• No results found

Rate Analysis for Road Construction

N/A
N/A
Protected

Academic year: 2021

Share "Rate Analysis for Road Construction"

Copied!
5
0
0

Loading.... (view fulltext now)

Full text

(1)

Rate Analysis for construction of Black top road

Sn Items

1 Sub grades Description Units Quantity Rate Amount

Preparation of Sub-grade for rehabilitation filling

or cutting depth of (10-20cm) unskilled m.d. 0.15 350 52.5

Common soil miscellane. % 3% 1.575

per Sub-Total 54.075

1 Sq.m Contractor overhead 15% 8.11125

Sub-Total 62.18625

Vat 13% 8.084213

Grand total with Vat Sq.m. 70.27046

per Sq.ft 6.530712

2 Sub-Base course Description Units Quantity Rate Amount

Providing, laying, spreading , watering, levelling and compaction of crusher run material for sub-base cource graidng SB1* lead upto 10m ( 10cm

thick) Skilled m.d. 0.005 450 2.25

Unskilled m.d. 1.4 350 490

sub base aggr. ( Gravel

size less than 70mm) Cu.m 1.3 1700 2210

Diesel Lit 0.66 73 48.18

Road Roller Hr 0.03 2984.50 89.535

per Sub-Total 2839.965

1 Cu.m Contractor overhead 15% 425.9948

Sub-Total 3265.96

Vat 13% 424.5748

Grand total with Vat Cu.m, 3690.535

per Cu.ft 342.9865

3 Base course Description Units Quantity Rate Amount

Providing, laying, spreading , watering, levelling and compaction of crusher run material for sub-base cource graidng SB1* lead upto 10m ( 10cm

(2)

Unskilled m.d. 1.5 350 525 Base aggr. ( Gravel size

less than 20-40mm) Cu.m 1.2 1500 1800

Diesel Lit 0.88 73 64.24

Road Roller Hr 0.04 2984.50 119.38

per Sub-Total 2510.87

1 Cu.m Contractor overhead 15% 376.6305

Sub-Total 2887.501

Vat 13% 375.3751

Grand total with Vat Cu.m 3262.876

per Cu.ft 303.2412

4 Prime coat Description Units Quantity Rate Amount

Providing and spraying bituminious prime coat MC30 / MC70 incluinding cleaning the road surface using wire, brushes, broom etc. before

applying prime coat ( Manual works) Skilled m.d. 0.003 450 1.35

Unskilled m.d. 0.046 350 16.1 Bitumen MC30/MC70 Lt 1.05 69.02 72.471 Kerosene Lit 0.1 73 7.3 Boiler Hr 0.014 0 Bitumen Distributor Hr 0.014 4299.25 60.1895 per Sub-Total 157.4105 Contractor overhead 15% 23.61158 Sub-Total 181.0221 Vat 13% 23.53287

1 Lt Grand total with Vat Lit 204.5549

5 Premix Carpet Description Units Quantity Rate Amount

Providing, mixing, laying and compaction of

premixed carpet ( 20mm thick) Skilled m.d. 0.45 450 202.5

Unskilled m.d. 4.5 350 1575

Bitumen MC30/MC70 Lt 77 69.02 5314.54

Kerosene Lit 7.7 73 562.1

Aggregate Cu.m 1.2 1500 1800

(3)

Sprayer Hr 0.5 4299.25 2149.625

per Sub-Total 13096.02

Contractor overhead 15% 1964.402

Sub-Total 15060.42

Vat 13% 1957.854

1 Cu.m Grand total with Vat Cu.m 17018.27

per Cu.ft 482.2024

6 Tact coat over premix carpetting Description Units Quantity Rate Amount

Providing mixing and laying fine slurry mix seal Skilled m.d. 0.2 450 90

per 100 sq.m Unskilled m.d. 3 350 1050 Emulsion Lt 122 350 42700 Cement Kg 8.3 11.1 92.13 Aggregate Cu.m 0.49 1500 735 Water Ls 10 Diesel Lit 8.4 75.00 630 Mixer Hr 0.07 2245.00 157.15

Pneumatic tyred roller Hr 0.55 3824.50 2103.475

3% of labour cost for T&P 34.2

Sub-Total 47601.96

Contractor overhead 15% 7140.293

Sub-Total 54742.25

Vat 13% 7116.492

100 Sq.m Grand total with Vat 100 Sq.m 61858.74

per Sq.m 618.5874

per Sqft 57.48954

7 Kerbs Description Units Quantity Rate Amount

Providing and laying M 15 Precast or Cast in situ concrete in kerbs with 12mm thick 1:3 cement sand mortar bedding and joints including

foundation excavation levelling etc. but excluding

foundation concrete or sand gravel materials. Skilled m.d. 0.1 450 45

(4)

Concrete ( M20) Cu.m 0.076 7971.1 605.8044 Cement Kg 1.3 11.1 14.43 Sand Cu.m 0.003 1500 4.5 Water Lit 0.5 0.10 0.05 Form work Sq.m 1 534.13 534.13 Sub-Total 1378.914 Contractor overhead 15% 206.8372 Sub-Total 1585.752 Vat 13% 206.1477

1 m Grand total with Vat M 1791.899

per Ft 546.3107

8 Concrete M15 Description Units Quantity Rate Amount

b) Providing and placing manually mixed cement concrete for the abutement, pier, wall etc, including compaction, curing, testing and lead 30m. etc. all complete as per specification and

drawing. (M15) Skilled m.d. 0.5 450 225

Unskilled m.d. 3.5 350 1225

Cement kg 260 11.1 2886

Sand Cu.m 0.46 1000 460

Water Ls 156 0.20 31.2

aggregate 10mm & down Cu.m 0.11 1500.00 165

aggregate 10-20mm Cu.m 0.24 1500.00 360 aggregate 20-40mm Cu.m 0.53 1500.00 795 Mixer Hr 0.6 800.00 480 Vibrator Hr 0.25 300.00 75 Diesel Lit 3 73.00 219 Petrol Lit 0.1 102.00 10.2 Sub-Total 6931.4 Contractor overhead 15% 1039.71 Sub-Total 7971.11 Vat 13% 1036.244

100 Cu.m Grand total with Vat cu.m 9007.354

per Cu.ft 255.2179

Nominal Kerb size 38cmX20cmx25cm.(HXBXL) Foundation concrete or sand gravel to be measured and paid separately as required from respective clause of specification.

(5)

8 Form work Description Units Quantity Rate Amount Providing , Preparing and Installing form work &

removing afte r completion for Precast elements.

(class F3 Finish) Skilled m.d. 1.5 450 675

i)Square/Rectangular Section Unskilled m.d. 2 350 700

a) Using Timber Plywood 9mm thick Sq.m 11 430.4 4734.4

Timber Cu.m 0.2 5500 1100 Nails Kg 2 65.00 130 Sub-Total 7339.4 Contractor overhead 15% 1100.91 Sub-Total 8440.31 Vat 13% 1097.24

10 Sq.m Grand total with Vat 10 Sq.m 9537.55

References

Related documents