• No results found

Transportation: San Francisco

N/A
N/A
Protected

Academic year: 2021

Share "Transportation: San Francisco"

Copied!
18
0
0

Loading.... (view fulltext now)

Full text

(1)

Capital Planning

March 3,2020

San Francisco Municipal Transportation Agency

Committee Update

Transportation: San Francisco

Citizen’s General Obligation Bond Oversight Committee

October 19,2020

2014 Transportation and Road Improvement

General Obligation Bond Update

(2)

T2030: 2014 Transportation and Road Improvement GO Bond Program

Presentation Content:

• T2030 GO Bond Program Update

• 3

rd

GO Bond Issuance Program of Projects / Lessons

Learned from Earlier Issuances

• Proposed 4

th

GO Bond Issuance Program of Projects

(3)

Transportation: San Francisco 3

As part of Transportation 2030 a $500M G.O. Bond for

transportation was added to the City’s 2014-2023 Capital Plan.

The Bond passed in November 2014 with nearly 72% of the vote

Issued to date:

$377.2M

Third Issuance Amount:

$138.9M ($134.3 M for projects)

Third Issuance Date:

September 17, 2020

Fourth Issuance:

Planned for early 2021

This was the first transportation bond passed in more than a

decade.

(4)

T2030 GO Bond Program Overview Total Bond (in millions) Already Issued (1st+ 2ndIssuances) 3rd Issuance Amount Estimated 4th Issuance Amount Im p ro ved Tr an si t

Faster, More Reliable Transit $191 $73 $79 $42

Accessibility Improvements $30 $3 $21 $5

Muni Facility Upgrades $70 $67 $0 $0

Major Transit Corridor

Improvements $28 $27 $0 $0 Caltrain Upgrades $39 $28 $11 $0 Sa fe r Str ee

ts Pedestrian Safety Improvements $68 $30 $22 $7

Traffic Signal Improvements $22 $6 $0 $12

Complete Streets Improvements $52 $5 $0 $42

Estimated Cost of Issuance and

Fees and Contingency $10 $6 $4

Total $500 $249 $139 $112

Program Summary

(5)

Transportation: San Francisco

Update –1st Issuance; nearly completely spent.

5

1st Bond Issuance Expenditures

$39,768,945 $44,777,036 $56,371,079 $58,165,370 $60,589,492 $62,670,614 $63,624,386 $63,301,922 $62,647,173 $62,865,849 $64,094,960 $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 12/31/2017 3/31/2018 6/30/2018 9/30/2018 12/31/2018 3/31/2019 6/30/2019 9/30/2019 12/31/2019 3/31/2020 6/30/2020

(6)

Update –1st Issuance; minor funds remain, savings and project closeouts remain. 1st Bond Issuance Expenditures

Muni Forward Rapid Network Improvements

Muni Facility Upgrades

Pedestrian Safety

Improvements Caltrain Upgrades

Major Transit Corridor Improvements Balance $890,806 $580,848 $155,283 $28,030 $1,482 Encumbered $8,472 $- $969 $- $-Expended $22,334,379 $24,605,602 $3,924,490 $7,731,970 $5,498,518 $5,000,000 $10,000,000 $15,000,000 $20,000,000 $25,000,000 $30,000,000

Expended Encumbered Balance

(7)

Transportation: San Francisco

Update –2nd Issuance; lesson learned –supplemental appropriation.

7

2nd Bond Issuance Expenditures and Projections

$29,246 $13,449,008 $21,097,398 $36,556,066 $53,759,799 $108,147,195 $119,831,189 $129,171,878 $0 $20,000,000 $40,000,000 $60,000,000 $80,000,000 $100,000,000 $120,000,000 $140,000,000 9/30/2018 12/31/2018 3/31/2019 6/30/2019 9/30/2019 12/31/2019 3/31/2020 6/30/2020

(8)

Update –2nd Issuance; working on programmatic balancing and project delivery 2nd Bond Issuance Expenditures

T2030: 2014 Transportation and Road Improvement GO Bond Program

Muni Forward Rapid Network Improvements

Muni Facility

Upgrades Pedestrian SafetyImprovements Caltrain Upgrades

Major Transit Corridor Improvements

Accessibility

Improvements ImprovementsTraffic Signal Complete StreetsImprovements Balance $14,530,066 $7,264,812 $10,758,233 $235,228 $(735,864) $2,916,636 $3,604,156 $765,512 Encumbered $32,889 $- $109,797 $- $- $- $- $-Expended $35,025,817 $34,257,531 $14,580,495 $19,784,772 $22,324,801 $83,364 $2,395,844 $719,255 $(10,000,000) $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000

(9)

Lessons Learned for 3rd Issuance:

• Fewer projects

• Larger amounts per project

• Active or nearing construction

T2030: 2014 Transportation and Road Improvement GO Bond Program

After the issuance and delivery of the first two issuances of the

GO Bond, the SFMTA learned numerous lessons integrated into

the program for efficiency in resource use and effective project

delivery.

(10)

3rd Issuance (Series 2020 B)

Update: $138,898,717 issued September 17, 2020, of which

$134,300,000 is for projects.

Project Amount

19th Avenue $ 18,100,000

22-Fillmore Muni Forward $ 25,000,000

BART Canopies/Better Market Street* $ 21,120,000

Caltrain Electrification $ 11,220,000

L-Taraval Muni Forward $ 36,000,000

Program Contingency $ 974,571

Taylor Safer Street $ 20,192,170

Western Addition Signals $ 1,693,259

Grand Total $ 134,300,000

T2030: 2014 Transportation and Road Improvement GO Bond Program

(11)

Transportation: San Francisco

Update –3rd Issuance; allocated to large projects ready for construction.

11

3rd Bond Issuance Projections

T2030: 2014 Transportation and Road Improvement GO Bond Program

$4,420,000 $19,725,000 $38,130,000 $61,935,000 $86,841,813 $103,409,643 $114,709,643 $121,709,643 $128,209,643 $134,300,000 $20,000,000 $40,000,000 $60,000,000 $80,000,000 $100,000,000 $120,000,000 $140,000,000 $160,000,000 9/30/2020 12/31/2020 3/31/2021 6/30/2021 9/30/2021 12/31/2021 3/31/2022 6/30/2022 9/30/2022 12/31/2022

(12)

3rd Issuance Project Schedule

FY 19/20 FY 20/21 FY 21/22 FY 22/23

Program/Project Name Third Issuance Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Faster, More Reliable Transit (Muni Forward)

19th Avenue $ 18,100,000 22-Fillmore Muni Forward $ 25,000,000 L-Taraval Muni Forward $ 36,000,000

Caltrain Electrification – San Francisco contribution $ 11,220,000

Accessibility Improvements

BART Canopies $ 21,120,000

Safer Streets (Signals & Complete Streets)

Taylor Safer-Street $ 20,192,170 Western Addition Signals $ 1,693,259

Planning Design, Bid & Award Construction

(13)

The fourth and final bond issuance is planned for early 2021.

Funding will likely support the following projects:

• Better Market Street (any remaining Phase I construction

funds)

• BART Canopies (planned funding swap with 3

rd

issuance)

• Safer Streets: Taylor Street or Folsom, depending on

pending ATP grant.

T2030: 2014 Transportation and Road Improvement GO Bond Program

(14)

Update –1st Issuance and 2nd Issuance

Projects Ready for Public Use

• Arguello. Beale Street Bikeway. • N Judah Transit Priority Project. • Mission Bay Loop.

• 30 Stockton Transit Priority Project.

• 8 Bayshore –San Bruno Avenue Project. • Underground Storage Tanks Project. • 19 Polk Street Transit Priority Project.

• Pedestrian Countdown Signals on High-Injury Corridors.

Projects Moving into Construction

• 22 Fillmore: OCS on Church/Duboce (Overhead Lines). • 28 19th Avenue: 19th Ave Rapid Project.

(15)

Transportation: San Francisco 15

Faster, More Reliable Transit: $79.1 million $18.1 million –19thAvenue

• Improve reliability, travel times and pedestrian safety of the 28 and 28 Rapid. Implementing various enhancements throughout the corridor. $25 million –22 Fillmore

• Transform the 16th Street corridor by improving transit reliability, travel time, safety, and

accessibility for all users. $36 million –L Taraval

• Replace track, Overhead Catenary System wires, trolley wire and trolley poles and provide safety and pedestrian enhancements along the corridor.

3rdIssuance Projects

Passengers exit an L-Taraval Muni train at Taraval Street and 30th Avenue in Parkside..

(16)

Pedestrian Safety Improvements $21.9 million $1.7 million –Western Addition Area-Traffic Signal Upgrades

• Build pedestrian countdown signals (PCS) and/or signal visibility improvements at 24 intersections.

• Build pedestrian-activated flashing beacons at 9 intersections in the Western Addition area.

$20.2 million –Taylor Safer Streets

• Design and construct a new Taylor Street that meets the city's Vision Zero goals of ending traffic fatalities for all road users. • Widen sidewalks from Turk to Ellis, reduce travel lanes from

Market to Sutter, and upgrade signals in addition to other

pedestrian safety improvements along the corridor. Conceptual design of Taylor Safer Streets intersection.

3rd Issuance Projects

Example of traffic signal visibility improvement that will be created for Western Addition.

(17)

Transportation: San Francisco 17

Accessibility Improvements $21.1 million Caltrain Upgrades $11.2 million $21.1 million -BART Canopies

• Part of larger BART’s Escalator Renovation and Canopy Program.

• Canopies will include a digital display to show train arrival times, new security grille, new LED lighting, security cameras, and other improvements.

• Canopies will protect the escalators from the elements, to help limit breakdowns.

$11.2 million -Caltrain Electrification

• Funds the electrification at the northern terminal of the Caltrain Corridor starting at San Francisco’s 4th and King Caltrain Station • Improves safety and service to the public

3rd Issuance Projects

BART canopy at Powell Station on Market Street.

The current diesel trains will be replaced by electric multiple units (EMUs).

(18)

Capital Planning

March 3,2020

San Francisco Municipal Transportation Agency

Committee Update

Thank You.

Jonathan Rewers

T2030 Program Manager

References

Related documents

The main essence of an adaptive design is that the dose level to be used for the next patient depends on the outcomes obtained from the previous patients who have al- ready

In conclusion this study demonstrates that an acute dose of acetaminophen is not an effective alternate pre-cooling method to cold water immersion when exercising at fixed

COVID-19, Developments, Engineering Department, Transportation Mobility and Master Plan, 2014 Bond Program, Capital Improvement Projects, Drainage Projects, Wastewater

Based on the literature review, we identified seven main themes that are further discussed in this article: the holistic model of dance teacher education; self-regulation

MoDMaCAO proved to be powerful enough to model different distributed cloud applications and we were also able to use its implementation framework to successfully provide plugins

Dubai Ports Authority $150 million financing Sole Lead Arranger Pertamina $322 million financing Co-Lead Arranger Dec 2004 BAPCO – Bahrain $330 million Ijara Mandated Lead Manager

3 Non-Traditionally Funded Transportation Projects: Transportation related projects that qualify for funding from sources not traditionally part of the state highway fund,

Every second year the Hidalgo County MPO in coordination with the Texas Department of Transportation and other interested parties prepares a Metropolitan Transportation