CHEVRON RESEARCH AND TECHNOLOGY COMPANY RICHMOND, CA
December 1998
Manual sponsor: For information or help regarding this manual, contact Daniel E. Moore at (925) 842-2120
Cost Estimating Manual
First Edition April 1995
Second Edition November 1997
Third Edition June 1998
Fourth Edition December 1998
The information in this Manual has been jointly developed by Chevron Corporation and its Operating Companies. The Manual has been written to assist Chevron personnel in their work; as such, it may be interpreted and used as seen fit by operating management.
Copyright 1989, 1990, 1992, 1995, 1997, 1998 CHEVRON CORPORATION. All rights reserved. This document contains proprietary information for use by Chevron Corporation, its subsidiaries, and affili-ates. All other uses require written permission.
Restricted Material Technical Memorandum
This material is transmitted subject to the Export Control Laws of the United States Department of Commerce for technical data. Furthermore, you hereby assure us that the material transmitted herewith shall not be exported or re-exported by you in violation of these export controls.
Cost Estimating Manual
The following list shows publication or revision dates for the contents of this manual. To verify that your manual contains current material, check the sections in question with the list below. If your copy is not current, contact the Technical Standards Team, Chevron Research and Technology Company, Richmond, CA (510) 242-7241.
Section Date
Title Page December 1998
Front Matter December 1998
Table of Contents April 1995
Section 50 (Preface) April 1997
Section 100 Section 101 April 1995 Section 102 April 1995 Section 103 April 1995 Section 104 April 1995 Section 105 April 1995 Section 200 Section 201 April 1995 Section 202 April 1995 Section 203 April 1995 Section 204 April 1995 Section 205 April 1995 Section 206 December 1996 Section 210 Section 211 April 1995 Section 212 April 1995 Section 220 Section 221 April 1995 Section 222 April 1995 Section 223 April 1995 Section 224 April 1995 Section 300 Section 301 December 1998 Section 302 April 1995 Section 303 April 1995 Section 304 April 1995 Section 305 April 1995
Section 311 April 1995 Section 312 April 1995 Section 313 April 1995 Section 400 Section 401 April 1995 Section 402 April 1995 Section 403 December 1995 Section 404 April 1995 Section 405 December 1998 Section 406 April 1995 Section 407 April 1995 Section 408 April 1995 Section 410 Section 411 April 1995 Section 420 Section 421 April 1995
Section 422 March 1995 (draft)
Section 423 March 1995 (draft)
Section 424 December 1998 Section 500 Section 501 April 1995 Section 510 Section 511 April 1995 Section 512 April 1995 Section 520 Section 521 April 1995 Section 522 December 1998 Section 523 April 1995 Section 600 Section 601 April 1995 Section 602 April 1995 Section 603 April 1995 Appendices Appendix A April 1995 Appendix B April 1995 Appendix C April 1995 Appendix D April 1995 Appendix E April 1995
Cost Estimating Manual
If you have moved or you want to change the distribution of this manual, use the form below. Once you have completed the information, fold, staple, and send by company mail. You can also FAX your change to (510) 242-2157.
❑ Change addressee as shown below. ❑ Replace manual owner with name below. ❑ Remove the name shown below.
Send this completed form to: Document Control, Room 50-4328
Chevron Research and Technology Company 100 Chevron Way (P.O. Box 1627)
Richmond, CA 94802
CRTC Consultants Card
The Chevron Research and Technology Company (CRTC) is a full-service, in-house engineering organi-zation.
CRTC periodically publishes a Consultants Card listing primary contacts in the CRTC specialty divi-sions. To order a Consultants Card, contact Ken Wasilchin of the CRTC Technical Standards Team at (510) 242-7241, or email him at “KWAS.”
Previous
Owner: Title:
Last First M.I.
Current
Owner: Title:
Last First M.I.
Company: Dept/Div:
Street: P.O. Box:
City: State: Zip:
Cost Estimating Manual
We are very interested in comments and suggestions for improving this manual and keeping it up to date. Please use this form to suggest changes; notify us of errors or inaccuracies; provide information that reflects changing technology; or submit material (drawings, specifications, procedures, etc.) that should be considered for inclusion.
Feel free to include photocopies of page(s) you have comments about. All suggestions will be reviewed as part of the update cycle for the next revision of this manual.
Send your comments to: Document Control, Room 50-4328
Chevron Research and Technology Company 100 Chevron Way (P.O.Box 1627)
Richmond, CA 94802
Page or Section Number Comments
Name Address
Manual Sponsor: Daniel E. Moore / Phone: (510) 842-2120 / E-mail: [email protected]
List of Current Pages
50 Using this Manual 50-1 100 Introduction to Cost Estimating 100-1 200 Primary Methods—Process Plants 200-1 210 Primary Methods—Offplot Facilities 210-1 220 Primary Methods—Other Facilities 220-1 300 Secondary Methods—Individual Cost Adjustments 300-1 310 Secondary Methods—Bottom-Line Cost Adjustments 310-1 400 Direct Cost Data—Equipment (Major Material) 400-1 410 Direct Cost Data—Bulk Materials (Minor Material) 410-1 420 Direct Cost Data—Construction Labor 420-1 500 Indirect Costs and Special Charges—Indirect Field Costs 500-1 510 Indirect Costs and Special Charges—Technical Services 510-1 520 Indirect Costs and Special Charges—Special Charges 520-1 600 Estimate Presentation and Review 600-1 Appendices
Appendix A Estimating Checklists
Appendix B Process Licensors' Sales Factors Appendix C Code of Accounts (EG-2757)
Appendix D Code of Accoounts for Buildings Projects Appendix E Glossary
This document contains extensive hyperlinks to figures and cross-referenced sections. The pointer will change to a pointing finger when positioned over text which contains a link.
T
he intent of the Cost Estimating Manual is to provide uniform procedures and
accompanying data for developing cost estimates for capital projects throughout
Chevron. We hope that the material in this manual will contribute to a common
understanding and consistent application of the cost-estimating process.
Using This Manual
The manual is arranged to follow the flow of a typical cost estimate: Chapter 100 provides an overview of cost estimating, estimate classes and estimating methods.
Chapter 200 describes the principal methods for making cost
estimates—primarily for process plants, but also for offplot and other types of facilities. Method-specific data is also included.
Chapter 300 includes factors and data to use with two or more methods described in the previous chapter.
Chapter 400 contains instructions and data for estimating individual components of direct costs. The data includes material, labor, and subcontract costs associated with purchasing and erecting the physical facilities.
Chapter 500 covers indirect costs and special charges. Indirect costs include construction indirect, engineering, and project management costs. Special charges are costs that may be unique to a project and, therefore, require specific identification and analysis.
Chapter 600 contains guidance for reviewing, presenting, and documenting completed cost estimates.
The Appendices contain general estimating reference materials, including checklists and a glossary.
This manual is sponsored by Project Resource Services, Project Resources. Questions, comments, and suggestions for improvement are welcome and encouraged, and may be addressed to the Manager, Project Resource Services, San Ramon.
100
101
Cost Estimating in General
102
Cost Estimating and the Phases of a Project
103
The Classes of Cost Estimates
104
Methods of Cost Estimating
105
Selecting a Method
Cost Estimating in General
W
ebster defines an estimate as an approximate computation of probable cost.
According to the American Association of Cost Engineers (AACE), cost
estimating is the predicting or forecasting ... of the costs required to construct and
equip a facility, to manufacture goods, or to furnish a service. The latter definition
more closely aligns with the objectives of this manual.
Objectives of this Manual
While the concept of estimating is familiar to most people, the process may not be familiar. To help you estimate projects for Chevron, the objectives of this manual are to
explain the various types of estimates and techniques for making them provide you with estimating data and guidance
Although this manual is written primarily for major downstream projects, it can also be applied to upstream projects and smaller downstream projects.
Reasons for Cost Estimating
Capital
Construction Generally, you associate estimates with capital construction projects to establish capital budgets
evaluate project economics obtain funding approval
monitor and control the execution of work
Annual Budgets Chevron operating companies and staffs base their annual operating expense budgets on estimates.
Other Acitivities Activities such as these also require estimates: Shutting down refinery plants for maintenance Overhauling tankers
Providing technical services for studies Writing computer programs
Planning business trips
The AACE definition points out that you may make a variety of types of estimates. In the next section, you’ll see how estimates fit into the different phases of Chevron project management.
Cost Estimating and the Phases of a Project
C
ost estimates are important in all phases of project management. In Figure 102-1,
note the role of estimating (shown in bold italic) in the Chevron Project
Development and Execution Process (CPDEP).
Phase 1 2 3 4 5
CPDEP1 Phase Identify & Assess Opportunities Select Alternative(s) Develop Alternative(s)
Execute Operate & Evaluate
CPMP2 Phase Concept Development
Feasibility Front-End Engineering
Execution Operation & Evaluation OBJECTIVES Identify Opportunities
Clearly Frame Goal Test for Strategic Fit Preliminary Overall Plan
Preliminary Assessment Plan for Phase 2
Generate Alternatives Preliminary Development of Alternatives Develop Preliminary Project Economics Identify Preferred Alternative(s) Plan for Phase 3
Fully Define Scope Develop Detailed Execution Plans Refine Estimate Develop Final Project Economics Submit Request for Funding Approval Plan for Phase 4
Implement Execution Plan
Finalize Operating Plan
Business Plan for Phase 5 Project Review Operate Asset Monitor and Evaluate Performance Identify New Opportunities
DELIVERABLES Business Objectives & Project Framework Block Flow Diagram & Preliminary Capacity Preliminary Milestone Schedule Class 1 Estimate
Preliminary Facility & Project Objectives Process Flow Diagrams & Equipment Lists Preliminary Project Schedule Class 2 Estimate
Final Facility & Project Objectives P&IDs, Plot Plans, One-Line Diagrams Detailed Schedule Class 3 Estimate Operating Facility Documentation Lessons Learned Class 4 (& perhaps 5) Estimates and Final Project Cost
Post-Project Assessment Lessons Learned & Best Practices Benchmark Performance
TOOLS & PROCESS
Set & Freeze Business Objectives Concept
Development FEL Checklist
Freeze Capacity, Technology & Site Feasibility FEL Checklist Freeze Definition Documents Front-End Engineering FEL Checklist Freeze Design Details Execute Post-Project Assessment Review & Share Lessons Learned
1 CPDEP = Chevron Project Development and Execution Process
2 CPMP = Chevron Project Management Process (Downstream Adaptation of CPDEP)
The Classes of Cost Estimates
C
hevron has adopted a series of cost estimate classifications as a part of the
CPDEP. These classifications establish a common understanding among
estimators, project managers, and their clients regarding these factors:
Variability in the information required
Appropriate estimating methods for each class
Resulting estimate quality
The Five Classes
Figure 103-1 summarizes the five classes. The first three are linked to the three phases of CPDEP Front-End Loading, where their purpose is to provide information to assist decision-makers.
Classes 1 & 2 Because the first two project phases may extend over a long time (two to three years for large projects), several Class 1 and Class 2 estimates may be necessary as the project team studies various alternatives.
Class 3 Class 3 is often called an appropriation estimate because it is the basis for preparing an appropriation request. Again, large projects may have more than one Class 3 estimate, especially if the first one exceeds the funds budgeted for the project. In that case, the team must adjust the scope of the project.
Classes 4 & 5 Contractors usually prepare the last two classes of estimates during project execution. Contractors may call the Class 4 a control estimate because it establishes a basis for managing (controlling) the contractor’s work during the construction phase. Class 5 is appropriate only for very large, multi-year projects. It is really a re-forecast of remaining work (and thus the final cost) because much of the cost is fixed by that time.
Contingency
The values shown in the Contingency column of Figure 103-1 indicate relative requirements only and show the benefit of improvement to the project definition as projects progress.
For Classes 1 and 2, especially, the typical contingencies shown apply to facilities known at the time of the estimate. Estimates can double or triple as the definition of required facilities evolves. You should not use this table to determine the actual contingency required for any estimate, but determine it from the characteristics of the specific project and estimate (see Section 313).
Class &
Project Phase Engr’g
Con-tingency Information Required
Estimate Methods Used/Cost Basis Major Equipment Other Materials Labor Class 1
Concept Development2
<1% 30-50%1 - Block flow diagrams - Facility capacity
- Preliminary major equipment list
- General location and site conditions
- Preliminary timing and schedule
- General business climate
Overall project or plant cost
a. Cost capacity data b. Historical cost data c. Industry published data d. Licensor estimate e. Installation factor times major equip. Class 2
Feasibility2
1-5% 15-40%1 Same as Class 1 plus: - Preliminary process design - Preliminary major equipment sizing
- Offplot description - Site specific plot plan
- Cost curves - Vendor tel. quotes - Recent purchases - Published estimating data - Other estimating guides - By ratio to major equipment - By ratio from similar facility based on historical data - By labor/ material ratio for similar work
- Productivity, taxes, wage rate, etc., in the area factor Class 3
Front-End Engineering2
15-30% 10-15% - Complete process design (PDC)
- Preliminary P&IDs, plot plan and one-line electrical diagrams
- Complete site survey and soils data
- Firm major equipment sizes - General projects specs - Defined offplot facilities - Preliminary utility balance - Environmental compliance plan
- Completed mat’ls selection - Contracting plan - Written equipment quotes - Escalation defined By ratio to major equipment - Escalation defined - Key quantities identified - By labor/ material ratio for similar work - Manhour units or other parameters - Productivity for area - Wage rates Class 4 Execution: Detailed Design 30-50% 5-10% - Approved P&ID’s - Plot plans issued for construction
- Detailed contracting plan - Minor contracts and final schedule
- Completed engineering data sheets
- Ordered major equipment costs - Major equipment ordered - Deliveries evaluated - Detailed quantity takeoff3
- Firm unit cost quotes - Schedule revised - Construction plan complete - Manhours by craft - Wage rates - Productivity - Defined indirects Class 5 Execution: Construction 90-95% 5-15% of unex-pended funds - Construction contracts awarded
- Ordered bulk materials costs - Construction 40-60% complete
Actual or committed costs to date
- All bulks ordered - Deliveries assessed - Scheduled updated
- Firm bid contracts or detailed evaluation of field manhours - Labor availability assessed - Field productivity included
1 Data from Chevron and the industry shows considerable scope growth (as much as 200 percent) as project definition evolves
during the Concept Development and Feasibility phases.
2 These three phases include the completion of Project Scope Packages, Project Execution Packages, and Project Decision-Making
Packages. These are described in several checklists in the Front-end Loading Handbook.
3 A quantity takeoff is a count of the quantities of bulk materials to be installed.
Methods of Cost Estimating
C
hevron uses various methods of cost estimating. Each has several components
(Figure 104-1), which are described in this manual.
Process Plants
Curve A curve estimate is based on finding the costs and capacities of plants similar to the one to be estimated. The estimator adjusts that data for date, location, and common facilities; calculates the new cost; and makes further adjustments to develop the estimate for the new facility. See Section 202, “Curve Estimates.”
Factored A factored estimate is based on determining the total cost of a plant (excluding special charges, escalation, and contingency) by assessing the cost of the tagged process (or utility) equipment and multiplying that total cost by a single factor. See Section 203, “Factored Estimates.”
Ratio A ratio estimate is possible only if the estimator has or can approximate ratios for similar facilities. The estimator assesses the cost of tagged process (or utility) equipment and then applies a series of ratios to that assessment to determine the costs of bulk material, direct labor, field indirects, design, and project management. The total is the plant cost excluding special charges, escalation, and contingency. See Section 204, “Ratio Estimates.”
Detailed/ Semi-Detailed
A detailed estimate is based on a complete definition of the work—when every element is identified and quantified, and engineering is 30-50 percent complete. Usually, you prepare this estimate to check project cost against budget or to manage the construction effort.
A semi-detailed estimate is a five-step process based on assessing only the direct costs in limited detail and then applying ratios to the direct costs to determine the indirect costs.
C o s t E s t i m a t i n g C l a s s i f i c a t i o n s F a c t o r M e t h o d E q u i p m e n t C o s t s B u l k M a t e r i a l C o s t s I n d e x e s M u l t i p l i c a t i o n F a c t o r M o d e r n i z a t i o n F r e i g h t S a l e s T a x M a t e r i a l s / E q u i p . R a t i o s L a b o r M a n h o u r s / M a t e r i a l C o s t R a t i o s L a b o r H o u r l y R a t e s L a b o r R e w o r k S u b - c o n t r a c t C o s t P r o d u c t i v i t y C u r v e M e t h o d R a t i o M e t h o d D e t a i l e d M e t h o d E q u i p m e n t C o s t s E q u i p m e n t C o s t s I n d e x e s I n d e x e s I n d e x e s A l l o w a n c e s A l l o w a n c e s F r e i g h t F r e i g h t S a l e s T a x S a l e s T a x U n i t M a n h o u r R a t e s L a b o r H o u r l y R a t e s P r o d u c t i v i t y I n d i r e c t F i e l d C o s t s A l l o w a n c e s E n g / M g m t C o s t s S p e c i a l C h a r g e s A r e a F a c t o r E s c a l a t i o n C o n t i n g e n c y I n d i r e c t F i e l d C o s t s E n g / M g m t C o s t s S p e c i a l C h a r g e s E s c a l a t i o n C o n t i n g e n c y E s c a l a t i o n C o n t i n g e n c y A r e a F a c t o r E s c a l a t i o n C o n t i n g e n c y P r o j e c t D e f i n i t i o n & S c o p e C o s t E s t i m a t i n g S p e c i a l C h a r g e s S p e c i a l C h a r g e s
Offplot Facilities
Many offplot facilities are estimated using the methods given above for process plants. Class 1 estimates can use the curve method (using offplot data) or a percent of onplot data. Class 2-3 estimates use the semi-detailed method and Class 3 or later estimates use the detailed method. For more information, refer to Section 211.
Selecting a Method
I
n general, the method of cost estimating you choose is based on
what you are estimating
the phase of the project
the information you have available or can obtain
Prerequisites
To make a cost estimate, you need the following information: Knowledge of the scope of the project.
For curve estimates, the capacity of the new plant, and the costs and capacities of two or more similar, completed plants.
For factored estimates, a sized list of equipment for all process and utility equipment.
For ratio estimates, the same as for factored estimates, plus cost and labor-hour ratios for similar plants.
For detailed estimates, every element of the planned work.
Awareness of direct costs (Chevron Group II)—equipment, materials, and installation labor directly involved in physical construction. Awareness of indirect costs1(Chevron Group I)—construction-related costs such as supervision, equipment rental, and temporary facilities; engineering and project management costs for both contractors and Chevron.
Awareness of special charges2 (catalyst, ocean freight, operating company G&A charges, dismantling, and so on); sometimes categorized as expense or working capital rather than as capital. See Sections 202–205, 211, and 221–224 for more information on methods of estimating.
See Appendix C, “Code of Accounts (EG-2757),” for more detail on these cost categories.
1 Not a final part of the installation but required for the orderly completion of the installation.
2 Unique to the Chevron system. Vary widely among projects. Segregated to avoid distorting the ratios and relationships
Resources
You can order a variety of manuals and other resources, such as the CRTC Consultants’ Card and the engineering design (gray) manuals, from CRTC Technical Standards Team.
200
201
Estimating Major Material (Equipment) Costs
202
Curve Estimates
203
Factored Estimates
204
Ratio Estimates
205
Detailed Estimates
206
Electronic Estimating: Questimate
Estimating Major Material (Equipment) Costs
F
or three of Chevron’s estimating methods—factored, ratio, and detailed, you must
first assess the cost of purchasing and delivering tagged equipment items (also
known as major material). These items fall under cost accounts C-G and K. See
Appendix C, “Code of Accounts (EG-2757).”
Estimating Cost Components for Equipment
Overview The total cost of equipment when making an estimate with the factored, ratio, or detailed method is the sum of the base cost, design allowance, freight, and taxes for each equipment item.
Information Needed Be sure you have an equipment list with each item sized and materials of construction specified. Also review the resources listed in Figure 201-1.
For This Manual Other Sources
Sources of Equipment Costs 401–408 - Purchase orders for the current project - Commercial data sources (e.g., Richardson or Questimate)
Cost Indexes 301
Design Allowances 303 Freight: Domestic & Ocean 304 Sales Tax Rates 305
Duty, Importation 521 - The Corporate Tax Department for current information on applicable duty on U.S.-imported equipment
- Chevron operating company sponsoring the project or a major international contractor for duty on material Chevron imports into a foreign country
Steps in Estimating Cost of Equipment
Figure 201-2 is a composite of the steps involved in assessing tagged equipment. Detailed procedures follow.
1 ESTIMATE EQUIPMENT COST, FOB THE FABRICATOR’S SHOP
Obtain or develop a complete equipment list, with sizing and metallurgical specifications.
For early (Class 1 or 2) estimates, you may have to create an equipment list from a preliminary flowsheet, which often omits essential process and utility equipment items. To compensate, add appropriate items or systems from Figure 201-3, modifying the list to suit your plant. By the time you begin to make a detailed (Class 3, 4, or 5) estimate, you should have access to a complete equipment list (including items in Figure 201-3). If the equipment list is cross-referenced to the approved P&IDs, estimating is easier.
Determine the cost of items on the equipment list (see Figure 201-4). If your sources are not current, then adjust the costs to the current date with an index, such as EDMI. See Section 301. Choose EDPI for field-erected equipment, such as large tanks, columns, and cooling towers.
2 DETERMINE THE DESIGN ALLOWANCE
Compensate for the difference between the estimate and the probable final cost of equipment by including a design allowance, usually between 3 percent and 15 percent (see Section 303). Incomplete specifications are the most common reason for cost variances.
3 ASSESS FREIGHT TO THE JOB SITE (OR TO THE ASSEMBLY YARD FOR SKIDDED OR MODULAR WORK)
Domestic Freight
Review the source of the cost data to determine whether or not freight is included in that price. Shipping can be a separate line item in a contractor’s estimate or shown on a formal quotation or purchase order.
See Section 304 for guidance on how to estimate domestic and ocean freight. Large process equipment requires a specific transportation plan that may include unusual routing and costly restrictions.
Boiler feedwater pumps (with or without a deaerator)
Condensate flash drums and pumps Condensers for large steam turbines (including jet ejectors and condensate pumps)
Desuperheaters (attemperators) Emergency product coolers
Equipment spares, such as spare pumps —installed and warehouse spares Feed surge drum
Feed booster pumps Flush oil systems Fuel gas knockout drums Fuel oil filters
Heat recovery equipment (energy savings) Interstage coolers/condensers and K.O. drums for reciprocating compressors (if not supplied by compressor vendor)
Jacket/tempered water systems
Lube and seal oil systems (often part of centrifugal compressor or high pressure pump packages)
Oil mist generators
Power recovery turbines (energy savings) Relief system knockout drum and pump Solids handling equipment
Sour water, caustic and/or acid flash drums and pumps
Start-up equipment
Steam separators (for ejectors, superheating coils, and some steam generators)
Suction and discharge pulsation dampers for reciprocating compressors
Sump pumps
Vent separators and condensers Note: Modify this list to suit other types of plants.
Figure 201-3. List of Items Often Omitted from Refinery Process Flow Diagrams
1. Purchase orders for the current project 2. Formal vendor quotations for the current project 3. Recent purchase orders for similar equipment 4. Recent formal quotes for similar equipment 5. Informal vendor estimates/phone quotes for the current project
6. Data correlations in this manual (or a similar database from a contractor)
7. Commercial data sources (e.g., Richardson or Questimate)
Figure 201-4. Sources for Estimating Equipment in Order of Quality & Preference
Ocean and Foreign Land Freight (see Section 521)
Estimate ocean freight concurrently with the equipment.
Deduct ocean freight for ratio or factored estimating methods before applying the ratios or factors, and then add it later. Ocean freight is considered a special charge in the Chevron system (see Section 521). Include insurance, packing/blocking/crating, port handling/clearance costs (at both ends), and carrier costs.
Identify as a special charge any foreign land freight costs, such as delivering the equipment from a foreign port to a construction site. See Section 521.
4 ADD SALES TAXES AND IMPORT DUTIES Domestic
Add a sales or use tax to the delivered cost of the equipment for most domestic locations.
See Section 305 for recent information on applicable tax rates for many Chevron locations.
Imported or Foreign
Contact the Corporate Tax Department for current information on applicable duty on U.S.- imported equipment.
Contact either the Chevron operating company sponsoring the project or a major international contractor for the duty on material Chevron imports into a foreign country.
As with ocean freight, import duties are considered special charges (see Appendix C, “Code of Accounts (EG-2757),” Item 77). Before applying factors or ratios for those types of estimates, you must set them aside and add them separately after applying the factors or ratios.
Curve Estimates
W
hen making an early Class 1 estimate, you will probably choose the curve
method. The premise of curve estimates is that costs vary exponentially with
capacity for many types of plants.
The Curve Method
Overview A curve estimate is based on finding the costs and capacities of plants similar to the one being estimated. The estimator adjusts that data for date, location, and common facilities; calculates the new cost; and makes further adjustments to develop the estimate for the new facility.
Information Needed To make a curve estimate of the cost of a new plant, you need to gather data on the capacity of the new plant and the cost and capacity for two or more similar plants.
Also review the resources listed in Figure 202-1.
Theoretical Basis The form of the cost-capacity equation is as follows:
y = a × (x)b
where:
y = cost
a(coefficient) = specific to plant type
x = capacity
b(exponent) = specific to plant type (close to 0.6 but can range from 0.3 to 1.0)
Resources In This Manual Adjusting to Common or Current Date Sections 301, 302 Adjusting to Common or New Location Section 311 Adding Special Charges Section 521 Adding Escalation Section 312 Adding Contingency Section 313 Figure 202-1. Resources for Curve Estimating
Graphically, this equation will plot as a straight line on log-log paper. In practice, the curve may not be smooth but may be stepped at certain points, such as when limitations of equipment size require twinning (using a parallel piece of equipment) or adding a second train.
✎
Because the exponent (slope of the graph) changes from a very low number (perhaps 0.3 at low capacities to nearly 1.0 at high capacities), extrapolation beyond knowncapacities can lead to a significant error in estimating.
Applicability The curve method is
suitable for geographically confined plants, such as process plants and
some utilities.1
unsuitable for new technology plants that do not have cost histories.2
Steps in a Curve Estimate
The steps in a curve estimate are described below and shown in Figure 202-3.
An example of a sour water stripper with a feed rate of 200 gallons per minute (gpm) is included to illustrate the steps.
1 DETERMINE THE DESIRED CAPACITY FOR THE TYPE OF PLANT BEING ESTIMATED
The terminology for operating capacity is given in Figure 202-2.
Typical Operating Capacity
Typical Plant Terminology Abbreviation
Thousands of barrels per operating day MBPOD Most Refinery Plants
Millions of standard cubic feet per day MSCFD Hydrogen Mfg., Gas Processing Short tons per day ST/D Sulfur, Coker
Millions of pound per year MPY Chemical Plants Figure 202-2. Typical Operating Capacity Terminology & Abbreviations by Type of Plant
1 Less-accurate cost-capacity equations for offplot facilities (such as tank fields) are given later in this chapter. 2 If the factored method is unsuitable, refer to the detailed method and semi-detailed method (later in this section).
2 FIND COST AND CAPACITY DATA FOR SIMILAR PLANTS
Check the data for process and offplot plants later in this section. If your plant is shown, use that data and skip to step 7.
If the data in those sections does not meet your needs, find the costs and capacities for similar plants from actual project cost data (see Figure 202-4) or from journals or other literature.
Identify the construction period associated with the costs (for converting to current or future costs).
3 ADJUST THE COSTS OF THE REFERENCE PLANTS TO A COMMON DATE— NORMALLY, THE CURRENT DATE—USING EDPI (SECTION 301)
If the data is older than 1983, modernize it by following the instructions in Section 302. See the example in Figure 202-5.
4 ADJUST THE COSTS OF THE REFERENCE PLANTS TO A COMMON LOCATION, USING AREA FACTOR DATA 1
See Figure 202-6 and Section 311.
Determining Data for Similar Plants: Sour Water Stripper1
Refinery GPM Original Cost Date EDPI Burnaby 85 $1.00 M 2/75 473.6 Pascagoula 165 $6.41 M2 8/74 449.8 El Segundo 240 $1.27 M 11/74 466.4 Richmond 350 $0.87 M 2/75 473.6
1 This example shows how we developed the sour waterdata used
to illustrate this method.
2 Includes H
2S recovery facilities.
Figure 202-4. Example of Project Cost Data
Adjusting Reference Plant Costs to Common Date:1 Sour Water Stripper
Refinery Original Cost Adjusted Cost
Burnaby $1.00 M $3.21 M2
Pascagoula $6.41 M $22.09 M
El Segundo $1.27 M $4.18 M
Richmond $0.87 M $2.79 M
1 EDPI for 1991 = 1100 (for example only).
2 Adjusted Cost = Original Cost x (1100/473.6) x (1.048.25) for Burnaby.
Figure 202-5. Example of Adjusting Costs to a Common Date
1 While Richmond is a standard reference, the common location may be any other place, such as the proposed plant site or
5 COMPARE PROCESS FLOW DIAGRAMS & ADJUST COSTS
Compare the process flow diagram for the proposed plant with those of the reference plants and note differences.1
Adjust the costs of the reference plants to a common facilities basis.2 See the example in Figure 202-7.
Adjusting Reference Plant Costs to Common Location (Richmond): Sour Water Stripper
Refinery Area Factor1, 3 Adjusted Cost2
Burnaby 1.15 $2.79 M
Pascagoula 0.95 $23.26 M
El Segundo 1.07 $3.91 M
Richmond 1.00 $2.79 M
1 Area factor relative to Richmond = 1.00
2 Adjusted Cost = Cost from Figure 202-5
Area Factor
3 Area factors shown apply only to the plants & dates for this
example; may differ from Section 311.
Figure 202-6. Example of Adjusting Costs to a Common Location
Adjusting Reference Plant Costs to Common Facilities Basis for Sour Water Stripper Refinery Adjusted Cost1
Burnaby $3.30 M
Pascagoula $4.69 M
El Segundo $5.73 M
Richmond $6.98 M
1 All reference plants require equipment additions or
deletions to make them match the “standard” plants in the curve data presented later in this section. Figure 202-7. Example of Step 5
1 Examples are differences in equipment (such as number of reactors and side-stream strippers, caustic and water washers,
6 PLOT COSTS
Plot the updated cost data for reference plants versus plant capacity on log-log graph paper (see Figure 202-8).
Draw a straight line through the data points.
ALTERNATIVE: DEVELOP EQUATION
You can also calculate the equation of the regression line through the data points, which is the equation for the sour water strippers given later in this section. See the example in Figure 202-9.
✎
If only one data point is available, assume an exponent of 0.6 when creating the graph or equation. This is commonly referred to as the Six-Tenths Rule (see Figure 202-10).
Figure 202-8. Example of Onplot Cost vs. Capacity (EDPI = 1100) for Sour Water Stripper
Linear Regression Performed on the Logarithms of Costs & Capacities for Sour Water Strippers
y = 0.314 x (x)0.53
where:
y = $M @ EDPI = 1100 x = GPM
7 CALCULATE (OR READ) THE COST OF THE NEW PLANT
Enter the equation or graph with the new plant’s capacity. Calculate (or read) the cost of the new plant at the common date used in step 3 (or the date of the equations shown later in this section, if used).
See the example in Figure 202-11.
Supposition:
You have a single data point for a plant costing $6 million and having a capacity of 10 MBPOD.
Develop equation from reference plant data based on the cost-capacity equation: y = a × (x)b
where: y = cost
a (coefficient) = specific to plant type x = capacity
b (exponent) = specific to plant type
Apply those values to the general equation: $6 M = a × (10 MBPOD)0.6 Solve this equation to give:
a = 1.51
Apply equation to similar new plant (same date): y = 1.51 × (x)0.6
where:
y = cost in $M x = capacity in MBPOD
Figure 202-10. Sixth-Tenths Rule
Calculate the Cost of New Plant at the Common Date for 200 gpm Sour Water Stripper From the equation
y = 0.314 × (200 GPM)0.53 = $5.2M at EDPI = 1100 (1991)
Where:
y = cost
The data in this correlation covers a range of 85 - 350 gpm. To use it at 50 gpm or at 400 gpm would be risky. In our example, 200 gpm is well within the range.
8 ADJUST THE NEW PLANT COST TO THE DATE OF THE CURRENT ESTIMATE USING EDPI (AND MODERNIZE, IF NECESSARY)
See the example in Figure 202-12.
9 ADJUST THE NEW PLANT COST FOR ANY FACILITY DIFFERENCES BETWEEN THE NEW AND REFERENCED PLANTS THAT WERE NOT RECOGNIZED IN STEP 5
See the example in Figure 202-13. Also adjust for duplication savings. If a contractor designs multiple, identical plants at the same time, efficiencies in engineering and procurement can reduce the costs for the second and subsequent plants by 10 percent. These savings may apply even if the plants are constructed at different locations.
10 ADJUST THE COST FOR LOCATION
See Section 311 and Figure 202-14. The equations shown later in this section are based on a West Coast (Richmond) location. If the facility being estimated will be built in another part of the U.S. or overseas, you must make an area factor adjustment.
Adjust New Plant Cost to Current Date for 200 gpm Sour Water Stripper The adjusted cost at EDPI = 1200, for example, would be
y = $ 5.2 M(1200/1100) = $ 5.7 M
where: y = cost
Figure 202-12. Example of Adjusting Cost to Current Date
Adjust New Plant Cost for Facility Differences Between New & Referenced Plants for 200 gpm Sour Water Stripper
Supposition: The process flow diagram for your particular plant showed no sour water cooler or degasser. Eliminating those facilities requires a deduction of about 18 percent from the cost (see data later in this chapter).
y = $ 5.7 M x 0.82 = $ 4.7 M
where: y = cost
Figure 202-13. Example of Adjusting Cost for Facility Difference
Adjust Cost for Location for 200 gpm Sour Water Stripper
In step 4, we adjusted the reference plants to Richmond (area factor = 1.00). The unspecified location for our new plant has an estimated area factor of 0.90, thus:
y = $ 4.7 M x 0.90 = $ 4.2 M
where: y = cost
11 ADD SPECIAL CHARGES SUCH AS CATALYST AND G&A
Use Section 521 as a checklist to identify possible special charges that may apply to the estimate.
12 OPTIONAL — ADD ESCALATION
If you need a then-current estimate, add escalation based on the anticipated schedule for the project (see Section 312).
13 ADD CONTINGENCY
Data for Curve Estimating
Cost-Capacity Coefficients and Exponents for Many Refinery Process Units
The tables that follow are to be used in an equation of the form:
Cost ($ millions, 1991) = Coefficient x (Capacity)Exponent
(EDPI = 1100)
The capacity is in thousands of barrels per day (MBPOD) except where noted.
The data comes from Company projects in the 1970s and from other sources. It has been updated to EDPI = 1100 (mid-1991). Because of the age of the underlying data, the correlations should be used with caution. Costs exclude catalyst, piling, computers, and winterizing, and are on a West Coast (Richmond) basis.
The tables contain adjustment factors that you can use in cases where plants being estimated differ slightly from the basis for the correlations.
D
A
T
A
Facility Coefficient at EDPI = 1100
Exponent Adjustments
One-Stage Crude Distillation Unit Contains an atmospheric distillation column, side cut stripping, overhead stabilizer and splitter, and either a one-stage desalter and flash drum or a two-stage desalter without flash drum.
2.837 0.700 To delete the overhead stabilizer and splitter, subtract 14%.
For a two-stage desalter with a flash drum, add 3.6%.
Two-Stage Crude Distillation Unit Adds vacuum distillation to the one-stage unit; also includes vacuum off-gas compression or vent gas scrubbing.
4.073 0.700 To delete the overhead stabilizer and splitter, subtract 10%. For a two-stage desalter with a flash drum, add 2.5%.
Vacuum Distillation Unit
Stand-alone unit similar to the second stage of a two-stage crude distillation unit.
3.300 0.700 Cost of PRCP plant was about 35% higher than this curve.
Deethanizer Depropanizer Debutanizer Deisobutanizer
LSR Splitter (Depentanizer) Gasoline Splitter (Dehexanizer) - These are single-column units that
separate the named component and lighter hydrocarbons from heavier hydrocarbons. 1.505 1.505 1.216 2.837 1.216 1.042
0.600 Units have steam reboilers and water-cooled overhead condensers.
Light Ends Recovery Unit (LER)
Combination of deethanizer and depropanizer columns.
5.836 0.580 Cost of PRCP plant was about 11% higher than this curve.
Gas Recovery Unit (GRU)
An LER with the addition of a debutanizer column.
5.385 0.600
Merox Treating
- Light straight run gasoline or cracked naphtha - Kerosene/jet 1.170 1.505 0.560 0.560 Figure 202-15. Cost-Capacity Coefficients and Exponents: Distillation and Treating Units
D
A
T
A
Facility Coefficient at EDPI = 1100
Exponent Adjustments
Naphtha Hydrotreater
Mid-Distillate Hydrotreater (SR) Light Cycle Oil (LCO) Hydrofiner Vacuum Gas Oil (VGO) Desulfurizer
These units remove sulfur and nitrogen from the oil feed by reacting it with hydrogen. The naphtha hydrotreater and mid-distillate hydrofiner include com-pression for make-up hydrogen; the other units require a high pressure hydrogen supply. Units include reactor(s) and re-cycle hydrogen compression.
4.314 4.674 5.142 4.169 0.640 0.670 0.670 0.700 Naphtha hydrotreater:
No make-up compression, subtract 7%. No make-up or recycle compression ("once-through"), subtract 13%.
Rheniformer
The second stage of a traditional catalytic reformer (the first stage is a naphtha hydrotreater); includes four reactors and recycle compression, but no compression for product hydrogen.
5.469 0.650 Curve has been adjusted to include current metallurgy.
For 3 reactors rather than 4, subtract 8%.
Figure 202-16. Cost-Capacity Coefficients and Exponents: Hydrotreating and Reforming Units
Facility Coefficient at EDPI = 1100
Exponent Adjustments
Hydrogen Plant
Process uses steam-methane reforming to produce 95 to 97% pure hydrogen from 100 psig natural gas feed; high-pressure plants have steam turbine-driven shift gas compressors; product is delivered at 1700 psig; cost excludes catalyst. Capacity is millions of standard cubic feet per day (MMSCFD) of product hydrogen.
7.180 0.610 Cost of PRCP plant was about 6% higher than this curve.
For gas turbine drive on shift gas compressor, add 12%. For 900 psig product, subtract 10%. To produce 200-250 psig hydrogen, subtract:
For natural gas feed 21% For LPG feed 17% For naphtha feed 10%
Figure 202-17. Cost-Capacity Coefficients and Exponents: Hydrogen Manufacturing and Compression Units
D
A
T
A
Facility Coefficient at EDPI = 1100
Exponent Adjustments
Sour Water Stripper
Separates H2S from water; consists of a
reboiled stripper with a feed degasser and two injection systems; feed storage is off-plot and is excluded from the cost; capacity is gallons per minute (GPM).
The reboiler uses low pressure steam (40 -50 psig) which requires a condensate drum and pump.
The column overhead includes an air-cooled condenser with a reflux drum and reflux pump.
0.314 0.530 To delete feed sour water cooler, subtract 6%. To delete feed degasser and pumps, subtract 12%.
To delete stripped water (bottoms) trim cooler, subtract 9%.
To delete one injection system (anti-foam for column feed or corrosion inhibitor for column overhead), subtract 1%.
To delete the reboiler (and use live stripping steam), subtract 12%. To use 150 psig steam in the reboiler and delete the condensate drum and pump, subtract 6%.
To use water-cooled condensing and delete the reflux drum and pump (gravity reflux), subtract 5%.
Waste Water Treater (WWT)
Combines a sour water stripper with ammonia recovery facilities (a proprietary Chevron process); capacity is gallons per minute (GPM).
1.372 0.410
H2S Recovery
Amine (usually diethanolamine, or DEA) is used to absorb hydrogen sulfide from a gas stream; the plant contains a 50% capacity absorption column (with DEA being circulated to additional absorbers located in other process units); a regeneration column with steam reboiler and air-cooled condenser; and ammonia and caustic relief scrubbers on the overhead H2S product stream; the plant
capacity used in the cost correlation is thousands of pounds per hour of H2S
recovered.
3.821 0.550 For a 100% capacity absorber in this plant, add 10%.
For a water-cooled regenerator overhead condenser and non-pumped reflux, deduct 5%.
To delete the ammonia scrubber, subtract 10%.
To delete the caustic relief scrubber, subtract 5%.
To substitute ammonia for caustic in the relief scrubber, add 15%.
Figure 202-18. Cost-Capacity Coefficients and Exponents: Hydrogen Sulfide Removal and Sulfur Recovery
D
A
T
A
Facility Coefficient at EDPI = 1100
Exponent Adjustments
Fluid Catalytic Cracker (FCC)
Reactor, regenerator, and distillation section to maximize gasoline production.
18.123 0.600
Butane Isomerization
Normal butane feed is catalytically converted (approx. 60%) to isobutane. Plant includes mole sieve driers (for both butane and hydrogen feeds), reactors, and product stabilizer.
6.340 0.588
Figure 202-19. Cost-Capacity Coefficients and Exponents: Cracking and Alkylation
Facility Coefficient at EDPI = 1100
Exponent Adjustments
Delayed Coking
Includes coke drums, on-plot coke handling and product distillation and treating. Capacity is short tons per day of coke produced.
0.832 0.700 The correlation is based on a coke yield to feed rate ratio of 50 short tons per 1000 barrels; for a different ratio of coke yield to feed rate, multiply the calculated cost by
3.02 x
coke make, STPOD Feed rate, MBPOD
−0.281
Figure 202-20. Cost-Capacity Coefficients and Exponents: Other Processes
D
A
T
A
Cost-Capacity Coefficients and Exponents for Refinery Offplot Facilities
Figure 202-21 contains cost-capacity coefficients and exponents for offplot facilities. We originally developed this data from 1970s Chevron experience. We updated the data to 1991 (EDPI=1100) without further validation except for adjusting the correlations of boiler plants, cooling towers, and tankfields to match experiences of projects in the early 1980’s. Facility descriptions appear on the following pages.
Facility At EDPI = 1100 Capacity Units Cost Adjustments Coeff. Exponent
Boiler Plant 0.28 0.77 M lbs/hr1 plus 2.5 percent of Onplot Investment Cooling Tower
Over 10 M GPM 0.93 0.75 M GPM1 Under 10 M GPM 2.08 0.4 M GPM1 Electrical Distribution 1.22 0.7 M KVA1 Tankfields
Crude 16.8 0.8 MM Bbl2
Other (ex. sulfur, LPG) 34.7 0.8 MM Bbl2 Sulfur
(incl. loading rack)
0.17 0.8 M Bbl2 Butane 0.38 0.7 M Bbl2 Propane 0.46 0.7 M Bbl2 Interconnecting Pipeways 8 percent of Onplot Investment Site Development 0.078 1.0 Developed Acres
Relief System 2 percent of
Onplot Investment3 Marine Facilities
(Coastal Areas Only)
Grass Roots Refinery 25.9 0.25 MBPOD Crude to Refinery Existing Refinery 0.20 1.0 MBPOD Incremental Crude to Refinery Loading Racks
Marine Location 0.10 1.0 MBPOD Incremental Crude Throughput Inland Location 0.30 1.0 MBPOD Incremental Crude
Throughput Effluent Treating
(Grass Roots Refinery)
9.9 0.3 MBPOD Crude to Refinery
D
A
T
A
Use the data in Figure 202-21 in an equation of the form:
Cost ($millions, 1991) = Coefficient x (Capacity)Exponent
The costs are on a West Coast (Richmond) basis. Facility descriptions appear on the following pages.
If you can determine the offplot facility’s size, this method gives better results than using a percentage of onplot cost (see Section 211).
While the locations and projects vary for facilities in each type of offplot plant, the following information summarizes the scope nominally
included in these estimating correlations.
Boiler Plant
Oil-fired boiler(s), with BFW treating, BFW pumps, and deaerator A fuel system (day tank, pumps, and oil heater)
Air systems (utility and instrument air compressors and auxiliaries) The cost equation is for the boiler plant’s own facilities; the additive piece, based on a percentage of the process plant costs, allows for the cost of incremental BFW capacity to support onplot steam generation.
Cooling Tower
Tower and basin, with circulating pumps, main supply and return headers serving multiple plants, and minimal water treatment Pump drivers are motors or back-pressure steam turbines
To delete main supply and return headers, subtract 23 percent. To change to condensing turbines, add 10 percent for 600 psig or 17 percent for 40 psig steam.
Electrical Distribution
Medium voltage wiring and switches, emergency power systems, and communications
No transformers or motor control centers
Assumes that power company provides high-to-medium voltage sub-station, and that plant substations are included in individual plant costs
Tankfields
Tankage and associated facilities within the diked area Tankfield pipeways Transfer pumps
D
A
T
A
Blending/metering facilities
Excludes process/utility area pipeways Provides for multiple tanks in each category Pressurized, refrigerated LPG tanks, as appropriate The sulfur storage cost includes sulfur loading racks.
Interconnecting Pipeways
Pipeways in the vicinity of process and utility plants
Excludes cooling water and relief headers, and tankfield pipeways
Site Development Rough grading Filling Roads Paving Bridges
Simple railroad spurs Fencing
Minor landscaping
Relief System
Free-standing elevated flare with molecular seal Knockout drum and pump
Ground flare with water seals Vent gas recovery compressor Main offplot flare header
As an alternative to using a percentage of onplot costs, consider a lump-sum cost per flare system (see Figure 202-21, Note 3).
Marine Facilities
For coastal areas only; includes piping to/from the refinery Provides product wharves for two-thirds of the products
For grass-roots only; provides a single-point mooring for crude receiving
D
A
T
A
Loading Racks
Truck and/or rail loading racks for one-third of products (marine location) or 100 percent of products (inland location)
The cost of sulfur loading racks is included in the tankfield cost for sulfur storage.
Effluent Treating
Offplot gathering system for oily water and storm water Oily water separator(s) with skim pump
Air flotation system
Activated sludge or other BOD reduction system No tertiary treatment included
D
A
T
A
Factored Estimates
T
he simplicity of the factored estimate makes it useful—especially for Class 1 or 2
estimates—when you have little design information, but you can identify the
equipment items from process flow diagrams.
The Factored Method
Overview When making a factored estimate, you arrive at the total cost of the plant (excluding special charges, escalation, and contingency) by doing the following:
Estimating the cost of tagged process or utility equipment items (see Section 201)
Multiplying the total equipment cost by a single factor called the
installation factor
Information Needed You need to develop or obtain a list of the tagged process or utility equipment and to review the resources listed in Figure 203-1.
Applicability The factored method is
suitable for geographically confined facilities.
The quantities of piping, electrical, and other bulk materials for facili-ties such as process plants and boiler plants are related to the normal layout of plant equipment and process flow. Bulk materials include engineered items such as instruments and electrical switchgear and shop-fabricated materials such as pipe spools and structural steel.
For This Manual
Estimating Tagged Process or Utility Equipment Section 401-408 Adjusting to Richmond Cost (Sales Tax) Section 305 De-escalating to 1991; Adjusting to Current Date Section 301 Adjusting with Area Factors Section 311 Adding Special Charges Section 521
Adding Escalation Section 312
unsuitable for scattered offplot facilities.1
The quantities (and costs) of bulk materials for facilities such as pipe-ways, relief systems, or cooling water systems are independent of the equipment and, therefore, can vary widely between projects and locations.
of limited suitability for plant modifications.
The plot space available for new equipment items is usually not opti-mal from the standpoint of plant layout or process flow. As a result, the quantities of bulk materials may be abnormally higher than for a new plant.
Sources of Data These are the four types of factors:
Cost-related. Recommended factors are those used in this procedure.
See Figure 203-2.
Specific plant type and location. CRTC Facilities Engineering Unit
has historical data by process and location for a number of Chevron refineries and chemical plants.
Figure 203-2. Average Cost-Related Factors for Equipment Based on Chevron Data
Factors on this plot are derived from Chevron’s completed process plant projects.
The total equipment cost is the final purchased cost (including domestic freight and sales taxes).
The average equipment cost is the total equipment cost divided by the number of equipment items.
The installation factor is the total plant cost (excluding special charges) divided by the total equipment cost. To develop the average equipment cost in this plot, review the Guidelines for Counting Equipment Items at the end of this section.
Type of general process (liquid, solid, or liquid and solid). While
these factors appear in the literature, Chevron does not work with them.
Specific types of equipment (e.g., pumps or heat exchangers).
Chevron does not work with this type of factor; however, one of our major contractors arrives at a total plant cost by applying standard, equipment-specific factors to develop total direct cost, and project-specific ratios to add indirect field and home office (engineering and project management) costs.
Steps in a Factored Estimate
The steps in a factored estimate are discussed below using the example of an estimate made for a distillation unit at Pascagoula during the first quarter of 1992. See Figure 203-3 for an illustration of these steps.
1 ESTIMATE THE CURRENT COST OF THE EQUIPMENT
See Section 201, Estimating Major Material (Equipment) Costs. Include design allowance, domestic freight, and tax for the specific project location.
Use the subcontract price for field-erected equipment such as large columns.
Use the full (assembled) cost of packaged or skid-mounted equipment.
✎
Do not reduce the equipment cost for savings expected due to the purchase of foreign or used equipment; instead, use a new U.S. cost for factoring purposes. Adjust the estimate for any savings at step 9.Example
The Pascagoula distillation unit consisted of a column, reflux drum, reboiler, air-cooled condenser, and three pumps with spares. The
equipment cost was estimated as $1,535M, including design allowance, freight, and Mississippi taxes.
2 ADJUST THE COST TO A WEST COAST (RICHMOND) BASIS
This is principally a sales tax adjustment. Delete the local sales tax.
Add the Richmond sales tax.
Example
By substituting California’s sales tax for Mississippi’s, the estimated equipment cost becomes $ 1,637 M.
3 DE-ESCALATE THE TOTAL EQUIPMENT COST
De-escalate to 1991 (EDMI = 850) by multiplying the equipment cost by this ratio:
EDMI = 850 Current EDMI
Example
The 1992 estimate was made at an EDMI of 856.3, so the de-escalated cost is ($ 1,637 M) x 850/856.3 = $1,625 M. Estimate Current Cost of Equipment 1 Determine the Installation Factor 6
Adjust Cost (sales tax) to Richmond, CA
2
De-escalate the Total Equipment Cost
3
Count Equipment Items 4
Calculate Average Equipment Cost
5
Calculate Total Plant (Installed) Cost
7
Adjust the Estimate 9 Adjust to Current Data
8
Add Special Charges 10
Add Escalation 11
Add Contingency 12
4 COUNT THE NUMBER OF EQUIPMENT ITEMS
Use the Guidelines for Counting Equipment Items at the end of this section.
Example
There were 18 equipment items, including three shells for the reboiler and seven bays for the air cooler.
5 DIVIDE THE DE-ESCALATED TOTAL EQUIPMENT COST BY THE EQUIPMENT COUNT TO REACH THE AVERAGE EQUIPMENT COST
Example
Calculate the average equipment cost in 1991 as $1,625 M /18 = $ 90.3 M
6 DETERMINE THE INSTALLATION FACTOR
Use either Figure 203-2 or the following equation:
a = (33.6) x (b)-0.386
where
a = installation factor at EPDI = 1100 and EDMI = 850 (1991) b = average equipment cost in $M
Example
Using the equation, calculate the installation factor for 1991 as (33.6) x ($ 90.3 M)-0.386 = 5.91.
7 CALCULATE THE TOTAL PLANT (INSTALLED) COST IN 1991
Multiply the de-escalated equipment cost (step 3) by the installation factor (step 6).
Example
8 ADJUST THE TOTAL PLANT COST TO THE CURRENT DATE1
Use EDPI and multiply by the ratio:
Current EDPI EDPI = 1100
Example
The EDPI at 1Q92 was 1116 so the plant cost was calculated as ($ 9,600 M) x (1116/1100) = $ 9,740 M.
9 CORRECT THE ESTIMATE
Re-adjust sales tax (step 2) to return to a real-site basis.2
Adjust for savings for foreign or used equipment by subtracting the incremental cost for new equipment, including freight and tax differentials.
Adjust for plant modifications (see Cautions following step 12). Adjust for duplication savings.3
Adjust area factor considerations such as piling, winterization, or labor productivity (see Section 311).
Example
The area factor for Pascagoula in 1992 was estimated as 0.95 relative to Richmond, including the difference in sales tax. The adjusted cost became ($ 9,740 M) x 0.95 = $ 9,250 M, or $9.3 M.
10 ADD SPECIAL CHARGES SUCH AS OCEAN FREIGHT, CATALYST, AND G&A (SECTION 521)
Example
The combination of Mississippi’s Contractor Gross Income Tax and the 1992 G&A rate for Pascagoula added $200 M for a new total of $9.5 M.
1 The current EDPI should be for the same time period as the current EDMI in step 3.
2 Note that, in most locations, sales tax applies only to material, and that material might represent only 48 percent (Section
603) of the estimate.
3 If a contractor designs multiple, identical plants concurrently, efficiencies in engineering and procurement can reduce the
costs of the second and subsequent plants by 10 percent. These savings may apply even if the plants are constructed at different locations.
11 OPTIONAL — ADD ESCALATION
If you need a then-current estimate, add escalation based on the anticipated schedule for the project (see Section 312).
Example
No escalation was considered. This estimate was reported in 1992 constant dollars.
12 ADD CONTINGENCY (SECTION 313)
The result of these steps is an onplot (battery limits) estimate only. Estimate any offplot requirements separately.
Example
For this Class 1 estimate of a conventional technology plant, the estimator selected a contingency of 37 percent, yielding a total onplot estimate of $13 M.
Cautions
Extrapolation. Do not extrapolate the curve beyond the plotted points
in Figure 203-2. The curve may flatten for low average equipment costs, resulting in installation factors probably not exceeding 9 or 10. Obviously, the factor cannot drop as low as 1.0 for higher-than-average equipment costs.
Complete Plants. As this method is based on actual costs for
complete new facilities with a mixture of equipment types, the factors shown in Figure 203-2 are most directly applicable to estimating similar plants.
You can, however, apply the method with a reasonable degree of accu-racy to individual equipment items (e.g., adding or deleting items for a proposed plant before it is built).
Alloy Equipment. The data for the curve came from normal refinery
and chemical process plants that have a limited amount of alloy equipment and piping. For plants with large amounts of alloy equip-ment and piping, the factored curve (equation) should still work—the average equipment cost being higher and the factor lower because the cost of most bulks (other than piping), labor, and indirects do not vary from those of a carbon steel plant. Since we have no data to verify this assumption, consider the factored method less accurate for a plant with extensive alloy materials.
Modifications. For modifications to existing plants, installation
factors may be higher or lower than for new plants. Generally, they are higher due to inefficient plant layout, dismantling, delays, work restrictions, shutdown work, and so on.
For rough estimates, apply the factored method and adjust the cost at step 9. Increase the labor cost to reflect poorer productivity due to con-gestion, work restrictions, etc. If, for example, you assume labor and related field indirect costs to be 34 per cent of the total (section 603) and anticipate 50 percent more labor hours, then increase the plant cost by 17 percent, as follows:
(0.34) x (1.50) + (1 - 0.34) = 1.17
Using the semi-detailed method covered in Section 205, estimate the direct and indirect costs (including productivity effects) for extra piping, electrical, and other bulk materials necessary because of inefficient location of the new equipment in the plant. Then estimate any dismantling costs, both permanent and temporary, for construction access.
Unusual Construction Features. Estimates for plants in a building or
with extensive vertical structures, jacketed or refractory-lined piping, sophisticated or redundant instrumentation, or concrete storage pits require larger installation factors than normal plants. Multiple-train plants have slightly smaller installation factors from savings through duplication. If storage tanks are included onplot, the installation factor is smaller than for a normal process plant.
Guidelines for Counting Equipment Items
The following counting rules were used to create Figure 203-2 so they should also be used when making an estimate. Fortunately, the results are not very sensitive to the equipment count. (A ten percent variation in equipment count changes the installation factor by only four percent.)
Do Count
Count the following items as one each:
Each reactor, column, or pressure vessel (even if stacked or with a common internal head). Be sure to count relief, fuel gas knockout, condensate flash, condensate receiver, blowdown, and steam separator drums.
Each heat exchanger or cooling tower. Each shell for shell-and-tube exchangers. Each bay for air-cooled exchangers.1
Each stack of double-pipe exchangers if there is more than one stack per service.
As one item, each set of external plate heat exchangers for one vessel or other equipment item.
Each bayonet-type exchanger.
Each furnace, boiler, in-line burner, or combustor. Each pump and each installed spare.
Each compressor and each installed spare, blower, fan, filter, mixer, agitator, venturi scrubber, cyclone, crusher, ball mill, belt or screw conveyor or feeder, weigh feeder, vibrating feeder or screen, bag house, large dust collector with fan, coke handling bucket crane, etc. Equipment used for batch operations, if permanently installed.2
Do Not Count
The following items are included in the equipment cost but not the count when deriving the average cost per piece of equipment:
Drivers (motors, steam or gas turbines, power recover turbines, diesel engines, etc.)
Items furnished as part of a package3
Items that can be considered an integral part of another item Bag house fans
Boiler and furnace fans, coils, steam and mud drums, stacks, preheaters, and stack gas treating equipment
Column, vessel and tank internals, heating coils, jackets, and floating roofs
Gas turbine inlet and exhaust facilities
Silencers and inlet air filters for blowers and compressors
1 A bay is generally limited to about 600 square feet of bare surface per tube row; e.g., for six tube rows, divide total bare
surface by 3,600. If more than one service per bay, count each service.
2 For example, for delayed coker plants, count each hoist and each power swivel for coke drum drill stems and each
unheading cart, cutting tool dolly and switch valve.
3 A “package” consists of two or more equipment items mounted on a skid or module, with substantial amounts of piping
and other bulk materials already installed. At estimating time, it is not usually known whether a package will come on one or more skids; therefore, count a package as one item even if it comes on more than one skid. Note that some systems are