All-in-one : Integrated one-stop data center solution
All-in-one configuration and subsystems introduction
Application scenarios and successful stories
With the rapid
development of
cloud computing
and mobile
Internet business,
the traditional data
center faces many
Challenges
Expansion is limited
Difficult to find a
suitable place
High OPEX
Energy
inefficiency
Difficult to meet the
mobile scene and flexible
expansion needs
Long construction period
Over one or two years commonly
High CAPEX
Large-scale data
center construction
costs of tens of million
Page 4 HUAWEI TECHNOLOGIES CO., LTD.
Container data center has been widely used
2005 2006
SUN : Black box
SGI :Ice Cube
2007
IBM:PMDC HP: 40’POD
Cisco : UCS
2008 2009 2010 2011
Google: Own use
Microsoft : Own use
Some enterprises have
already used the container
data center:
Huawei launched the IDS
container data center family of solutions
Huawei :Container data center
... …
... …
The data center construction standards go unified
TIA-942
The Uptime Institute
Gartner Infrastructure Maturity Model
China GB ASHRAE HAVC Cooling power other
Needs of data center building change:
Infrastructure design needs to be changed in order to support high density computing ;
Using a variety of automated operations, management tools ; Based on the new design to improve the efficient use of
infrastructure such as power and cooling.
Supply-demand balance
planningof DC resources
Traditional DC-supply Modular design of DC - supply Container DC “future” supply Future DC resource requirement ”current“ requirement ”future“ requirement ”current“ supply
The
modular
concept become an
important trend in the current
data center construction.
The
scalability
of the data center
has also become an important
indicator of the success of data
center construction.
Page 6 HUAWEI TECHNOLOGIES CO., LTD.
Huawei All-in-one
:
Complete basic functions
Centralized
cooling / power
distribution
Management
Remote
maintenance
Aseismatic
Waterproof/
lightning proof
Fire fighting
Low TCO
Fast
deployment
expansion
Flexible
All-in-one
High
reliability
Wide
Page 8 HUAWEI TECHNOLOGIES CO., LTD.
Fast deployment, put into operation in advance
10-week manufacturing,1-week installation:
Solution simplification, factory prefabricated, shorten
the construction period, do not need room of building
Improve ROI
:
Compared with the traditional DC, can be put in operation ahead of 1 ~ 2 years.
Easy on site:
only
need place, power
and network
network
power
Data center
Fast deployment Low TCO Flexible expansion Wide adaptability High reliabilityOne stop solution meets backup or mobility requirement
One-stop solution:providing the whole infrastructure such as IT racks, cooling system, power supply etc, adopting integrated management system.
Environmental adaptability :adapting high & low temperature district and drought area, passed salty moisture and ocean shipping test.
Anti-earthquake& anti-vibration: powerful anti- crash and shock absorption system, passed NEBS testing. Supporting working in the transporting way, satisfying military standard of anti-shock, passed 480km testing on 3rd class road.
Satisfying dynamic deployment and moveable scenario such as military, disaster saving, oil, reconnoitering, fieldwork.
Backup system for
Page 10 HUAWEI TECHNOLOGIES CO., LTD.
Flexible expansion
cluster and stack deployment
transport
Ready to meet
any customer
migration
requirements
Fast deployment Low TCO Flexible expansion Wide adaptability High reliability1. Reuse or construct new traditional IDC equipment rooms 2. Deploy in modules and flexibly expand servers
3. Determine the deployment scenario
Warehouse scenario
1. Super-scale stacked cluster deployment.
2. Flexible equipment room pre-installation schemes
3. Modular design, including the UPS, D.G., and cooling equipment.
Awning scenario
1. A complete system
2.Can be deployment quickly 3. Disaster relief and Opera
Outdoor scenario
Page 12 HUAWEI TECHNOLOGIES CO., LTD.
Internally and externally stable and reliable
Internal :Tire 3 design concept
Key components (power supply and cooling) are N + X backup Batteries provide 10 minutes backup
The key components powered by the UPS Three levels lightning protection design
External
:
High reliability container design
Windproof Can fight against hurricanes in work conditionSeismic 8 degree
Anti-theft
Side door, the compartment door to the installation of security door locks, air conditioning outdoor unit and vents has a good anti-theft design
Waterproof The locks, vents and outlets are all complete waterproof sealed Fast deployment Low TCO Flexible expansion Wide adaptability High reliability
Low TCO, reducing constructing cost and operating cost
Low OPEX:
Green energy, hot and cold aisles are separated, hot and cold air are
not mixed.
Efficient modular UPS, upgrade the UPS conversion efficiency.
NetEco management system, unified management and maintenance.
Enables remote management, reduce labor costs.
Low CAPEX:
Outdoor applications, the external civil works is simple, just need main
powers and network.
The whole systems are in one box, simple installation and low cost .
Reduce 50%
HUAWEI TECHNOLOGIES CO., LTD. Page 14
All-in-one : Integrated one-stop data center solution
All-in-one configuration and subsystems introduction
40ft container
20ft container
Management system
Application scenarios and successful stories
A container integration of all systems , such as cooling, electricity, equipment, etc.;
Cabinet number: 8 IT cabinets +1 UPS cabinet+1 PDF
Cooling method: air-cooled precision air-conditioning, 4 +1 backup;
Power systems: UPS N +1 backup; 10 minutes backup.
Power density: 7.5KW / cabinet (rated);
Page 16 HUAWEI TECHNOLOGIES CO., LTD.
All-in-one
(
40ft
):
Compact layout
Four functional areas: air conditioning outdoor unit area, equipment area, battery area, entrance hall.
Complete cooling and power supply system
This system supports the Africa and Latin America market requirements. Other voltage standard (such as dual FireWire 110V, 480V, etc.) can be used transformers to solve.
Support 2-way power input;
UPS N +1 backup, 40 batteries; backup time is 10 minutes.
Input 380VAC 50Hz/480VAC 60Hz Cooling capacity 12.5kW
Refrigerant R22
Cooling method Air-cooled precious cooling
Backup 4+1
Protection degree LCU:IP20;Outdoor:IP55
Page 18 HUAWEI TECHNOLOGIES CO., LTD.
All-in-one
(
40ft
):
Scenes design comprehensive
Scene for high temperature (T3 conditions) , high-density scene (rated power density ≥10KW / rack):
Environment
:
-45
℃
-55
℃
,
enclosed water
cycle, can be set in arid area
Cooling system
:
Air-cooled chilled water,
Double outdoor units
,
1+1 backup
(
80KW/unit
)
Five LCUs
,
4+1 backup
(
20KW / unit
)
MAX cabinets: 8 -10 racks(without UPS)
Average power
:
11-15KW/rack
(
rated
)
Power system
:
modular UPS
,
5+1
redundancy
,
battery backup is 10min
If operator does not need the ups system, 40 ft All-in-one can also provide ten-cabinets solution.
Cooling system cooled precision
air-conditioning, 4 +1 backup;
MAX cabinets: 10 racks
HUAWEI TECHNOLOGIES CO., LTD. Page 20
All-in-one : Integrated one-stop data center solution
All-in-one configuration and subsystems introduction
40ft container
20ft container
Management system
Application scenarios and successful stories
A container integration of all systems , such as
cooling, electricity, equipment, etc.;
Cabinet number: 4 IT cabinets +1 UPS cabinet
Cooling method: air-cooled precision air-conditioning,
2 +1 backup;
UPS systems: UPS 2 +1 backup; 5 minutes backup.
Power density: 7.5KW / cabinet (rated);
Applicable to the environment: -33
℃
-55
℃
;
adapt T3 conditions .
Page 22 HUAWEI TECHNOLOGIES CO., LTD.
All-in-one
(
20ft
):
Compact layout
Three functional areas: air conditioning outdoor unit area, equipment area, entrance hall.
Hot and cold aisles are separated.
FM200
AC
AC
Complete cooling and power supply system
Item parameter
Input Dual power supply
Rated input voltage Three-phase 380VAC
Input voltage range 342V~440VAC
Maximum input current 63A
Typical power consumption 20KW
Three precision air conditioning, power 12.5KW,
2 +1 backup, come with heating humidification
function;
All refrigeration components are set in one
container, easy to deploy and move.
HUAWEI TECHNOLOGIES CO., LTD. Page 24
All-in-one : Integrated one-stop data center solution
All-in-one configuration and subsystems introduction
40ft container
20ft container
Management System
Application scenarios and successful stories
NetEco can provide centralized monitoring and integrated management to power, environment and security system. Adopting flexible structure and modular design, NetEco can manage not only single IDC infrastructure, but also several IDC infrastructure
Switch
Switch
CCU CCU CCU CCU
RS485 RS485 RS485 RS485 Modular 1 Modular n NetEco Switch
PDF A/C UPS ATS Cameral Smoke Temp. Water-immersion Access
FE FE
Page 26 HUAWEI TECHNOLOGIES CO., LTD.
NetEco management function panoramagram
NetEco
Solution
Smart inform method of warning
Real time equipment monitoring
SMS Email acousto-optic Upper mgt system Display screen
Process of work order mgt
Warning database
Warning receiving Relativity analysis Warning storage Warning display Accumulate and share of operation experience Guide operation efficiently maintain Assign work order Result feedback Finish confirm
Page 28 HUAWEI TECHNOLOGIES CO., LTD.
Report management
Template
Plenty of reports template and reports style inside the system
Customized
Support user-defined reports, instrumental operation etc.
Traceable
Support user-defined periodic report by email Support checking by excel, PDF and word format.
Reports & Chart
Prolific presentation such as histogram , pie chart, curve chart
联动配置
Interact
configuration
Video system Lighting system
Access mgt system will interact with lighting and video system, turn on the light automatically , change the direction of cameral to the warning area , take photo and record when it detects normal punching card or illegal invasion.
A c c e s s mgt s y s tem
access video and lighting interaction Fire extinguish warning and video interaction
Network warning and video interaction Support modification and edition
Interact
demonstration
HUAWEI TECHNOLOGIES CO., LTD. Page 30
All-in-one : Integrated one-stop data center solution
All-in-one configuration and subsystems introduction
Application scenarios and successful stories
Contents
Scenarios
Research institute
Digital library
University
Large hospital
Group headquarter
Medium financial institute
Carton center
Data Center Features
Under 100KW ICT power consumption
200-400 server scale(on the basis of 1U server)
40ft All-in-One Container Data Center
Page 32 HUAWEI TECHNOLOGIES CO., LTD.
Scenarios
Digital library
Hospital
Petroleum
Exploration projects
Film production unit
Disaster relief
Data Center Features
Under 30KW ICT power consumption
20ft container data center
Benefits for customer
Sales support is advanced for Xmas, sales increase 14.7%
Phase-1 system deployment completed in 5 months, put into use before Xmas, shorten over 50% construction period .
Huawei solutions
As local temperature is relatively low and wind power resource is abundant, Huawei offers chilled-air solution.
Considering that Christmas is coming soon, 2 sets of system is deployed and put into operation primarily to meet the Xmas demand. Another 2 sets will be added later on, phase by phase .
Customer requirements and challenges
No. 1 retailer in Russia, occupies 73% market share
The ordering and logistic system is not able to burden pressure from the large scale business in coming Christmas. Megapolis decide to adopt cloud computing to build a new ordering and logistic system for the coming Xmas festival.
Traditional data center requires huge investment and very long period to build the infrastructure.
Page 34 HUAWEI TECHNOLOGIES CO., LTD.
Benefits for customer
Completes system construction in 6 months, 5 months less than traditional construction method.
Builds complete backup and disaster tolerant system, promote operation competitiveness.
Reduces 40% energy OPEX as calculated by 5 years. Increases 80% storage resources utilization rate.
Huawei solution
Provides professional data center services and disaster tolerant plan, including consulting and design services.
Offers a solution of chilled-air type container , combined with highly dependable flywheel UPS power supply container.
Provides a integrated solution of data migration, backup and remote disaster tolerant
Customer requirements and challenges
Constructs dependable RDTS(remote disaster tolerant system) quickly, take old storage system in consideration
Traditional DC construction required huge investment, can not meet budget in a short time
Local power supply system is not stable
Case 2: Venezuela ANTV data center
Biggest CT in Venezuela-ANTVBenefits for customer
Fast deployed integrated data center, ensure the project going on smoothly.
Flexible to shift, Sufficiently utilize the investments.
Increase over 30% density of IT rack than traditional way.
In response to nation environment protecting appeals , decreases
Huawei solutions
Provides chilled-air container type integrated solution
Provides professional consulting & customized service for data center.
Provides customized production for internal equipment also.
Customer requirements and challenges
Require fast deployment: complete in 2 months.
High standard: meets international advance design standard,
green & energy-saving
Portable: able to move after construction
Page 36 HUAWEI TECHNOLOGIES CO., LTD.
Benefits for customer
Expand the data center easily without changing existing equipment room structure.
Comparing traditional way of construction, save 47% cost. Sufficiently utilize space (Deploy on existing parking zone.)
Huawei solutions
Provides an integrated solution of IDC container.
Provides a independent chilled-air container, lower demands for ground and environment.
Highest NAS in industry, offers doc storage solution
Customer requirements and challenges
investments of traditional data center construction is too high Existing building is difficult to rebuild, not able to meet the
requirement of data center.
Network multimedia teaching class and network lab is required.
Case 4: Mackenzie University DC-
flexible deployment
Benefits for customer
Flexible mobility, meets special demands of field prospecting Reduce huge infrastructure investments, capable to shift flexibly
with project.
Huawei solutions
Provides integrated All-In-One IDC solution
Integrated power system, cooling system and IT equipments into one container.
Offers a customizing power system design.
Customer requirements and challenges
Traditional IDC can not meet portable demands in field
prospecting.
Traditional IDC constructing takes high costs and long period, not
able to meet business requirement
www.huawei.com
Copyright©2012 Huawei Technologies Co., Ltd. All Rights Reserved.
The information in this document may contain predictive statements including, without limitation, statements regarding the future financial and operating results, future product portfolio, new technology, etc. There are a number of factors that could cause actual results and developments to differ materially from those expressed or implied in the predictive statements. Therefore, such information is provided for reference purpose only and constitutes neither an offer nor an acceptance. Huawei may change the information at any time without notice.