BESA İnşaat Taahhüt Sanayi ve Ticaret Ltd. Şti., active for 20 years in the construction sector, particularly in substructure contracting works, has always prioritized technological innovations and quality in its efforts. Our firm, enjoying the rightful pride of delivering all of its projects without a problem, owes its success to uniting our engineering information and experience with quality labor force and powerful equipment.
OUR VISION
Meeting all product and service expectations of our customers at world standards, prioritizing health and safety and fulfilling labor safety liabilities. Realizing our goals in compliance with the corporations and people we are related to without any harm on the environment and the nature, keeping a close eye on the global developments in the construction sector.
1
OUR SERVICES /
SUBSTRUCTURE WORKS
SUPERSTRUCTURE WORKS
ROAD WORKS
PROJECT MANAGEMENT
SUPPLY AND PROCUREMENT
---PRINCIPLE OF
LABOR
SAFETY
TIMELY
WORK
DELIVERY
3
COMPLETED PROJECTS-LIBYA /
LIBYA-AL ASSA
Al Assa Villas Construction Project (411 Villas and
24 Social Buildings Superstructure and Infrastructure and
Landscaping Works)
DATE OF COMMENCEMENT:
01.02.2008
REMARKS:
Construction of 411 nos of
villa and 24 nos Social
Buildings(~220.000 m2)
with all the infrastructure
network.
TYPE:
Superstructure
NAME OF THE WORK:
CLUB 1 BUILDING
5
CLUB 3 BUILDING
SCHOOL BUILDING
POLICE STATION
OFFICE BUILDING
7
COMPLETED PROJECTS /
İSKİ - Beyoğlu
Beyoğlu Branch Directorate being Responsible
Miscellaneous Sewerage Works (2002 unit prices)
DATE OF COMMENCEMENT:
01.02.2002
DATE OF COMPLETION:
08.06.2002
STATUS OF WORK:
Final Acceptance Made
NAME OF THE WORK:
İSKİ - Gaziosmanpaşa
Gaziosmanpaşa Branch Directorate being
ResponsibleConstruction and Repair of
Wastewater and Potable Water (2008 unit price)
DATE OF COMMENCEMENT:
31.05.2008
DATE OF COMPLETION:
11.11.2008
STATUS OF WORK:
NAME OF THE WORK:
İSKİ - Bayrampaşa
Bayrampaşa Branch Directorate being Responsible
Works of Construction, Maintenance and Rehabilitation
of Water, Canal and Rainwater Canals (2006 unit prices)
DATE OF COMMENCEMENT:
13.09.2006
DATE OF COMPLETION:
31.17.2009
STATUS OF WORK:
Final Acceptance Made
NAME OF THE WORK:
İSKİ - Gaziosmanpaşa
Gaziosmanpaşa Branch Directorate being
ResponsibleThe Work of Partial Renewal
and Rehabilitation on Broken, Collapsed,
Damaged and Out-Of-Service Wastewater
and Potable Water Lines
DATE OF COMMENCEMENT:
27.07.2009
DATE OF COMPLETION:
26.08.2010
STATUS OF WORK:
11
NAME OF THE WORK:
İSKİ - Esenler
Esenler Branch Directorate being Responsible
The Work of Complete and Partial Renewal and
Rehabilitation on Existing Partially Broken, Collapsed,
Damaged and Out-Of-Service Potable Water and
Wastewater Lines (2008 Unit Prices)
DATE OF COMMENCEMENT:
16.02.2009
DATE OF COMPLETION:
30.07.2009
STATUS OF WORK:
ONGOING PROJECTS /
İSKİ - Şile
Şile Branch Directorate being Responsible
The Work of Partial Renewal and Rehabilitation
on Broken, Collapsed, Damaged and Out-Of-Service
Wastewater and Potable Water Lines
DATE OF COMMENCEMENT:
25.04.2011
ESTIMATED DATE OF COMPLETION:
15.04.2014
NAME OF THE WORK:
Büyükçekmece Belediyesi
Büyükçekmece District 1st Region Road
Maintenance, Repair and New Road
Construction Work
DATE OF COMMENCEMENT:
04.01.2013
ESTIMATED DATE OF COMPLETION:
31.10.2013
SURVEY AMOUNT:
1.793.647,50 TL
NAME OF THE WORK:
Büyükçekmece Belediyesi
Throughout Büyükçekmece District
Work of Rainwater Canals Construction and Repair
DATE OF COMMENCEMENT:
19.11.2012
ESTIMATED DATE OF COMPLETION:
İLYAS SAVAŞ
PROJECT NAME:
Beyazıt Beyaz Saray Bazaar and Hotel Construction
PROJECT DETAİL:
Savaş Construction, as the contractor of SİSKA Construction firm, was commissioned in the project of construction of Istanbul Beyaz Saray Palace Bazaar and Hotel in 2001. 14.000 m2 of reinforcement and new block construction were made within the framework of the project.PROJECT NAME:
Yalıköy Holiday Village
PROJECT DETAİL:
Savaş Construction was commissioned in the substructure improvement project of a 171-flat holiday resort in Silivri in 2000. Within the framework of the project, necessary works were successfully completed for elimination of cesspools of the resort, construction of sewerage network and their connection to the collection on the coast.PROJECT NAME:
Construction of Extension for Istanbul Light Metro System
from Yenibosna to the Airport
PROJECT DETAİL:
Savaş Construction was commissioned in the project of Gülermak firm for construction of Light Metro System in Istanbul in 2000. Within the scope of the project, necessary works like rough construction of the transformer building, putting up of the walls, drainage, wooden settled roof and roof cover, dismantling of locked parquets have been completed with successs.PROJECT NAME:
Bakırcılar Industrial Site and Birlik Industrial Site
Distillation Plant Project
PROJECT DETAİL:
Savaş Construction has been commissioned in the distillation plant projects of Düzey Construction between 1996-1999. Within the scope of the project, the construction of the distillation plants, and the rough construction works of Beylikdüzü Çevreciler Housing Complex Cooperative consisting of2 Blocks and 120 apartments have been realized.
PROJECT NAME:
Istanbul Fast Trolley 2nd Stage Construction Project
PROJECT DETAİL:
Savaş İnşaat has been commissioned in the 2nd Stage Construction of Istanbul Fast Trolley Project of Oluşum Yapı Mühendislik Construction firm between 1992-1994. Within the scope of the project, the following works have been performed successfully.• Bus Terminal viaduct construction • Mimar Sinan station construction • Bahçelievler station construction • Yenibosna station construction • Yenibosna transformer construction • Yenibosna culvert construction
• Mimar Sinan transformer construction
COMPLETED INDIVIUAL WORKS
PROJECT NAME:
S.S. Uyumkent Housing Construction Cooperative
Construction Project
PROJECT DETAİL:
Savaş İnşaat has taken successful part in the project of Construction of S.S. Uyumkent Housing Construction Cooperative of TİMSA Construction firm between 1986-1992.10
İLYAS SAVAŞ REFERENCE DOCUMENTS
MEHMET ÖZEN
1998 – 2000 Çukurova İnşaat A.Ş. Bağcılar Olympic Enclosed Gym Rough Construction Chief
2000 – 2000 Net Yapı Akaretler Multi-Storey Car Park Rough Construction Chief
2001 – 2001 Çukurova İnşaat A.Ş.Aydın Municipality Service Building Construction Construction Chief
2002 – 2003 Lidya Yapı Kadıköy Wastewater Preliminary Distillation Plant Rough Construction Chief
2002 – 2003 Hona İnşaat Topkapı City Park Multistorey Car Park Rough Construction Chief
2003 – 2003 Timsan İnşaat Üsküdar Multistorey Car Park Rough Construction Chief
2003 – 2005 Çukurova İnşaat A.Ş. İSKİ Beyoğlu Branch Directorate Maintenance and Repair Construction Chief
2005 – 2006 Çukurova İnşaat A.Ş. Beyoğlu Municipality Road Construction and Repair Construction Chief
2006 – 2007 Çukurova İnşaat A.Ş.İSKİ Bağcılar Branch Directorate Maintenance and Repair Construction Chief
2007 – 2008 Besa İnşaat Ltd.Şti. İSKİ Bayrampaşa Branch Directorate Maintenance and Repair Project Manager
2008 – 2009 Besa İnşaat Ltd.Şti. İSKİ G.O. Paşa Branch Directorate Maintenance and Repair Project Manager
2008 – 2009 Besa İnşaat Ltd.Şti. İSKİ Esenler Branch Directorate Maintenance and Repair Project Manager
PROFESSIONAL EXPERIENCE
19
MEHMET ÖZEN
21