• No results found

Safety & Loss Prevention

N/A
N/A
Protected

Academic year: 2021

Share "Safety & Loss Prevention"

Copied!
80
0
0

Loading.... (view fulltext now)

Full text

(1)

Contractor:

Project Name:

Construction of pier and integrated building On

Alhuwisat Island.

Owner:

General Administration for border guards

Contract No.

219 m / 34/24

(2)

Job Title:

Construction of pier and integrated building On

Alhuwisat Island.

Scope of work:

Is to construct a pier and a full integrated building

on the Island in the eastern area which include:

1. Main building.

2. Mosque.

3. General location.

4. Communication tower.

5. Breakwater & pier.

(3)
(4)

INDEX

Chapter

No.

Safety Topics

Page No.

1 Introduction

2 Function & Responsibilities

3 Construction Safety Organization 4 Safety Education & Training 5 Site Planning & Housekeeping

6 Personal Protective Clothing & Equipment 7 Accident Report & Records

8 Safety Orientation of Craft Man, 9 Welding & Cutting Operation 10 Hand & Power Tools

11 Fire Protection & Hazards

12 Housekeeping

13 Temporary Heating Devices 14 Fire Extinguishers

15 Work Permit

16 Traffic Safety

17 Safety Officer's & Supervisors safety meeting

18 First Aid

19 Incentive Program

20 Proposed Security Program 21 Emergency Procedures & Numbers 22 Ten basic Safety Rules

(5)

PROPOSED SAFETY, SECURITY & FIRE

PREVENTION PROGRAM

1.Introduction

It is the intention of ABSAR to implement and ensure as far as is reasonably practicable, the health and safety of all their employees, subcontractors, and all personnel those who are entering to the project and all other bonafide visitors. Safety officer will ensure that all personnel entering to project construction site comply with the client safety rules and procedures. Safety officer will also ensure all employees and subcontractors are aware of the safety rules and regulations. Provide induction training and safety instructions to all workers and visitors entering the worksite and ensure that it is fully understood.

(6)

DEFINITIONS

GENERAL CONTRACTOR: Arabian Building Support and Rehappitation Company , General Contractor

CONTRACTOR (Designated) SAFETY COORDINATOR: The individual assigned by the Contractor or Subcontractor to perform the onsite safety duties.

EMPLOYER: Any insured performing work under contract at the job site. OFF-SITE: Any premises outside the fenced property of the job site. ON-SITE: The premises within the fenced property of the job site. OWNER: General Administration for border guards.

PROJECT: Construction of pier and an integrated building Al-Houisat island

PROJECT MANAGER (TBD): The individual assigned by the General Contractor with overall project responsibility.

PROJECT SAFETY COORDINATOR (TBD): The individual assigned by the General Contractor that supervises all of

the Subcontractors to ensure safety at the job site.

PROJECT SAFETY PROGRAM: The manual that identifies the requirements for The Project’s safety and loss

prevention program as established by the General Contractor.

PROJECT SUPERINTENDENT (TBD): The individual assigned by the General Contractor who supervises all

Subcontractors at the job site.

(7)

2.0 Functions And Responsibilities:

A)Policy is an important element of the project and requires the attention and involvement of all

project personnel. Every individual in the company will be made aware of the company’s safety policy and attitude towards the control of accidents, damage to equipment and fire, and of the part one has to play to achieve this end. Each employee should satisfactorily discharge the responsibilities allocated to him and there should be no doubt that his safety records will be taken into account when promotion or other rewards are being considered.

(8)

Contractor project

manager

Contractor Safty

Officer

Site Engineer

Forman

LOGISTIC

OFFICER

Client

Consultant project

manager

Constsltant safty

officer

3.0 CONSTRUCTION SAFETY ORGANIZATION

The management at each level of authority will be responsible for the result of construction safety program.

A.Project Manager

The project Manager has the over all responsibility for implementation and supervision of the project safety program, and for providing the interface between senior management, other department managers and Safety Officers. This does not relieve all other managers and personnel from their responsibility to actively promote and supervise safety activities within their respective organizations and does not preclude day-to-day working relationship between safety officer and all other

organizations.He will administers the safety policy of the company during the duration of the contract for construction and other related jobs.

(9)

He will implements the safety policy of the company for the control of injury , damage and fire. He will follow the requirements of contract and the relevent parts of government workman's regulations and ensure that they are complied with.

He will ensures that all levels of supervision receive adequate safety training and are qualified. He will coordinate with representatives of the Loss Prevention Division and other involved organization.

He will make sure the reporting system involving accident or fire , is in accordance with the

requirements this Safety Manual and the International OSHA Standard Requirements and he will set a personal example.

B. Site

ENGINEER:-He will follow the requirement of construction contract and relevent parts of the Government Worksman's Regulation and will ensure ,they are complied with.

He will allocate the responsibility for all key men of company, subcontractors and others. He will follow the Work Permit Procedures in restricted areas.

He will be responsible for adjustment to change in the safety requirements of construction project. He will be responsible for potential hazards on new contracts before work start.

He will recommend to improve existing work methods and work areas.

He will conducts investigations of accidents analyze causes and recommend preventive measures to avoid and minimize occurances of accidents.

He will insist in the safety training of employees in coordination with safety officer. He will conduct weekly safety meeting in coordination with safety officer and all workers..

C.Safety Officer:

(10)

safety requirements and of client safety program procedures.

Training site personnel, conducting weekly safety meeting, ensuring that all personnel adhere to safety requirements, periodical checking of personnel and safety equipment’s coordination and site visit with safety representative,ABSAR ensuring corrective action if found any lapses, perform safety audit and submit records to Contract Administrator, or Client Representative cooperate with the client and consultant representative in complying with all safety rules and procedures.

All necessary records related to safety will be maintained and Safety Officer will report directly to the Project Manager if there is NO Safety Manager or Safety Supervisor required in the project.

He will be responsible for safety training of employee and will conduct weekly meetings with all workers and keep a record of the meeting and He will attend job progress meeting regularly.

He will conduct daily safety inspection in the work areas and will take notes of unsafe conditions and recommends the means of removing hazards in the job and correct unsafe acts of workers and He will keep a permanent record of all injuries and property damage at the site

He will motivate employees to work safely through safety promotion activities.

He will prepare the topics, supervise and observe weekly Safety Tool Box Talks to be conducted by the Craft Foremen, and Supervisor for a 15-20 minutes every first day of the work week, with records keep.

D.FOREMAN

He will be familiar with the requirements of the contract.

He will conduct weekly Safety Tool Box meetings with workers and will correct unsafe acts commeted by workers and He will give instructional safety talks to workers prior to the start of the job He will report unsafe conditions in the job site as well as unsafe acts by workers.

*based on the JSA (Job Safety Analysis) initiated by the Safety Department, or Safety Officer based on the approved Method of Statement of that specific activity.

E.LOGISTIC OFFICER

he will ensure equipment to be used in construction work is safe.

He will ensure that equipment operators are trained , qualified, & authorized and certified by a 3rd Party Certifying Agency approved by the client.

He will check the periodic testing , routine inspection and maintenance schedules on due dates and He will ensure that equipment checklist have been filled up and signed by proper authority prior to its daily use or operation at site.

(11)

He will recommend site management to take dangerous or defective equipment out of service untill repaired.

He will be responsible for delivery of materials and equipment to site in safe.

F. Q.A & Q.C. Engineer

He will be well familiar with the requirements of the contract.

He will be responsible for the safety regarding his side for insuring the Q.A & Q.C. program. He will insure the safety of equipment used in Q.A. & Q.C. program.

He will coordinate and familiarize the safety program with independent testing laboratory which will do the testing of deferent material etc.

He will attend the safety meeting whenever it is required.

He will coordinate with safty department\crew for any safty barrication or signbord requirment for any material and equipment deliverd to the site.

G.WORKERS

All the workers will use correct tools and equipment.

All the works will be done safely and always they will follow existing safety procedure. All the workers will keep tools in a safe condition.

All the workers will wear safety shoes,hard hat and other required protective clothing and equipment as per the nature of work.

Do nothing to endanger self or workmates.

Refrain from horseplay and abuse of safety devices, equipment, and welfare facilities. Report any accident, near misses, or hazardous conditions to immediate supervisor. Read company safety rules, and take of the safety precautions for the new activity at site. Obey all posted warning signs.

H.DRIVERS

All the drivers will have government's driving license.

All the drivers will have accessory tools and other safety equipment.

All the drivers will follow posted minimum and maximum speed on highways and in towns as well inside plants.

(12)

All the drivers will be responsible for the maintenance of the equipment they are using and see to it that it is in good condition always.

4.0 Safety Education And Training:

A.Policy:

Safety Officer will make sure that each employee is instructed regarding work hazards and methods and the methods by which these hazards are controlled. Instruction regarding safety program will be provided through weekly tool box safety meeting.

B.Orientation of Manual and Non-Manual Employees:

The minimum of 15 minutes will be allotted for the safety orientation of all new hired employees by the contractor. The individual responsible participation in this orientation program will be encouraged. This will be minuted and records keep for future reference.

C. ADDITIONAL TRAININGS:

All ABSAR employee are trained for there job and tool box training will be sufisiant for keeping the workers in safe condition.

Each employee who is potentially exposed to chemicals or physical hazardous

will receive training:

New employees will receive training on the contents of this program and

specific training on the chemicals that the individuals will be directly

working with during orientation and prior to performing work where

exposure may occur.

Additional training will be provided for employees whenever a new chemical is

introduced into their work area.

As warranted, training may be provided based on the uniqueness of the hazards

to be encountered at an inspection worksite.

The training program will emphasize the following elements:

a. A summary of the HCS and the written program;

(13)

b. Hazardous chemical properties, including visual appearance and

odor, and methods that can be used to detect the presence or

release of hazardous chemicals;

c. Physical and health hazards associated with potential exposure to

hazardous chemicals;

d. Procedures to protect against hazards, such as personal protective

equipment, work practices, and emergency procedures;

e. Hazardous chemical spill and leak procedures; and

f. Location of MSDSs, how to understand their content, and how

employees may obtain and use appropriate hazard information.

And In case of a new job ariconduct training how to do the job and the workers awareness about the safety requirements in doing the job if the need arises.

5.SITE PLANNING AND HOUSEKEEPING

5.1 INTRODUCTION

Good housing keeping will be done because it is an important element of the construction safety program and an essential tool in accident prevention.

Good housing keeping will be planned at the beginning of the job , carefully supervised and seriously followed up until the final clean up.

5.2 SITE PLANNING

ABSAR co. will carefully analyze the loss prevention program and its implentation scheme from the planning stage , through the duration of construction work and up to the final stage of the contract prior to the start of any construction contract.

Site layout will be planned before work is started. Items to be included in the plan are site office ,parking facility, watersupply, drainage supply , electricity supply, safe means of excess and egress, perimeter fencing, and fire protection.

The contractor will maintain the entrance and exit of people in the worksite and offices by a security personnel at the gate with the workers issued ID PASS and wearing ABSAR worker outfit and safety clothes.

(14)

 5.2.1: SITE SAFETY STAFF: Contractor has to maintain a qualified and client approved Safety Staff to monitor all the Safety Related activities, conditions and situations to maintain the worksite at its acceptable level of safety.

The minimum number of Safety Staff shall be in accordance with the following: CONTRACTOR SITE SAFETY STAFF REQUIREMENTS: #

Employees

Safety Manager Required

Min. # Safety Supervisors Required

Ratio of Safety officers to Employees Present (min)

1 - 25 No No At least One (1)

26 - 50 No No One (1)

51 - 500 No One (1) 1:50

501 - 1000 Yes 1 for every 10 Safety

Officers

1:50

5.2.1a Site Safety Manager Shall be fluent in written and spoken English and Shall have at least 10 years of Safety Experienced

.

Specific to the Contract’s scope of work.

5.2.1b Site Safety Supervisor shall be fluent in written and spoken English and shall have at 7 years of safety experienced specific

To the contract’s scope of Work.

5.2.1c Fields Safety Officer Shall be fluent in written and spoken English and

.

Have at least 5 years of safety experienced specific to

.

The contract scope of Work.

5.3 GOOD HOUSEKEEPING

.A high standard of housekeeping will be established by ABSAR Co. within the construction site.

Housekeeping activities will be done on daily basis ofter finishing any activity to maintain the safe working environment.

Working areas, roadways, access ways, stairways, and scafolding platform will be kept free of unnecessary obstruction.

Tools, nuts, bolts, washers, fittings etc, will be kept in boxes.

Electrical cables, welding hoses, conduits, and pipes will be properly arranged so they do not become a tripping hazard. Cable Management shall be carefully adopted and maintain in all areas of work throughout the project site.

(15)

The following list provides a general of certain electrical safety requirements should be considered that affect the average employer.

1. Trained personnel only should be permitted to perform electrical work.

2. Employees must report, as soon as possible, any obvious hazards to life or property observed in connection with electrical equipment or lines.

3. All employees who may be working on electrical equipment or lines must be instructed to make preliminary inspections or conduct appropriate tests to determine the existing conditions before they start such work.

4. Switches must be opened, locked out, and tagged when electrical equipment or lines will be serviced.

5. Portable electrical tools must be grounded or double insulated.

6. Extension cords used in the workplace should have a grounding conductor.

7. Extension cords must be inspected and their condition recorded in a written inspection log on monthly basis. Extension cords longer than 150 feet should never be used. Multi-plug adapters are prohibited.

8. Temporary circuits must be protected by suitable disconnecting switches or plug connectors at the junction with permanent wiring.

9. Exposed wiring and cords with frayed or deteriorated insulation must be replaced or repaired promptly.

10. Flexible cords and cables must be free of splices or taps (splices in a cord used to add another outlet).

11. Clamps or other securing means must be used for flexible cords or cables at plugs, receptacles, tools, and equipment, for example, and the cord jacket must be securely held in place.

12. All cord cable and raceway connections must be intact and secure.

13. For wet or damp applications, electrical tools and equipment must be the appropriate type, or otherwise protected, for such use.

14. The location of electrical power lines and cables (overhead, underground, under floor, or other sides of walls) must be determined before digging or similar work begins.

15. Use of all metallic measuring tapes, ropes, hand lines, or similar devices with metallic thread woven into the fabric is prohibited when these items may contact energized parts of equipment or circuit conductors.

16. Use of metal ladders is prohibited when a ladder or the person using that ladder could contact energized parts of equipment, fixtures, or circuit conductors.

17. Disconnecting switches and circuit breakers must be labeled to indicate their use or the equipment served.

18. All disconnecting means must be opened before fuses are replaced.

19. All interior wiring systems must include provisions for grounding metal parts of electrical raceways, equipment, and enclosures.

20. Sufficient access and working space must be provided and maintained around all electrical equipment to permit ready and safe operations and maintenance.

21. All unused openings (including conduit knockouts) in electrical enclosures and fittings must be closed with appropriate covers, plugs, or plates.

22. All electrical enclosures such as switches, receptacles, and junction boxes must be provided with tight-fitting covers or plates.

23. Each motor disconnecting switch or circuit breaker must be located within sight of the motor control device.

24. Employees who regularly work on or around energized electrical equipment or lines must receive CPR training.

Scrap lumbers, materials, unused materials and unnecessary materials such as debris will not be scattered around the job site nor the offices. It will be collected on daily basis and transported to the in the denailing area, barricated and sign posted. Making it clear that NO scrap wood / plywood with protruding nails scattered around the worksite.

(16)

Trash cans will be available and used.

5.4 Dust Suppression

The contractor will Supress Dust in the worksite especially at roads and other access ways, on daily basis At summer days using :

1. Limit Cleared Areas 2. Physical Barriers 3. Site Traffic Control 4. Earth Moving management

5. Watering Sprays

 Spraying of water on access roads shall be done twice during summer, one in the morning and one in the afternoon or as required when the road become dry and dusty due to the passage of construction equipment and other vehicles. The water to be used shall be determined by the QA / QC or as required if it affects quality requirements of the project.

 Reverse Alarm and rotating blinking Lights of the Water Tankers must be activated and Bunks Man to wear the required Reflectorized Vest all the time at site and he must not positioned himself that is concealed from the side view mirror of the driver.

6. Soil Compaction 7. Site Completion

Reverse Alarm as for all the heavy duty vehicle will be activated and Bunks Man will wear the required reflectorized vest all the time at site.

5.5 HAZARD IDENTIFICATION PLAN:

hazards which are expected in the project by workers include:  Falls (from heights);

 Scaffold collapse;

 Electric shock and arc flash/arc blast;

 Failure to use proper personal protective equipment; and  Repetitive motion injuries.

S/N

Activity

Sub - Activity

Significan

t Health

and Safety

Hazard

Preventive / Control Measures

(17)

welding getting rid of combustible materials and scraps.

• Welding Machine Safety checklist to be filled in prior to start work. • Fire Watch shall be employed in the

area of work.

• Stationed Fire extinguishers, water and sand buckets near the area of work

• Cover weld location with Fire Blanket to refrain sparks from flying out . Burns • Use the specified hand gloves for the

job.

• Use the appropriate clothing and special protection intended for the work like ultra violate rays protection • Use the correct and appropriate

welding mask.

2. Excavation Mobilization of

Equipment Unstable Soil condition

• Provide access for the heavy equipment delivery in the worksite.

4 Equipment collision with other equipment and existing installations.

• Licensed and Heavy Equipment driver.

• Assign Bunks man with whistle and wearing high visibility jacket. • Reverse Alarm to be activated

.

Mechanical

Digging Underground Utilities • Licensed and certified equipment operator to be used at site. • Identify and marked presence of

underground utilities by cable /pipe detector base on as-built drawing. • Expose all underground utilities by

trial exploration by manual excavation.

• When exposed identify and marked prior to mechanical excavation. • Assigned an experienced and trained

spotter to guide the operator during excavation.

• Barricade the area around the excavation and install Deep Excavation Signboards. Cave – ins or

collapse • Assign competent person to evaluate the type of soil being excavated. • As a protection to avoid cave ins or

collapse either put shoring as appropriate, or slope back to the required angle or benching.

• Install ladders at 25 ft, distance from its other.

• Barricade the area around the excavation and install Deep Excavation Signboards.

(18)

standby man with rescue equipment ready.

High Water

Table • Install Dewatering System Provide Competent Maintenance personnel for a continuous operation. • Barricade the area around the

excavation and install Deep Excavation Signboards

• Inquire from authority where to dispose the dewatered water to verify if safe to dispose in the area or back to the sea.

5 Scaffolding Falling Scaffold must be sound, rigid and

sufficient to carry its own weight plus four times the maximum intended load without settling or displacement. It must be erected on solid footing.

• Unstable objects, such as barrels, boxes, loose bricks or concrete blocks must not be used to support scaffolds or planks.

• Scaffold must not be erected, moved, dismantled or altered except under the supervision of a competent person.

• Scaffold must be equipped with guardrails, midrails and toeboards. • Scaffold accessories such as

braces, brackets, trusses, screw legs or ladders that are damaged or weakened from any cause must be immediately repaired or

replaced.

• Scaffold platforms must be tightly planked with scaffold plank grade material or equivalent.

• A "competent person" must inspect the scaffolding and, at designated intervals, respect it.

• Rigging on suspension scaffolds must be inspected by a competent person before each shift and after any occurrence that could affect structural integrity to ensure that all connections are tight and that no damage to the rigging has occurred since its last use.

• Synthetic and natural rope used in suspension scaffolding must be protected from heat-producing sources.

• Employees must be instructed about the hazards of using

(19)

diagonal braces as fall protection. • Scaffold can be accessed by using

ladders and stairwells.

• Scaffolds must be at least 10 feet from electric power lines at all times.

6 Plastering Fall

Protection • Consider using aerial lifts or elevated platforms to provide safer elevated working surfaces;

• Erect guardrail systems with toe boards and warning lines or install control line systems to protect workers near the edges of floors and roofs;

• Cover floor holes; and/or • Use safety net systems or

personal fall arrest systems (body harnesses). • • • • • •

5.6 MECHANICAL LIFTING AND LIFTING EQUIPMENT:

(20)

• 5.6: MECHANICAL LIFTING AND LIFTING EQUIPMENT:

5.6.1 CRANES AND LIFTING EQUIPMENTS:

5.6.1a Contractor / ABSAR shall mobilized any crane of the required capacity either company owned or from a rental company shall be of good operating condition complying with the standard requirements for sound operation. Load Moment Indicator (LMI) SHALL BE OPERATIONAL. Anti-two Blocks control operational; with the Load Chart inside the Operator cabin. The Hook Safety locked in good working condition. If wind velocities are above 32 k/h (20mph) the rated load and boom lengths shall be reduced according to manufacturer’s specifications. If the crane to be operated near Electrical Power Lines the following shall be followed:

Line Voltage Absolute Limit of Approach

Up to 250,000 Volts 20 ft. (6 m)

Over 250,000 Volts 25 ft. (7.5 m)

5.6.1b ABSAR shall only mobilize Crane of the required Capacity in the project site with the valid 3rd Party Certification issued by a 3rd Party certifying Agency approved by the client.

5.6.1c Contractor / ABSAR shall mobilized Crane Operator in the project with the valid 3rd Party certificates issued by a 3rd Party Certifying Agency approved by the client.

5.6.1d Contractor / ABSAR shall mobilized Rigger in the Project site with a valid 3rd Party Certificate issued by a 3rd Party Certifying Agency approved by the client.

5.6.1e Contractor / ABSAR to assign a competent person to categorize whether a lift is critical or not, if Critical Lift per SA GI 7.028; A critical Lift Plan / Lifting Plan shall be prepared by the contractor Rigger II OR Project Engineer and approved by the Rigger – I OR client’s representative prior to start the work at site, using the standard Lift Plan Form.

5.6.2 SLINGS AND LIFTING GEARS:

1. 5.6.2a Contractor /ABSAR shall use only lifting or rigging hard wares with the SWL (Safe Working Load) inscribe in the hardware body itself with certifications from the manufacturer. For the following: Chain Slings, Wire Slings, Synthetic Webbing Slings, spreader bars, shackles, man baskets. Etc.

2. 5.6.2b Contractor to maintain all rigging hardware’s in good condition always, protected from direct sunlight and rain and before storing it need slight application with grease. It has to be inspected regularly, every 6 months with records.

(21)

3. Forklifts

 Train and certify all operators to ensure that they operate forklifts safely.  Properly maintain haulage equipment, including tires.

 Do not modify or make attachments that affect the capacity and safe operation of the forklift without written approval from the forklift's manufacturer.

 Examine forklift truck for defects before using.

 Follow safe operating procedures for picking up, moving, putting down and stacking loads. Drive safely--never exceed 5 mph and slowdown in congested or slippery surface areas.  Do not handle loads that are heavier than the capacity of the industrial truck.

 Remove unsafe or defective forklift trucks from service.  Operators shall always wear seatbelts.

 Avoid traveling with elevated loads.

 Assure that rollover protective structure is in place.

 Make certain that the reverse signal alarm is operational and audible above the surrounding noise level.

5.6.3 MECHANICAL EQUIPMENT COMMONLY USED AT SITE:

5.6.3a Contractor will describe that the following list of equipment and its operators shall be certified by a 3rd party certifying agency approved by the client before it will be used at site as a standard requirements.

5.6.3b The following are the equipments:  Cranes  Excavators  Bobcats  JCB  Graders  Dozers  Forklifts  Welding machines  Roller Compactors

5.6.4 GENERAL RULE OF OPERATION AT SITE:

5.6.4a No passenger to be allowed in any Heavy Equipment while operating the site. 5.6.4b No passenger to be allowed at the back loading cab of trucks, pick ups, and other

machineries except seating be provided and adequately covered for passenger protection. 5.6.4c All machineries, trucks, pick ups and other vehicles shall follow the maximum Speed

limits posted in the worksite.

5.6.4d Towing of small machineries can be allowed provided it is properly hooked to the towing machines and it shall be driven at a maximum of 40kph, but if in the work site the posted maximum speed shall be followed at any time.

5.6.4e The operators cabin of Cranes, Wheel Loaders, Excavators, JCB’s etc. shall be 360° visible to the operator; no obstruction of vision at any degress whatsoever.

(22)

5.6.4f All heavy equipment used at site shall have its Reverse Alarm and rotational blinking lights activated. For the reverse alarm it must be audible within a 15 meter distance from the equipment.

5.6.4g At any instance any Heavy equipment going back and forth along the site or maneuvering at site, Bunks Man shall be assigned to alert other people and the drivers for any incoming or pertinent hazard.

4.6.4h Traveling Heavy Equipment / Cranes at site can be allowed with an escort vehicle back and front with the Flashing Lights activated.

5.7 EXCAVATION, TRENCHING, AND SHORING

5.7.1 The purpose of the excavation is to provide a sewer pipe lines and electical cable and communiction cables with shalow depthes and no obstructions is expected and incase of excavation deeper than 1.5m contractor will provide suitable shoring for the area

5.7.2 Contractor will describe the Method of Excavation (to be submitted and approved prior to start work at site)

5.7.3 From the approved JSA, contractor will draft a JSA (Job Safety Analysis), submit to client representative for approval prior to start work at site.

5.7.4 INSPECTION:

5.7.4a Contrator will inspec the excavation by a competent person on daily basis prior to the start of the work inside an excavation and incase of unusual condition contractor will keep a supervisor at the excavation area.

5.7.4b Excavated materials piled must be 0.6 m (2 ft) away from the brim of the excavation at all sides.

5.7.5 ACCESS and EGRESS:

5.7.5a Standard Straight Ladders to be installed at an interval of 15 meter (50 ft.).To Extend 1 m. (3 ft.) above the landing ground and it shall be securely fixed. 5.7.5b For crossing the excavated trench need to install a closed planked bridge with

standard guard rails, keep clear of excavated materials at both ends.

5.7.6 EMERGENCY RESCUE:

5.7.6a Contractor/ ABSAR shall assign Standby man outside an excavation 1.5m and below. With the log of the workers entry and exit from the excavation. 5.7.6b Contractor / ABSAR to provide Breathing Apparatus; Full Body Harness with

(23)

ready in case of emergency.

In case hazardous atmospheric condition exist, or may develop during the work in an excavation ABSAR to ensure that Gas Test equipment be available with the trained Gas Tester ready in any event of emergency..

5.8 WELFARE FACILITIES FOR SITE AND CAMPS:

5.8.1 Contractor workers will have there food allawance and will be responsible for there daily meals.

5.8.2 Contractor will provide rest shelter for workers at site during summer days with cold water and first aid equipment.

5.8.3 Contractor will provide Toilet Facilities at site and at camps. (either by rental portable toilets) it conform with the ratio of 15:1 or less. will be maintained in sanitary condition always.

5.8.4 Contractor will providing adequate drinking water to the workforce at site and camps with desposal glasses.

5.8.5 No smoking allwaed to the workers at site. 5.8.6 FIRST AID FACILITIES:

5.8.6a contractor will provide a suitably constructed ambulance ( or a suitable transportation) carriage maintained in good condition, for the purpose of the removal of serious cases of accident or sickness, unless arrangements have been made for obtaining such a carriage when required from a hospital or other place situate not more than 4 kilometers from the site, , and in telephonic

communication therewith

5.8.6b workforce Site Clinic to be will be a support for ambulance and a competent, trained, and certified medical staff / Male Nurse.

5.8.6d Male Nurse or First Aider will not be prescribe medicines.

5.9 CONCRETE, CONCRETE FORMS AND SHORING:

(24)

concrete will be poured using pump and the preparation of the area of pouring taking into consideration the checklist to be signed by all concerned discipline prior to pouring. 5.9.2 No concrete pouring will be done to or from high elevation due to the type of the project. 5.9.3 a provision of adequate lighting will be provided incase of concrete pouring outside the

regular daytime to the access point and at the work area.

5.10 DEWATERING SYSTEM:

5.10.1 Contractor to describe the procedures of dewatering system to be used at site. Describe the methods how it will be done enumerating the hazards to be incurred and the control measures to alleviate if not completely removed the hazard for the protection of the workers to be involved of the activity. JSA to be prepared by the SAFETY DEPT. to be approved by client representative prior to commence work at site.

5.10.2 Contractor also to site some special PPE solely intended for the job which also requires some special skilled individual.

5.10.3 Contractor to describe also the timing that the dewatering system will be working, with the provision to stand by personnel or mechanic during such timings.

5.10.4 Contractor to describe where to dispose dewatering water with the approval of local authorities to avoid problems with the environment. ( If it need sample for analysis for a 3rd party for it to be disposed in the locality then it must be done) Documentation is very important.

5.11 WORKING ON OR ADJACENT TO WATER:

5.11.1 Contractor to identify if cofferdams be required in the project. If it is so describe the hazards associated with it and state the control measures to alleviate it or completely eliminate it in the activity.

5.11.2 If so method of statement to be approved prior to start work. And JSA shall be drafted by the safety dept. and approved by the client representative prior to start at worksite.

(25)

job.

5.11.4 Contractor to describe the Emergency Procedure to evacuate the workers in case of emergency. 5.11.5 Contractor to describe special PPE for the workers to be involved in this activity.

5.11.6 Contractor to describe if Diving Operation will be required in this operation. If required then it shall be given due emphasis because it has its different requirements.

5.11.7 Remember the rise and fall of sea water as one of the factor to be considered.

6.

PERSONAL PROTECTIVE CLOTHING & EQUIPMENT

6.1 INTRODUCTION

The wearing of personal protective clothing and equipment will be compulsory requirement. Any worker if he fail will be penalize and will not be allowed to work at site.

Proper type of protective clothing will be provided to all labours as per the requirement of the job. Foremen and other supervisors will educate the importance of wearing protective clothing.

6.2

PROTECTION:-Every employee will wear a hard hat at all times on the job site as mandatory. Employees will be provided any of following personal protective equipment, such as eye protection, hearing protection, hand and foot protection, long trousers and long sleeves shirts, etc. whenever is considered to be necessary.

The wearing of the safety shoes is mandatory and no other unsuitable foot wears such as tennis shoes, slippers will be allowed.

Safety glasses will be used for eye protection against frontal impact and exposure to flying particles. Coverall chipping goggles will be worn when caulking , yarning, drilling, picking, sawing or chipping and for other dust producing conditions.

To protect hand proper type of gloves as per requirement of the job will be provided to each worker. Foot protection will be followed strictly.

No labour will be allowed to work without proper safety shoe.

All the safety shoe will be fitted with metal toe cap and comply with standard.

All employee will comply safety shoe rules when joining into the area where foot protection is required.

(26)

hazardous area and to reduce the possibility of a fall.

Ear plugs or ear muffs will be provided to labours in the working area if the noise level measurement is more than standard.

6.3 IMPLEMENTATION

Safety Officer will ensure that all employees will wear safety belt when work is above 2 . mtr or above the ground or when working in a revious position.

The lanyard shall be securely attached to the employee 100 percent of the time and shall allow maximum fall distance of 2.0 mtr.

Safety belt shall also be worn and attched to the tie off rail when working out of extensible and articulating boom platform and to vertical drop lines when working from.

7.

Accident Report And Records:

7.1 Report:

A report of all accidents will be made contract Administrator through the incident reporting system. Reports required shall be submitted promptly. Written report shall be submitted not later than 24 hours following occurrence. An immediate oral report will be made to the Authorized Representative in case of: all fatal injuries. All injuries requiring medical attention all incidents involving damage of

Contractor’s materials all fires initial oral reports of such incidents will followed by a written report detailing the circumstances, corrective action taken and recommended action to prevent recurrence. The written report will be made on a standard form acceptable to the client. In case of serious accidents, a full detailed account of the circumstances, with witness statements and descriptive photographs will be submitted.

7.2 Records:

In addition to the reports above, we will keep a record of all injuries and damage incidents on a form approved by the authorized representatives. A copy of this record will be sent each month to the authorized representatives. Injury analysis will be completed following each injury by the injured employee’s supervisor.

(27)

7.3 Monthly Safety Reports:

Monthly Safety Reports with worked man-hours and injury reports in the prescribed format shall be submitted to main client. The monthly report format shall be part of this Safety Manual, to be submitted and approved by the client’s representative.

a.) INCIDENT INVESTIGATION AND REPORTING:

• Contractor will notify, investigate, and report any injury, damage, or near misses occuring both in the worksite and outside the worksite. Incident report to be submitted to consultant, or client representative within 24 hours after the incident happen.

8.0 Safety Orientation Of Craft Foreman:

To ensure the foreman are familiarized with their supervisory safety responsibilities, a safety

orientation session will be conducted by the safety officer, with each foreman upon deployed on site. These session will highlight the project safety program and cover the following aspects:

8.1 Safe Work Area:

(28)

of his crew are assigned. Unsafe conditions that exist in the work area will be corrected prior to commencement of work, wherever possible. Otherwise, the problem shall be reported to the attention of general supervisor or the responsible superintendent who will initiate corrective action. The supervisor shall seek the assistance of the safety officer on complicated problem.

8.2 Safe Work Practice:

When making work assignments, the supervisor will inform his crew of the safe practice, work methods, and personal protective equipment required. He is responsible for ensuring that his men have the proper protective equipment and suitable tools for the job.

8.3 WORKING

PLACE:-a)Safety Officer will ensure that good housekeeping is maintained at all times on job site.

He will ensure that trash barrels are located throughout the job site, that excess scrap materials and rubbish dumped therein.

He will also ensure that toilets and other sanitary facilities are kept clean and food waste, paper bags are disposed off in the covered containers.

Construction site will be kept safe,clean and spacious. There should be adequate lighting & ventilation.

Portable fire extinguishers will be provided at working place. Emergency light will be provided and used when needed.

Contractor will keep good housekeeping withen the job site to prevent slipping , tripping and falling accidents.

8.4 Ladders

:

The ladders which will be used at job site will be enough length and good quality. Safety officer will ensure that workers comply with safety requirements.

When using ladders e.g.base of ladder set back 1/4 of the working length of the ladders, that it will be extended at least 1 mtr. above landing when used for access to a floor or platform.

Ladders projecting into passageways or doorways will be protected by barricades or guards. The ladder will be inspected every three months for any damage , deterioration , wear and tear, corrosion or structural failure.

Defective ladders will not be used and immediately removed from site.

(29)

Single rung and single clear ladders will be used by only one man at atime.

The user will not carry tools and materials in his hands when ascending or descending the ladder. Ladders shall be secured whenever it is positioned for use.

(30)
(31)
(32)

Proper scafolding will be provided to do all elevated work.Scafolding will be designed by a Scaffold Engineer if it be erected to a height of 38 meters and above. Built and dismantle by a competent and certified Scaffold Erector, under the supervision of the Certified Scaffold Supervisor and inspected by a scaffold supervisor if the height does not exceed 6.0 meters (20 ft), if higher a Certified Scaffold Inspector can only inspect scaffold is 6.0 meters high and above. The certified Scaffold Supervisor can sign and affix a Scaffold Tag to his limit of inspection only otherwise the Certified Scaffold Inspector can sign and affix Scaffold Tags. The only thing a Safety Officer can do to any scaffold, is to check for the tagging for conformity of erection and validity of date and recommend the mode of use by the end user.

Only scaffold conforming to the OSHA standard shall be erected at site Inspected by a competent and certified Scaffold Supervisor or Scaffold Inspector and appropriately tag.

All scaffolding will be erected and maintained to conform with established standards. It must be appropriately Tag; to guide the end user; For a Red Tag - it means it is incomplete and I or UNSAFE. It shall not be used; For a Yellow Tag- it means Scaffold was not built to meet scaffolding standard or the scaffold is incomplete Any person who will use or access the scaffold shall use or wear the Personal Fall Arrest System (PFAS) or the Full Body Harness.; If GREEN TAG - it means : Scaffold was built to meet scaffolding regulation and is complete and safe to use. Scaffold Inspection Tag to be valid only for two (2) weeks (fifteen days) after this duration, the scaffold tag shall be invalid, so reinspection shall be required.

The height of rolling scaffold will not exceed four times the minimum base dimension.

The work platform will be blanked tight for the full width of the scaffold. Each plank on a scaffold platform deck shall be cleated or clamped with a standard plank clamp otherwise wire tied to the bearer to refrain it from moving.

(33)

• SPECIAL INSTRUCTIONS ON SCAFFOLDS:

1)

Scaffold shall be inspected after erection; modification; adverse weather condition; accidental damage; and after every two (2) weeks.

2)

Any scaffold over 25 ft. (7.6) meter high should have the access ladder turned inside the framing and alternate sides of landing. At no time will a person be allowed to climb the outside of a scaffold over 25 ft. (7.6 m). 3) Design drawing of scaffold 38 m (125 ft.) high shall be approved by client representative prior to erection at site. 4) Scaffolding component shall not be welded except as supplied by the manufacturer.

5) Scaffolding component shall be kept free of rust, and threaded surfaces shall be lubricated regularly. 6) Adjusting screws shall be installed between sills and vertical frame section only. They shall never be used

together with casters. Adjusting screws shall not be extended more than two thirds of the total length of thread at any time.

7) For Mobile scaffolds all caster wheels are to be locked while employees are on the scaffold, or when the scaffold is not in motion.

8) No one is to ride a Mobile Scaffold that is being moved. Remove all loose materials and equipment from the desk before moving the scaffold.

9) Mobile scaffold shall be used only on level, smooth surfaces without any obstruction whatsoever. 10) Mobile Scaffold shall only be erected to a height not more than 4 times the minimum base dimension.

11) Mobile scaffold must be tagged YELLOW always so that users shall wear the Full Body Harness so that during working it must be hooked to a permanent structure of the building or establishment he is working on and not on the scaffold member.

12) Scaffold planks to be used for scaffold decking only: 2' x 10" (5 cm. x 25.4 cm) or 2" x 12" (5 cm. x 30.4 cm.) of approved scaffold grade materials.

13) Scaffold must be erected at least 3 planks wide. No employee shall be allowed to work from a single planked scaffold at any time.

14) Scaffold planks are not to extend over their end support more than 18 " (45. 7 cm) or less than 6" (15.2 cm.) except cleated.

15) All planking on platform shall be overlapped 12' (30.4 cm) or secured for movement. 16) Overhead protection shall be provided for men on scaffold exposed to overhead hazards.

17) Drums or barrels shall not be used as means of scaffolding and welding of scaffold joints is not permitted. 18) Earth lead for welding shall never be attached to a scaffold.

19) Any suspended scaffold shall have a platform 18" wide suspended by ropes that are spaced not more than 10 ft. apart. Wire rope used for scaffold suspension shall be capable of supporting at least 6 times the intended load, and all attachment hardware shall be inspected before use.

20) Each person working on the suspended scaffold shall be provided with a safety Full Body Harness attached to a separate line extending from roof to the ground.

(34)
(35)
(36)

9. WELDING & CUTTING OPERATION

1. Safety precautions will be omplemented during cutting and welding operations to minimize accident occurances.

2. Defective equipment, poor housekeeping, inadequately ventilation will be avoided. 3. A work permit will be obtained before any welding or cutting will be started.

4. Standard Oxyacetylene welding and cutting equipment in first class operating condition will be used.

5. Portable fire extinguishers will be availble at the welding site. 6. Prescribed personal protecting clothing and equipment will be worn.

7. Welding spark will not be permitted to fall on top of gas cylenders & flamable materials. 8. Protective canvas or flamproof tarpauline will be placed on top of any flamable items.

9. Adequate ventilation will be mainted when performing welding and cutting jobs in a confined spaces.

10. Cylenders will be stored in a safe , dry and wel ventilated places. 11. The valve of empty and loaded cylenders will be closed.

12. Valve protection cap will be always in place when cylenders are in use. 13. Oxygen cylenders will not be stored with acetylene cylender.

14. Each cylender will be properly identified as to its content, date of manufacture and hydrotesting period.

15. A helper will be on guard to monitor and assist in case of a fire when welding will be performed. 16. Wiring installations for a power supply and electrical outlet should be done in accordance with the

requirements and provision of the national electrical code.

17. Frames of electrical welding equipment operated from power circuit will be grounded with copper wire.

18. Welding jackets, aprons will be used to protect welders from radiant heat and sparks.

19. Welding mask will be provided from eye protection against ultravoilet and infrared rays produced by welding operations.

20. Install Flash back arrester after the acetylene and oxygen regulator before the hose and on the mixing chamber side after the hose. It is mandatory.

21. Never lift Acetylene and oxygen cylinders in a lifting equipment by tying on the body, rather in steel basket or a cylinder trolley intended for that purpose.

(37)

22. Never move a cylinder empty or full without the valve caps installed.

23. Safety in handling, use and storage of compressed gases shall be part of a weekly safety toolbox talks as required.

24. Housekeeping in the area of weld shall be undertaken first removing all flammables in the area 25. prior to welding.

26. Fire blankets shall be available in the welding site always.

27. Trained Fire Watch shall be assigned in any weld location to monitor any possible ignition. 28. Welding Machine checklist shall be performed by the Welder prior to start any weld. 29. Hot Work Permit to be procured prior to start welding.

30. Welder and brazer has to be certified by a grct party approved by the client.

WELDING & BURNING OPERATIONS.

When doing either welding and burning operations , employee will follow the following precautions. Before starting burn or weld area will be inspected to ensure that sparks or molten will not

fall on combustible materials.

Welding or burning in hazardous area with out obtaining written authorization from the responsible authority is prohibited.

Check to be sure that suitable fire extinguishing equipment is available in work area vicinity.

Each employee is responsible for maintaining the burning or welding equipment is using in safe operating condition.

10. HAND & POWER TOOLS

1. Proper instructions and training will be given to all workers to insure that the workers are using correct and safe tools for the jobs.

2. ABSAR co. will provide high quality tools and eleminate risk of accidents. 3. Only trained workers will be allowed to use power tools.

4. Good maintenance , proper usage and adequate supervision will be made in time. 5. Hand tools will be regularly inspected before and and after use and repair will be done

immediately if deficiencies are noted.

(38)

7. All the tools will be kept clean, protected against corrosion.

8. Periodically checkup , clean and lubrication will be done for all the tools. 9. Cutting edges will be kept sharp to use in safe.

10. Tools will be stored in tool box after use every day. 11. Right tools will be selected for the job.

12. During use of electrical power tools , voltage ratings on the name plate, the condition of the plug top , the robust protection for the conductor insulation , the condition and position of the cable will be checked before use

13. Protective fuses will be checked that they are of the correct ratings for the circuit before putting a power tool into service.

14. Before using a power tools grounding connections will be checked. 15. Compressors will be operated by trained technicians.

16. Horsplay will be strictly forbidden if any labours found he will be panelized. 17. Extra precautions will be taken during use of compressor.

18. .Air compressors will be regularly inspected , tested and maintained. 19. A daily checkup will be done before starting the machine.

20. Fuel, water, oil level will be checked every day before starting the machine. 21. Air hose will be checked every day before using the compressor in operation. 22. Damage air hose will be removed from the job site immediately.

23. Air compressors will be kept every day after work at a proper place where it will be safe and avoid any accident.

24. Experienced electrician shall be assigned to do inspection and repair of all electrical power tools and apply the color coding after the inspection showing that it is ready and safe for use.

25. All electrical temporary connections for construction use shall be 3 pin plug and the circuit protected with the GFCI (Ground Fault Circuit Interrupter) in all instances.

26. All electrical extension cables and temporary lighting connections shall comply with the cable management proposed by the ABSAR.

27. No electrical lines I cables of any power tools shall be directly inserted to female receptacles without a male plug. Any violator shall be penalized.

28. No non electrical crew shall be allowed to repair or conduct any work related to electricity shall be allowed. Violators shall be penalized.

(39)

29. Avoid many connections or joints in a single electrical lines or cables.

30. Color coding to be complied by ABSAR for an efficient monitoring of power tools and equipment.

11. FIRE PROTECTION AND HAZARDS

Each supervisor is obliged to maintain a constant awareness of the fire potential in his area of responsibility. If a potential fire hazard is noted, the supervisor will initiate corrective action or notify safety officer about the problem.

Good housekeeping, safe work area good wiring installation and protection of combustible materials will be maintained to minimize potential sources of fire.

All fires will be reported to the client construction representative and loss prevention. Fire Drill to be conducted in a regular basis to enhance awareness on tha part of the workers.

Controling Flammable and Combustible Storage

1. Storage area separated from combustible material by 3m 2. Storage area locked and vented

3. Storage area protected from vehicular/ industrial motorized traffic 4. Portable pressurized (Full or Empty) cylinders secured when not in use 5. Area have proper signage or placard in place

6. A current or updated list of dangerous goods on site in construction trailer

7. A portable extinguisher in close proximity to storage and work areas(minimum rating 4A-40BC fire extinguisher)

8. Storage area away from egress and access routes to the site

9. The site supervisor and or safety coordinator shall be responsible for all flammable and combustible storage

Hot works operations and control of igniton sources:

1. The area shall be clear of flammable and combustible materials

2. Fire watch assigned during hot works operation and for a period of 60 minutes after its completion to the person responsible for the hot works.

3. A final inspection of the hot works area 4 hours after completion will be completed by site supervisor or designate.

(40)

4. All work shall be performed by trained or certified personnel

5. Adjacent to any hot works operations – cutting torch, welding, torching and or hot tar pots a minimum rating 4A-40BC fire extinguisher shall be provided.

6. Proper ventilation, as required

7. Safety coordinator shall issue a hot works permit prior to any work

Training of site personnel on evacuation .

1. Site orientation and company safety guidelines will be given to each new worker on site by the safety coordinator.

2. Regular fire safety meetings incorporated into regular safety meetings(tailgate meetings) 3. Simulated fire drills as applicable and warranted will be given by the safety coordinator.

12. HOUSEKEEPING

Absar co. will keep an effective housekeeping schedule in order to maintain a safe

working area.

All necessary materials such as scrape lumber,membrane,heatinsulation boards empty

cans ,cartons etc. will be collected and disposed of in a timely mannaer to proclude

formation of tripping hazards.

A good fir preventive method is to be used.

Regular fire and safety inspection will be made to spot check for unsafe condition.

13. Temporary heating devices.

4. Care will be taken during temporary heating.

5. Hot air welding gun will be used for welding the PVC membrane for which all the electrical connections will be checked before application.

6. The additional safety practice and procedures will be observed for the proper installation and use of hot air welding heater.

(41)

14. FIRE EXTINGUISHERS

Portable fire extinguishers will be avaialble throughout the construction site.

Extinguishers will be located closed to potentials fire hazards to make the protection more effective. Fire extinguishers will not be blocked or hidden by stocks , finished materials or machines.

Proper type of fire extinguishers (class A/B/C) will be provided based on location and type of hazards. Fire extinguishers will be inspected regularly taking note of operating condition, inspection tags,charging pressure and CO2 cartridge .Any deficiencies will be corrected immediately.

Workman will be trained in the proper use of portable fire extinguishers.

Monthly inspection of Fire Extinguishers shall be conducted with records, taking note of the inspection tags affixed to every cylinder.

Fire Extinguisher Training to be conducted to the workers taking into account the types of fires and the corresponding Fire Extinguisher needed to extinguish it.

Adequate portable Fire Extinguishers to be installed around the offices and at Camps with locator signboards and Instruction for use.

FIRE EXTINGUISHER INSTALLATION ON THE WALL

INSTRUCTION HOW TO OPERATE THE FIRE EXTINGUISHER

INSTRUCTION HOW TO OPERATE THE FIRE EXTINGUISHER

LOCATOR SIGN FOR THE FIRE EXTINGUISHER

LOCATOR SIGN FOR THE FIRE EXTINGUISHER

FIRE EXTINGUISHER INSTALLED ON THE WALL OF THE BUILDING.

FIRE EXTINGUISHER INSTALLED ON THE WALL OF THE BUILDING. TIE IT THERE WITH A WIRE OR CABLE TIE. TIE IT THERE WITH A WIRE OR CABLE TIE.

(42)

FIRE EXTINGUISHER INSPECTION TAG:

15.WORK PERMIT

15.1 INTRODUCTION

Work permit will be obtained from client before starting the work in restricted areas.

The work permit will be received as per the nature of the job is being done.

The work permit will be requested from the authorized issuer of client as per job is to be

done.

15.2 ISSUANCE & APPROVAL

Work permit receiver will request work permit from the authorized issuer before doing

work in restricted area.

The issuer and receiver will conduct a joint safety inspection of the job site before issuing

work permit.

They will review the nature of the job and check the prevailing conditions for hazards that

might affect the job.

The issuer & receiver will check the validity of work permit certificate cards.

ASSIGN CYLINDER NUMBER HERE. ASSIGN CYLINDER NUMBER HERE.

(43)

15.3 PRECAUTIONS

The list of minimum safety mentioned in the work permit will be followed strictly.

Only those who are directly involved in work activities and members of the project

inspection team will be allowed to be present at job site.

15.4 HANDLING OF ISSUED WORK PERMIT

The receiver of work permit will keep a copy in his possession at the job site for the

duration of the job so that it can be presented for safety inspection when required.

The receiver will remain at job site throughout the duration of the work.

The work permit will be closed by the signature of both authorizes issure and authorized

receiver after work has been completed.

16.0 TRAFFIC SAFETY

Traffic safety is an essential part of this construction safety program and will be an integral part of this program. All regulations normally enforced by Saudi Arabian Traffic Police shall be complied with regulations. Our employees will be informed following technical information requirement for road safety.

16.1) Extract from Ministry of Communications standards road safety features.

16.2) Mandatory signs /danger sign (display sheet).

16.3) Driver Requirement: All employees who drive will, inaddition to having a valid Saudi driver’s license.

16.4) Be able to read and understand the standard traffic signs.

16.5) Truck drivers shall be instructed on operation of particular truck they are to drive, including safe speed and stopping distances.

16.6) Be examined for adequate vision and depth perception.

16.7) Posted Speed limits shall be followed by all drivers at site. Any violation shall be dealt with Accordingly.

16.8) Provide a separate access for vehicles and workers.

16.9) Ensure that all vehicles are having Fire Extinguisher with it. 16.10) Provide bunks man / spotters to maneuvering vehicle at site

(44)

TRAFFIC VIOLATIONS PENAL TY POINTS

Penalty points will be issued to the drivers of vehicles that were involved in a vehicle infraction. Penalty point categories are listed below. Penalty points assigned should reflect such factors as whether an MVA or violation involved personal injury, damage to property, or repeated infractions.

Penalty Points I. Motor Vehicle Accidents

1. Preventable MVAs:

• Vehicle total loss 20

• $1000 or more damage 10

• Less than $1000 damage 05

2. Reckless driving results in injury 20

3. Non- preventable or non- recordable MVA’s 00

II. Moving Traffic Violations

1. Reckless driving (combination of moving violations) 20 2. Speeding: Exceeding speed limit by

• 10 kph or less 01

• 10 to 20 kph 03

• 21 to 30 kph 05

• Over 30 kph 10

3. Driving on the wrong side of a divided roadway 20

4. Passing in a "No Passing" zone 10

5. Failure to obey a traffic signal or stop 20

6. Not using seat belts (drivers or passengers) 10

7. More than 3 people in front seat 05

8. Passengers in back of open pickup truck 05

9. Loading/unloading passengers in the middle of the road or at intersection 05 10. Failing to give right of way to emergency vehicles 05

(45)

III. Parking Offenses

1. Parking in an emergency route or emergency vehicle space 10

2. Parking in a Posted Handicapped Parking area 05

3. Parking on the wrong side of the street (against the traffic flow) 05

4. Parking in a posted "No Parking" zone 05

5. Parking within four (4) meters of a fire hydrant 05

6. Parking in front of a private driveway 01

(46)

17.SAFETY OFFICER'S & SUPERVISOR'S SAFETY MEETING

The subject material will be typed and reproduces for distribution at the meeting, which will be conducted by the safety officer. These safety meeting will conform to the following guide lines, covered at each meeting.

17.1.Review of note worthy cases since the previous meeting, identify principal accident causes. Accident prevention methods to be initiated by the responsible individuals will be elaborated.

17.2.Review of the most frequently noted serious, non-serious but repeated safety violations. Corrective action required by the responsible individuals will be established.

17.3.The Safety Officer will encourage group discussions on methods of corrections, improvement, etc.

17.4.Bonafide safety complains will be resolved.

17.5.Supervisors will be selectively assigned to groups to ensure that adequate supervision is maintained in the field.

17.6.Each group will be scheduled for a meeting every other week.

17.7.The meeting time will be around 30 minutes except in unusual circumstances.

17.8.Attendance at these meeting will be mandatory. Each supervisor who conducts a Tool Safety Meeting will list all employees who at these attend, and all safety suggestions and/or questions developed during the meeting.

The completed Tool Box Safety Meeting report will be returned to the safety officer for review and action.

The Safety Officer will prepare a written summary of each meeting, high-lighting the major items of discussion, unresolved issues.

(47)

18. FIRST AID

The supervisor will ensure that all employees under his supervision are aware of their obligation to immediately report all injuries however minor they be for first aid. First aid personnel will be

introduced to the employees well in advance. ABSAR CO. will provide all necessary first aid facilities for all its employees including subcontractors. If the injury is serious, it will be referred to nearby hospital and in case of ambulance services is necessary, we will arrange it.

19.

INCENTIVE PROGRAM

In order to improve safety performance and safe work practice, Bintami will encourage and reward all its employees including subcontractors.

.GENERAL

Well coordinate with the safety representative to implement safety rules and regulations. Employees will be informed that they are obligated to report all kind of unsafe acts and conditions to their foremen, who will either resolve the problem or refer it to his supervisor. Unresolved problems shall be reported by the employees to the safety officer.

20.0 PROPOSED SECURITY PROGRAM

20.1 DAILY SECURITY ACTIVITIES LOG BOOK

A daily security activities log book will be kept at security office. Materials, tools, equipment movements, work rule violation, incidents or special reports will be recorded in the log book.

all known company vehicle will be checked and inspected while leaving or entering the job site. When reporting to or departing from duty, the security guards assigned on that shift should sign in and out in the log book.

20.2.DUTY STATIONS

A security guard will be stationed at the entrance of the field office area as indicated with singed guard post. Security guards will assume roving inspection duty during night shift to cover the all project area. A key of the office will be given to the guard so he can use the telephone at night time.

References

Related documents

• Twenty-five years teaching strategy, entrepreneurship, international business, management and marketing courses at San Francisco Bay Area universities as an adjunct professor.. •

According to Cutting (2002), violating towards maxim of quantity happens when a speaker does not give enough information to a hearer about the whole picture or the topic

Metode ini menyajikan dua buah grafik yang disebut spektrum, yaitu spektrum kapasitas (capacity spectrum ) yang menggambarkan kapasitas struktur berupa

856, supra (providing or maintaining an Internet Web site for merchants is one device that national banks may use as finders to provide information to the merchants'

The aim is to obtain a view of the agent - body - environment interaction based on the information flow (Max Lungarella and Olaf Sporns 2006) that occurs between them. The

Of the six explanatory variables, estimated values for the OLS (global) model for distance to CBD and open space were statistically significant.. There is agreement between the

Naïve Bayes shows high precision rates of 98% but low performance in accuracy and recall, probably due to the higher volume of spam- training examples.. C4.5 has the