• No results found

Construction Claims in

N/A
N/A
Protected

Academic year: 2021

Share "Construction Claims in"

Copied!
31
0
0

Loading.... (view fulltext now)

Full text

(1)

Construction Claims in

the Gulf

the Gulf

ICES CPD Event – 12/2012

ADMC Auditorium

19 December 2012

D I S P U T E S & I N V E S T I G A T I O N S • E C O N O M I C S • F I N A N C I A L A D V I S O R Y • M A N A G E M E N T C O N S U L T I N G

(2)

Context

»

Aftermath of 2008 / 2009 financial crisis

Some settlements but many claims now in arbitration / local courts

Suspension and termination

Exodus of personnel (and knowledge)

Exodus of personnel (and knowledge)

Payment issues (Insolvency ?)

Unresolved variation accounts and claims

Subcontractor vs. Main Contractor

Quality factors

Relationships / hope for negotiated settlement

Many claims prepared quickly

Many claims prepared quickly

Complex factual matrix

Lack of personnel / recordsp

(3)

New reality

»

Culture changes

Taboo of disputes reduced (not extinguished)

Ability to settle changed

Greater accountability

Greater accountability

Need to show value achieved

Maturity ?

»

Markets

Workloads improving regionally – still competitive / lower margins

Return of Inflation

Future overheating ?

Financial / political uncertainty

Financial / political uncertainty

»

Lessons to be learnt

(4)

What does a Claim do ?

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources, D (and not for

th

)

any other reason)

4

D cost E

4.

D cost E

(5)

Evolution

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources D

4.

D cost E

(6)

Evolution

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources, D

4.

D cost E

(7)

Causal Linkage

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources, D

4.

D cost E

(8)

Causal Linkage

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources, D

4.

D cost E

(9)

Causal Linkage

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources, D

4.

D cost E

5.

E, under the Contract or at Law, is the liability of A

(10)

Causal Linkage

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen (and not some other cause)

3.

C involved or affected the resources, D

4.

D cost E

5.

E, under the Contract or at Law, is the liability of A

(11)

Causal Linkage

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources, D

4.

D cost E

5.

E, under the Contract or at Law, is the liability of A

(12)

Causal Linkage

1.

A did or did not do B

1.

A did or did not do B

2.

B caused C to happen

3.

C involved or affected the resources, D

4.

D cost E

5.

E, under the Contract or at Law, is the liability of A

(13)

Typical Components

»

Delays to completion

»

Delays to Work

»

Increases in cost and resources

»

Changes

»

Allocation of risk

»

Delays to payment

»

Delays to certification

y

(14)

Authority for a Claim

»

Claim under the Contract – a Clause that allows for or provides for a

claim

claim

Eg. FIDIC – Clause 42.2 – Failure to give Give Possession

If the Contractor suffers delay and/or incurs costs from failure of the If the Contractor suffers delay and/or incurs costs from failure...of the Employer to give possession... The Engineer shall...determine

(a) any extension of time....and (b) the amount of such costs...

»

Claim for Breach of Contract

F il f t d thi d i thi i f th t

Failure of someone to do something or doing something in excess of that

provided under the Contract for which there is no express procedure to claim eg. failure to give approval

»

Claim at Law (other than Breach of Contract)

Pursuant to a provision of the Civil Code or some other part of the law (eg. acting i b d f ith f bilit f d d

in bad faith, enforceability of pre-agreed damages

(15)

Delay / Prolongation Claims

»

Delay analysis (usually a component)

Different types of analysis (subject in its own right)

Often need for regularly updated programmes Logical programmes

Logical programmes

As Built records / progress reports

Analysis / result can be confused and expensive to ascertain if problems with the Analysis / result can be confused and expensive to ascertain if problems with the above

Records, records, records – who did what, when and why ?

f f

Identification of when delay occurred

Identification of concurrent delays

How to deal with concurrent delays

How to deal with concurrent delays

Acceleration ?

(16)

Delay / Prolongation Claims

»

Time does not always equal money

Cl 44 1 (b) E T f d l f d t i th diti

Clause 44.1 (b) – EoT – any cause of delay referred to in these conditions

Cl 6.4 – Delayed issue of Dwgs – Time and cost

Cl 12 2 – Obstructions – Time and costCl 12.2 Obstructions Time and cost

Cl 27.1 – Fossils – Time and cost

Clause 44.1 (d) – EoT – delay, impediment or prevention by the Employer

Money ?

Clause 44.1(e) – EoT – Other special circumstances (not Contractor default)

Money ? Money ?

[ Force Majeure under FIDIC 99 allows cost for some events]

(17)

Prolongation Costs – Periods of Delay

»

Use the correct periods of time

Period when delay actually occurs

Site running costs (not preliminary prices) Direct additional HO costs

Direct additional HO costs

Overrun period (between original / extended completion date) Overrun period (between original / extended completion date)

Insurances / bonds

Escalation / inflation

HO Overhead / formulae claims

Financing claims

Identify periods of concurrent delay

SCL Protocol

(18)

Prolongation Costs – Operational costs

E t d d i t

»

Extended running costs

Critical delay periods

Non–critical delay periods - prolongation of specific items – eg tower cranes

Non–critical delay periods - prolongation of specific items – eg. tower cranes

Site running costs

Need Cost ledgers – need to prove cost – invoices

Separate running costs from mobilisation / demobilisation

Separate time related costs from work related costs ff C

Head office Costs

Specific resources allocated and involved with Project – need some sort of record

Procurement

Specific Management

(19)

Prolongation Costs – Escalation

»

Escalation / inflation

Function of delay ?y

Delay in completion - Overrun period – outside risk of original contract period in price

D l i t ithi C t t P i d ll l / l

Delay in procurement – within Contract Period – usually complex / unclear

Concurrency

Duty to mitigateDuty to mitigate

(20)

Prolongation – Loss of Contribution

»

Lost Head Office overheads

The A Team were tied up on the Project

The A – Team were tied up on the Project

But for the delay in completion they would be earning operating profit / overhead contribution elsewhere

Uses a formulae

Variety to choose from

S t t i t di t th f t t d i th US d l

Some controversy – trying to predict the future – accepted in the US and lesser degree the UK

Tests to satisfy y

Constraint

Proof that other work turned away / reduction in overhead recovery – drop in tturnover

That resources were finite – couldn’t hire another A Team

No increase in turnover that could pay for lost contributionNo increase in turnover that could pay for lost contribution

(21)

Prolongation Costs - Financing

»

Funding of construction over a longer period ?

»

Funding of construction over a longer period ?

Release of retention

Comparison of cashflows

Speculative

Proof of loss / cost – Financing costs

C t i diti

Current economic conditions

Low interest rates

(22)

Acceleration

»

Instructed acceleration - a variation

Agreement to accelerate with liability for costs

Clause 51.1 (g) – Change in sequence, timing of the works

O j t t ld t h

?

»

Or just told to hurry up ?

»

Constructive acceleration

L ll l / t i

Legally complex / uncertain

»

To calculate cost (if not pre-agreed cost and resource)

Need to know exact delays and causes

Need to know exact delays and causes

Need to know which resources overcame which delays

»

If no agreement / instruction to accelerate then why are you doing it ?

»

If no agreement / instruction to accelerate then why are you doing it ?

Calculated risk

(23)

Disruption - 1

»

Difficult

Definition

Took longer / cost more because of some change in circumstance Usually complex many factors

Usually complex – many factors

Records, records, records

Webcams / TechnologyWebcams / Technology

Detailed records – contemporaneous allocation of resource to activity and location

C ( ) C f

Clause 51.1 (g) – Change in sequence, timing of the works

Level of return ? - Cost of labour / Cost of plant

Level of return ? - Cost of labour / Cost of plant

No easy answers – lots of books full of impractical advice

(24)

Disruption – 2

»

Global Claim

Total cost / resource less planned cost / resource

Circumstances in which appropriate / successful – very rare Impossible to otherwise calculate

Impossible to otherwise calculate

No other causes / Contractor default

Planned resource / cost was realisticPlanned resource / cost was realistic

Additional costs / resources realistic

Mitigation

Don’t do it - Credibility ?

Reversal of burden of proof ?

Reversal of burden of proof ?

(25)

Disruption – 3

»

Measured Mile – Project data

Find undisrupted work

Compare with disrupted work

Need to know which resources were doing what and when

Need to know which resources were doing what and when

Better than global claim

But ensure that both disrupted / undisrupted periods are not contaminated (or But ensure that both disrupted / undisrupted periods are not contaminated (or make proper allowance / adjustment)

»

Measured Mile – Industry data

Oil & Gas industry good at this because of QA - can usually retrospectively rebuild project from data – Civils and Building Industry is not

rebuild project from data – Civils and Building Industry is not

Few studies – how is the performance of MEP installation in Idaho relevant to Dubai ?

(26)

Finance Claims

»

Legal issues in UAE / GCC

Get legal advice on what is admissible

Potential distinction between claim for Financing Cost

Financing Cost

Claim for Interest

When does it run from ?

Penalised if you don’t borrow money ?

(27)

Conditions Precedent

»

Notices

A need to alert the Engineer / Employer

Mitigating action

No reason not to get them in if you are not sure whether any effect then say so

No reason not to get them in – if you are not sure whether any effect then say so but rectify as soon as possible

Sanctions vary under different contracts - Legal issues re. relying on procedural issues to escape liability – degree of prejudice

Don’t give opportunity for argument and at least open dialogue (argument ?) on topic

topic

»

Particulars

Similar issues apply – submit as soon as you are able – if not possible (or only Similar issues apply submit as soon as you are able if not possible (or only partially possible) then say so

Level of detail – enough for the Engineer to do his job – sufficient for arbitration ?

(28)

Interim Certificates

»

Insolvency / Suspension / Termination

»

Defects

Deduct fairly from interim certificates M f d d ti

Measure of deduction

Price of work in Contract Price or

Cost of remedial Work by a third party ?Cost of remedial Work by a third party ?

Insolvency / Termination

Back to back Subcontracts

»

Valuation of Preliminaries

Time related

Work related

Contractor delay / dispute delay

Rebase preliminaries

(29)

Consequences

It is perfectly clear that some of the elaborate literary efforts put forward as… claims are works of fiction rather than fact It is all too easy for a contractor who finds at the end of a contract that he has lost rather than fact. It is all too easy for a contractor who finds at the end of a contract that he has lost money to exaggerate the minor delays inevitable in large-scale work and to distort the real sequence of events by alleging delay caused by the engineer when in fact he was not in any case ready to do the work involved The result is a wildly exaggerated claim costed out in the vaguest possible way work involved. The result is a wildly exaggerated… claim costed out in the vaguest possible way.

Provided his lawyers create the maximum confusion at the arbitration about what actually happened on the works (and the standard arbitration procedure almost seems designed to help to that end …) he can hope for a substantial award from an arbitrator.

can hope for a substantial award from an arbitrator.

It is grossly unfair both to employers and contractors that the mechanism to determine the actual full costs….. to a contractor, and to divide them from the costs due to his own inefficiency, is lacking more often than not

often than not.

A party to a dispute, particularly if there is arbitration, will learn three lessons (often too late): the importance of records, the importance of records and the importance of records. It is

impossible to exaggerate the extent to which lawyers can find unexpected grounds often quite impossible to exaggerate the extent to which lawyers can find unexpected grounds, often quite real, on which to cast doubt on evidence if it is not backed by meticulously established records. It must also be remembered that the arbitrator will know nothing about the history of the work, which must be reconstructed… with all its complexities and nuances, from the records

which must be reconstructed… with all its complexities and nuances, from the records available.

(30)
(31)

Construction Claims in

the Gulf

the Gulf

ICES CPD Event – 12/2012

ADMC Auditorium

19 December 2012

D I S P U T E S & I N V E S T I G A T I O N S • E C O N O M I C S • F I N A N C I A L A D V I S O R Y • M A N A G E M E N T C O N S U L T I N G

References

Related documents

The study is helpful for many players in Home Appliances to make following strategies related to advertising for any particular company: -..  Advertising

Results of the survey are categorized into the following four areas: primary method used to conduct student evaluations, Internet collection of student evaluation data,

The key segments in the mattress industry in India are; Natural latex foam, Memory foam, PU foam, Inner spring and Rubberized coir.. Natural Latex mattresses are

We have loved them during life, let us not abandon them until we have conducted them, by our prayers, into the House of the Lord.. Jesus, have mercy on the

A number of test procedures was developed within the case study environment to assess the ability of virtual commissioning to aid to the validation of a system and the

If breastfeeding by itself doesn’t effectively remove the thickened inspissated milk, then manual expression of the milk, or the use of an efficient breast pump after feeds will

Identifying the CTD under Different Market Conditions 31 Profit and Loss Profile on the Last Trading Day, Long Fixed Income Futures 33 Profit and Loss Profile on the Last Trading

For the poorest farmers in eastern India, then, the benefits of groundwater irrigation have come through three routes: in large part, through purchased pump irrigation and, in a