THE
DESIGNAND
PE O NCEOF
THE
STATI
P NICHOLSON
...'EEF•
D
•'SENIOR
GEOTECNNiCA£ ENGIN
OVE ARUP AND PARTNERSSUMMARY
Newton Station is about 180m
long
by
21m wideby
15mdeep.
Ground conditions at the sitecomprise
softf•arine
Clay
up to,20mdeep overlying
Fluvial§ands.
• .id
Clays
which are underlainby
Cor0!bletel•'
•:•
Decomposed
Granite.Inv,estiga.,tions
i•entified.•threeZ:.-:•:il
'buried'chan•ls •nning t•ansve•'sely
•cross
the station
The paper discusses thedesign
andperformance
of theperimeter diaphragm
walls
at the eastern end of thestation,
where areasonably
complete
set ofinstrumentation data are
available.
Thepredicted
movements of the
top
down excavation arecompared
with the, field measurements.
INTRODUCTION
Newton Station forms
part
of the newSingapore
Metro which is
being
constructed for the MassRapid
Transit
Corporation
(MRTC).
In addition the station has beendesigned
as a Civil Defence Shelter. The maincontractor for this
design
and construct contract wasDragages Sembawang
Construction. eveArup
andPartners were their
designers.
THE
SITE
Road
adjacent
to the Newton Circusjunction
with theBukit Timah
Road,
seeFigure
1. At the western end ofthe station is a crossover which also formed
part
of thecontract but will net be discussed in this paper. Ground levels at the site vary from 103.0m in the
west to 102.5m in the east. This is close to the mean sea level of 100m.
Occasionally
the eastern end of thesite•is•fi0ode•
durin•
periods
of veryheavy
rainfall.GROUND
CONDITIONS
The
results
of fivephases
of siteinvestigations
comprising
56 boreholas and 25 Dutch cone testsrevealed
highly
variableground
conditions at NewtonStation and the
CrosSover.
The soil classification in this •.paper isin-accordance
with Andrews and Morton(1).
Geological
Setting
At
depth,
the site is underlainby
the Bukit TimahGranite.
The surface of this formation has been weathered in situ toCompletely
Decomposed
Granite(G4).
Contours of thetop
of the G4 are shown inFigure
2. These show the presence of three buried channels
running
in a N-S direction across the station. Thesechannels were
probably
erodedduring glacial
periods
when the sea level was
Iowar,
as discussedby
Pitts(2).
The
investigations
showed that the eastern andcentral,
valleys
weremainly
inffiled with FluvialSand
(F1),
whilst
thewestern
andpart
of the easternvalley
were infilled with Lower Marine
Clay
(M•)
to a level ofHotel
Federal
Nine'
/ X/.X/
••heetpiles
FIGURE 1. SITE PLAN 147
about +90m, as shown in the seCtion in
Figure
3.Subsequently,
about 12000years
ago, the sea leveldropped
aga n,exp£sing
the Lower MarineClay. During
thisperiod
amixtur•
of Fluvial Sands(F1),
andClays
(F2),
weredeposited
to about +91melevation.
About10000 years ago the sea level rose
again
and theUpper
MarineClay
(Mu)
wasdeposited
to about 101m.•,•
.,..Over
the
past
50 yearsreclamation
schemes
h
avefilled
t•
•-•;thesitei'to
its•present ground
level.
Marine
Clays
(M)
TheUpper
and Lower MarineClays
are very soft to softlight
greenish-grey
silty clays
with some intact shelts
containing
water.Very
fewsoil
<:'<
fabric features arepresent. Occasional peat layers
androots were
encountered.
Index.
properties
are shown inThe soil for
laborator•
tests was obtainedby
piston
'and thin wall
sampling. Laboratory
undrainedstrengths
(C.)
from thesesamples
were lower than the in situ':vane
strengths,
seeFigure
4. TheUpper
MarineClay
undrained
strength design
line is also shown inFigure
4. It
represents
about 80% of the average field vanestrength.
For aplasticity
index of 70•/oBjerrum
(3)
recommended
a 70% reduction in the field vanestrength.
Thisdesign
linegenerally
corresponded
to aratio of
c•/p=
0.23 where p• is thepreconsolidation
<tpressure. The direct correlation between Dutch
(electric)
cone
resistance
(q=)
and field vane(%)
was 12and
15for
Upper
and Lower MarineClay
respectively.
Typical
consolidation
parameters
obtained
fromoedometer
and Delftpiezocone
tests aresummarised
in Table 1. Anundrained
soil modulus(E•)
was derivedassuming
Eu/c•
450._.[
q
mopofG4
/
\
s'l
k_/,
i" )
t
)
J
1
°s,Borehole ' Piezometer •'°'Set-t
em•Rt
point
iIn&linometer
FIGURE
2. PLAN OFSTATION
metres 100- 90- 80-- 70--
Ftii
Mu
FIGURE
3.SECTION
A A -,/Mglm 40 80 120 1.4 Cu kNlm= 1.8 0 20 40Laboratory
• Vanei• Design
o'•:
lineFIGURE
4. MARINECLAY PROPERTIES
TABLE 1. CONSOLIDATION
PARAMETERS
Soil
Oed6rfiet•r'
PiezoconeFluvial
Deposits (F)
The Fluvial Sands(F1)
andClays (F2)
between the M aridM•,!ayeps.•ar,•:•hig•!y
variable. The Sands
comprise
very oose to;Ioose,-gFey
fine to coarseang,ular
quaGz
sand with•some•:si!t•,:,Th•,
Clays
comprse
firmm6•led
•:e•LI•6WH
"•ii•
and•lays•
desiccation and a
design
c. •kN/m• wasadopted.
Adrained
angle
of internal resi•ance•
35.5 wasdetermined from trivial and shear •x tests.
Howeve•
avalue of •o was used in the calculations. Index
prope•ies
and SE results for the Fluvial soils •are:•p•ed in-Figure'
5.:
•:•:
•:
•'%"•:•:•'•"
•onsolida{ion
p•ram•tePs
for:the
:Clays
(F2)•Areset
out in Table 1. The Delft
•iezocones
recorde•,,
5ydrost&tiC
•Snditions:
•n
•e
S•H•
(F1):•sh•]•:}•t
they
wereh•hly
per•eabl#..A,correlation,be•een
Dutch
(ele•ric)
coneresis{a•c'e
(q• •:•
0.SN MN/m 2 was established for
•the
clays..(E2)
Ej%
450 wasadopted. •(,the•saBds
a drained modulus•
•.5q•
was
esed:"
•
Completely Decomposed
Granite(G4).
•his
s0il
comprises
medium densebecoming
ve• dense with,"'8•#th;
sCeckled grey-gree6Lbrown-red
clayey
sil•
withT
some fine to coarse
angular
qua•
sand. Indexprope•ies
and S• results are shown inFigure
5. Atthe eastern end of the station numerous inta•
granite
boulders were encountered,
paGicularly
be•een thecentral and eastern buried
channels,
seeFigure
2.These were
exposed
during
excavation
and were oEenfound to be more than 2m across. Rock head was not established
[n
any of the boreholes.The
silty
nature of the G4 soil means that it issensitive to
sample
disturbance andrapidly
becomespartially
saturated. Therefore in situ tests were reliedupon to derive
parameters.
Thefollowing
correlationswere
used;
q= 0.165N MN/m•,
q¢30%
and c.5.5N kN/mZ•
Consolidation parameters
for the G4 soil"are
set out in Table 1. The soil modulus was assessed;_,.u.sing,E•c•_
650.
A drainedangle
of internal•i•hce
•:•
3•
-•was
used.Pumping
TestsPumping
tests were conducted to assess thedewatering requirements
for the station and thepossibility
that the Fluvial Sandlayer
might
behorizontally
continuous. Well W3 was installed at theposition:shown
inFigure
2. Fluvial Sand was-encountered between 16.7 and 20.0m
depth
in this well. To monitordrawdown,
piezometers
wereinstalled
inseparate
boreholes in the F1layer
and in the G4 at about thedepth
of theproposed
toe of thediaphragm
wall(80m
level).
Thesepiezometers
were installedalong
the
length
of the station and weresubsequently
used tomonitor the excavation
dewatering.
Pumping
from the 275mm diameter well was started on the 2.4.84 andcontinued for 7
days.
The water level in the well waskept
at 86m elevation and thepumping
rate settled down to about 1.2m3/hr.The
piezometers
in the F1 reached theirsteady
stateafter 1
day
whilst those in the G4 stabilised after 2days.
The initialpiezometric
levelstogether
with those after 7days
pumping
areplotted against
the distancefrom the well in
Figure
6. This shows that drawdowns ofabout 2.5m and 2.2m occurred in the F1 and G4
respectively:to
• distance of 100m from the well.Beyond
this distance little drawdown occurred. This showed that
the F1 was
hydraulic•Jly
continuous over most of thestation
length.
It should also be noted that the drawdown in the F1 sand was
always
greater
than in the G4. This isconsistent with an
upward
flow ofwater
into the F1layer
-and then
horizontally
to the well. Thecalculated
permeabilities
of the F1 and G4 were about 8 x 10 "s and5 x 10 • m/sec
respectively.
The
rapid
response of the G4confirmed
the use ofeffective
stressparameters
andsteady
statedrainage
conditions
rather thanadopting
undrained
strength
parameters
for the G4.During
excavation the roof slab was also used as asupport-from
which the£oncourse
sl.ab
wastemporarily
hung.
Th,
e roof alsoprovided
a reaction for theinclined
struts, see
Figure
7 temporarystage.
Once the
permanent
baseslab,
centralcolumns
andinternal walls had been
constructed
thehangers
andinclined struts were
removed
seeFigure
7permanent
stage.
Tl?e
central
columnsenabled
the roof slab tobe
In
addition,
ground
surfacesettlements
werei:monitored ddring
the.pumping
test. Therecorded
used
:tO
r•ist thelong
termhydrostatic
pressureacting
nts
between-the
2nd and12th
April
1984al;e
•
"•settteme
[
ed •'•."
Tl•t•.t•porai•':•hangers
and inclined struts wereplotted
inFigure&
Thesesettlements deveop
steadily
throughout
thepumping
test and resulted fromthe
consolidation
of the MarineClay.
Ti•
e
•T,.;i-I'
'•
efe
n
•
•
requiremeni-for,
a:
heaviiy
r•inforced'.
2.0m thick roof slab wasincorporated
into thetop
downconstruction
by using
it as thetop
strut for the walls.relatively
short andtherefore
easy to manoeuvre in thevery soft
ground
conditions
encountered
whilstexcavating
below the roof slab. Anotheradvantage
of the'iiqclined strut#
was thatthey
did not obstruct theexcavation
to thefinal
formation
level.Studies
hadindicated
that if the inclined strut hadbe•en•.•it{•l•¼th•n-il•
•0utd have been necessary to increase thediapt•ragm
wall thickness from 0.8 to 1.0mand to
deepen
the toeembedment
depth.
zFinal
9.4.8410 20 50 100
DISTANCE FROM WELL W3 metres
'/•
KEY 7
Borehole
No •' Initial(2.4.84)
:•-•:;•'•
FIOURE
0,R•S•LTS
OFP•PINO
TESTmetres
Roof slab Central column
)urse
slabInternal
walls 0.8mDiaphragm
wall
r
DIAPHRAGM
WALL
DESIGN
The
design
of thediaphragm
wall involved thefollowing:
i)
Seepage
analysis.
ii)
Lateralstability
analysis
to determine toe levels.iii)
Wall deformationanalysis
forbending
moments.the
passive
earth pressure coefficients in accordancewith CP2
(4).
Full wall adhesion was assumed in the Mand F2
clays
whilst wall friction of 0.5#•1
wasadopted
inthe F1 and G4.
iii)
DeformationAnalysis
The wall deflections andbending
moments associated with excavation of thestation were calculated
using
thecomputer
programBearing capacity
for vertical loads. BILL describedby Pappin
etal,
(5).
A cracked walliv
v•)
Lon g term h
•
drostatic u-lift•
resistance section stiffness El 355 MN.m 2 wasused,
thisbeing
:L.:•..:•..
i
:._•: •-:::-•
.i:•about_hatf•the•al.astic
sectionstiffne.ss.
N,o,
factors
of.
Theseanalyses
are showndiagrammatically
inFigure
safety
were,a,pplled
to
!he
"beste.stlm,ate,
.de•sl•gn
,,s,o,•l,
8. To cater for thevarying
soil conditions theperimeter
parameters.
Mowever, the momen[s CalCu]a[ea oy •[.wall was
eventually
divided into 9design
cases, wereincreased
by
1.2 and 1.6 for the reinforcedi)
Seepage
Analysis
OveArup
andPartners'
finiteelement program SEEP was used to calculate the
steady
statepiezometric
pressures
around the toe of the wall. Thesepiezometric
pressures
were used in thecalculations for toe embedment
depth
and deformationanalysis.
SEEP alsopredicted
flow rates so that thepumping
requirements
inside the station could beassessed. Where the buried channels contained F1
(s,•,r•d
it was necessary to extend the toe of the wall 2mthe
underlying
G4 top•'ovide
.ahydraulic
cut-off andlimit
drawdown outside the stationduring
excavation. Fordesign
purposes
the extema-drawd•wn
was•l!m!ted
to101m in the Fluvial
Sands.
ii)
ToeDepth
The toeembedment
stability
was assessedusing
a factor ofsafety•f
2
onconcrete
design
in thetemporary
andpermanent
conditions
respectively.
Ground settlements were estimated from the BILL
predictions
of tateral wall movementsusing
the methodproposed
by
Milligan
(6)
with a small modification basedon field observations
reported
by
Tan etal,
(7)
for theneighboudng
MOEbuilding
shown inFigure
1. Detailsof these movements are
given
inFigure
9 where D isthe
depth
at which the maximum lateral wallmovements occurs. Additional allowances were also
made for
diaphragm
wall installation and consolidationsettlement,
iv)
Bearing
Capacity
During
excavation thediaphragm
wallsprovided
the verticalsupport
for the roof andC•ncourse
Slabs.
Excavation within the station led to a•:ed•ctionlof
the
overburden
pressure and effectivestress at
the
toe of the wall and hence a reduction inSeepage
Toestability
Bending
/
DeformationBearing
capacity
FIGURE 8.
DIAPHRAGM
WALL DESIGN20 10 ' 0 ':•,l•.•i 20 10
6.8m
incIin0meter
bearing
capacity.
The horizontal effective stresses forcalculating
wall friction were taken from the BILLdeformation
analysis.
The maximumallowable
piezometric
levels at the toe of the wall were calculatedat various
stages
of theexcavation
to maintain the factorof
safety
of 2 on the ultimatebearing
capacity.
During
the final excavation
stage
about 30% of theworking
load wascalculated
to be takenby
endbearing
onthe
base of the
diaphragm
wall.v)
Hydrostatic
Uplift
Oncompletion
of the base slab and internal walls the waterpressure
was allowed toreturn to its
original
level.Calculations
showed
that thedead load of the station and the
diaphragm
wall wereadequate
to resist thehydrostatic
uplift
pressures.
FIELD
PERFORMANCE
Monitoring
The
performance
of the wallduring
excavation
wasmonitored
using
inclinometers, settlementpoints
andpiezometers.
The inclinometers were either
installed
within the wall('"•,anels
orjust
outside, as with inclinometerI3,
seeFigure
2. Ground surface settlementpoints
were locatedat different distances from the
excavation.
Thepiezometers
wereinstalled
inboreholes
outside theexcavation either in the G4 or in the
overlying
FluvialSand. In addition
piezometers
wereinstalled
immediately
below the base of the
diaphragm
walland
inside the stationexcavation,
e.g. TP6 and IPI.The toe
piezometers
and wall inclinometers wereinstalled
by
rotary
coring
through
steel tubesattached
to thediaphragm wall
pane!,
reinforcement
cages. Thisprovided
theopportunity
to core the soilimmediately
below the base of the wall andconfirmed
that allslurry
and
excavation
debris had beenremoved
and thereforegood
endbearing
wasprovided.
Diaphragm
WallInstallation
Previous
experience
withcompletely decomposed
granite
inHong Kong
has demonstrated theimportam•
of
maintaining
anadequate
netslurry
pressure to maintain trenchstability
and limitground
movements,
see Davies and Henkel
(8).
At Newton Station thetable was often less than 0.5m below the ground
surface and therefore the
guide
walls wereextended
lm
above the
ground
level,
toprovide
the netslurry
pressure. Ground settlements of 20ram were
allo•d
letin the
design.
The
ground
movements recordedby
inclinometer
during
theexcavation
ofpanel
58 followedby
57 are shown inFigure
10. These show inward movements ofup to 15ram
occurred
in the G4during
excavation.However outward movements of 20mm occurred in the
Marine
Clay during concreting
to about 0.5mabove
ground
level. Theconcreting
also resulted in theadjacent
ground
heaving by
about 10mm.Excavation
Before
commencing
excavation,
new datumreadings
wereestablished
for all settlementpoints
andinclinometers. The
excavation programme
is shown at thetop
ofFigure
11. Thisfigure
also shows thesettlement records at
$1,
$2 and$18,
together
with thechanges
inpiezometric
levels inside theperimeter
wall(]P1),
below the toe of the wall(TP6)
and outside thewall
(B5a
andB5b).
Theirpositions
are shown inFigures
2 and 3.Pumping
fromthe
wells within thediaphragm
wallbox was started at
ihe beginning
ofJanuary
1985. Therapid
drawdown
in the F1layer
inside the box is shownon
Figure
11. The moregradual
response
at the toe andoutside the
excavation
can also be seen. Thepumping
rate was controlled to suit the
calculated
piezometric
level
requirements
Set
for the toepiezometers.
Once the base slab was cast. the pumps wereswitched
off(August
1985)
and the wells allowed to overflow onto the base slab.To reduce drawdown outside the
excavation external
recharge
wells were installed in the F1 sandlayer.
These were fed with waterpumped
from the internal wells. T3 metres 0 Fill -20 -10 • 102.6m 2¢ 58 57 56 .:L__.-_:•::•".
:•!:
± -:;: FGURE::I0,
i3RO.UN[•MOVEMI•.-N•.,S.--:D•E[•TO;INSTA•
LATION OF -:" !::PANEL:,58
•bLEO•E•"iB•?P'RNEIL
57:,;;.
152o
•o-
104 100- E •" 92- LU 84- 80-Roof
Concourse•
Base •I• • • Excavation [• • Concrete
r-11984
1985 N O N D j_F
M A M J 1J A S O•B5a
BSb TP1FIGURE
11. MEASUREDSETTLEMENTS
ANDPIEZOMETER
READINGS. 102.6 CaseA 1"3 Design DEFLECTION((•)
mmL40
80 0 040x•
80' 7--I-FI
Roof
Concourse 40 80 120/'
"28.685:Base
FIGURE
12.PREDICTED
ANDMEASURED
DEFLECTIONS.
The lateral movements
recorded
by
inclinometer I3 for .theroof, concourse•and
base slabexcavation
stages.ar•
shown in
Figure
12. Thepredicted
walldeflections
forthe Case A soil
profile
at the samestages
are also shown.The roof slab
excavation
to 100m level in thispart
ofthe station was
completed by
10.10.84. At this time about20mm lateral
deflection
hadoccurred
at theground
surface,
seeFigure
12. The roof slab was not cast untilthe end of November and
by
22.11.84 creep effects had-increased the movement to
60ram,
seeFigure
12. Thiswas similar to the
predicted
surface deflection.
Howeverbelow
12m,
depth
in the F2 andG4,
thepredicted
deflections were about
twice
thosemeasured.
This may be associated withunderestimating
the small strain•.stiffn-(•ss•of.theq•situ-soil•:-•h•_predicted
andmeasured
deflections for the
subsequent
excavation
stages
were •n.reasonable
agreement,
seeFigure
12. The maximumpredicted
deflection
was about 100mmcompared
with 110mmmeasured.
The inclinometer I3
deflections
recorded
on the 28.7.85 areplotted
inFigure
13. Also shown are the'"undrained"
surface settlements
predicted
from I3using
the method
given
inFigure
9. Inaddition
Figure
13shows the
settJements recorded
for$1,
$2
and $18 on the 28.7.85. It can be seen that these settlementpoints
have settled about 100mm more than those
predicted
from I3. This
.additional
settlement is due to theconsolidation
of
the MarineClay
resulting
from drawdown in the Fluvialdeposits.
The effect of the
consolidation
settlement can also beseen from the record of $2 shown on
Figure
11.Rapid
increases in
&ettlement
wererecorded
during
theconcourse an•I base
excavation
stages
inFebruary
and
May
1985.However,
a moregradual
settlementof about
:10mm/month
occurred between theseexcavation
stages.
This settlement rate is similar to
$18,
which isoutside
the influence of
exctavatien
,movemen•,•n.•'•is4her•fo•
considered
to reIlect theconsolidation
of-the MarineDISTANCE
FROM WALL
metresDEFLECTION
30 20 10 0 100mm•100
20028.7.85
!
InclinometerT3
---• /profile
28•7.85
30-FIGURE 13. GROUND SURFACE SETTLEMENTS.
CONCLUSIONS
Pumping
tests andpiezocone
testsprovided
valuableinformation on the
permeability
andhydraulic
continuity
of the Fluvial Sand
layers.
These tests also demonstratedthat
steady
state(flownet)
drainage
conditions would berapidly
established in theunderlying
Decomposed
Granite and therefore effective stress soilparameters
were
adpoted
in these soils.The
top
down constructiontechnique
proved
to besuccessful. This used the 2m thick roof slab to
support
the concourse slab and
provide
the reaction for thetemporary
inclined struts whichpropped
the final excavationstage.
The Ove
Arup
and Partners'computer
program BILLwas used to calculate deflections and
bending
momentsin the
diaphragm
walls. The programincorporates
theeffects of wall
stiffness,
propping
system
andground
conditions. Reasonableagreement
with the measured deflections was obtained.As the excavation
progressed
thepredicted
wall(•-'•
deflections and toepiezometric
levels werecompared
with the field instrumentation records. This enabled the
Contractor,
Designer
and MRTC to monitor theperformance
of the wall at allstages
of the excavation. Asimple
method ofpredicting ground
surface settlements associatedwith
walldeflection
wasadopted.
This method differs from
the
approach
describedby
Peck(9)
because thepredicted
surface settlements aredirectly
related to the wall deflections rather than the excavationdepth.
It has been used toseparate
theundrained deformation settlements outside the wall from
the consolidation settlements associated with
dewatering.
REFERENCES
(1) ANDREWS,
D. andMORTON,
K.,
Geotechnical Studies forSingapore
MassRapid
Transit. Proc. 2ndConf. on Mass
Transportation
inAsia,
Singapore,
1984,
pp 272 283.(2) PITTS,
J.,
A Review ofGeology
andEngineering
Geology
inSingapore. Quarterly
Journal ofEng.
Geol.,
London, 1984,
Vol.17,
pp 93 101.(3)
BJERRUM, L.,
Problems of Soil Mechanics andConstruction on Soft
Clays.
Proc. 8th Int. Conf. SoilMech. and Found.
Eng.,
Moscow, 1973,
Vol3,
pp. 109159•"
(4)
CP2.
EarthRetaining
Structures. The Institution of StructuralEngineers,
London,
1951.(5)
PAPP1N, J.W.,
SIMPSON,
B., FELTON,
RJ. andRAISON, C.R.,
NumericalAnalysis
of FlexibleRetaining
Walls. Proc. Int. Conf. on NumericalMethods in
Engineering: Theory
andApplications,
Editedby
Middleton,
J. andPande, G.N.,
Swansea,1985,
pp. 789 802.(6)
MILLIGAN, G.W.E.,
Soil Deformations NearAnchored
Sheetpile
Walls.Geotechnique,
London,
1983,
No.1,
pp. 41 55.
('7)
TAN,
S.B.,
TAN. S.L. and CHINY.K.,
ABraced
Sheetpile
Excavation in SoftSingapore
MarineClay.
Proc.
11th Int. Conf. on Soil Mech. andFound.
Eng.,
San
Francisco, 1985,
Vol.3,
pp. 1671 1674.(8) DAVIES,
R.V. andHENKEL, D.J.,
Geotechnical
Problems associated with the
construction
of Chater Station. Conf. on MassTransportation
inAsia, Hong
Kong,
1980.(9)
PECK, R.B.,
Deep
Excavations andTunnelling
inSoft
Ground.
Proc. 7th lnt. Conf. Soil Mech. andFound.
Eng.,
MexicoCity,
1969,
State of the art volume,pP.
225 290.
ACKNOWLEDGEMENTS
The Author would like to thank his