1. INTRODUCTION
1.1 Background Information
Provide high level background information to the project.
1.2 Purpose of the Project Plan
The project plan provides planning and control tools to ensure that the project is successfully completed and implemented.
2. PROJECT PLAN 2.1 Project Charter
2.1.1 Contract / Appointment Details
Date of appointment, contract type, level of approval, etc.
2.1.2 Client Details
Name, contact details as per contract, address, etc.
2.1.3 The Company Responsible Person
Who in the Company is responsible and accountable for the successful delivery of the project.
2.2 Project Scope
2.2.1 Project Product
Brief description of the project product.
2.2.2 Project Deliverables
A list of the sub-products whose full and satisfactory delivery marks completion of the project.
2.2.3 Project Objectives
Quantifiable criteria (critical success factors) that must be met in order for project to be considered a success.
Criteria must include, at least, cost, schedule and quality measures. Objectives should have an attribute (e.g. Cost), a measurable value (e.g. Rands) and an absolute or relative target (less than X amount).
2.2.4 Terms of Reference
The Client’s Terms of Reference for the project.
2.3 Work Breakdown Structure
Provide a detail Work Breakdown Structure
Project Deliverables and Milestones
High Level job allocation to be included
Page 2 of 6
Figure 1: The following is an example and by no means complete
2.4 Organisation Breakdown Structure
2.4.1 The Company’s Resources
Provide and OBS for the Company’s involved resources depicting lines of reporting.
Project E.g. Office Responsible Person
E.g. Person 1
Sub Project A E.g. Prelim Design Responsible Person
E.g. Person 2
Sub Project B E.g. Detail Design Responsible Person
E.g. Person 3
Sub Project C E.g. Documentation Responsible Person
E.g. Person 4
Sub Project D E.g. Implementation Responsible Person
E.g. Person 5
Task 1 E.g. Roads Design Responsible Person
E.g. Person 7
Task 2 E.g. Structural Design
Responsible Person E.g. Person 8
Task 3 E.g. Water and
Sanitation Responsible Person
E.g. Person 9
Activity 1 E.g. Geometric Design
Responsible Person E.g. Person 10
Activity 2 E.g. Pavement Design
Responsible Person E.g. Person 11
Activity 3 E.g. Drainage Design
Responsible Person E.g. Person 12
Figure 2: E.g.
Provide a detailed list of all the Company’s involved resources and their responsibilities
2.4.2 Sub Contractors
List the details of all Sub-Contractors that will be used on this project and their responsibilities.
Managing Director Person 1
Project Manager Person 2
Design Person 6
Planning Person 7
Construction Management Person 8
Prelim Design Person 9
Detail Design Person 10
Documentation Person 11
Page 4 of 6 2.4.3 Responsibility Matrix
Provide a detail task assignment and responsibility matrix. See following example template.
Table 1: Responsibility Matrix
PROJECT X
CONTRACT NO.
PROJECT RESPONSIBILITIES MATIX
Legend:
P = Primary Function I = Information A = Approve / Arrange S = Secondary Function D = Distribute
Technical Specifications Contractual Issues Design Drawings - Roads Drawings - Structures Drawings - Water Drawings - Sanitation Manuals Documentation Control Meetings Technical Meetings - Progress QA/QC Safety, Health and Risk Test Commissioning Close Out
Name Designation Company