• No results found

Bakun Dam Ppt

N/A
N/A
Protected

Academic year: 2021

Share "Bakun Dam Ppt"

Copied!
19
0
0

Loading.... (view fulltext now)

Full text

(1)

Bakun Dam

Bakun Dam

(2)

 Bakun Dam is located on the Batang Balui, a

tributary of the Sg. Rajang, 37 km upstream of  Belaga

 Batang Balui has a length of 341 km and 15 354 m2

catchment area with the highest peak originating from Mount Makati at 1360 m.

 Bakun Dam was constructed on the sole purpose for 

hydroelectric energy to meet the high demand from the industries instead of domestic.

 The dam will have an ultimate installed capacity of 

2400 MW comprising 4 x 300 MW turbines in the first phase and 4 x 300 MW turbines in the second

phase.

(3)
(4)

 Built as a Concrete Faced Rock Fill Dam (CFRD),  The height of the dam is 207 m with an approximate

crest length of 748 m and a fill volume of 117M m3.

 The flood area of the dam is 69 640 hectares and

has a catchment area over 1.5M hectares.

 The dam is complete with 8 power tunnels,

powerhouse and spillway

 Township is also built within the area of the dam for 

employees and owners of Bakun Dam. The

accommodations inclusive of houses, barracks, guest chalets and club house.

(5)
(6)
(7)

Issues on Bakun

 Resettlement  Safety

(8)

Issues on Bakun - resettlement

 Resettlement had involved the relocation of the

population of the upper Balui in the Belaga river  system.

 The state of Sarawak through the State Planning

Unit had created a new section known as Special Task Section for Resettlement had been in charge on the relocation of the indigenous people

 More than 10 000 people from 15 different

communities have been forced to move to Kampung Sungau Asap and Kampung Sungai Koyan through a codename of ‘Operation Exodus’.

(9)

  At the resettlement area, people are suffering from

poverty, malnutrition, unemployment and adverse socio-economic conditions.

 There are claims that the house units at the Asap

Resettlement Scheme were not in accordance with that promised in the relocation plan (Swain & Ang, 2004).

 There were further claims that, the compensation have

not been fully fulfilled until present time. They were

promised 15 hectares per family before relocation instead the actual acreage allocated for them finally was only 3 acres.

 Due to deteriorating conditions of the resettlement area,

some communities have moved back to their original homes in the inundation zone by building jelatong and staying in the vicinity of the dam. They have established new villages near the dam fish, hunt and farm the land nearby the dam.

(10)

Issues on Bakun - Safety 

  A group of citizen who residing downstream of 

Bakun Dam claimed that they have been kept in the dark over the content of the Emergency Rescue Plan (EPR).

 The Sarawak Conservation Alliance for Natural

Environment (Scane) has called upon the

government to make public its Emergency Rescue Plan (ERP) prior to the impoundment of the dam.

(11)

 The Sarawak Hidro managing director and chief 

executive officer Zulkifle Osman claimed that the dam will not break due to its solid foundation and

has been in perfect condition since the impoundment in October 2011

 Upon completion, the dam will be scrutinised and

check by an international independent panel of  experts once in every 10 years.

 He further assured that the dam is monitored on

daily basis and reading will be sent to the state

government’s security committee once every three to four months for review.

(12)

Issues on Bakun-Hydropower

 Bakun Dam coincides the core of Sarawak Corridor 

of Renewable Energy (SCORE) in energy resources, particularly in hydropower, coal and natural gas.

 The estimated investment on the projects is RM94

bil and in 2030 an investment of RM300 will

transform Sarawak into an industrialized state and energy hub of Borneo.

 Therefore, the state needs to guarantee a

sustainable energy supply at a competitive rate in order to encourage continuous inflows of 

(13)

  Adding up all the dams’ total combined capacity is

4500 MW.

 With the excessive power available there is an issue

where the power should go and how they can be fully utilized for people.

 Suggestions are bound to leave the dams idle such

(14)

Mitigation efforts - resettlement

 The solution to social problems created must be

solved through policy formulation and legal frameworks

 That must be complimented with the followings:

  A population and baseline income survey as part of 

feasibility study

  A detailed resettlement plan for people’s socio-economic

re-establishment

  A relocation timetable correlated with advances in civil

works

  A distinct budget for resettlement

(15)
(16)

Mitigation efforts

 – 

safety: Emergency Action

Plan (PNSB)

Level Alert Triggering event Action

1 Low Spill expected Release reservoir water from the lower level of the draw-off  tower 

2 Medium High rainfall and spill continues. Reservoir level above maximum.

Rapid increase in seepage quantity and seepage water  is murky

Set up Emergency Task Team. Check with Jabatan Kajicuaca on the forward weather forecasting.

Consult SMHB for advice on rapid drawdown of reservoir. Inform District Office of possible flooding close to the dam and need for evacuation. Contact Civil Defense Dept. To standby.

3 High High rainfall and spill continues. Reservoir level above maximum

Dam failure considered  possible.

Contact emergency services and place them on full alert. Inform them of the need to establish emergency control centre and evacuation of affected area as per inundation maps.

(17)

 For alert level 3 and 4, JKAS will contact the followings

organization:

 State administration to inform the potential disaster and

mobilize disaster relief machineries

  Army to set up control centre, start evacuation procedure and

maintain civil order,

 Police to start evacuation procedures and maintain civil order   District Offices and Civil Defense Department to aid the

evacuation procedures.

 Medical services to be alert on receiving casualties

 Fire and rescue services to be alert for disaster relief and

rescue

 Local radio and TV stations to coordinate information services

and warnings to the public

(18)

Mitigation efforts

 – 

excessive energy 

 The National Energy Policy 1979 was aimed to

ensure the provision of sufficient, secure and cost-effective energy supplies by developing both

renewable and non renewable energy using least cost options and diversification of supply sources both within and outside Malaysia.

 Therefore, excessive power of Bakun Dam should

be utilized accordingly to the energy needs inventory of the policy, not only for industrial but also domestic.

(19)

References

Related documents

Quantitative funds ex- perienced heavy declines in August 2007 (which rebounded later in the month) due to the heavy unwinding of crowded trades, significantly beyond

administration costs, thus giving the aggregated group greater buying power. The reduced costs are then passed on to YOU, the Haverhill resident or business* as savings to

The method involves quantifying catchment and river geomorphic variables (slope, channel width, valley bottom width, catchment area, stream power) extracted from

Sí, sí, això és el pitjor: haver de fer els deures a la cuina només perquè ella fer els deures a la cuina només perquè ella vol «controlar què faig»

If the goal of assistance is to increase the incomes of the poor, or to raise households above a certain common standard of income or nutrition, targeting the assistance to

Without checking this feature, the derivation would crash resulting in the sentence being ungrammatical (see Section 2.2). According to the spoken language literature,

Despite concerns regarding psychological effects of video games on the academic performance of players (Maass, Kollhorster, Riediger, MacDonald, & Lohaus, 2011), many

The principal goal of enterprise and entrepreneurship education is that graduates of HEIs’ major education and training programmes (e.g. bachelor’s, master’s and doctoral