• No results found

Capital Assets Plan. Capital Assets Plan. Overview

N/A
N/A
Protected

Academic year: 2021

Share "Capital Assets Plan. Capital Assets Plan. Overview"

Copied!
26
0
0

Loading.... (view fulltext now)

Full text

(1)

Overview

Each year the City partakes in a detailed capital planning process that forecasts the infrastructure needs over the next 5, 10 and in some

circumstances 40 years. All infrastructure is reviewed and prioritize based on asset age, condition, capacity, and identified corporate priorities. After Council has reviewed and approved the five-year capital plan budgets are generated to ensure that all encompassing costs of all planned future infrastructure upgrades are anticipated and accounted for.

The major groups or categories for the capital plan and budget are:  Transportation (intersection control, sidewalks, street signs, bus

stops, roadways and bridges)

 Utility Infrastructure (water & waste water systems including sanitary and storm)

 Public Assets (fleet and equipment, emergency response apparatus, information technology, municipal buildings and dikes)

 Recreation and Culture (facilities, parks and recreation, and cultural/historical)

Capital Assets Plan

(2)

The 2016 Preliminary Capital Budget funding requirements amount to $7,475,475 The individual project category requirements are as follows:

For 2016, the majority of funding will come from the City’s Capital Reserve Fund with smaller contributions from DCC’s and third party contributors.

2016 Capital Funding Sources

Further information for each of the major asset categories above are detailed within this report. Each subsequent section provides further detail on the overall asset category, its condition, proposed projects and allocated budget. Lifecycle schedules are dependent on routine maintenance schedules being followed and repairs being addressed as needed. The proposed 2016 capital budget and 2016-2020 capital plan represents an investment of $32.2 million in capital assets over this five-year period.

The current Capital requirements exceed cash flow and grant opportunities; therefore, unfunded projects have been pushed into later years so as not to exceed available and approved funding capacity. Projects could be realized earlier if funding or financing opportunities are realized.

Funding Source Amount

DCC’s $5,000 Grants $0 3rd Party Contributions $18,000 Reserves $7,452,475 Debts 0 Total $7,475,475

(3)

Transportation

Transportation projects include: intersection control, sidewalks, street signs, bus stops, roadways and bridges. Projects in this category include the design, maintenance, construction and purchase of these assets to keep them functional and in a good state of repair in order to maintain an exceptional level of service to our residents.

The Engineering and Operations divisions are responsible for these assets. The engineering division collates these corporate projects and helps prioritize them based on criteria that include the age and condition of the assets, their forecasted level of service, any health or safety risks and the availability of funds. When a project is identified as a priority and is approved by Council, the engineering division assumes responsibility for managing the design, construction and acquisition of these assets through a third party engineering contractor. An investment of $2,363,125 is required to fund the preliminary 2016 transportation projects.

Transportation Challenges for 2016

Pavement Management

 A pavement management survey is conducted every five years to determine if the City’s asphalt repair program is keeping pace with asphalt degradation.

 The pavement management survey conducted in 2012 by third party consultants indicates that the current asphalt repair/replacement program is not keeping pace with the

increasing number of asphalt failures that are occurring, in particular on rural roads and recommends the City consider increasing funding for road rehabilitation.

Pedestrian and Cycling Master Plan

 The City has adopted a Pedestrian and Cycling Master Plan along with recommended improvements to the City’s Active Transportation Infrastructure (sidewalks, pedestrian crossings, bike lanes and multi-purpose pathways). Currently funding is allocated for projects identified in the Plan. Council has approved funds for a 5-year period to allow projects to proceed. 2016 projects to be prioritized by the Active Transportation Committee in early 2016.

 In addition, a Transportation Master Plan was completed in 2013 that identifies priority roads projects for consideration as part of future Capital Plans.

Traffic Patterns and Volumes

 The two new bridges, Golden Ears (east side of the City) and Pitt River (west side of the City) have changed traffic patterns on City roads which is creating issues on those routes

(4)

experiencing increased traffic volumes, future capacity requirements (road widening with additional lanes) and more complaints from adjacent residents.

 East west traffic volumes through Pitt Meadows are increasing as development continues in the communities to our east and these volumes will continue to increase in future years. This increase will continue to put pressure on the City’s corridors, as traffic will seek alternate east/west routes other than the Lougheed Highway.

 Continued Provincial focus on the transportation of goods through the Gateway network. The result is an effect on the Pitt Meadows rail and road networks as rail is expected to see higher volumes and longer trains in the future.

2015 Transportation Achievements

 Repaving Ford Rd (193rd St to 18994 Ford Rd) Baynes Rd (Ford Rd to 11715 Baynes Rd)

Harris Road Rehabilitation

(Cranberry Slough to S. Alouette Bridge)

Ford Road Detour

(17280 Ford Road Detour to 17368 Ford Road Detour

Bonson Rd @ Park Rd Intersection  Reconfigurations

Ford Rd

(extended bike lanes east to 193rd St) Ford Rd @ Harris Rd

(created east and west left turn lanes)

Hammond Rd and Wildwood Trail

(added pedestrian controlled crosswalk with median)

Harris Rd at West Coast Express Crossing

(5)

At A Glance - Transportation Asset Statistics

 Total road lengths have increased 7.7% (7,750) since 2001.  Bike road lane lengths have increased 28% since 2004.

 Off road Multi-use Trails have increased 95% since 2000; dikes are not included in this total.

The current estimated replacement value for the City’s transportation infrastructure assets is $65.8 - $72.3M.

Current Assets

Asset Category Quantity

Roads 114.3 km

Bike lanes 31.0 km

*Bridges 9

**Off Road Trails/Paths 15.0 km

Traffic Control Signals 8

Street Lights 1,009

Sidewalks 58.6 km

Traffic signs 2034 signs on 1,249 poles

*Includes all Vehicle Bridges, CP Pedestrian Overpass & Heron Pedestrian Bridge. **Not including Dikes

Sustainability (Life Cycle) Considerations

 Pavement structures have an estimated service life of 20 to 30 years.  Bridge structures have an estimated service life of 50 to 100 years.

 Concrete or corrugated metal road culvert structures have an estimated service life of 50 years.  Concrete curb and gutter and sidewalk structures have an estimated service life of 40 years.  Regulatory and other traffic signs have an estimated service life of 20 years.

 Street furniture, refuse bins, and other related appurtenances have an estimated service life of 25 years.

(6)

Key Transportation Initiatives for 2016

Draft Transportation Capital Plan for 2016

2016 Proposed Projects Value

Wildwood Cr Repave (Hammond to Bonson) $250,000

McNeil Rd Repave (196C to Rannie) $400,000

Ford Rd Overlay (Harris to 189B) $200,000

Baynes Road Repave (11715 Baynes to Airport Way) $100,000

Rannie Rd Repave $800,125

South Alouette Bridge Rehab $275,000

(7)

Utility Infrastructure

Utility infrastructure projects include water and waste water systems (both sanitary and storm drainage. Projects in this category include the design, maintenance, construction and purchase of these assets to keep them functional and in a good state of repair in order to maintain an exceptional level of service to our residents.

The Engineering and Operations divisions are responsible for these assets. The engineering division collates these corporate projects and helps prioritize them based on criteria that include the age and condition of the assets, their forecasted level of service, any health or safety risks and the availability of funds. When a project is identified as a priority and is approved by Council, the engineering division assumes responsibility for managing the design, construction and acquisition of these assets through a third party engineering contractor. Depending on complexity, these projects may require multiple years to complete. Accordingly, projects may be segmented to match funding constraints.

An investment of $2,455,000 is required to fund the preliminary 2016 utility infrastructure projects.

Key Utility Challenges for 2016

Sustainable Funding

 Obtaining sustainable funding for asset lifecycle and replacement purposes is a challenge for the City. The steady pressure to reduce capital funding in order to balance cash flow forces the deferral of necessary infrastructure work. The risk is an eventual increase in costs in the future when assets fail.

 Prices fluctuate with the economy, with the cost of fossil fuels influencing material, labour and construction costs. As this trend continues, estimating project costs is becoming increasingly difficult to budget to maintain current infrastructure replacement levels. Projects are often reviewed and reduced in scope to fall within the dedicated budget amount.

 Despite investments in drainage, the City’s storm drainage infrastructure, in particular pumps and culverts, continues to age faster than the City’s current rate of replacement, which in turn drives up operating costs. The two biggest challenges in the utility are:  trying to spread the costs of upgrading and or replacing infrastructure that is well beyond its expected useful life out over the long term to manage costs and the risk associated with infrastructure failure; and

 building up reserves to sustainable levels in order to reduce the City’s reliance on borrowing and grants.

(8)

 An Integrated Stormwater Management Plan for the urban area, mandated by Metro Vancouver and the Province, was completed in 2015. This plan includes capital expenditures and highlights areas of immediate focus.

Environmental Protection

 Environmental protection and fisheries mandates continue to challenge implementation of the City’s ditch maintenance system and pump station upgrades.

 There is an increased public interest in Katzie Slough. Volunteer groups have an interest in planting the foreshore in hopes of establishing more habitats. Access is often via private property providing a challenge to this activity.

 A three-year cleaning of the Katzie slough of vegetation concluded in 2015. While the project has been successful in improving water conveyance, regrowth of the vegetation is occurring at a rate faster than anticipated.

Water Distribution

 The City is responsible for the delivery of potable water to a population of approximately 18,673, including agricultural water users. The provision of domestic water to

agricultural users is unique to this region and sets Pitt Meadows apart from the rest of Metro Vancouver. Over 55% of the City’s water distribution system services the rural area. As a result, the City of Pitt Meadows is one of the largest per capita water users in Metro Vancouver. Infrastructure demands in the rural area are driving significant

upgrades in the water distribution system. Sanitary Sewer System Maintenance

 The City’s sanitary sewer Asbestos Cement (AC) pipes have been reviewed for life cycle replacement and additional testing has been completed on extracted pipe sections to determine time frames for these replacements. A comprehensive rehabilitation schedule with estimated costs has been completed for a long-term replacement funding strategy. A strategy has been developed to re-line existing mains with poly vinyl chloride (PVC) material as an alternative to full replacement of the AC mains. To date the City has rehabilitated approximately 2,993 meters (16% of AC mains) by this method.

2015 Utility Achievements

Water main Replacement

Wildwood Crescent and Wildwood Place

(19742 Wildwood Crescent to 19867 Wildwood Place)

Ford Road

(9)

McKechnie Road Water main

(Old Dewdney Truck to Connecting Road)

 Culvert Install / Replacement

Harris Rd Bridge Removal & Culvert Replacement

(Cranberry Slough)

Ford Road Detour Culvert Extension

(17324 Ford Road Detour)

13219 Sharpe Road Culvert Replacement 19393 Old Dewdney Culvert Replacement 13415 Hale Road Culvert Replacement

At A Glance - Utility Infrastructure Asset Statistics

Water Distribution System

 The City purchases the water it distributes from Metro Vancouver, and the City’s trunk distribution system is constructed, maintained and upgraded under a Joint Supply Agreement with Metro Vancouver.

 A significant portion (80%) of the water distribution system is constructed of Ductile Iron pipe and is in good condition.

 Approximately 50% of the annual water capital budget is designated for the replacement of Asbestos Cement (AC) water mains with a target of 2025 for the replacement completion of all AC mains.

 The length of water main inventory has increased by 12% (or 13,164 metres) since 2001.  Estimated Replacement Value for the City’s water distribution assets is $51,500,000 -

(10)

Sanitary Sewer System

 The sanitary sewer collection system discharges to the Metro Vancouver Sanitary Sewer Collection pump station on Baynes Road on-route to the regional Annacis Island

Sewerage Treatment Plant in Delta, B.C.

 The City has a long-term replacement plan for the conversion of Asbestos Concrete (AC) mains to PVC mains, and where possible, mains are re-lined with PVC to extend their useful life for an additional 50 years.

 Development activity provides for the installation, extension and or capacity upgrades of sanitary sewer mains, as required.

 The City replaced approximately 2,993 meters of sanitary sewer main since 2010 with cured in place polyethylene (CPP).

Current Assets

Asset Category Quantity

Water mains 112.5 km

Pressure Reducing Stations 6

Booster Station 1

Fire Hydrants 481

Valves 984

Meters 720

Service Connections 3,935

Sustainability (Life Cycle) Considerations

 Ductile iron water mains have an estimated service life of 70 years.  Asbestos concrete water mains have an estimated service life of 40 years.

 Water valves, fittings and appurtenances have an estimated service life of 50 years.  Water pressure reducing stations have an estimated service life of 50 years.  Water service connections have an estimated service life of 50 years.

(11)

 The City’s sanitary sewer inventory has increased 22.9% (11,129m) since 2001.

 Estimated Replacement Value for the City’s sanitary sewer system assets is $23,500,000 - $25,300,000.

Storm Drainage

 In 2004, a Storm Sewer Audit was completed for the urban area piped system and the audit found the system to be in good shape with no major deficiencies identified.  Development activity provides for extensions from trunk sewers.

 There are 4 separate municipal drainage systems in the City with a total of 204 km of ditches that require regular cleaning and maintenance.

 The ditch and culvert system was reviewed by a consultant in 2007 to determine existing and future capacities. Despite investment in drainage infrastructure in the short term, drainage infrastructure continues to age faster than the City’s current rate of

replacement.

 The majority of the drainage pump stations were constructed in the early 1980`s under the Agriculture and Rural Subsidiary Agreement (ARDSA) program and the pumps are now coming to the end of their life cycle and need replacement. This work has been underway since 2010.

Pump Stations

 The pumps in the Area #1 station were replaced in 2010 with a grant from the Emergency Flood Response Program.

 The pumps in the Area #2 and #3 are now being slowly replaced, as funding is available.

Current Assets

Asset Category Quantity

Sewer Mains 48.5 km

Sewer Lift Stations 8

Pumps & Controls 16

Manholes 697

Generator 6 fixed & 1 portable

Service Connections 3,019

Sustainability (Life Cycle) Considerations

 Asbestos cement sanitary sewers have an estimated service life of 30 years.  PVC sanitary sewers have an estimated service life of 50 + years.

 Manholes and other related appurtenances have an estimated service life of 50 years.  Pumping stations have an estimated service life of 50 years.

(12)

 The pumps in the Baynes Road Pump Station were retrofit including new controls in 2014.  The pump station in area #4

was built in 1954 and requires replacement; parts are limited due to the age of the station. The City continues to actively pursue grant opportunities for

a full replacement of the station, at the same time the City is looking for a more cost effective replacement option.

The estimated Replacement Value for the City’s drainage infrastructure assets is $49,500,000- $57,000,000.

Current Assets

Asset Category Quantity

Storm Mains 48.9 km

Service Connections 2,327

Catch Basins 1,405

Manholes 720

Pump Station & Flood Boxes 6

Pumps 15

Culverts 740

Open Ditches 176.7 km

Floodgates 11

Sustainability (Life Cycle) Considerations

 Concrete storm mains have an estimated service life of 60 years.  CSP storm mains have an estimated service life of 40 years  PVC storm mains have an estimated service life of 100 years

 Manholes, catch basins, inlet / outlet structures and other related appurtenances have an estimated service life of 60 years.

 Service connections have an estimated service life of 50 years.

 The pump station structures have an estimated life of 100 years, the pumps average 25 – 35 years and the major electrical components have 25-year expectancy.

(13)

Key Utility Initiatives for 2016

Storm Drainage Projects Value

Culvert Replacements $100,000

Pump Station Trash Rack System

(location considerations Baynes or McKechnie) $350,000

Cranberry Slough Flood Box Repair $120,000

Sanitary Sewer Projects

AC Sewer Repair (CIPP) $300,000

North Lougheed Lift Station Replacement $200,000

Sewer Rate Review/Inflow and Infiltration Review $60,000

Water Projects

Blakely Rd Water main Replacement $175,000

117B, 193A & 193B Mains Replacement $275,000

192A, 192B & 116B Mains Replacement $250,000

Wildwood Crescent Mains Replacement $275,000

(14)
(15)

Public Assets

Public asset projects include fleet and equipment, emergency response apparatus, information technology, municipal buildings and dykes. Projects in this category include the purchase, repair and replacement of these assets to keep them functional and in a good state of repair in order to maintain an exceptional level of service to our residents.

Individual departments responsible for these assets identify the projects based on approved master plans, emerging community needs, and general asset upkeep. This is the first level of prioritization. The Engineering division collates these corporate projects and helps prioritize them based on criteria that include health and safety, and other risks, contractual obligations and availability of funds. Once a project is placed on the priority list and is approved by Council, the Department that made the initial project request assumes responsible for managing the acquisition.

An investment of $1,919,150 is required to fund the preliminary 2016 public asset projects.

Key Challenges for 2016

Capital Replacement Reserve

 The City’s public assets portfolio represents a significant investment valued at approximately $74,000,000 - $75,300,000.

 Currently a Dike assessment underway by the Ministry of Forests, Lands, and Natural Resource Operations focusing on the effects rising sea levels will have on the seismic stability of BC dikes. Findings could result in considerable future capital expenditures.

 With the exception of a few buildings, the City’s building portfolio is in good condition, although several facilities will need minor to major upgrading within the next few years.

Information Technology

 Technology Changes - Technological change is fast, constant and significant. Our data holdings are growing faster than ever before challenging our IT infrastructure to manage them. Our Citizens, businesses and staff expect current technologies to interact with the City and perform business functions. IT must balance the cost of change with user expectations and available resources while ensuring corporate business objectives are met.

 Rising Technology Costs - The current economic climate has had a severe impact on the cost of technology. The rising US dollar has had a real impact on IT operating and capital costs. Canadian vendors of US technology hardware have had to substantially raise prices to deal with the exchange rate. The City also uses software from US based vendors

(16)

with annual maintenance contracts invoiced in US dollars. These cost pressures appear to have reached a plateau with the current 30% rate differential however IT will be watching this closely over the coming year and making adjustments where possible to minimize cost impacts.

2015 Achievements

Municipal Fleet and Equipment

 Purchased and Replaced. The following equipment was purchased:  Hoe pack replacement

Information Technology

 Billing, Permitting, Licensing & Taxation System - BLiTS. The City successfully went to market for an enterprise, land based, billing, permitting licensing and taxation system that will replace existing revenue software systems and offer new functionality for planning and permitting. This eighteen-month project will ultimately provide

comprehensive, end to end work flow for staff in revenue collection and development project management as well as new online account and e-commerce capabilities to support residents and businesses into the future. This project falls under IT as the facilitator but it must be noted that it is truly a corporate initiative with business benefit for the entire organization and all Pitt Meadows residents.

 High Definition Robotic Video System for Council Chambers. To reduce reliance on SHAW cable volunteers, greatly enhance our video live stream capabilities and support open government and transparency initiatives overall; a High Definition Robotic Video system has been installed in Council chambers. Any meeting or event now held in Council Chambers can be live streamed via our website, digitally recorded or both in High Definition.

 Digital Audio System for the Committee Room. To enhance our live stream capabilities and also continuing to support open government and transparency initiatives, a digital audio system has been installed in the Meadows Room. Any meeting or event now held in the Meadows Room can be audio live streamed via our website, digitally recorded or both.

 PC Replacement An end of life PC replacement providing new desktop PC’s across the enterprise. The new PC specifications exceed business machine standards to ensure high performance and extend the lifecycle replacement frequency.

 Fire & Rescue Services Ruggedized Laptop Replacement. An end of life Laptop replacement for four emergency vehicles. This replacement moves mobile connectivity

(17)

from an old cellular data technology to the current LTE data standard significantly reducing ongoing operational costs.

 Firewall Replacement. An end of life Firewall appliance replacement contributing to enhanced network security and streamlined security management for IT.

 CartêGraph OMS – Implementation of a major CartêGraph software update that will provide enhanced tracking of asset activity and provide mobile access to assets and assigned tasks.

 Time Capture Implementation – In partnership with Finance, IT completed implementation of an electronic time capture and approval system for all inside staff.

At A Glance - Public Asset Statistics

Municipal Fleet and Equipment

 Municipal equipment is utilized to perform over 140 maintenance, public works and development services functions.

 The City’s fleet is used to maintain the water, sewer, drainage, roads, buildings and solid waste assets of the municipality and for bylaw enforcement, building inspection and fire to respond to emergencies.

 Estimated Replacement Value for the City’s fleet and equipment is $2,200,000 - $2,500,000.

 Estimated replacement value for the City’s fire vehicle fleet and emergency response apparatus is $4,265,000.

Current Assets

Asset Category Quantity

Works Vehicle Fleet 22

Works Equipment 37

Works Small Tools 42

Fire Vehicles 4

Apparatus 4

*Fire small equipment 100

*Includes: Rescue Tools (jaws of life, Breathing Apparatus, Radio Equipment and personal Protective Equipment

Sustainability (Life Cycle) Considerations

 Major heavy duty equipment has an estimated service life of between 12 and 20 years  Minor equipment and standard vehicles have an estimated service life of 10 years or less.

(18)

Municipal Buildings

 The City owns eight buildings and the estimated replacement value for these buildings is $19,500,000.

 City Hall was built in the 1970’s with major renovations/additions occurring in 1991 and 2005/06. Minor renovations were completed in 2014.

 The City Hall Annex was constructed in 1984 and the Public Works building and complex was completed in 1984. Renovations were completed to the Annex in 2013 and to the Public Works building in 2015.

 The Fire Hall was constructed in 1983 with miscellaneous renovations and upgrades in recent years.

 The Visitor Information Center was formerly an addition to the old City Hall (pre-1984) and was moved to its present position in 1985.

 The Masson House at the corner of Harris Road and 122Nd Street was moved to its current location from the corner of Park and Bonson Roads. The house was extensively renovated and is now leased as a restaurant.

 The Struthers House on Harris Road has been upgraded after a fire destroyed most of the interior in 2009; it is now being leased as a music teaching facility.

 The Civic Centre Parkade adjacent to the Pitt Meadows Family Recreation Centre was built in 2011.

Diking System

 Pitt Meadows is a community bordering three major rivers (Fraser, Pitt and Alouette).  Pitt Meadows has approximately 86% of its 9,516 hectares of land mass in the floodplain.  Flood protection is provided by 61 km of dike systems across 4 separate diking and

drainage areas. There is no plan at this time to raise the dikes to the new recommended standard.

Current Assets

Asset Category Quantity

City Owned Buildings 8

Sustainability (Life Cycle) Considerations

 The four main buildings (City Hall, Fire Hall, Annex, and Works Yard) have estimated service lives of 40 years.

(19)

 There are two types of Dikes in Pitt Meadows. Type 1 dikes are standard dikes built between 1977 and early 1989 and Type 2 Dikes are nonstandard agricultural dikes constructed/rebuilt between 1949 and 1950.

 Diking Area #2 and #3 dikes (type 1) were rebuilt in 1977 to 1989 and have an indeterminate lifespan. Operations have completed periodic gravel topping over the years. Recent toppings have improved the surface to accommodate pedestrian traffic.  Diking Area #1 and #4 are agricultural standard dikes and has an indeterminate lifespan.

Operations maintain the slopes by mowing and removal of any trees within the dike structure.

 New flood construction elevations recommended by Fraser River Basin Council will require all standard dikes to be raised by 0.3 m to 0.9 m. There is no timeline or dollar value determined at this time to raise the dikes.

 Approximate Replacement Value for the City’s dike infrastructure is $43,400,000 - $54,000,000.

Information Technology

 IT Manages 20.82 KM of private fiber optic cabling connecting City Hall to the Works Yard, Annex, Pitt Meadows Family Recreation Center and Fire Hall.

 Estimated Replacement Value for the City’s IT infrastructure is $1,800,000 - $2,000,000.

Current Assets

Asset Category Quantity

Dike (type 1) 30.5 km

Dike *(type 2) 30.4 km

*Agricultural dike (including Pitt Addington dike)

Sustainability (Life Cycle) Considerations

 Desktop computers and desktop software have an estimated service life of 4 to 5 years.  Wide Area Network and Local Area Network have an estimated service life of 7 years.  Fiber Optic Network have an estimated service life of 40 years.

 Main Systems Software have an estimated service life of 7 years (excluding ongoing patches and repairs to existing systems).

 Mobile devices (tablets & smart phones) have an estimated service life of 3 to 5 years.  Printers have an estimated service life of 4 to 7 years.

 Council presentation equipment has an estimated service life of 4 to 7 years.  Main application, data, and message servers have an estimated service life of 4 years.  Records Management systems have an estimated service life of 7 years.

(20)

Key Public Assets Initiatives 2016

 Financial Software systems have an estimated service life of 4 years before substantial upgrades are required.

 Financial Performance systems have an estimated service life of 4 to 7 years.  Web site and public access services have an estimated service life of 4 years before

significant upgrades are required.

 Web content management tools have an estimated service life of 4 to 7 years.  GIS hardware, software, and application data have an estimated service life of 4 years.  SCADA monitoring systems have an estimated service life of 7 years.

 Work, Resource, and Asset Management systems have an estimated service life of 7 years.

 The IT Strategic Plan has an estimated service life of 5 years before substantive revision is required.

2016 Proposed Projects Value

Billing, Permitting, Licensing & Taxation System—BLiTS (multi year 2015 - 2017)

$330,000

Fire Hall Server Room Replacement $85,000

Storage Area Network (SAN) Replacement $226,600

Fiber Phase V and VI $214,500

Hiab Truck Replacement $120,000

Dump truck Replacement $120,000

Pickup Replacement $40,000

New Position Vehicle (Environmental Services Coordinator) $35,000

Utility Vehicle $20,000

Works Yard Paving $65,000

(21)
(22)
(23)

Recreation, Parks & Culture

Projects in this category are the responsibility of the City’s service delivery partner, Maple Ridge Parks and Leisure Services through a Joint Leisure Services Agreement. Maple Ridge and Pitt Meadows Parks and Leisure Services staff prioritize projects based on approved master plans, emerging community needs and health considerations. In some instances, Parks and Leisure Services collaborate with other non-profit organizations in the region to provide funding for community based projects.

Capital projects are administered by managers in parks, facilities and recreation for each of their corresponding areas of responsibility. Parks projects include new park planning and construction, and trail construction. Staff in this area also administers the lifecycle repair and replacement of playgrounds, sports fields as well as a wide variety of other park amenity structures.

The Facilities section administers all building envelope improvements such as the Family Recreation Center and RCMP building expansion. This section also administers all lifecycle replacements and repairs in recreation buildings, community halls, and arena and heritage buildings. The Recreation department is responsible for ensuring the adequate supply of furnishings and program equipment as well as specialized fitness equipment at each of the recreation buildings and community halls.

Parks and Leisure services staff prioritize capital and lifecycle projects base the age and expected useful life of equipment and facilities, as well as emerging needs, the Parks and Leisure Services Master Plan and projects identified or approved by Council.

An investment of $738,200 is required to fund the preliminary 2016 recreation parks and culture projects.

Key Recreation, Parks & Culture Asset Challenges for 2016

Sport Field Resource Demand

 Pitt Meadows has hosted several baseball and soccer tournaments in 2015 resulting in very positive feedback from both regular users of the facilities as well as visiting teams from other parts of the region. Council has heard from the soccer community recently that up to four new synthetic sports fields will be needed in order to meet the growing demand for registrations in this sport. Similar comments have also been received by staff from other sports including rugby and lacrosse who feel they will need more practice time allocations in order to remain competitive with other teams in the region.

(24)

Invasive Plant Species

 Staff in the Parks and Bylaws departments has been receiving calls asking for additional information on how to deal with Japanese Knotweed on private property, and how to find a contractor who is qualified to complete pesticide applications. In other cases, citizens have been reporting Knotweed on public lands, which has been most helpful in compiling an inventory list for mapping.

2015 Recreation, Parks & Culture Asset Achievements

 Pitt Meadows Senior Secondary change rooms

At A Glance - Recreation, Parks & Culture Asset Statistics

 The Heritage Hall was built in the 1940’s.

 The Family Recreation Centre was built in 2001 and upgraded in 2014.  The South Bonson Community Centre was built in 2011.

 The Pitt Meadows Arenas (Pitt Meadows Athletic Park) was extensively renovated in 2012 and is operated by an independent entity.

 Estimated Replacement Value for the City’s recreation assets is $36,400,000 – $40,200,000.

Current Assets

Asset Category Quantity

Recreation Buildings 4

Developed Park Land 19 acres

Cultural & other buildings 8

Sustainability (Life Cycle) Considerations

 Recreational building envelopes can have a service life of up to 50 years with routine maintenance

 Parks, dykes and green spaces can maintain their functionality indefinitely through the use of sound maintenance practices.

 Typical facility roofs can survive up to 30 years with ongoing routine maintenance and repairs.

 Building heating, cooling & ventilation (HVAC) and other electro/mechanical equipment can last from 15 to 30 years if adequately maintained.

(25)

Key Recreation, Parks & Culture Initiatives for 2016

Draft Recreation, Parks & Culture Capital Plan for 2016

 Park play equipment can perform for up to 20 years if routine maintenance schedules are met.

 Park furnishings (benches, picnic tables, fences, trails etc.) can last 10 years.  Tennis & basketball courts can last up to 20 years.

 A typical heavily used playing field can perform for 20 years before major retrofits are required.

2016 Proposed Projects Value

Pickleball Courts (Cottonwood Park) $50,000

PMFRC Weight Room Equipment $16,000

Harris Pool Staff Shelter $25,000

Harris Park Shade Structure Over Skate Park $55,000

(26)

References

Related documents

Kumar (2010) categorized auto component manufacturers in Chennai into three groups: (1) large enterprises supplying to automobile assemblers as tier one suppliers,

Transaction Grouping - Do the data capture and delivery approaches support logical transaction groupings of the data for both the source and target to insure effective data

The guarantee provides that the performance of the obligations in an underlying contract is guaranteed so that, if a contractor fails to perform or pay money, the guarantor will

Since the objective in the study is to develop and test pressure sensors at for low frequency range and low pressure level applications such as human blood pressure monitoring,

from E14 (discussed in Appendix A4), and we are interested in the variation of Cepheid parameters with the choice of period cut (as with distance anchor and rejection algorithm

Chaib-draa, An online POMDP algorithm for complex multiagent environments, in: Proceedings of the 4th International Joint Conference on Autonomous Agents and Multi-Agent Systems,

For example, using nationally representative cross sections of employees offered 401(k) plans, the availability of employee matching is estimated to increase employee participation by

A bachelor’s degree from a college or university in corrections, criminal justice, law enforcement or a related major field will substitute for 1 year of the required