AN INFORMATION GUIDE
Joint Provisioning Guidelines for Shallow Utility Services in Residential Areas where the Electric, Gas, Telephone & Cable TV facilities are Buried in the same
Trench in the City of Calgary
SCOPE
ENMAX Power Corporation, ATCO Gas, SHAW Cablesystems and TELUS Communications underground residential distribution (URD) facilities in new subdivisions (for single-detached and semi-detached dwellings) are in a common trench in the City of Calgary.
This pamphlet provides guidelines for developers and home builders regarding the provisioning of those shallow utility facilities.
It provides information on: Who is responsible for what The process
Main and Service trench configurations
Utility wall configurations Minimum clearances of gas
meter from windows, vents, etc.
CONTACT
John Thiessen
Tel: (403) 514-2070
Email: [email protected]
PROJECT MANAGER
The four shallow utilities have entered into an agreement with ENMAX Power Services
Corporation as the 4-Party Project Management Consultant responsible for carrying out the work for URD main trench joint use construction on their behalf.
ENMAX Power Services currently contracts its survey, construction and civil inspection activities to subcontractors.
JOINT PROVISIONING BENEFITS
For the Utilities:
Safer product; cost reduction Reduced damages during initial
construction and installation Gas workers do not have to
work around energized power cables
More accurate facility locates For the Developers and Builders: Faster service
URD Main Trench Joint Provisioning Process
Scheduling Construction Administration
Design Developer submits subdivision plans to shallow utilities
Shallow utility planners send designs / quotes
to Developer Developer approves designs / quotes Utilities issue work packages to the Project Manager No Yes Project Manager schedules construction work To Construction Process Project Manager confirms project site ready date
Project Manager conducts pre-construction meeting Construction Contractor completes trench construction Construction Contractor completes utility facility placement To Administration Process Project Manager conducts post-construction meeting Project Manager allocates costs to the utilities Project Manager receives Construction Contractor invoice Project Manager pays Construction Contractor Project Manager issues invoices to the Utilities and Developer
DEVELOPER INFORMATION
To start the URD provisioning process, the Developer provides the following information and plans to ENMAX Power and the other shallow utilities:
Two copies of the subdivision tentative legal plan
An autocad diskette with the subdivision digital information Easement plan
Deep utility plans Sidewalk cover sheet Overland drainage plan Shallow utilities plan Driveway plan Grade plan
Indication of the size of the electrical services
(i.e. 100A or 200A)
Indication of extra electrical coil length where required
(i.e. more than 25m) Tentative in-service date
PROJECT & SITE READY DATE
The project is ready for construction of the shallow utility infrastructure when the following criteria are met: Developer’s Consultant has
approved all shallow utility final designs, and the plans have been received by the 4-Party Project Manager
Deep services are completed Site is within 150mm of final
grade
Developer’s Consultant requests start (option of shallow utility construction before or after surface improvements)
Developer has met all required shallow utility financial
obligations
Any significant Developer-initiated revisions to the approved final shallow utility designs will be chargeable to the Developer, and may result in the project losing its position in the construction queue. In the event that frozen ground conditions are encountered, the Developer is required to provide the equivalent of frost-free conditions for the installation of the shallow utility infrastructure.
CONSTRUCTION OBJECTIVES
It is expected that the construction of the shallow utility (mains)
infrastructure will be completed within a six-week window after the project site ready date.
The site is then available for commencement of house building and the provisioning of the shallow utility service lines to the dwelling. The Developer is responsible for any incremental costs within the six-week window caused by early building starts, obstructions in the utility rights-of-way, etc. The shallow utilities will be responsible for the above incremental costs in the event that the shallow utility construction extends beyond the six-week window.
URD SERVICE TRENCH STANDARDS & RESPONSIBILITES
Service Trench Standards Minimum depth of 1 metre
below grade level from the service stub out to the foundation excavation, then angled down to the foundation footing level
The electric, telephone and cable TV cables are to be
placed in rigid conduit of 2 inch, ¾ inch and ¾ inch minimum respectively, and the gas line will be placed in a ¾ inch sleeve; all of which are to rest on the foundation footings at the point where the vertical risers extend to the meter or service connection locations
Conduits are to be sealed at the easement end, and vented at the house
A 30 cm separation is
maintained between the gas line and the cables from the stub out location at the edge of the easement up to the base of the foundation; the conduits may be bundled together along the foundation for added strength and protection
Service trench is to be backfilled with good earth backfill to grade level
Service Trench Responsibilities Builder’s contractor excavates
the service trench from the house to the service stub-out at the easement
Builder’s electrical contractor installs the electric and
telephone conduits, and installs the electric cable in the electric conduit
TELUS installs the telephone cable in the telephone conduit SHAW’s contractor installs the
cable TV conduit and cable ATCO Gas’ contractor installs
the sleeved gas line facility Builder’s contractor backfills the
service trench
Service Connection Responsibilities ENMAX crew installs the
electrical meter and energizes the service
ATCO Gas’ contractor installs the gas meter
TELUS crew installs the telephone service connection SHAW crew installs the cable
URD SERVICE TRENCH CONFIGURATION P C T G
Service Trench
Configuration
(Down to Footings)
M
ain
T
ren
ch
Electric,
Telephone
& Cable TV
Cables
Gas Line
Service
Stubs
Meters &
Service
Connections
Foundation
Excavation
Bundled Conduits
Resting on the
Foundation Footings
G T C P 700 mm 250 mm 200 mm 400 mm 1600 mm to 1800 mm 16 in 30 in 10 in 8 in 5 ft to 6 ft
Utility Wall
(Gas Meter on Left Side)
(Minimum Distances)
(To Service Trench)
Base PlateGrade Level
C T P G 400 mm 16 in 1600 mm to 1800 mm 5 ft to 6 ft 300 mm 250 mm 200 mm 8 in 10 in 12 in
Utility Wall
(Gas Meter on Right Side)
(Minimum Distances)
(To Service Trench)
Base PlateGrade Level
Foundation Footing
Note: Please contact ATCO Gas if this layout does not meet the Builder’s needs.