Safety Health & Environment Manual
for
Construction Site
Larsen & Toubro Limited
E & C DIVISION
SAFETY, HEALTH AND ENVIRONMENT
MANUAL FOR CONSTRUCTION SITE
Contents
Part I: SHE - Administration
• Foreword
1. Introduction 2. SHE Policy
3. SHE organisation and Management
3.1. Management Commitment
3.1.1. Site commitment 3.2. SHE Organisation
3.2.1. Safety Control - Organisation Chart 3.2.2. Site Safety Organisation Chart 3.2.3. Duties and Responsibilities
3.2.3.1. Management
3.2.3.2. Safety Control Department 3.2.3.3. Resident Construction Manager 3.2.3.4. Site Engineer
3.2.3.5. Site Safety Officer 3.2.4. Returns
3.2.4.1. Site Opening / Closing Report
3.2.4.2. Monthly Reports
3.2.4.2.1. Monthly statistics report 3.2.5. Positive Reporting
3.2.5.1. Format
3.2.6. Daily Log – Book
3.2.6.1. Format
3.2.7. Safety Promotion and Recognition
3.4.1. Basic Requirements for Contractors 3.4.2. Rules governing contractor’s work 3.4.3. Safety in Contractor’s work
3.5. Safety Committee
3.6. Construction Safety Plan
3.7. Accident reporting and Investigation 3.8. SHE Audits
3.9. SHE Training
3.9.1. Tool Box Talks 3.9.2. Training at Site 3.10. Permit to work System 3.11. Safety of L&T Site Visitors
Part II: SHE - Implementation
4. Concept of Accident Prevention 5. Site Planning
5.1. Site layout
5.2. Construction details 5.3. In-built safety measures 5.4. Housekeeping 5.5. Safety at stores 6. Civil Work: 6.1 Blasting 6.2 Excavation 6.3 Piling 6.4 Working at heights 6.4.1 Ramps and Runs 6.4.2 Ladders
7. Mechanical Works 7.1 Manual Handling
7.1.1 Winch
7.1.2 Reeving
7.1.3 Rigging Procedure and Precautions 7.1.4 Test Certificates
7.1.5 Operators & Banksman
7.1.6 Safe working load for men and women.
7.2 Crane Safety
7.3 Erection of Structures
7.4 Use, Care and Maintenance of Slings 7.4.1 Synthetic Ropes / Slings
7.4.2 Wire Ropes
7.4.3 Lifting Gears – Hooks, Shackles etc
7.5 Hoists
7.6 Other mobile machinery and their movement at the site 8. Critical Jobs:
8.1 Work over water
8.2 Confined Space
9 Welding and Gas Cutting 10 Health and Hygiene
10.1 Work Environment
10.1.1 Noise and Vibration 10.1.2 Lighting
10.1.3 Ventilation ( Heat Stress ) 10.2 Personal Protective Equipment
11 Occupational Health Center and First Aid 12 Electrical Safety
13 Non Destructive Testing 13.1 Radiography
14 Abrasive blasting and spray painting 15 Hand tools and power tools
16. Handling of chemicals / hazardous substances 16.1. Handling and Storage of Chemicals 16.2. Material Safety Data Sheet ( MSDS ) 17. Fire prevention
18. Onsite emergency preparedness plan
Part III: Commissioning of plant Part IV: Environment protection
On behalf of Safety Control Department I am pleased to issue this (SHE) Safety, Health and Environment manual to E&C division. This manual will serve as a ready reference for methods and procedures to be followed in Safety, Health & Environment by those who are
engaged in construction activity.
This four-section manual contains information based on the most current knowledge and practices with the SHE (Safety Health &
environment) much of this information based on practice and research and will remain relevant during the next decade. However changes are bound to occur that will require Site managers to find innovative
solutions to SHE problems on the job.
The need for a SHE manual for those engaged in or concerned with construction activity was recognized during the activities of Business Specific initiatives for safety Assurance by the senior management. I appreciate the assistance given by D.Venugopal our consultant, all team members of safety assurance team and my colleagues in the preparation of the text of the manual.
I hope, By following safe methods and procedures in construction let us all in L & T E & C division make Safety - A way of life.
1. Introduction
1.1.1 This Safety, Health and Environment Management Manual has
been developed for Projects under construction in E&C Division to ensure compliance of the Safety, Health & Environment requirements during project construction.
1.1.2 This Safety, Health and Environment Management Manual
includes the procedures, responsibilities and safe practices required to be followed at project site by all personnel involved in the project, including crews and representatives of Contractors.
1.1.3 This Safety, Health and Environment Management Manual shall be followed while carrying out activities at project site and this manual supersedes any other document on these subjects.
Engineering & Construction Division
CORPORATE POLICY
1. To Engineer and Execute projects with consistent quality, cost and delivery in line with
the requirements of our customers, and to exceed or meet their expectations, whilst enhancing our shareholder value.
2. To set and review quality objectives for Continual Improvement of our products and services, whilst implementing the globally recognised management systems for Quality, Safety, Environment and Information Technology, and integrating these systems with our business partners and customers.
3. To design / operate and maintain safe and environmentally friendly plants which meet all applicable statutory and regulatory requirements.
4. To advance / ensure the use of better and cleaner technology to minimise adverse environmental impacts.
5. To continually reduce the risk of pollution through setting environmental objectives in our design / operation and maintenance processes, based on the feedback.
6. To deploy Information Technology for increasing the efficiencies of our business processes, while ensuring its security by protecting information as valuable assets and ensure availability, integrity and confidentiality of all information.
7. To comply with all applicable occupational Health & Safety legislation and continually improve safe working practices through setting health and safety objectives and ensure good health, safety and security of all our people, our biggest asset.
8. To encourage enthusiasm, innovation and empowerment whilst developing inspiring leaders to make working at L&T a rich experience and create new global benchmarks in whatever we do.
9. To promote a culture of mutual trust, caring and sharing achievements, with our people, our society, our stakeholders and our customers for the growth and benefit of our Nation.
10. As an undisputed leader in the Indian context, we continue to make things that make India proud, and shall strive to be amongst the globally outstanding companies, which the World is proud of.
3. SHE organisation and Management
In order to implement the policy of the management given under chapter-2 SHE policy, a committed organisation is required. After careful consideration the management has made Safety organisations at different levels with each person’s commitment well defined. These are given in this chapter.
3.1. Management Commitment
The E&C Division of L&T, is committed to continuous improvement in creating and maintaining:
- A safe and healthy Environment at all its work places and project sites
- A Zero accident record; - A risk free operation;
- An improved business performance; and - A responsible image within the marketplace.
E & C Division
SAFETY COMMITMENT
Pursuant to the L&T Safety Policy Statement, we L&T employees at this
site shall comply with the L&T Safety Management System by the
following actions.
!
Work with competent and adequately resourced contractors to
carry out work and ensure their co-ordination and co-operation.
!
Ensure that contractors have information about risk on-sites and
they provide details of how they intend to safely carry out high risk
operations.
!
Ensure that workers on site will be given adequate training and
comply with the site safety rules.
!
Monitor health and safety performance.
!
Ensure that all workers are properly informed and consulted on
hazards and risks of their work.
!
Make sure that only authorised people are allowed on to the site.
!
Communicate by reports and safety meetings with all concerned at
the site and Powai about all safety matters.
!
Give priority to safety in our day-to-day work.
!
Follow L&T Rules and Procedures to ensure accident-free, safe
construction site.
Site Safety Officer ________________
3.2. SHE Structure
The SHE organisational structure of L&T’s E & C Division Safety Management’s system and personnel responsible for safety aspects are as follows:
Sr.Vice President (Operation) and Member of the Board
Cluster Heads Business Group Leaders Head (Safety) LEGEND : Communication / Interaction Site Safety Officers Chief (Management Services) Resident Construction Managers Safety Engineers Head (Project Management/ER&C)
3.2.1. Safety Control Organisation Structure
3.2.2. Site SHE Organisation Structure
The Site SHE organisational structure of L&T’s E & C Division Safety Management system and personnel responsible for Safety aspects are as follows:
3.2.3 Duties and Responsibilities
3.2.3.1. Management
3.2.3.1.1 The management shall have ultimate responsibility for SHE management system. The responsibilities include.
• Providing adequate resources essential to the
implementing continual improvement of SHE organisation system. Site Safety Officers Resident Construction Managers Head (Safety) Safety Engineers
3.2.3.2. Safety Control Department Responsibilities
3.2.3.2.1. To set up standards for prevention and control of losses
3.2.3.2.2. To participate in safety activities and give full support for the programme.
3.2.3.2.3. To review and act upon safety records.
3.2.3.2.4. To insist on safety being planned into all the operations undertaken at all times under any conditions.
3.2.3.2.5. To review an OH&S management programme.
3.2.3.2.6. To review the effectiveness of the provisions of the Safety, Health and Environment Manual.
3.2.3.2.7. To periodically inspect and audit the site for SHE to provide training to the engineers and supervisors.
3.2.3.2.8. To identify hazard and carry risk assessment and keep the information up to date.
3.2.3.2.9. To identify and have access to the applicable legal requirement and keep the information up to date.
3.2.3.2.10. To ensure communication to all employees and other interested parties on the SHE requirements including legal and other requirements.
3.2.3.2.11. To set up an OH&S objectives and consider the above while setting up the objectives.
3.2.3.2.12. To establish and maintain OH&S management program for achieving objectives.
3.2.3.3. Resident Construction Manager
He is overall in-charge of the safety of the site, for the
statutory compliance and adherence to the guidelines given in this manual. In addition to this his other responsibilities are: 3.2.3.3.1. To ensure & maintain safe working conditions and practices
for all employees under his supervision.
3.2.3.3.2. Ensure that contractors follow safe working practices in line with the company policy and will take steps to rectify.
3.2.3.3.3. To provide adequate training to all personnel working at site. 3.2.3.3.4. To ensure the understanding of the job hazards and safe
3.2.3.3.7. To encourage safety suggestions and act upon them immediately.
3.2.3.3.8. To conduct regular safety meetings.
3.2.3.3.9. To ensure that SHE manual is made available at site and copies/ abstracts are issued to all concerned including sub contractors.
3.2.3.3.10. To ensure that sub contractors are given proper instructions to comply with safety standards and entries are made in the daily logbook maintained at the site of all verbal instructions given to the contractors.
3.2.3.3.11. To ensure proper feedback is given to the connected L & T departments about shortfalls in design etc. from construction safety point of view, for future actions.
3.2.3.3.12. To ensure First aid arrangement are made and maintained at work place.
3.2.3.4. Site Engineer
The site engineer is responsible for ensuring the compliance of the statues and the recommendations given in this manual by the contractor and sub-contractors working under them. In addition to this he will:
3.2.3.4.1. Inspect working area regularly.
3.2.3.4.2. Report accidents and near misses immediately to RCM/SSO. 3.2.3.4.3. Ensure that all persons working under him are trained on safe
and proper working procedures by giving toolbox talk.
3.2.3.4.4. Assist the Site Safety Officer in conducting accident investigation involving his workers.
3.2.3.5. Site Safety Officer
The site safety officer is responsible to ensure the over all safety of the site. Functionally he will be reporting to the safety control department and take guidance from them. In addition he will:
3.2.3.5.1. Promote & implement the SHE manual at project sites.
3.2.3.5.5. Advise RCM to stop work when the need arises. 3.2.3.5.6. Advice on legal requirements affecting safety.
3.2.3.5.7. Maintain liaison with other departments such as Medical and Training, official bodies such as Factory Inspectorate and Insurance Companies and outside bodies such as the National Safety Council, Productivity and Standards Board, etc.
3.2.3.5.8. Propagate safety through leaflets, memos, reports, poster, notices, etc.
3.2.3.5.9. Provide assistance to all level of management to implement accident prevention activities.
3.2.3.5.10. Arrange and participate in periodic safety inspection of work areas.
3.2.3.5.11. Prepare and keep adequate records of accidents and reports and tendering of advice to prevent recurrences.
3.2.3.5.12. Monitor and man the access and egress to project on the work site.
3.2.3.5.13. Liase as required with the Fire Watch.
3.2.3.5.14. Conduct Safety meeting at least once a month to discuss various aspects on safety with sub contractors and clients and minuted.Initiate Tool-Box talks with workers
3.2.3.5.15. Be important member of the on-site emergency team and perform duties as mentioned in the emergency plan.
3.2.4. Returns
3.2.4.1. Reporting about Opening/ Closing of Construction Sites 3.2.4.1.1. Objective
In order to conform with norms set in the safety policy, it is essential to know in advance the opening and closing of a site.
A detailed procedure is given below for compliance.
3.2.4.1.2. Procedure
3.2.4.1.2.1 This Procedure requires that SCD at Powai should be informed about opening and closing of a construction site within seven days of its opening/ closing.
3.2.4.1.2.2 The information to be sent to SCD, Powai shall be filled in the format annexed to this Procedure.
3.2.4.1.2.3 It should be sent by a fax message (No. 022 - 8581020) for the attention of Head-Safety Control followed by a confirmatory copy by post/ courier.
3.2.4.1.2.4 Project Execution Manager at Powai / Baroda shall be responsible to provide the information. However, RCM/ RCE shall ensure that the information has been sent to SCD, upon taking charge of the site.
3.2.4.1.2.5 All construction sites of E & C Division shall be covered under this Procedure so long as any person/s of E & C division and/ or its appointed contractors/ agents carry out activity of any kind at the site.
3.2.4.1.3. Definitions
3.2.4.1.3.1. Opening of a Construction Site
3.2.4.1.3.1.1. An event/day when L&T personnel or L&T’s contractor/s or L&T’s vendor/ agent/s start carrying out activity of any kind at a site where construction activities will be further carried out.
3.2.4.1.3.2.1. An event/day after which no further activity of any kind is carried out by L&T personnel or L&T’s contractor/s or L&T’s vendor / agent/s at the site.
3.2.4.1.3.2.2. RCM/ RCE will stop sending reports to SCD from this day onward, for the specific site, which is closed.
3.2.4.1.4. This revision:
The annexed form has been revised to request additional information while opening a site.
3.2.4.1.5 RECORD
Forms Records
Annexure -1
Larsen & Toubro Limited Safety Control
Powai, Mumbai E & C Division
To: Head (Safety Control), E & C Division
(A) SITE OPENING REPORT : (Attach separate sheet if required)
1 Name of site/ project
2. Project job no. & Debit code no. 3. Location
4. Complete address
Telephone, V-sat (hotline) & fax nos.
e - mail address
5. Name of Resident Construction Manager / Resident Engineer 6. Names of Site Engineers 7. Name of Site Safety Officer 8. Names of contractors & nature/
type of their activities
9. Estimated no. of man-hours 10. Duration of construction activities 11. Safety manual, procedure
manual and DACP (Safety -34 )
Available at site / required at site
12. Whether commissioning is in L&T’s scope of responsibilities or whether L&T will provide commissioning assistance only to the client ? 13. When will ownership of the plant/
facility be transferred to the client? (a) After mechanical completion. (b) After commissioning & Test-run.
14. Date of opening of construction site 15. Any other relevant information
Annexure 2
Larsen & Toubro Limited Safety Control
Powai, Mumbai E & C Division
To: Head (Safety Control), E & C Division
(B) SITE CLOSING REPORT :
This is to certify that there will be no further construction/ commissioning activity of any kind on the construction site at ________________________ (location), from _______________ (date of closing of construction site).
Total no. Of man-hours worked at this site from _______________ (date of opening of construction site) is ____________________.
I have handed over to Mr. ___________________________* / retained with me * all safety documents listed in point A (11) of the annexed form.
Date: __________ Signature : _____________________
Name : _____________________
(Project Execution Manager/ Resident Construction Manager)
Copies to: : All SBU Heads
: Project Execution Manager - Powai/ Baroda : Champion of concerned SBU
3.2.4.2. Monthly Reporting & Analysis of Mishap at L & T Construction Sites
3.2.4.2.1. Objective
3.2.4.2.1.1. This procedure is to report and highlight monthly safety performance record of L&T sites to the management. 3.2.4.2.1.2. Based on these reports, the management can take
necessary steps and augment safety efforts as required at the sites.
3.2.4.2.2. Procedure
3.2.4.2.2.1. SSO shall write the correct Accident Data & Man – Hours as per the standard format given by Safety Control Dept. E & C Division.
3.2.4.2.2.2. SSO & RCM shall sign report. If RCM is not present, his representative will have to sign and to be forwarded to Safety Control Dept. in the first week of every month. 3.2.4.2.2.3. Monthly statistic report are processed and analysed by
Safety Control Dept. and performance is evaluated for further action. Also it will be published in quarterly safety bulletin.
3.2.4.2.3 Administration
3.2.4.2.3.1 Site Safety Officer of E & C Division or Main Contractor shall send the report to Safety Control Dept. by the first week of every month.
3.2.4.2.3.2 If Site Safety Officer is not present, RCM will be responsible to send the report to SCD.
3.2.4.2.3.3 If there is nothing to report in a particular month then “ Nothing to report’’ will be written in “ Month under report ‘‘ and the same cumulative data as that of previous month shall be written.
3.2.4.2.4.2 ACTUAL man - hours lost, which equals to stoppage of work by the injured person/s. i e. No. of injured person / s X no. of hours not worked.
3.2.4.2.4.3 NOTIONAL man - hours lost which equals to no. of hours not worked ( for medical treatment , etc. ) by the injured person/s, even if he is replaced/ transferred to other site, after his recovery from the ailment.
(Total man - hours lost due to stoppage work, as a result of accident /mishap, by the site work-force may also be reported as a third parameter, to record overall consequence of the accident).
3.2.4.2.5 RECORD
Form Reference
Larsen & Toubro Limited
Date of Issue : __________________E & C Division Project Name & Job No. : __________________
Ref.: CSC-02-MR-R1
MONTHLY STATISTICS REPORT
For the month of ________ Year ________
Accident Data
a
Lost time Accidents
No. Ofincidents Man hours lost No. of people Involved No. of Contractors involved L & T Person If any No. of reporting to Govt. For the month under report ( ____2000)
Cumulative
From _______ 1999 to________ 2000
b
Minor Injuries
For the month under report ( ____2000) Cumulative From _______ 1999 to________ 2000 c
Fires
No. Of cidents Man hours lost No. of person injured No. of equipment damaged Loss in Rs. No. of fires reporting outside For the month under report(____,2000)Cumulative
From _______ 1999 to________ 2000
d Other mishaps not covered
in a, b, c. No. of Near-Miss No. of First aid cases No. of person injured No. of eqpt. Damaged Loss in Rs. Total Near miss & First aid For the month under report ( ____2000)
Cumulative
From _______ 1999 to________ 2000
Data for Man hours worked
Details L&T E & C
(A) Main Contractors (B) Sub-contractors (C) No. of People
Man hours worked
O.T hoursTotal Man hours
Grand total of man hours worked during the month ( A + B + C ) :
Cumulative man-hours ( from _________1999 to _________2000) :
3.2.5. Positive Reporting on Safety At Construction Sites 3.2.5.1. Objective
Procedure Nos. CSC-01 and CSC-02 deal with reporting of accidents and mishaps at E & C Division construction sites. These reports give negative information, albeit necessary, about Safety Performance & Management at the sites and enables measurement of safety in terms of reduction in injury/harm/loss.
However, when Safety Performance is good, and injury & loss are low at a particular site, these negative measurements are not sufficient to have adequate feedback for managing safety, because potential for injury/mishap may be high at the site but likelihood of risk of events may be very low. Hence, absence of accidents is not a sufficient indication of good Safety Management and other measurements of Safety Performance are necessary to have assurance that the absence of accidents is due to good Safety Management.
3.2.5.2. Procedure
The Procedure deals with formally reporting to the Safety Control Department (SCD) of E & C Division, at Powai, in writing, about the positive aspects of safety such as follows in construction activities at sites.
(a) Compliance to Safety Control Procedures (CSC) in the Procedure Manual.
(b) Provision and use of APTs to/by L&T and Contractors at site
(c) Regular On-site training of workmen, mock fire-drills etc. (d) First Aid and Fire Fighting Training of site personnel (e) Any additional safety provision at site
(f) Any aspect of safety promotion at site such as Safety Slogans/essay/quiz competition, safety poster display etc.
Before reporting, RCM/E should ensure that the following requirements are met:
(I) Compliance/provision being reported must be of permanent/regular nature, i.e. they must continue at the site until the site is closed.
(II) Compliance/provision must be seen as having definite and positive effects on preventing mishaps and personal injuries at the site.
3.2.5.3. Administration
(a) Whenever a positive action is taken at the site, RCM/E will send its details to SCD in the form attached to this Procedure. Both RCM/E and SSO will sign the form.
(b) The information may be sent at any time, as and when the positive safety action is taken at the site.
(c) Safety Officer from SCD will check the actual provision of the measure/s reported by RCM/E, when he visit the site. (d) SCD will record the action and use it for co-relation of such actions with the Safety Performance of the site and also use it for safety awards, when instituted in E & C Division.
Annexure
Positive Safety Measure/Action
Name of Site :
Ref. : Date : To: Head Safety Control
E & C Division L&T-Powai. From :
We are pleased to report the following positive safety measure/s at our site:
Sr.
No. Date of action/implementation Description Whether one-time orContinuous/regular (Frequency)?
We shall ensure that this measure/practice will continue until the site is closed.
3.2.6. Daily Log - Book
The Site Safety Officer is required to make the Safety Inspection of the facility and Observations of the work
methods and procedures adopted by the contractors and their men and record the same in the daily logbook. The entries should be shown to the Resident construction Manager for getting his signature and for prompt proper action
Annexure
Format for Daily Log - Book
DATE SR.
3.2.7. Safety Promotion and Recognition
3.2.7.1. Display of Safety Performance at Construction Site 3.2.7.1.1. Objective
One of the Codes of Conduct in the E & C Division - ‘Safety Policy Statement’ is to promote interest and enthusiasm in safety efforts through awareness and recognition of safety performance. This is possible, if all persons working at the L&T site are informed about the safety performance at the site. Efforts to correct/improve poor safety performance and to maintain good safety performance will be put by people at the site, if they know about the current performance, on continuous basis.
One of the methods of informing persons working at the site about safety performance of the site, is by displaying it on a board which is placed prominently and up-dated daily. Persons working at the site, when they read the information on the Board, will feel proud of their good safety performance and will strive to maintain it.
The objective of this Procedure is to require all construction sites to display information about the safety performance of their individual sites.
3.2.7.1.2. Procedure
The Procedure deals with the preparation, installation and updating of the Display-Board giving up-do-date, correct and accurate information about safety performance of the construction site, where the Board is installed.
3.2.7.1.3. Suggested specifications of the board:
Dimensions - 1500 mm L x 1000 mm H
(Dimensions may be reduced proportion-ately to suit site conditions but not below 1000 mm L x 800 mm H).
- Number Plates : 230 mm H x 115 mm W
Material : Aluminium (preferable) or G.I.
Sheet
1 mm thick or plywood 5 mm thick
Colour : Background : White
Lettering : Dark Green Numbers & L&T Logo: Black
Layout : See Annexure for a Specimen
Quantity : One or more depending on the
area of the site
3.2.7.1.4. Location of the Board shall be such that it is visible to all persons working at the site while they move around the site.
One of the following locations shall be considered:
* Hung on the outside wall of L&T site office near entrance to RCM office
* Mounted on a grouted frame at the entrance to the L&T site.
3.2.7.1.5. Languages of safety information on the Board:
- English or Hindi (top half of the Board) - Local language (lower half of the Board)
3.2.7.1.6. Administration
(a) Within 15 days from the effective date of this Procedure RCM/Site In-charge will get the Display Board/s ready and have them installed at any of the suggested locations mentioned in 2.2 above.
(b) Nos. of days to be displayed will be from the date of the last LTA/MI/DI. (See Definitions in 3.8).
(c) The safety performance shall cover
persons/equipment/assets of L&T-Group II (P) and of all its Contractors at the site.
(d) Responsibility of operating/updating the Board shall be of the Site Safety Officer (SSO). If SSO is not present at the site, then RCM or his designated person shall be responsible for operation/updating of the Board.
(e) Name of the person responsible for operation of the Board and date of updating shall be clearly shown on the Board.
(f) SSO/RCM shall update the information on the Board every day (except on weekly offs) at 9 A.M., after reviewing information of the previous 24 hours.
(g) Safety Officer from SCD (Powai) shall include, in his inspection, working of this Procedure, during his site inspection/audit and check that the information matches with the one provided through Accident Reports sent to SCD by the site RCM vide Procedure of existing CSC-01. (h) Definitions of Lost Time Accident (LTA), Minor Injury (MI)
and Dangerous Incident/Occurrence (DI) are given below for ready reference.
Lost Time Accident (LTA):
An incident which causes death of a person or which causes bodily injury to a person due to which s/he is prevented from working for a period of 48 hours or more immediately following the incident.
Dangerous Incident/Occurrence (DI) :
An incident in which (with or without personal injury) there is or could have been a damage/loss to property, equipment, materials of L&T or its Contractor and in the surrounding. Examples: Fire, gas leak, explosion, vessel/cylinder bursting, collapse or failure of structure, machine etc., subsidence of floor, roof, chimney etc. and such incidents.
Personal injury/ies during a Dangerous Incident shall also be covered separately in LTA or MI as may be the case.
1200
400
400
200
PEOPLE ON THIS
L & T – E & C DIVISION SITE
HAVE WORKED
WITHOUT LOST TIME
ACCIDENT FOR
WITHOUT MINOR
INJURY FOR
WITHOUT DANGEROUS
INCIDENT FOR
D
A
Y
S
+
ÉäãÉ +
Éäxbñ
]
ñÉ
Ò - <Ç +
Éäxbñ ºÉÉÒ
ÉÊbñ´cÉÒZÉxÉBÉäE <
ºÉ ºÉÉ<Ç]ñ {
É®õ
BÉEÉàÉ
cÖ+ÉÉ
cè
-JÉiÉ®õxÉÉBÉE +É{
ÉvÉÉiÉ
BÉäE
ÉʤÉxÉÉ
àÉÉàÉÚãÉÉÒ
SÉÉä]ñ
BÉäE
ÉʤÉxÉÉ
cÉÉÊxÉBÉEÉ
®õBÉE
nÖõvÉÇ]
ñxÉÉ
BÉäE
ÉʤÉxÉÉ
DATE SITE NAME JOB NO.
D
A
Y
S
D
A
Y
S
ÉÊnõ
ÉÊnõ
ÉÊnõ
Annexu
re
Saf
e
ty
Per
form
a
nc
e Boa
rd
3.3. Statutory Requirements:
The Government of India has enacted “THE BUILDING AND
OTHER CONSTRUCTION WORKERS (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) ACT, 1996” AND “THE BUILDING AND OTHER CONSTRUCTION WORKERS (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) CENTRAL RULES 1998” and the
copy can be procured for the site.
In order to facilitate for easy reference for important chapters, the rules governing the subject of the chapter are also given.
3.4. Prequalification for selection and performance of Contractors for L & T work
(A) Objective
This procedure is to scrutinise / evaluate L & T Construction
Contractors w.r.t their sutability to work safely on L & T sites.
It is expected that by emloying the contractors who meet the qualification requirements laid in this procedure, accidents and dangerous occurences on L & T sites would be minimised. By following the procedure, L & T Manager should encourage contractors on safety and make every effort to qualify them by advising them corrective actions to be taken by them.
(B) PROCEDURE
The Procedure covers basically four situations / status w.r.t. the contractors at E & C Division sites and these are shown in tables below :
CONTRACTOR CONTRACTOR PROCDURE STATUS ACTIVITY NO. CSC-03/
1. New Request for prequalification; / 1
(Not qualified in no bidding safety by L & T)
2. New Bidding for a specific / 2
(Not qualified in project safety by L & T)
3. Existing Working at Group II- / 3
(Not qualified in projects site / s safety by L & T)
4. Existing Not Working at Group II - / 4
(Not qualified in projects site / s safety by L & T)
Procedure for Prequalification in Safety of a New Contractor ( Not bidding for specific project )
1. Contractor desiring to register with L & T E & C Division, approaches any BU Manager / SAFETY CONTROL, for working on L & T project .
In any case, the original must come to Head – Safety Control and others retain copies.
3. Safety Control Engineer (SCE) from Safety Control scrutinises the information and visits the contractor office / sites for inspection, if he finds more than 80 % of the requirements are met . SCE advises the contractor about the shortfalls, if any.
4. If 80 % requirements not met, Head – Safety Control reject the contractor’ s application to register and asks him to resubmit when is ready to meet the requirements. If the contractor intends to know, Head – Safety Control will inform the contractor in writing about his shortcomings in safety qualification.
5. If the contractor qualifies,
- Head – Safety Control will inform the contractor about his acceptance by L&T for registration.
- Head Safety Control will inform all BUH’s / DGM’s / AGM’s / PM’s / SM’s by a memo and a copy of updated list of prequalified contractors.
6. If during the site inspection of SCE , any shortfall in the qualified contractor safety capability is observed , he will be instructed to corect it within a specified time , failing which he will be disqualified. Then
- Head – Safety Control will inform the contractor about his disqualification.
- Head – Safety Control will inform all BUH’s / DGM’s / AGM’s / PM’s / SM’s by a memo and a copy of updated list of prequalified contractors. Name of the disqualified conractor will be deleted in this list.
It will be decision & responsibility of PM / SM about the continuation of services of the subject contractor at the ongoing sites. In any case, the contractor shall not be awarded any new contract for work/services, untill he requalifies in safety.
Procedure for Prequalification in Safety of a New Contractor ( Bidding for a specific L & T project )
3. Same as in Procedure No. CSC-03/1. 4. Same as in Procedure No. CSC-03/1. 5. Same as in Procedure No. CSC-03/1.
6. If the contractor fails to meet the qualification standards of Safety, DGM ( QA & I ) will inform him accordingly , in writing , with copies to BUH’s / DGM’s / AGM’s / PM’s / SM’s, who shall not award work to the said contractor / s at Group II Project sites .
7. Same as No. 6 in Procedure No. CSC-03/1.
Procedure for Prequalification in Safety of an Existing Contractor ( Working at L & T Group II projects site / s )
1. PM / SM at the site / s issues the CSCE form to the contractor and
requires him to fill in and submit it to PM / SM within 15 days.
2. PM / SM will snd the original to DGM - QA & I , retaining a copy of the same.
3. SCE scrutinises the information given inthe csce and visits the contractor office site / s. If the Safety requirements are not met satisfactorily , SCE advises , in writing , PM / SM about the shortcomings , and sends a copy of the advice to the contractor for correcting / reinforcing his safety capability.
4. If 80 % of the requirements are not met within 15 days after SCE’s advice to the contractor, DGM - QA & I rejects the contractor from qualifying in safety and informs the contractor and BUH’s / DGM’s / AGM’s / PM’s / SM’s in writing.
It will be decision & responsibility of PM / SM about the continuation of services of the subject contractor at the on-going sites . In any case the contractor shall not be awarded any new contract for work/services, untill he requalifies in Safety.
Procedure for Prequalification in Safety of an Existing Contractor ( Not Working at any L & T Group II projects site / s )
1. All such contractors , who are desirous of working at L & T site, within one year , are informed by PM / SM about L & T’s requirement for pre-qualification in SAFETY.
2. Same as in Procedure No. CSC-03/1. 3. Same as in Procedure No. CSC-03/1.
(C) Administration
(a) Books containing 5 sets of CSCE Forms will be sent to all sites by Safety Control Department . More forms can be obtained from Safety Control Department. However, if forms are exhausted, the CSCE should be prepared in photocopy/typed copy and submitted to Head Safety Control.
(b) SE will periodically check at all E & C Division Sites whether the contractors working at sites are qualified in Safety by L & T and advise Sr. V. P. / BUH’ s about the status every quarter.
(D) Definitions / Abbreviations
- BUH : Business Unit Head
- Head–Safety Control : Deputy General Manager, E & C Division. - SCD : Safety Control Department
- SM : Site Manager - PM : Project Manager
- SCE : Safety Control Engineer from QA & I - CSC : Construction Safety Control
- RFQ : Request For Quotation ( Same as ITB - Invitation to Bid )
3.4.2 Rules governing Contractor’s work
(A) Objective
Procedure No. CSC-06 stipulates that the standard Terms & Conditions (T&C) of HSE should be included in the contract/purchase orders issued to the L&T site contractors, by the respective Project/Site Managers of E & C Division
In order to ensure that the managers, engineers, supervisors & safety officers of L&T and the contractors are constantly made aware of these T&C, it is necessary that these T&C are available readily with these persons, as Rules in the form of a booklet, which are individually issued to each of these persons.
(B) Procedure
This Procedure deals with the issuing of standard Rules of SHE to all L&T-and contractors-managers, engineers, supervisors and safety officers, who are concerned with health and safety of their employees working at the site.
The following actions are required to be taken by RCM/RCE of L&T/LTCG (in case of site synergy situation).
1. RCM/RCE shall request to SCD adequate no. of copies of the booklet well in time before any contractor is employed at his site.(Fifty booklets are being sent with this procedure, for the on-going sites) .A sample copy of the same is enclosed in the annexure.
2. REC/RCE shall ensure that the booklet is individually issued to L&T and contractor personnel who are responsible for supervising their workers activities at his site.
3. RCM/RCE shall fill up the necessary details and sign them, and have the person (to whom the booklet is issued) sign, in the space provided for this purpose.
4. RCM/RCE shall ensure that the persons issued with the booklet shall have the booklet with them at any time while they are working at the site, have read and understood the Rules and have been provided with clarifications as needed.
(C) Administration
1. SCD shall maintain adequate stock of the booklet in Powai. 2. RCM/RCE shall request to SCD for copies of the booklet
allowing adequate time for mailing etc.
3. If the stock of the booklet is exhausted temporarily at the site, RCM/RCE shall issue photocopy of the booklet from the contract document and immediately request SCD for additional copies.
4. During the site visits, Safety Officers from Powai shall check that the booklets issued to all concerned are available with them. Safety Officer shall also check that the Rules are understood by them.
5. SCD shall send 50 booklets with this procedure, to RCM's/RCE's of the on-going sites.
TO BE UPDATED IN JANUARY EVERY YEAR SECTION A – BASIC DETAILS
COMPANY NAME ADDRESS FOR COMMUNICATION
MAIN CONTACT NAME / DESIGNATION TELEPHONE NUMBER FAX NUMBER
PERSONNEL RESPONSIBLE FOR SAFETY AT SITE
TYPE OF COMPANY / INDUSTRY / FIRM (TICK AS APPROPRIATE)
PUBLIC PRIVATE GOVERNMENT PARTNERSHIP PROPRIETRY CONTRACTORS OTHERS (SPECIFY)
SECTION B – EVALUATION REQUIREMENTS SERVICE PROFILE (TICK AS APPROPRIATE)
CIVIL MECH.ERECTION PIPING ELECTRICAL INSTRUMENTATION
INSULATION PAINTING STRUCTURAL OTHERS (SPECIFY)
SCOPE OF APPROVAL
THE SCOPE OF APPROVAL DETERMINES THE NATURE OF YOUR SERVICES YOU INTEND TO PROVIDE TO L&T
LARSEN & TOUBRO LIMITED TELEPHONE : 022-8581401/1411 E & C Division – Safety Control Department TELEFAX : 022-8581020 Saki Vihar Road, P.O.Box 8901, Powai, Mumbai 400 072, India
Give details, no. of safety officers, their qualifications, their accountability and authrities, their nature of work. (Full-time or Part-time?) _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ 2. Do you nominate trained safety observers among workmen at your job-sites? Yes / No
Give details and account of their effectiveness.
_______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ 3. Do you have formal / written accident (personal & equipment) reporting & investigation system? Give details and attach blank
forms used in your company. How does the system work?
_______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ 4. Do you keep records of all accidents, mishaps, dangerous occurrences at all your job-sites?
_______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________ _______________________________________________________________________________________________________
SECTION D – SAFETY RECORD / PERFORMANCE 1. Give the following details (for last three years) (incl: your sub-contractors)
Incident No. No. of job-sites No. of man-hours Compensation paid /
Involved worked Loss (Rs.)
a. Minor injuries _____ _____________ ________________ _________________
b. LT accidents _____ _____________ ________________ _________________
c. Fires _____ _____________ ________________ _________________
Involved for the year (Rs.) ______ _______________ ________________ ___________________ ______ _______________ ________________ ___________________ ______ _______________ ________________ ___________________ ______ _______________ ________________ ___________________ ______ _______________ ________________ ___________________ ______ _______________ ________________ ___________________ ______ _______________ ________________ ___________________
3. Was your company / company official involved in any litigation due to accident / fire etc. at your job sites in the last three years? Is there any court case pending against your company / company official? Give details.
_________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________
SECTION E – ADDITIONAL INFORMATION 1. Give additional information (on safety), if any.
_________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________
SECTION F – YOUR PROPOSAL FOR THE SPECIFIC JOB-SITE FOR WHICH ARE BIDDING TO L&T 1. Give details of insurance, legal arrangement etc. you will provide / have provided for in this bid.
_________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________ 2. Will you indemnify L&T and its personnel against any legal action due to accident, fire, dangerous occurrence at L&T site & its
surroundings? Give details.
_________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________ _________________________________________________________________________________________________________
3.5 Safety Committee 3.5.1. Introduction:
Statutorily (See section 38 of The Building and other construction workers (Regulation of employment and condition of service) Act 1996) each site should have a safety committee having equaled number of representatives from management and workers/ contractors. A well-planned safety committee is a great motivator for safety. It’s primary purpose is to enable management and workers to work together to monitor the site safety plan, so as to prevent accidents and improve working conditions on site. Its size and membership will depend on the size and nature of the site and upon differing legal and social conditions in the state concerned, but it should always be an action orientated group of people in which both management and workers are represented. The safety committee carrying out a site inspection together raises the level of safety consciousness at the site.
The procedure for forming the safety committee, scope and objectives of the committee, meeting procedures, minutes preparation and circulation and follow up action is listed in annexure.
Annexure
Formation of safety committee, membership, objectives, meetings, minutes and follow up action.
1) Formation of Safety Committee
Each site will have one Safety Committee.
Safety Committee will consist of/be represented by site – in –
charge of all contractors / sub – contractors and headed by the L&T site Manager. This committee will have periodic meetings headed by L&T Site Manager.
2) Meeting Frequency
a. Meetings of the safety committee and shall be held at least once in a month, in the second week of each month.
Dates of the next meeting shall be informed to all members in the preceding meeting, so that the members can make themselves available for the next meeting. This is important so that the members find / make time available to attend the meeting.
b. Special safety committee meeting shall be held as required to discuss serious accidents, potentially accident – prone
activities and such matters.
3) Scope / objectives of the Safety Meetings
Regular and frequent meetings to discuss the safety and health programme on site and to make recommendations to management. Discussion of accident and illness reports in order to make recommendations for prevention.
Evaluating improvements made.
Examination of suggestions made by workers, particularly by safety representatives.
Planning and taking part in educational and training programs and information sessions.
Agenda shall include review of MoM of the previous month, acceptance by all participants (to be recorded) and record of actual completion dates of action items.
Larsen & Toubro Limited.
Site _______________E & C Division Date of Issue ________
Sheet ____of ____
Minutes of Safety Committee Meeting
held on _______, at the site for the month of __________’2000
Present Sr.
Larsen & Toubro Limited.
Site:________________E & C Division Date of Issue: _______
Sheet ____of ____
Minutes of Safety Committee Meeting
held on _____________________, at the site Sr.
No. (Including recommendation)Particulars of the minutes ActionBy TargetDate for action Actual Comple-Tion Date of Action
1 Review of previous MoM held on ______
The next safety committee meeting will be held on
___________________________ ____________________
Name & Signature of Site Safety Officer Name & Signature of RCM/RCE
3.6 Construction Safety Plan (A) Objective
(i) This procedure is to inform, familiarise, involve and get commitment of Project-ites of E & C Division, about L&T’s concern for and recognition of Safety, Health and Environment (SHE) during construction, from the very beginning until the project is completed and handed over to a client.
(ii) Provisions for SHE during construction of projects have to be thought about, planned, incorporated and committed by L&T from the time a tender is submitted to a client, and carried through in techno-commercial discussions with the client, in the contract/order document, and in the project execution such that construction is possible to be carried out in safe/accident-free manner.
(iii) It is expected that by following this procedure, the Client, Project Execution and Construction Departments will be enabled to make adequate provision for safety during construction.
(iv) ‘Construction Safety Plan’ is meant to be a part of `Project
Safety Plan’ (PSP) which will cover not only construction
safety but also safety in engineering, procurement and commissioning, i.e. Total Safety Management (TSM) in a project.
(v) `Project Safety Plan’ will be incorporated as separate Procedure and Document.
(B) Procedure
The procedure deals with making available General Construction Safety Plan (CSP-G) to Marketing, Prospective Clients (through Marketing), Project Execution and Construction Departments of E & C Division, who have all to play important roles in its implementation in the steps described below.
(C) Steps for Implementing the Procedure:
Step No.
Event Action Action By 1. Marketing Dept. sends
proposal/tender to a client
(a) Attach Construction Safety Plan (CSP-G) to the Proposal / Tender.
Marketing
(b) Provide for safety require-ments (Sections 1 to 6 of CSP-G) in the price quoted to the client.
Marketing
(c) Request the client to fill-up Sections (7) & (8) of CSP-G.
Marketing
2. Client wants to inspect
the attachments to CSP (a) Show the attachmentsviz. Safety Manual, Policy Statement, Procedure Manual, Terms & Conditions for
Contractors on Safety, to the Client. Do not
submit them to the client.
Marketing
(b) Provide one copy of Construction & Procedure Manuals to Marketing Department (for client’s inspection).
SCD
3. Technical discussions with
the Client (a) Obtain sections (7) & (8)of CSP duly filled up, from the Client prior to the technical discussions.
Marketing
(b) If necessary, invite Safety Control Dept., Project Execution and Construction Depts. for discussions on safety matters with the Client.
Step No.
Event Action Action By 4. Techno-Commercial
discussions with the client
(a) Adjust the price quoted, if necessary, for additional provisions for safety according to the informat-ion provided by the client in Sections (7)&(8) of CSP-G Marketing + Project Execution
(b) Discuss the above with the client, finalise and get the client’s commitment on the information in Sections (7) & (8). Marketing + Project Execution 5. Contract/Purchase Order
with the client
Include CSP-S, which is specific for the client in the CO/PO attaching Sections (1), (2), (5), (6), (7) & (8) of the CSP. Sections (7) & (8) will contain the information and commitments from the client in Step Nos. 3 & 4 above.
Marketing
6. Project Execution Hand over the PO/CO and specific CSP (CSP-S) to Project Execution and Safety Control Depts.
Marketing
7. 15 days before
Construction starts (a) Hand over PO/CO with(CSP-S) to the Construction/Resident Manager
Project Execution
(b) Send copies of Policy Statement, Construction Safety Manual, Procedure Manual to the Resident Manager (if he does not
have these).
SCD
8. Pre-Construction Meeting
at the site (a) Invite SCD to participateto explain CSP-S to the site personnel, contractors and the Client.
Resident Manager
Like in case of any Company Procedure, TIMELY & SINCERE ACTIONS by as also CLEAR AND COMPLETE COMMUNICATIONS among the concerned departments viz. Marketing, Project Execution, Construction & Safety Control Dept. is key to the success of this procedure which is essential and important to achieve accident-free construction sites of E & C Division.
(D) Administration
(i) Safety Control Dept. (SCD) will initially provide copies of CSP-G and Procedure No. CSC-07 to the Marketing Managers of E & C Division. Besides, CSP-G and the Procedure will also be sent out to the recipients of controlled copies from SCD.
(ii) Copies of the Construction Safety Manual, Procedure Manual, Policy Statement Placard, Model Terms & Conditions for Contractors on safety will also be sent to the Marketing Managers, who have not received them from SCD.
(iii) Clarifications/Suggestions, if any on this Procedure should be communicated to SCD in writing for subsequent revisions. (iv) Marketing Department is requested to print/photo copy
(without any alterations/changes) the original CSP for their future requirement.
(E) Definitions
(i) `Project Safety Plan’ (PSP), of which `Construction Safety Plan’ (CSP) will be a part will be developed and issued in the near future.
(ii) CSP-G: `General Construction Safety Plan’ which contains
blanks for a client to fill up in the Section (7) of CSP and does not have the client’s specific safety requirements in the Section (8) of CSP.
(iii) CSP-S: `Specific Construction Safety Plan’ which contains detailed information and commitments in the Sections (7) & (8) from the client. The cover-page of CSP-S will bear the name of the site “For __________________Site”.
3.7 Accident reporting and Investigation (A) Objective
(i) Objective of this procedure is to ensure that Safety Control Dept., E & C Division is notified of all accident as soon as possible.
(ii) This procedure will also provide a systematic method of investigating and reporting an accident at construction site and identify corrective action steps to prevent a reoccurrence.
(iii) This procedure also outlines the method of communicating with Safety Control Dept., E & C Division.
(B) Definitions
Fatal : Death resulting from an accident. LTA (Lost Time Accident):
An injury causing disablement of an injured person beyond 48 hours excluding the days of accident and reporting to work back. which should also include Sundays and holidays.
(a) Immediate loss of any part of the body or any limb or part there of.
(b) Crushed or serious injury to any part of the body due to which loss of the same is obvious.
(c) Any injury which is likely to prove fatal. (d) Unconsciousness due to accident.
(e) Severe burns or scalds due to chemicals, steam or any other cause.
Dangerous Occurrences:
(a) Bursting of a vessel used for steam having pressure greater than atmospheric pressure.
(b) Collapse or failures of any lifting machine (crane, wire rope hoist, chain pulley block, etc), lifting Tackle (chain sling, wire rope sling, shackle, clamp, etc.) and lifts (passenger, goods and service).
(d) Explosion of a receiver or container used for storing any substance (gas, liquid, solid etc.) at a pressure greater than atmospheric pressure.
(e) Collapse or subsidence of any floor, gallery, roof, bridge, tunnel, chimney, Wall, building.
Minor Injury:
An injury, which requires Medical treatment, causing any
disablement of injured person from work less than as mention in LTA. Person is resumed the site within 48 hours after receiving an injury.
First aid injury:
An injury, which requires first-aid treatment only without causing any disablement of the injured person from work. Person is resumed site within two hours after receiving an injury.
Near - Miss Occurrence:
These are incidents / occurrences wherein a serious accident as described in 1, 2, 3, 4, and 5 above has not happened but could have happened or could happen, if the unsafe situation / act continues, or it did not happen due to absence of a factor, which could have resulted in the serious accident.
(C) Procedure
The procedure deals with reporting of accidents involving people, machinery, buildings, structure, surroundings, environment (air, water, land), dangerous occurrence and near accident & first aid occurrence which could have resulted in an accident and / or dangerous situation.
1. Responsibility of reporting - Residence Construction
Manager
2. Reporting - As per distribution given in the forms.
3. Method of reporting - e-mail / by fax / courier
(i) Form (Accident Report)
- This is for reporting Fatal, Lost Time Accident, Minor Injuries, Fire & other dangerous occurrence.
- To be filled by the supervisor / engineer of L & T/ Contractor and sent to his site - in - charge with copies for L & T Site Manager and others as shown in the form, immediately within 24 hours.
- If there is any fatalities, an oral report must be made to DGM (Safety), within 4 hours and following information must be provided
• The facility name;
• The location of the incident; • The time of incident;
• The no. of fatalities or hospitalized employees and their names;
• The name of contact person and his Tel. No. and;
• Brief description of the incident.
(ii) Form ( Accident Investigation )
- It is for reporting investigation of the accident / dangerous occurrence already reported in (i).
- It has to be filled in by the SSO / person
investigating or nominated by Site Manager and copies to be sent as shown in the form within 72 hours.
- When indicated by the severity of the incident, steps to secure the incident site must be initiated immediately to ensure the investigating party can reconstruct the events leading to the incident. - Individual interviews should be conducted with
each person at the time of the incident.
• The witnesses should be interviewed promptly, separately and privately.
• The interviewer should avoid questions that give a yes or no answer.
• After the interview, the interviewer should
document any concerns identified.
• The investigation should be directed at
determining the root cause.
• The investigation team must focus on getting accurate and complete information.
• The investigation will identify corrective
actions, both immediate recovery actions and long term follow – up actions to prevent the incident from reoccurring.
(iii) Form (Near Miss)
- It is for reporting Near- miss accident.
- Accident, which does not come under above
category i.e, Lost time accident, minor, first aid should be send as shown in the form within 24 hours after an accident take place.
- To be filled by the supervisor / engineer of L & T/ Contractor.
(iv) Form (First Aid cases)
- It is for reporting only first aid cases (Please refer its definition in Section 2.0, Sub Section 2.1, Clause 5)
- To be filled by SSO / person investigating or
nominated by Site Manager, one copy to be send to Safety Control Dept. of E & C Division and others as shown in the form within first week of the month.
(D) Administration
1. Safety Control Department will send revised procedure with the forms to all sites. The reports in photocopy or in typed form should be prepared and submitted to Safety Control Department of E & C Division within stipulated time frame as
authorities as per the Section 88 of Factory Act 1948., besides these internal reports.
3. Employees responsibility :
- Inform immediately to SSO or concern supervisor for work related illness and injuries (i.e. on the same day).
(E) Records
Form Reference
1. Accident Report CSC-01-R1-AR.
2. Accident Investigation CSC-01-R1-AI.
3. Near miss Accident Report CSC-01-R1-NA.
(CSC-01-R1-AR NO.__________) To be submitted immediately after the Accident (Within 24 hours)
Project Name & Job no. Exact location of Accident / Incident Date & Time of Incident SBU
Accident that has occurred ( Tick as applicable )
! Personal Accident ! Fire / Explosion ! Mechanical ! Collapse of Structure ! Spillage of dangerous fluids ! Others ( Specify ) : Event ( Tick as applicable )
! Injury ! Property damage ! Material loss ! Environment pollution ! Others ( Specify ) :
Name of Injured Designation & Token no. Age : ____ Sex : ____
Name of Contractor ( with whom he / she is working ) :
Brief Description of Accident :
Specify the injury, extent of damage / loss
( e.g. Fatal, loss of fingers, fracture of leg, scald etc. )
Location of Injury
( e.g. right leg, left hand, left eye etc. )
Object causing injury
( e.g. structural material., m/c, tools etc. )
Whether there was any unsafe condition Yes ! No !
Whether any unsafe act by injured person Yes ! No ! Whether the person was wearing protective equipment
Yes ! No ! If Yes, relevant PPE used :
Was he under the influence of Alcohol / Drugs Yes ! No ! Whether medical aid was given
Yes ! No ! Whether person was hospitalised
Yes ! No !
Has report been given to authorities Yes ! No ! If Yes, to whom ( Specify ) :
Probable cause of Accident & any additional information :
Name of two witnesses and signatures 1. Name : 2. Name :
Date : ( Signature ) : Date : ( Signature ) :
____________________________________ Name of supervisor of L & T / Contractor
(CSC-01-R1-AI NO.__________) Investigation of the Accidents reported in CSC-01-R1-AR by persons nominated by L&T site manager ( within 72 hours )
Name & designation of investigating person Project name & Job no. Exact location of Incident Name of Injured Designation & Token no. Age : _____
Sex : _____
Date & Time of Accident
Accident details ( CSC-01-R1-Accident Report (AR) No. ___________)
What was Injured doing at the time of Accident :
State whether it is Personal Injury / Property damage ( Specify value in Rs. )
Whether LTA or Minor or Others Name of Contractor
Whether there was Unsafe Act? Give details
Whether there was Unsafe Condition? Give details
Was he under the influence of alcohol / drug Yes ! No ! The Injured person working
Since : ________ Month, ________ Year
Date & Time the person resumed work after accident
Specify the failure / deviation from Safety norms :
Cause of Accident
What immediate actions have been taken to prevent such accidents :
What actions could be taken to prevent such accidents in future :
(CSC-01-R1-NA NO.__________) It is important that the reporter removes unsafe condition or stops unsafe act before filling the form Project Name & Job no. Exact location of Incident Date & Time of Incident SBU
Probable Accident that could have occurred ( Tick as applicable )
! Personal Accident ! Fire / Explosion ! Mechanical ! Collapse of Structure ! Spillage of dangerous fluids ! Others ( Specify ) : Name of Contractor Brief description of Unsafe Act / Condition observed
Brief description of Incident :
Whether the unsafe practice / Act / Condition was informed to the person/s involved or contractor supervisor or L&T engineer before filling the form : ! Yes ! No
To whom reported ( Give name of persons ) :
What action was taken after reporting as mentioned above
Name of the reporter with whom he is working / SSO ________________________________________
Name
TO BE SUBMITTED WITHIN 1ST WEEK OF EVERY MONTH
Project Name & Job no. : For the Month of SBU
Sr.No. Date Time Name of Injured Age Sex Name of Contractors
1.
2.
3.
Sr. No.
Type of Injury Location of Injury Object causing Injury Deviation in Safety norms
1.
2.
3.
Brief description about accidents :
1.
2.
3.
Unsafe act Unsafe Condition
1.
1.
2.
2.
3.
3.
____________________________________ ____________________________________ NAME OF REPORTING SUPERVISOR / SSO NAME OF RCM