CITY COUNCIL

WORKSHOP

MAY 24, 2016

Capital Budget FY 2016-2017 & 2017-2018

(2)

FY 2015-16 Accomplishments

Projects Completed during FY 2015-16

Projects Under Construction or soon to be Other On-going Projects

Two – Year Capital Budget

Capital Budget Development Funding Sources

Grant Funds and Opportunities Proposed Projects

(3)

Projects Completed

in FY15-16

(4)

Centre Concord Movable Walls & Coverings (PJ2182)

(5)

Farm Bureau Road Safe Route to School Improvements (Wren Ave. to Willow Pass Rd.) (PJ2251)

GRANT FUNDING (SRTS + Measure J Bond): $722,290; TOTAL COST: $1.4M

AFTER BEFORE

(6)

Farm Bureau Rd. Pavement Reconstruction Design (Wren Ave. to Clayton Rd.) (PJ2252)

TOTAL COST: $88,450

(7)

Farm Bureau Rd. Pavement Reconstruction Design (Wren Ave. to Clayton Rd.) (PJ2252)

TOTAL COST: $88,450

(8)

Cowell Road Safety Enhancements (2314)

(9)

FY14-15 Pavement Maintenance – Zone 3 (2329)

TOTAL COST: $1,862,000

(10)

Electronic Bike Locker Install (PJ2336)

Before After

(11)

Citywide Bridge Repair Program – Group 1 Bridge Construction (2342)

GRANT FUNDING (FHBP) : $682,834; TOTAL COST: $851,000

(12)

Todos Santos Plaza Archways (PJ2294)

(13)

Todos Santos Plaza Decorative Tree Lighting Replacement (PJ2309)

(14)

Analysis of Golf Course Infrastructure & Deferred Maintenance Conditions (PJ2348)

(15)

Detroit Avenue Pedestrian and Bicycle Improvements (PJ2276)

Before

(GRANT FUNDING: $1.8M; TOTAL FUNDING: $2.7M)

(16)

Citywide Accessibility Improvements (PJ2325)

(17)

Concord Blvd. PG&E Utility Pole Relocation and

Pavement Rehabilitation

Citywide Budget Management Software

Citywide Electronic Document Management System Sewer Lateral Replacements

Reroofing of Willow Pass Center and Keller House Meadow Homes Spray Park - Spray System Control

Upgrade

(18)

Projects Under Construction

or Soon to Be

(19)

Clayton Road/Treat Blvd. Intersection Capacity Improvements (PJ2144)

GRANT FUNDING (Regional Measure J): $2.33M;

(20)

Concord Various Streets Preservation (PJ2292)

GRANT FUNDING (OBAG): $757,000; TOTAL FUNDING: $1.7M

Project Limits Project Limits

Concord Boulevard (6th Street to Port Chicago Hwy)

Arnold Industrial Pkwy (Port Chicago Hwy to Pike Lane)

(21)

Pavement Rehabilitation – Salvio Street and Oak Grove Road (PJ2331) & Salvio Complete Streets Sidewalk

Installation (PJ 2355)

GRANT FUNDING (511 Contra Costa + Measure J Bond): $582,000; TOTAL FUNDING: $3.1M

Oak Grove Road – Monument Blvd. to Whitman Rd.

Salvio Street – Port Chicago Hwy. to Parkside Dr.

(22)

Pavement Rehabilitation – Salvio Street and Oak Grove Road (PJ2331) & Salvio Complete Streets Sidewalk

Installation (PJ 2355)

GRANT FUNDING (511 Contra Costa + Measure J Bond): $582,000; TOTAL FUNDING: $3.1M

(23)

Electric Vehicle Replacement (PJ2193)

GRANT FUNDING (MTC): $280,000; TOTAL FUNDING: $550,000

LOCATIONS

• Civic Center: 4 EVs; 2 dual charging stations • Police Department: 4

EVs; 2 dual charging station

• Corp Yard: 2 EVs; 1 dual charging station

(24)

Traffic Signal Upgrades – Various Locations (PJ2285)

(25)

Traffic Signal Upgrades @ Oak Grove Rd./Sierra Rd.

(PJ2293)

GRANT FUNDING (CMAQ): $504,900; TOTAL FUNDING: $570,300

(26)

Franquette Avenue Pedestrian & Bicycle Trail Connection (PJ2307)

GRANT FUNDING (Measure J Bond): $470,000; TOTAL FUNDING: $520,000

(27)

Central Concord Pedestrian Improvements and Streetscape (PJ2239)

(28)

Willow Pass Park Field Lights Replacement (PJ2347)

(29)

Tennis Court Resurfacing and Pickle Ball Court Installation

(30)

Tennis Court Resurfacing and Pickle Ball Court Installation

(31)
(32)

Ellis Lake Park Restroom Building (PJ 2351)

(33)

Ellis Lake Park Playground and Park

Improvements (PJ 2349)

(34)

Meadow Homes Park Playground Installation

(PJ 2352)

(35)

Willow Pass Park Restroom & Concession Facility Replacement – Field #1 (PJ2334)

(36)

Replace Pump System Components at 4 Park Locations

(PJ2242)

(37)

Citywide Bridge Repair Program (PJ2060)

GRANT FUNDING (FHBP): $1.0M; TOTAL FUNDING: $1.65M

(38)

Market Street Utility Undergrounding (PJ2111)

(39)

Downtown Concord Bicycle Improvements (PJ2277)

(40)

Downtown Concord Bicycle Improvements (PJ2277)

(41)

Downtown Concord Bicycle Improvements (PJ2277)

(42)

Downtown Concord Bicycle Improvements (PJ2277)

(43)

Detroit Ave./Whitman Rd. Pedestrian Improvements

(PJ2318)

(44)

Monument Blvd. Design Improvements (PJ2319)

TOTAL FUNDING: $100,000

(45)

Farm Bureau Rd. Complete Streets – Phase 2

(Wren Ave. to Walnut Ave.) (PJ 2354)

(46)

Citywide Bicycle and Pedestrian Master Plan

(PJ 2280)

GRANT FUNDING: $300,000)

(47)
(48)

Various Street Maintenance and Repair Projects Monument Neighborhood Shuttle (PJ2279)

Subdivision Ordinance Update (PJ2308)

Citywide Traffic Signal System Upgrade (PJ2322) Operational Improvements on Parallel Arterials

(PJ 2356)

Marsh Drive Bridge Seismic Retrofit (PJ1854)

On-Call Citywide Sidewalk Replacement Program (PJ2341)

Water Quality Improvements at City Park Ponds (PJ2353)

Various Information Technology Projects

(49)

Proposed 2-Year

Capital Budget

(50)

Change to Biennial Capital Budget Cycle

Focused on Council Priorities

Total Program is $32.4 million over two years

(51)

Project Proposals Start at the Departmental

Level

Tied to Community and Commissions

Needs Greater than Resources

Focus on Priorities

(52)

Project Evaluation Criteria

Does the project implement one or more Council

Initiatives?

Does the project address critical health and safety needs?

Is the project continuing from a previously approved CIP?

Is the project needed to satisfy regulatory compliance

issues?

Is the project primarily funded with grants, enterprise, or

other restricted funds?

Does the project implement the City's Complete Street

policies?

Does the project help implement the City's Climate Action

Plan?

(53)

Project Evaluation Criteria (cont.)

Has the project been identified in the General Plan?

Does the project conform to General Plan Principles?

Does the (IT) project conform to IT Principles?

Does the (IT) project impact a large customer base?

Does the project increase ability to provide service

effectively?

Does the project generate new resources, reduce or add

ongoing costs?

Does the project promote economic development goals?

(54)

Projects Reviewed By Staff

Recommendations Reviewed Executive

Committee and City Manager

Draft Capital Budget Presented to Council

(55)

Funding Sources

Total All Sources $32,436,116

(56)
(57)

Active Transportation Program

Applications Due June 15, 2016

Downtown Corridors and Green Frame

One Bay Area Grant

Call for Projects Expected Summer 2016 Monument Boulevard Complete Streets Willow Pass Road Improvements

Citywide Bicycle and Pedestrian Master Plan

(58)

Originally Approved by Voters in November

2010

Extended to 2025 in November 2014

Ratified with 76.3 % approval and helps

protect/maintain Concord’s City Services

Lease Revenue Financing Agreement (LRFA)

Approved in March 2015 provided $22.4 million

Measure Q funds in the proposed budget total

$11.75 million (36%)

(59)

Measure Q LRFA

Council Approved $22.4 Million in Debt Financing

(March 2015)

Programmed for Roadway Maintenance

Pavement / Pothole Repair

Local Street maintenance and resurfacing

Arterial and Collector Street maintenance and resurfacing

Pavement Maintenance Expenditure Plan approved

(60)

Planned Pavement Maintenance Projects

Measure Q Pavement Repair Project #1 - Hillsborough Dr.

and E. Olivera Rd. (PJ 2359)

Measure Q Pavement Repair Project #2 - Solano Wy., Wren

Ave., & 6th St. (PJ 2361)

Measure Q Pavement Repair Project #3 – Walters Wy. &

Detroit Ave./Monument Blvd. Intersection (PJ 2362)

Measure Q Pavement Repair Project #4 – Pothole and Base

Repairs at Various Locations (PJ 2364)

Measure Q Pavement Maintenance Project #5 – Zones 4 & 5

Measure Q Pavement Repair Project #6 – Zones 4 & 5

Measure Q Pavement Maintenance Project #7 – Zones 1 & 2

(61)

Project Phases

Conceptual / Preliminary Design Project Final Design

Environmental Review Construction

Budget Estimating

Initial Budgetary Estimates

Refined through Preliminary and Final Design

Phases

Actual Construction Costs Determined by

Competitive Bids

(62)

CIP Challenges

Needs Resources Funding Staffing Grant Requirements Environmental Clearance Regulatory Requirements

(63)
(64)

Full Trash Capture Device Installation (CD-17-001)

Green Infrastructure - Framework (CD-17-002)

(65)

Citywide Accessibility Projects (CDBG)

Citywide Accessibility Improvements No.3 (2357)

Citywide Accessibility Improvements No.4 (CD-18-005) ADA Transition Plan Update (CED-17-004)

(66)

Facilities Maintenance Projects

Civic Center Restroom ADA Improvements (PW-17-018)

(67)

Police Department Safety Improvements (PW-17-005) Police Department Roof and Equipment Paint and

Sealing (PW-17-013)

Trim Replacement at Civic Center and Willow Pass Rec (PW-17-014)

(68)

Public Building Maintenance (PW-17-010)

Civic Center Generator Replacement (PW-17-012)

(69)

Street Median Turf Conversion (PW-17-005)

Park and Median Smart Irrigation Controllers (PW-17-002)

(70)

Concord Community Pool Deck Repair (PW-17-011) Playground Replacement Program (PW-17-004)

(71)

Golf Course Safety Needs (PW-17-001)

Willow Pass Park Restroom & Concession Facility

Replacement – Field #2 (UF-1602)

(72)

Downtown Sidewalk, Curb and Gutter Improvements (PW-17-007)

(73)

FY16-17/17-18 Sewer Projects

SEWER PROJECTS

Citywide Sewer Condition Assessment Study (PJ2208) Sewer Capital Facility Replacement (PJ2209)

Citywide Sewer Lateral Replacement Program (PJ2244) El Molino Cross-Tie (ENG-17-006)

Downtown Sanitary Sewer Upgrade – Phase IIb (SWR-1511) Cowell Road BART Area Sanitary Sewer Upgrade (SWR-1302)

(74)

Information Technology

Projects

(75)

Active Information Technology Projects

Public Works Asset Management

TOTAL FUNDING: $260,000

• Computerized asset management system for Public Works

(76)

Active Information Technology Projects

Replace Downtown Security Cameras

TOTAL FUNDING: $101,000

(77)

Active Information Technology Projects

P.D. Law Enforcement Records Management System (RMS)

TOTAL FUNDING: $1,526,975

• Replaces the City’s custom built Police Records Management System • Automates reporting to the State and FBI

(78)

Active Information Technology Projects

Uninterruptible Power Service Supply Replacement @ PD (PJ2032)

TOTAL FUNDING: $178,000

• Replaces end of life Uninterruptible Power Supply (UPS) for the Police

(79)

FY16-17 New ITP Projects

Timecard System Software Replacement

TOTAL FUNDING: $150,000 (IT Replacement Project Fund)

• Replaces the City’s custom built timekeeping system

• Provides web access functionality, mobile device accessibility and

integration with exiting Lawson financial system.

(80)

FY16-17 New ITP Projects

Website Rehosting

TOTAL FUNDING: $105,000 (IT Replacement Project Fund)

• Upgrades the City’s website functionality with a Content

Management System

• Allows for City staff to update the website without technical

assistance or resources

(81)

FY16-17 New ITP Projects

911 Phone System Replacement

• State funded project to replace Concord’s 911 Phone System

• Assures the 911 Dispatch Center is equipped to handle new E-911

call handling requirements

(82)

FY16-17 New ITP Projects

Mobile Data Computer Replacement

(TOTAL FUNDING: $660,000; IT Replacement Project Fund)

• Replaces Public Safety’s existing Mobile Data Computers

• Provides equipment that supports latest security and technology standards

• Provides mobile platform public safety Records and Computer Aided Dispatch

(83)

FY17-18 New ITP Projects

CCTV Public Safety and Crime Prevention Technology

Improvements

(TOTAL FUNDING: $350,000 including Measure Q Projects FY17-18: $250,000; Federal Asset Forfeiture FY17-18: $100,000)

(84)

Electronic Plan Review

(Technology Surcharge FY17-18: $315,000)

• Streamlines the submission and processing of building plans • Allows for electronically submitted building plans

• Will also allow for internal electronic review and processing

(85)

Point of Sale System Replacement

(IT Replacement Projects FY17-18: $160,000)

• Replaces the City’s End of Life Point of Sale system ( The system

that staff uses to process payments for permits, licenses and fees)

• Provides for a new system that meets regulatory needs for payment

processing and revenue collection

(86)

Capital Budget FY2016-2017 & 2017-2018