Pipeline Design and Construction
Pipeline Design and Construction
Presented by: Presented by: Engr
Engr. Md. . Md. SanwarSanwar HossainHossain Dy
Dy. Manager , Operation. Manager , Operation Gas Transmission Co. Ltd. Gas Transmission Co. Ltd.
Pipeline design
Pipeline design
QQmmscfdmmscfd=0.00128084((P=0.00128084((P1122--PP2222)/L)/Lmilesmiles))0.510.51DD2.532.53
For successful implementation of a pipeline project, For successful implementation of a pipeline project,
the following steps are to be considered in general: the following steps are to be considered in general:
1. Market survey
1. Market survey-- Present & future demandPresent & future demand 2. MAOP & Design pressure
2. MAOP & Design pressure
3. Map of the preliminary selected pipeline route (L) 3. Map of the preliminary selected pipeline route (L)
4. Pipe Size (D) 4. Pipe Size (D)
5. Wall thickness (t) 5. Wall thickness (t)
Pipeline design ( contd.)
Pipeline design ( contd.)
6. Pipe specification / grade 6. Pipe specification / grade
7. Bill of materials 7. Bill of materials
8. Total cost estimate 8. Total cost estimate 9. Selection of ROW 9. Selection of ROW
10. Detailed survey and Preparation of alignment 10. Detailed survey and Preparation of alignment
drawings drawings
Pipeline design ( contd.)
Pipeline design ( contd.)
Load consideration: Load consideration:
In earlier days , pipeline design was done In earlier days , pipeline design was done
considering the present load and 15 to 30% considering the present load and 15 to 30%
increment of load. increment of load.
NowNow--a days, the use of natural gas increased a days, the use of natural gas increased
tremendously. As a result the concept of pipeline tremendously. As a result the concept of pipeline
design has also changed. design has also changed.
Presently pipeline design is being done considering Presently pipeline design is being done considering
the present load as well as the assumed gas load of the present load as well as the assumed gas load of
the that particular area for the next 20 years ( the that particular area for the next 20 years (
effective life of the pipeline) effective life of the pipeline)
Pipeline design (Contd.)
Pipeline design (Contd.)
Modified Panhandle equationModified Panhandle equation-- most useful for most useful for
transmission pipeline : transmission pipeline :
QQmmscfdmmscfd=0.00128084((P=0.00128084((P1122--PP2222)/L)/Lmilesmiles))0.510.51DD2.532.53
where , P
where , P11=Upstream pressure, PSIA=Upstream pressure, PSIA P
P22=Downstream pressure, PSIA=Downstream pressure, PSIA D=Inside pipe
Pipeline design (contd.)
Pipeline design (contd.)
t= DP/(2YFL JT)t= DP/(2YFL JT)
where, where,
t=Pipe wall thickness, mm t=Pipe wall thickness, mm
P=design pressure ,psig P=design pressure ,psig
D=outside
D=outside diadia of pipe in mmof pipe in mm
Y=minimum yield strength, psig Y=minimum yield strength, psig
F=design factor F=design factor
L= Location factor based on class location L= Location factor based on class location
J=welding joint factor J=welding joint factor
T=Temp.
Line
Line
Pipe
Pipe
: API 5L Grades
: API 5L Grades
Grade
Grade Minimum yield Minimum yield strength(
strength( MPa)MPa) Minimum Tensile strength( MPaMinimum Tensile strength( MPa)) B B 241241 413413 X42 X42 289289 413413 X46 X46 317317 434434 X52 X52 358358 455455 X56 X56 386386 489489 X60 X60 413413 517517 X65 X65 448448 530530 X70 X70 482482 565565 X80 X80 551551 620620
Design
Design
and Location Factor
and Location Factor
Canadian Standards association (CSA)
Canadian Standards association (CSA)
suggests design factor of 0.8 While location
suggests design factor of 0.8 While location
factors are:
factors are:
Area
Area Class Class Location
Location ASMEASME CSACSA Deserted Deserted 11 0.720.72 0.800.80 Village Village 22 0.600.60 0.720.72 City City 33 0.500.50 0.560.56 Metropolis Metropolis 44 0.400.40 0.440.44
Joint factor :
Joint factor :
Weld type
Weld type ASME B31.8ASME B31.8 Seamless Seamless 11 ERW ERW 11 SAW SAW 11 But Welled But Welled 0.60.6 Spiral seam Spiral seam 0.80.8
Temperature factor:
Temperature factor:
Temperature (
Temperature ( ̊ F)̊ F) ASMEASME-- B31.8B31.8 Up to 250 Up to 250 1.001.00 251 251--300300 0.970.97 301 301--400400 0.930.93 401 401--450450 0.910.91 451 and above 451 and above 0.870.87
Pipeline Construction Process
Pipeline Construction Process
DPP DPP
Land acquisition & RequisitionLand acquisition & Requisition
Tender Document PreparationTender Document Preparation
TenderTender
Bid EvaluationBid Evaluation
Tender AwardTender Award
ProcurementProcurement
MobilizationMobilization
Pipeline Construction Process (contd.)
Pipeline Construction Process (contd.)
Welding and NDTWelding and NDT
Trenching, Lowering & BackfillingTrenching, Lowering & Backfilling
TieTie--inin
Hydrostatic TestingHydrostatic Testing CleaningCleaning CommissioningCommissioning OperationOperation
Pre construction
Pre construction
ROW Acquisition & RequisitionROW Acquisition & Requisition
--ROW SelectionROW Selection
--DC OfficeDC Office
--CompensationCompensation
Pre construction (Contd.)
Pre construction (Contd.)
General Guideline for Pipeline Routing
General Guideline for Pipeline Routing
Minimize overall pipe length.Minimize overall pipe length.
Parallel existing utility corridors (Highway, High Parallel existing utility corridors (Highway, High
tension Electric transmission line). tension Electric transmission line).
Avoid areas of high population density.Avoid areas of high population density.
Minimize highways, railways, river, Minimize highways, railways, river, khalskhals, canals, , canals,
ponds, hills & mountains crossing to reduce the ponds, hills & mountains crossing to reduce the
project cost. project cost.
Cross highways, railways, river, Cross highways, railways, river, khalskhals, canals at or , canals at or
close to 90 deg. angle. close to 90 deg. angle.
Minimize crossover of existing facilities.Minimize crossover of existing facilities.
Pre construction (Contd.)
Pre construction (Contd.)
General Guideline for Pipeline Routing
General Guideline for Pipeline Routing
Avoid the following areas:Avoid the following areas: •
• Swamps and WetlandsSwamps and Wetlands
•
• Rocky areasRocky areas
•
• Unstable soilUnstable soil
•
• Populated areasPopulated areas
•
• Historical areasHistorical areas
•
• Environmentally sensitive areas ( Forest, Tea Environmentally sensitive areas ( Forest, Tea
garden , Rubber garden etc.) garden , Rubber garden etc.)
•
• Religious sensitive areas ( Mosque , Graveyard, Religious sensitive areas ( Mosque , Graveyard,
temple etc.) temple etc.)
Pre construction (Contd.)
Pre construction (Contd.)
Land acquisition / Requisition:
Land acquisition / Requisition:
Normally Normally 10 m10 m wide strip along the proposed wide strip along the proposed
pipeline route is to be acquisition and a
pipeline route is to be acquisition and a 15 m15 m wide wide strip on one side of the acquisition strip is to be
strip on one side of the acquisition strip is to be requisition.
requisition.
Acquisition is permanent possession for use of land Acquisition is permanent possession for use of land
but requisition is completely a temporary affair , only but requisition is completely a temporary affair , only
for the working period. for the working period.
For scraper station and Valve station separate block For scraper station and Valve station separate block
lands of required size have to be acquisition. lands of required size have to be acquisition.
Pre construction (Contd.)
Pre construction (Contd.)
Submission of proposal for land acquisition & requisition:
Submission of proposal for land acquisition & requisition:
The company submit the proposal with requisite no. of The company submit the proposal with requisite no. of
drawings (Normally
drawings (Normally mouzamouza map) showing acquisition & map) showing acquisition & requisition strip in two distinct colors (red for requisition strip in two distinct colors (red for
acquisition & green for requisition) to DC office. acquisition & green for requisition) to DC office.
The process of acquisition & requisition in our country The process of acquisition & requisition in our country
is done through the DC office of the particular district. is done through the DC office of the particular district.
The whole process continues in accordance with The whole process continues in accordance with
Ordinance, Acts, Rules & Regulations issued by the Ordinance, Acts, Rules & Regulations issued by the
government from time to time. government from time to time.
Pre construction (contd.)
Pre construction (contd.)
TenderTender
--FloatingFloating
--Bid Receiving & EvaluationBid Receiving & Evaluation
--Contract Award & Contract ManagementContract Award & Contract Management
ProcurementProcurement
Major steps for pipeline Construction
Major steps for pipeline Construction
Cleaning & Grading the ROWCleaning & Grading the ROW
Stringing the pipe along ROWStringing the pipe along ROW
Welding the pipe joints togetherWelding the pipe joints together
NDT of welding jointsNDT of welding joints
Coating & Wrapping Coating & Wrapping
Ditching / Trenching Ditching / Trenching
Holiday testHoliday test
Lowering & backfillingLowering & backfilling
PiggingPigging
Hydro TestHydro Test
Equipment used for Pipeline Construction:
Equipment used for Pipeline Construction:
BulldozerBulldozer-- Used to clearing & grading of ROW.Used to clearing & grading of ROW.
ExcavatorExcavator--Used to trenching , pipe lifting, pulling the Used to trenching , pipe lifting, pulling the
welding machine etc. welding machine etc.
Side boomSide boom-- Used to lift the pipe during welding and Used to lift the pipe during welding and
lay the pipeline in the trench. lay the pipeline in the trench.
Crane Crane –– Used to handle heavy equipments and Used to handle heavy equipments and
machineries. machineries.
Welding generatorWelding generator
Trailer/ TruckTrailer/ Truck-- used to carry the line pipe from store used to carry the line pipe from store
yard to the working site. yard to the working site.
Pipeline construction Equipment
Pipeline construction Equipment
Excavator Excavator
Side boom Side boom
ROW Clearing & Grading
ROW Clearing & Grading
ROW is cleared of barriers and graded for ROW is cleared of barriers and graded for
movement of construction equipment, materials movement of construction equipment, materials
and ultimately construction of pipeline. and ultimately construction of pipeline.
Pre Welding Activities
Pre Welding Activities
Welders testWelders test -- an exam for the welders before an exam for the welders before
going to production weld. going to production weld.
Selection CriterionSelection Criterion-- Visual inspection & NDT ( Visual inspection & NDT ( API API
1104) 1104)
PQR / WPS TestPQR / WPS Test
--Tensile strength testTensile strength test
--Face bend testFace bend test
--Root bend testRoot bend test
Stringing
Stringing
Stringing is aligning the Stringing is aligning the pipe along the ROW
pipe along the ROW
ready for welding .
ready for welding .
Trailer, Side boom etc Trailer, Side boom etc are used to stringing the
are used to stringing the
pipe.
Welding
Welding
Root pass/ Stringer passRoot pass/ Stringer pass
Hot passHot pass
Filling pass Filling pass
Cap PassCap Pass
NDT ( Non Destructive Test)
NDT ( Non Destructive Test)
Dye Dye penetrantpenetrant testtest
Magnetic Particle testMagnetic Particle test
Eddy current testEddy current test
Radiographic testRadiographic test
Ultrasonic testUltrasonic test
NDT ( Non Destructive Test)
NDT ( Non Destructive Test)
Radiography TestRadiography Test
o o EquipmentEquipment o o MethodMethod o o SourceSource o
NDT ( Non Destructive Test)
NDT ( Non Destructive Test)
Ultrasonic TestUltrasonic Test
o o EquipmentEquipment o o MethodMethod o o SourceSource o
Common welding defects
Common welding defects
Porosity
Porosity
Cluster porosity
Cluster porosity
Slag inclusion
Slag inclusion
Lack of fusion
Lack of fusion
Lack of penetration
Lack of penetration
Internal concavity
Internal concavity
Burn through
Burn through
Welding defects:
Welding defects:
Tie
Tie
-
-
in welds
in welds
The final weld to join two separate section
The final weld to join two separate section
together.
together.
Should be properly aligned without use of
Should be properly aligned without use of
jacks or any external force.
jacks or any external force.
Should be done within operating temp ( 5
Should be done within operating temp ( 5
-
-
30
30
deg. Celsius).
deg. Celsius).
Roads and Railway Crossing
Roads and Railway Crossing
Two different ways Two different ways
Thrust boring/ Horizontal boring methodThrust boring/ Horizontal boring method
--Drill a hole under the roadway without disturbing Drill a hole under the roadway without disturbing the road/ rail surface.
the road/ rail surface.
A casing pipe is placed through the hole and then A casing pipe is placed through the hole and then
the pipeline is placed inside the casing. the pipeline is placed inside the casing.
Spacer is used to center the pipeline within the Spacer is used to center the pipeline within the
casing pipe. casing pipe.
Pipe Coating
Pipe Coating
All except a portion ( about 6 inch ) of each pipe is All except a portion ( about 6 inch ) of each pipe is
often coated in the factory before deliver to the site. often coated in the factory before deliver to the site.
Three types of coatingThree types of coating
--3LPE coating3LPE coating
--FBE coatingFBE coating
--Polyethylene coatingPolyethylene coating
3LPE coating 3LPE coating
--Apply adhesive on clean pipe surfaceApply adhesive on clean pipe surface
--Epoxy paint ( 40Epoxy paint ( 40--100 micron)100 micron)
Bare pipe
Bare pipe
Steel Pipe without coating Steel Pipe without coating
3 LPE Coated Pipe
3 LPE Coated Pipe
Features:Features:
--Cleaning ( sand Cleaning ( sand Blasting)
Blasting)
--Apply AdhesiveApply Adhesive
--Apply epoxy paint ( 40Apply epoxy paint ( 40- -100 micron thick)
100 micron thick)
Concrete Coated Pipe
Concrete Coated Pipe
Features:Features:
--Apply 3LPE CoatingApply 3LPE Coating
--Set wire mesh above 3LPE Set wire mesh above 3LPE Coating
Coating
--Apply Concrete coatingApply Concrete coating
-- Provide Provide ––VeVe buoyancy buoyancy
force force
-- Apply on ditch, canal , Apply on ditch, canal ,
pond,
Set
Set
-
-
on
on
-
-
Weight
Weight
Features:Features:
--Put on above 3LPE coated Put on above 3LPE coated pipe
pipe
--one on each pipeone on each pipe
--Provide Provide ––VeVe buoyancy buoyancy force
force
Joint coating
Joint coating
Heat shrink sleevesHeat shrink sleeves
--Approx. 14 inch length and Approx. 14 inch length and diadia larger than pipe larger than pipe diadia..
Ditching, Holyday test, Lowering & Backfilling
Ditching, Holyday test, Lowering & Backfilling
DitchingDitching
Holyday testHolyday test
-- Apply 10 KV on coated pipe surfaceApply 10 KV on coated pipe surface
--Any coating defect will result an audible sound.Any coating defect will result an audible sound.
LoweringLowering
-- Lay pipeline on Trench of approx. 1.2 m depthLay pipeline on Trench of approx. 1.2 m depth
--Put Put
Set
Set
-
-
on
on
-
-
weight
weight
on burriedon burried pipe for antipipe for anti--buoyancy buoyancy forceTesting :
Testing :
Brush / cup pigBrush / cup pig
--Clean internal rustClean internal rust
Gauge pigGauge pig
--To check pipe To check pipe ovalityovality
Foam PigFoam Pig
Pig Receiver
Pig Receiver
To receive pig at the To receive pig at the
terminal point terminal point
Pig Traps
Pig Traps
Pig Receiver connected with pipeline Pig Receiver connected with pipeline
Hydro test
Hydro test
After mechanical completion of pipeline After mechanical completion of pipeline
Min test pressure should be 1.5 times of design Min test pressure should be 1.5 times of design
pressure. pressure.
Conventional hydro test pressure for high pressure Conventional hydro test pressure for high pressure
pipeline= 1.5 X 1135
pipeline= 1.5 X 1135 psipsi = 1703 = 1703 psipsi
Before commencing pressurization need to obtain Before commencing pressurization need to obtain
necessary permission from the competent authority necessary permission from the competent authority .As per Gas Safety rules Department of explosive is .As per Gas Safety rules Department of explosive is
the competent authority in Bangladesh. the competent authority in Bangladesh.
Prior notification of testing should be given, in Prior notification of testing should be given, in
writing to persons in the vicinity of the pipeline . writing to persons in the vicinity of the pipeline .
Hydro test (contd.)
Hydro test (contd.)
Prior notification of testing should be given to local Prior notification of testing should be given to local
police and other authorities, who may be affected. police and other authorities, who may be affected.
Warning notice stating “WarningWarning notice stating “Warning--PipeLinePipeLine Under Under
Test” and “No Parking” should be placed at Test” and “No Parking” should be placed at
appropriate locations for the duration of the test. appropriate locations for the duration of the test.
Patrols should be provided to watch special points of Patrols should be provided to watch special points of
hazard during the test, in particular road, rail and hazard during the test, in particular road, rail and
water crossing and points of public access. water crossing and points of public access.
Standby emergency crew should be available to deal Standby emergency crew should be available to deal
any unwanted situation. any unwanted situation.
Commissioning
Commissioning
Prior to the commissioning the pipeline should be dry Prior to the commissioning the pipeline should be dry
up. up.
Methods available for drying up are:Methods available for drying up are:
--Using dry air (compressor) push a series of foam Using dry air (compressor) push a series of foam pigs through the pipeline collecting water until the pigs through the pipeline collecting water until the
required dryness is achieved. required dryness is achieved.
The pipeline should be purged of before the The pipeline should be purged of before the
admission of the gas to be transmitted . admission of the gas to be transmitted .
Use inert gas to purge of air.Use inert gas to purge of air.
After drying up a pipeline can be commissioned After drying up a pipeline can be commissioned
straight to gas. straight to gas.
Codes and Standards
Codes and Standards
ASME B31.8 ( Onshore & Offshore)ASME B31.8 ( Onshore & Offshore)
ASME B16.5 (Flange & Flange Fittings)ASME B16.5 (Flange & Flange Fittings)
ASME B16.21 ( Gaskets for Flanges)ASME B16.21 ( Gaskets for Flanges)
API 5L ( Line Pipe)API 5L ( Line Pipe)
API 6D (Valves)API 6D (Valves)
API 1104 (Welding Inspection)API 1104 (Welding Inspection)
ASME UASME U-- Stamp ( Pig Traps & Launcher)Stamp ( Pig Traps & Launcher)
ASME Boiler & Pressure Vessel Code ( Scrubber, KOD ASME Boiler & Pressure Vessel Code ( Scrubber, KOD
and Other pressure Vessels) and Other pressure Vessels)