TO: OFFICE OF THE PROVOST AND SVP, ACADEMIC AFFAIRS J. EMMETT WINN, ASSOCIATE PROVOST FOR FACULTY AFFAIRS SUBJECT: MONTHLY PROJECT STATUS REPORT

DATE: 09/01/2021

Please find attached this month’s status report for all projects related to your office that are currently being managed by Facilities Management.

If you have any questions or comments about these reports or any of the projects contained therein, please let us know.

D. Scott Fuller

Assistant Vice President, Client Relations (334) 844-7379

scott.fuller@auburn.edu Dan Berry

Program Manager, Project Support / Planning, Design, & Construction (334) 844-9115

berrycd@auburn.edu

ADDITIONAL INFORMATION:

For the purposes of this report, the OFFICE OF THE PROVOST client group currently includes the following:

Office of the Provost and Senior Vice President for Academic Affairs, Associate Provost for Faculty Affairs, VP and Associate Provost for University Outreach, VP and Associate Provost for Inclusion & Diversity, Associate Provost for Academic Effectiveness, VP for Research and Economic Development, Assistant VP for Strategic Initiatives and Communications, Graduate School, and Institutional Research.

However, separate reports are issued for the University Libraries, the Office of Accessibility, and each of the primary Colleges and Schools.

HELPFUL FACILITIES MANAGEMENT LINKS (press Ctrl while clicking the links below to open in your web browser):

AU Facilities Management - Home Page

AU Facilities Management - Organizational & Contact Information AU Facilities Management - Project Request Form

AU Facilities Management - Maintenance Work Order Request (ReADY)

AU Facilities Management - Major Construction Projects, Upcoming and Under Construction AU Facilities Management - Major Construction Projects, Published Construction Updates AU Facilities Management - Temporary Road Closures and Other Campus Disruptions AU Facilities Management - Seasonal (Summer or Holiday) Construction Map AU Interactive Campus Map - Building Info & Floor Plans

F A C I L I T I E S M A N A G E M E N T

C

L I E N T

R

E L A T I O N S

/ P

L A N N I N G

, D

E S I G N

& C

O N S T R U C T I O N M E M O R A N D U M

(2)

Client Projects (by Phase)

PROVOST AND ACADEMIC AFFAIRS Total Projects: 33 PROGR.: 12 CONSTR.: 3 HOLD_SCOPE: 0 Total Approved Budgets: $163,326,795 DESIGN: 9 CLOSEOUT: 8 HOLD: 1

PROGRAMMING 12 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

19-565 D: Judd Langham

C: Andrew Spurlin

JC Smith Museum Of Art - North & South Garden Renovations Status: SCOPING

Phase:PROGRAMMING

11/18/19 B: 1/14/20 E:1/15/20 A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

6/21/21 Judd Langham

Schedule: Fall Proposed Budget: T.B.D.

Previous Task: Continue inventory and analysis, initiative concept designs. Coordinate with Landscape Services to determine minor improvements.

Current Task: Discussing next steps with JCSM staff

Next Step: Develop preliminary planting plan for both courtyard gardens. Coordinate with Landscape Services and JCSM staff to determine next steps.

20-378 D: Mary Melissa Taddeo C: Nicholas Nowlin

STEM & Agricultural Sciences Complex - New Facility Status: PROGRAMMING

Phase:PROGRAMMING

8/10/20 B:

E:5/26/21 A:

$8,287,410 B:

E:

A:

B:

E:5/2/22 A:

B:

E:6/1/22 A:

B:

E:6/3/23 A:

Grp: OUA

8/16/21 Mary Melissa Taddeo

SCHEDULE: Programming deliverable anticipated 8/20. Schematic Design begins 8/23.

BUDGET: Budget increased to $165-M TPC per July EFC meeting.

CURRENT TASK: OA amendment draft

NEXT STEP: Pull plan, TVD targets and schedule workshops with JE Dunn; schedule user group meetings for SD-DD

21-154 D: Mary Melissa Taddeo C: Jonathan Tucker

Dawson Building - Renovate For Use By The Early Learning Center Status: PROGRAMMING

Phase:PROGRAMMING

4/6/21 B:

E:

A:

$300,482

B:

E:

A:

B:

E:12/9/21 A:

B:

E:1/3/22 A:

B:

E:6/24/22 A:

Grp: OUA

8/16/21 Mary Melissa Taddeo

Budget: Anticipated $2.5M+. Design-only budget approved. PO for Survey issued.

Schedule: November BOT meeting; bid date 11/18/21. DCM initial submission complete.

Current Task: Weekly meetings with design team; OA agreement being finalized through Project Support. PSC for cost estimation routing.

Next Task: Schedule user group, AU unit meetings.

(3)

denotes "Client Priority Projects" Client Projects (by Phase)

PROVOST AND ACADEMIC AFFAIRS Total Projects: 33 PROGR.: 12 CONSTR.: 3 HOLD_SCOPE: 0 Total Approved Budgets: $163,326,795 DESIGN: 9 CLOSEOUT: 8 HOLD: 1

PROGRAMMING 12 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

21-155 D: Whitney Brock

C: Hank Moreman

Research Park Bldg 1 - 2nd Floor, Renovate For Use By CHEER & The MFT Center

Status: PROGRAMMING Phase:PROGRAMMING

4/6/21 B:

E:

A:

$22,860

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

8/24/21 Whitney Brock

Budget: Tentative $1,500,000

Schedule: On schedule to move tenants May 2022.

Current Task: SNA has completed schematic layout of spaces. Design review with end users 8/24-8/30. Stakeholder meeting set up for 9/2 to finalize lease/project and construction schedules. Conway and Owen reviewing mechanical plans for accuracy.

Next Task: Complete CDS- 8/31-9/24 for DCM final review 9/27-10/15. Will need to submit for November BOT.

21-312 D: Contina Mccall C: Hank Moreman

Foy Hall - 2nd Floor Lobby, Additional Workstations For International Programs Status: PROGRAMMING

Phase:PROGRAMMING

7/6/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

8/23/21 Contina Mccall

Budget: Not developed.

Schedule: Not developed.

Current Task: Furniture dealer developing furniture quote.

Next Step: Use quotes to develop a project budget.

21-334 D: Nicholas Blair C: Tyler Hand

Whitten House - New Concrete Pad For Back Porch Area Status: PROGRAMMING

Phase:PROGRAMMING

7/19/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

21-346 D: Contina Mccall C: Hank Moreman

Haley Center - Rm 1439, Renovate & Convert Into A Pride Center Status: PROGRAMMING

Phase:PROGRAMMING

7/22/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

8/23/21 Contina Mccall

Budget: Not developed.

Schedule: Not developed.

Current Task: Developing scope of work.

Next Step: Submit scope of work for estimating.

(4)

Total Approved Budgets: $163,326,795

PROGRAMMING 12 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

21-366 D: Sarah Rakestraw

C: Hank Moreman

Haley Center - Rms 2238 & 2240, Interior Refurbishments For Academic Support

Status: PROGRAMMING Phase:PROGRAMMING

8/2/21 B:

E:8/25/21 A:

B:

E:

A:

B:

E:

A:

B: 1/3/22 E:10/2/21 A:

B:

E:12/1/21 A:

Grp: OUA

8/27/21 Sarah Rakestraw

Budget: in progress Schedule: TBD

Current task: preliminary design - meeting with client 08.27

Next steps: confirm design plans with client, submit scope for estimating

21-399 D: Contina Mccall C: Hank Moreman

Samford Hall - Suites 213 & 215, Interior Refurbishments & New Furnishings Status: PROGRAMMING

Phase:PROGRAMMING

8/17/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

COVID-19 8/23/21

Contina Mccall

Budget: Not developed.

Schedule: Not developed.

Current Task: Developing scope of work.

Next Step: Review scope of work with Client. Submit scope of work for cost estimating.

21-407 D: Contina Mccall C: Hank Moreman

Nichols Center - Rms 115 & 116, Restroom & Shower Renovations Status: PROGRAMMING

Phase:PROGRAMMING

8/18/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

8/23/21 Contina Mccall

Budget: Not developed.

Schedule: Not developed.

Current Task: Scope of work submitted for JOC cost estimate.

Next Step: AUFM to review JOC estimate. Develop project budget and schedule.

21-411 D: Contina Mccall C: Hank Moreman

Nichols Center - Rm 126, Renovate & Convert Storage Area Into Classroom Space

Status: PROGRAMMING Phase:PROGRAMMING

8/19/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

21-416 D: Bradley Prater University Outreach - Space Needs Assessment & Utilization Study 8/23/21 B: B: B: B: B:

(5)

denotes "Client Priority Projects" Client Projects (by Phase)

PROVOST AND ACADEMIC AFFAIRS Total Projects: 33 PROGR.: 12 CONSTR.: 3 HOLD_SCOPE: 0 Total Approved Budgets: $163,326,795 DESIGN: 9 CLOSEOUT: 8 HOLD: 1

DESIGN 9 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

19-597 D: Walker Davis

C:

Nichols Center - New Security Camera System Status: CONST CONTR

Phase:DESIGN

12/13/19 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: PRSUP

20-554 D: Mary Melissa Taddeo C: Joshua Conradson

Hood-McPherson Building (Bham) - Comprehensive Renovation Status: DESIGN

Phase:DESIGN

12/14/20 B: 3/9/21 E:3/9/21 A:3/9/21

$1,640,850 B:

E:

A:

B: 1/25/22 E:1/25/22 A:

B:

E:

A:

B: 3/25/23 E:3/25/23 A:

Grp: OUA

8/16/21 Mary Melissa Taddeo

Budget: Full design budget approved.

Schedule: On schedule. Design to be completed by end of 2021, Construction to be completed early 2023.

Current Task: Design development deliverable ETA 08/19/21. Will be submitted for pricing.

Next Task: Consultant contract amendment #1; review and reconcile budget estimates. Prepare for DRC and EFC meetings in September.

21-084 D: Sarah Rakestraw C: Daniel Dix

Nichols Center - Rms 141 & 151, New Furnishings For Army ROTC Classrooms Status: DESIGN

Phase:DESIGN

2/23/21 B:

E:3/15/21 A:

$48,519

B:

E:

A:

B:

E:5/3/21 A:5/3/21

B:

E:5/3/21 A:5/3/21

B: 5/28/21 E:5/20/21 A:5/20/21

Grp: IHC

8/27/21 Sarah Rakestraw

Budget: In budget; $1675 remains Schedule: on schedule

Current Task: Pending roller shades installment, ordered 08.25 Next Step: FF&E installation, financial closeout.

21-129 D: Whitney Brock C: Daniel Dix

Biggio Center - Multiple Relocations & New Furnishings Status: DESIGN

Phase:DESIGN

3/22/21 B: 4/2/21 E:3/30/21 A:3/30/21

$130,000

B:

E:

A:

B:

E:

A:

B: 3/30/21 E:3/30/21 A:3/30/21

B: 5/28/21 E:5/29/21 A:

Grp: OUA

8/24/21 Whitney Brock

Budget: $130,000

Schedule: Behind Schedule- supply issues/noise complaints

Current steps: Foy 305 and 306: HVAC/Noise complaints from new occupants. Bob Hix created plan to modify HVAC to minimize noise transfer. Awaiting AMCO estimate. Foy 312: Card Access Reader parts have arrived- to be installed week of 8/30.

Next Steps: HVAC modifications. RM 312 Card Reader completion.

(6)

Total Approved Budgets: $163,326,795

DESIGN 9 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

21-156 D: Whitney Brock

C: Hank Moreman

Foy Hall - Suites 136, 144 & 145, Renovate For Use By The EAGLES Program

Status: DESIGN Phase:DESIGN

4/6/21 B:

E:

A:

$64,787

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

8/24/21 Whitney Brock

Budget: Estimated $500,000

Schedule: Schedule to complete by Dec 2021

Current Task: SNA sent plans to DCM for preliminary review on 8/23. Bluebeam review for Facilities 8/24-8/31. Finish selections with end users. Getting estimates for construction per plans.

Next Task: Complete CDS- for DCM final review. IHC to begin ordering long lead items and prep for construction.

21-255 D: David Robison C:

Statewide - ACHE Facilities Inventory For 2021 Status: STUDY

Phase:DESIGN

6/2/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

21-326 D: Benjamin Burmester C:

Auburn Research Park - Master Plan Update Status: STUDY

Phase:DESIGN

7/14/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

7/28/21 Benjamin Burmester

Schedule: No schedule. ARTF leading project.

Budget: N/A. ARTF lead project.

Current Status: Providing existing campus data to consultant team Next Steps: N/A

21-335 D: Hank Moreman C: Hank Moreman

Haley Center - Rm 2240, New Door & Card Access System Status: DESIGN

Phase:DESIGN

7/19/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: IHC

8/31/21 Patrick Ledbetter

WPL 8/31/2021

Access Control Worksheet is currently with Access Control. Awaiting response for Jobsite evaluation meeting.

21-344 D: Sarah Rakestraw JC Smith Museum Of Art - Main Lobby, Reception Area Renovations 7/22/21 B: B: B: B: 9/25/21 B: 9/25/21

(7)

denotes "Client Priority Projects" Client Projects (by Phase)

PROVOST AND ACADEMIC AFFAIRS Total Projects: 33 PROGR.: 12 CONSTR.: 3 HOLD_SCOPE: 0 Total Approved Budgets: $163,326,795 DESIGN: 9 CLOSEOUT: 8 HOLD: 1

CONSTRUCTION 3 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

15-034 D: Bradley Prater

C: Nicholas Nowlin

Academic Classroom & Laboratory Complex (ACLC) - New Facility Status: CONSTRUCTION

Phase:CONSTRUCTION

2/10/15 B:

E:11/16/15 A:11/16/15

$83,000,000 B:

E:10/31/19 A:

B: 3/21/19 E:3/21/19 A:3/21/19

B: 5/13/19 E:5/13/19 A:5/13/19

B: 4/16/22 E:4/16/22 A:

Grp: CPM

8/13/21 Nicholas Nowlin

BID PACKAGE-2 ACLC GENERAL WORKS

Schedule: On schedule, (NTP) 3.30.20 (SC) 4.15.22 - Through CO # 14 Budget: On budget.

Current Task: Site wall footings are complete and being waterproofed on the North elevation. Curtain wall is ongoing and permanent dry-in is scheduled to be accomplished 9.3.21. Roofing is complete less the expansion joint. Fall protection install is ongoing. Level 1 In wall and ground floor is completed and drywall / insulation has began. Overhead mechanical and electrical is ongoing on all floors with heavy concentration on the overhead work in the machinal level which will be on going through mid Sept. Medium and low pressure duct will continue until December.

Next Step:

Install fire pump, continue with overhead rough-in. Finalize building permanent dry-in and prep for metal panel installation in October. Complete site wall brick and install electrical transformer. Permanent power is scheduled for 9.13.21. Ground level overhead inspection is scheduled for 8.20.21, Level 2 in wall inspection CL 1-9 is scheduled for 9.7.21 Level 1 Overhead CL 1-12 is 9.17.21, Level 1 Overhead CL 12 - 24 is 10.4.21.

20-387 D: Nicholas Blair C: Nicholas Blair

JC Smith Museum Of Art - New Playground Shade Structure & Outdoor Benches

Status: CONSTRUCTION Phase:CONSTRUCTION

8/17/20 B: 12/9/20 E:12/9/20 A:

$42,430

B:

E:

A:

B: 4/13/21 E:4/13/21 A:4/13/21

B: 8/16/21 E:8/16/21 A:8/16/21

B: 9/15/21 E:9/15/21 A:

Grp: CPM

8/12/21 Nicholas Blair

Budget: Budget is sufficient.

Schedule: The NTP date has been set to August 16th to coincide with shipment of the materials to JA Lett.

Current: Material lead time.

Next Step: NTP August 16th

21-272 D: Contina Mccall C: Joe Moody

Melton Student Center - Suites 2101 & 2103, Renovations For CCCE Status: BUYOUT

Phase:CONSTRUCTION

6/10/21 B:

E:

A:

$21,824

B:

E:

A:

B:

E:8/6/21 A:8/6/21

B:

E:8/6/21 A:

B:

E:10/5/21 A:

Grp: IHC

7/16/21 Contina Mccall

Budget: DRAFT Budget developed for discussion with the Client.

Schedule: Not developed.

Current Task: Finalize the scope of work and budget package.

Next Step: Receive signed budget and proceed with the required work.

(8)

Total Approved Budgets: $163,326,795

CLOSEOUT 8 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

15-158 D: David Bess

C: Joshua Conradson

Gogue Performing Arts Center - New Building Status: WARRANTY/CLOSEOUT

Phase:CLOSEOUT

6/8/15 B:

E:10/5/15 A:

$69,600,000 B:

E:7/18/17 A:

B: 7/20/17 E:7/20/17 A:7/20/17

B: 8/14/17 E:8/14/17 A:8/14/17

B: 8/14/19 E:8/19/19 A:8/20/19

Grp: CPM

8/23/21 Joshua Conradson

Budget: In budget.

Schedule: Project is substantially complete.

Current Task: Working through warranty items and addressing final Day 2 change requests.

Next Step: Project closeout.

19-039 D: Mary Park C:

Extension Hall - Window Replacements & Repairs Status: WARRANTY/CLOSEOUT

Phase:CLOSEOUT

1/22/19 B: 3/1/19 E:2/28/19 A:2/28/19

$8,200

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

7/27/21 Mary Park

Current Task: Closeout

19-471 D: Chris Murphy C: Patrick Ledbetter

Office Of Accessibility - Various Bldgs, Accessibility Improvements For FY20 Status: WARRANTY/CLOSEOUT

Phase:CLOSEOUT

10/4/19 B: 11/13/19 E:11/13/19 A:

$64,413

B:

E:

A:

B: 4/15/20 E:4/15/20 A:4/15/20

B: 8/16/20 E:6/8/20 A:2/19/21

B: 8/16/20 E:9/30/20 A:9/30/20

Grp: IHC

8/31/21 Patrick Ledbetter

WPL 8-31-21 Budget : In Budget Schedule : On Schedule

Current Status: All projects are complete.

Next Step: Financial closout

20-283 D: Bradley Prater C:

Cater Hall - COVID-19 Compliance, Signage & Improv. Study For Honors College

Status: WARRANTY/CLOSEOUT Phase:CLOSEOUT

6/26/20 B: 8/6/20 E:8/11/20 A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: OUA

COVID-19 1/27/21

Bradley Prater

SCHEDULE: N/A BUDGET: No budget CURRENT TASK: Complete NEXT STEPS: Complete

(9)

denotes "Client Priority Projects" Client Projects (by Phase)

PROVOST AND ACADEMIC AFFAIRS Total Projects: 33 PROGR.: 12 CONSTR.: 3 HOLD_SCOPE: 0 Total Approved Budgets: $163,326,795 DESIGN: 9 CLOSEOUT: 8 HOLD: 1

CLOSEOUT 8 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

20-383 D: Patrick Ledbetter

C: Patrick Ledbetter

JC Smith Museum Of Art - Basement, Provide Card Access Between Corridors C004 & C001

Status: WARRANTY/CLOSEOUT Phase:CLOSEOUT

8/14/20 B:

E:

A:

$14,520

B:

E:

A:

B: 9/28/20 E:9/28/20 A:9/28/20

B: 12/7/20 E:12/7/20 A:12/14/20

B: 1/22/21 E:1/22/21 A:1/15/21

Grp: IHC

8/31/21 Patrick Ledbetter

WPL 8/31/21 Budget ; In Budget.

Schedule: On Schedule

Current status: Work is now complete. We have replacement materials on order.

Nextstep: Financial closeout

20-430 D: Walker Davis C: Walker Davis

JC Smith Museum Of Art - Various Rooms, New Office Furnishings & Casework Status: WARRANTY/CLOSEOUT

Phase:CLOSEOUT

9/21/20 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: PRSUP

21-032 D: Sarah Rakestraw C: Sarah Rakestraw

JC Smith Museum Of Art - Grand Gallery, New Window Treatment System Status: WARRANTY/CLOSEOUT

Phase:CLOSEOUT

1/27/21 B:

E:4/22/21 A:4/22/21

$64,600

B:

E:

A:

B:

E:5/14/21 A:5/14/21

B:

E:5/17/21 A:5/17/21

B:

E:6/11/21 A:6/11/21

Grp: OUA

8/27/21 Sarah Rakestraw

Budget: funded $8971 remains Schedule: on schedule- work complete.

Current Task: new punch items: shades catching and fraying when lowered, ETI/Mecho shades to address (contract holders) Next Steps: close project

21-103 D: Perry Wood C: Perry Wood

Research Park Bldg 1 - Suite 202, Paint Interior Walls Status: WARRANTY/CLOSEOUT

Phase:CLOSEOUT

3/8/21 B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

B:

E:

A:

Grp: MAINT

(10)

Total Approved Budgets: $163,326,795

HOLD 1 Projects

B: = Baseline Date E: = Estimated Date A: = Actual Date

Project Num D = Design Lead

C = Construction Lead

Project Name Project

Initiation

Budget Approved

Final Design

Bid Date

Notice to Proceed

Substantial Completion

21-046 D: Sarah Rakestraw

C: Daniel Dix

Foy Hall - Suite 118, Interior Refurbishments & Furnishing Reconfigurations Status: HOLD

Phase:HOLD

2/5/21 B:

E:2/24/21 A:2/24/21

$15,900

B:

E:

A:

B:

E:4/2/21 A:4/2/21

B:

E:4/2/21 A:

B:

E:5/31/21 A:

Grp: OUA

8/27/21 Sarah Rakestraw

Budget: $2867 remains

Schedule: occupants are in space, substantially complete

Current Task: Pending final punch with IHC - still waiting on IHC to resolve punch items: glass board placement, and touch up paint. Working with clients on addition of branding vinyl to corridor and gta space.

Next Step: design branding package

References

Related documents

The results revealed four central features of teacher–infant social exchange: (i) infants were more likely to respond to teachers interaction initiations when teachers used verbal

One way is to pool procurement resources together (horizontal collaborative procurement) in a bid to benefit from economies of scale, gain stronger negotiation power,

Word embedding methods are used to map words to numeric vectors which can be used for computation.There are 4 ways in this thesis to do word embedding, which is doc2vec, word2vec,

Arresting the control lever of incoming gas valve in the working position.. Packaging:

This Final Assessment Report contains the Implementation Plan (Appendix C) developed by the Director of the Norman Patterson School of International Affairs and agreed to by the

The fractional change in the divider ratio is smaller than δ by a factor of the (small) divider ratio itself. Since the thermistor resistance ranges from about 0.5KΩ to 2.5KΩ

Provost and Senior Vice President for Academic Affairs Hofstra University.. Panelists Professor

Tháng này trong tạp chí Golden Age chúng tôi muốn chia sẽ vài mẹo vặt để làm cho cuộc sống của chúng ta dễ dàng hơn khi về già. Đây là một vài cách để công dân

Vice Provost for Academic Affairs and Undergraduate Programs 2014 - 2017 Interim Vice Provost for Academic Affairs and Undergraduate Programs 2013 – 2014 As Vice Provost, I

platí pre všetky výstavy Mesiaca fotografie v SNM/ valid for all Month of Photography exhibitions in SNM Kontakt / Contact +421 2 20 46 92 12 www.snm.sk Vernisáž / Opening 3..

Global, regional, and national incidence, prevalence, and YLDs for 301 acute and chronic diseases and injuries for 188 countries, 1990-2013: a systematic analysis for the

The Provost / Vice President – Academic Affairs serves as the university’s chief academic officer and is responsible for ensuring excellence and innovation across the

Senior Associate Provost for Academic Affairs: Catrina Hamilton-Drager (without vote) Vice President for Enrollment Management: Catherine McDonald Davenport (without vote)

Provost and Vice President for Academic Affairs Aswani Volety Senior Associate Provost for Faculty Affairs Tim Peeples Associate Provost for Academic Affairs Jennifer Platania

Immers: voor het doen van een uitspraak over de hoofdvraag is het relevant hoeveel (bijvoorbeeld) protestanten, liberalen of 58-jarigen er zijn benoemd in een commissie, niet of

Microscopic findings: Microscopic examination of tissue sections showed that the mixture of honey and nano zinc has a significant impact on third-degree burn recovery

Trinitas School of Nursing, 40 West Jersey Street, Elizabeth, New Jersey, and Union County College, Cranford, New Jersey, jointly conduct a Cooperative Nursing Program.. The

Derrida's writings themselves articulate a rejection of the concept of alienation in similar terms, but particularly on the basis of its supposed dependence on the notion

RNA-Seq Data Further Supports that ApGPx1 is Highly Expressed in Salivary Glands I mapped the plant-fed and diet-fed RNASeq reads from the previous chapter of this thesis to

However, a study in renal cell carcinoma showed that combined therapy with ATRA and IL-2 reduced the number of MDSCs whereas monotherapy with IL-2 did not impact on

In 2013, Blue Cross and Blue Shield of Rhode Island’s Quality Management Program accomplished several quality improvement objectives, restructured its quality committees to

We examine how the unique organizational structure opportunities within the medical malpractice insurance market, along with an insurer’s diversification profile, affect its