs:

$110,000

 Includes labor, power,

maintenance/parts

20-Year Net Present Value: $4.9 Million

(22)

Portola Pump Station Risk

Portola Pump Station Risk

Risk of damage to existing force main

Redundancy in pumping provides firm capacity equal to design flows

Multi-year schedule for implementation (schedule risk)

Permitting will be complicated (CEQA, Coastal Commission) and

(23)

No Project Alternative Costs

No Project Alternative Costs

Initial Cost: $300,000 (Settlement payment)

Annual Cost: $192,000

 $97,000 Portola Pump Station (existing)

 $95,000 labor, equipment rental/maintenance for high flow

management (unverified)

20-Year Net Present Value:

(24)

No Project Alternative Risk

No Project Alternative Risk

Labor and maintenance intensive approach

Failure to complete a capacity improvement project per the Settlement is likely to place SAM under additional scrutiny and increased risk of larger fines or legal action in the event of a future spill.

(25)

200,000 Gallons of Storage Costs

200,000 Gallons of Storage Costs

Construction Cost: $1.4 Million

 Excludes 5% soft costs, “shovel ready”

Settlement Credit: ($300,000)

Net Construction Cost: $1.1 Million

Annual Operating Costs: $97,000 (Portola Pump Station)

(26)

200,000 Gallons of Storage Risk

200,000 Gallons of Storage Risk

Passive overflow not dependent on mechanical systems

SAM experience indicates low cost to maintain (high availability)

(27)

400,000 Gallons of Storage Costs

400,000 Gallons of Storage Costs

Construction Cost: $2.9 Million

 Excludes 25% Soft Costs

Settlement Credit: ($300,000)

Net Construction Cost: $2.6 Million

Annual Operating Costs: $97,000 (Portola Pump Station)

(28)

400,000 Gallons of Storage Risk

400,000 Gallons of Storage Risk

Passive overflow not dependent on mechanical systems

SAM experience indicates low cost to maintain (high availability)

(29)

Summary of Alternatives

Summary of Alternatives

Pump Station Improvements No Project 200,000 Gallons Storage1 400,000 Gallons Storage1 Construction/Initial Cost $3.4 Million $300,000 $1.1 Million (Net) $2.6 Million (Net)

Net Present Value $4.9 Million $2.9 Million $2.4 Million (Net) $3.9 Million (Net)

Risk Assessment MODERATE HIGH MODERATE LOW

(30)

Recommended Project

Recommended Project

400,000 Gallons of Storage is the Recommended Project

No Project (Status Quo) 200,000 Gallons of Storage 400,000 Gallons of Storage Portola Pump Station Improvements

(31)

Additional Considerations

Additional Considerations

Storage can be phased for capital expenditure planning

 Two 200,000-gallon projects will cost marginally more than a single

400,000-gallon project due economy of scale

It is the Granada Force Main limitations that drive the recommendation away from the Pump Station Improvements

 With a parallel force main, the Portola Pump Station alternative would be much

more compelling, and the risk of a force main break would also be largely mitigated

(32)

COMMITMENT &INTEGRITY DRIVE RESULTS

Sewer Authority Mid-Coastside

Wet Weather Flow Alternatives

July 27, 2020 Presented by: Tony Valdivia, P.E.

Thank You!

Questions?

(33)

BACKUP SLIDES

BACKUP SLIDES

(34)

Summary of Alternatives

Summary of Alternatives

Pump Station Improvements No Project 200,000 Gallons Storage1 400,000 Gallons Storage1

Construction/Initial Cost $3.4 Million $300,000 $1.4 Million

$1.1 Million (Net)1

$2.9 Million $2.6 Million (Net)1

Net Present Value $4.9 Million $2.9 Million $2.7 Million

$2.4 Million (Net)1

$4.2 Million

$3.9 Million (Net)1

Risk Assessment MODERATE HIGH MODERATE LOW

References

Related documents

These questions follow from the thesis’ two objectives: (1) to understand the complexity of the conflict between the oil and gas industry and small-scale fishing

Many Jefferson County public high schools promote the 25 Book Campaign, which, as the name suggests, encourages students to read at least 25 books during the

Stage 2 Child Care, which is available to families on welfare and with stable employment. Families may be eligible for Stage 2 Child Care for up to 24 months after they stop receiving

This paper was organized as the following structure: (a) the intro- duction of the new approach of the real-road simulation, combining the traffic and vehicle simulations; (b)

The primary aim of this research was to examine the production of JA, vocalizations, and co- occurrences between them in infants who are at heightened risk for ASD. The study was

INTRODUCTION: The selected anterior cruciate ligament (ACL) augmentation procedure, either anteromedial (AM) or posterolateral (PL), has been introduced as a treatment of choice

The very high spikes in respiration rates modelled by CenW from July onwards corresponded to days when there were large grazing events that should have been observed at the EC

1,2 Major factors associated with drug resis- tance development include presence of cavitation together with smear-positive sputum and positive sputum culture, non-adherence to