FACILITY PLAN AND NEEDS ASSESSMENT

A.C. Ward Water Treatment Plant

West Des Moines Water Works, West Des Moines, Iowa

(2)

FACILITY PLAN AND NEEDS ASSESSMENT STUDY

• Technical Memorandum No. 1 – Regulations, Goals, and Desired Improvements

• Technical Memorandum No. 2 – Evaluation of Existing Facilities

• Technical Memorandum No. 3 – Plant Process and Code Evaluation

• Technical Memorandum No. 4 – Facility Improvements and Alternatives Evaluation

• Facility Plan and Needs Assessment Report & Capital Improvements Plan

Study Comprised of 5 Tasks:

(3)

TECHNICAL MEMORANDUM NO. 1

Regulations, Goals, and Desired Improvements

(4)

REGULATIONS, GOALS AND DESIRED IMPROVEMENTS

• Evaluate Condition of Existing Infrastructure

• Process, Structural, Architectural, Mechanical, Electrical, and Hazardous Materials

• Evaluate Water Treatment Plant Capacity

• Existing Unit Process Capacities

• Existing Hydraulic Capacity/Identify Bottlenecks

• Identify Improvements to Further Improve Water Plant Redundancy

• Other Desired Improvements

• Improve Recarbonation System Redundancy and Reliability

• High Service Pumping Improvements

• Evaluate Filter Media Replacement

Goals and Objectives Identified for the Study:

(5)

REGULATIONS, GOALS AND DESIRED IMPROVEMENTS

• Water Quality Improvements

• Improve Taste and Odor

• Total Dissolved Solids Reduction

• Fluoride Reduction

• Manganese Reduction

• Sulfate Reduction

• Evaluate Regulatory Compliance

• Identify Applicable Codes and Standards

• Lead and Copper Rule Changes

• Historical IDNR Sanitary Survey (e.g. cover Solids Contact Units)

Goals and Objectives Identified for the Study:

(6)

REGULATIONS, GOALS AND DESIRED IMPROVEMENTS

• Evaluate Compliance with Future Regulations

• Ground Water Under the Influence Standards

• Potential Per- and PolyFluoroalkyl Substances (PFAS) Limits

• Potential Perchlorate Limits

• Distribution Department Space Needs

Goals and Objectives Identified for the Study:

(7)

TECHNICAL MEMORANDUM NO. 2

Evaluation of Existing Facilities

(8)

EVALUATION OF EXISTING FACILITIES

• Current Condition of Water Treatment Facility

• Structural

• Mechanical

• Electrical

• Current Condition of Unit Processes & Remaining Useful Life

• Presence of Hazardous Materials (Visual Inspection Only)

• Distribution Department Spaces and Future Needs

• Office and Garage Space

Evaluation looked at the following:

(9)

EVALUATION OF EXISTING FACILITIES

Building No. 1 Structural Issues

BUILDING NO. 1

VERIFY IF CONCRETE TANK REPAIRS ARE NECESSARY BEHIND BRICK VENEER DURING REPLACEMENT REMOVE AND REPLACE STEEL ROOF DECK, REPAINT ROOF FRAMING, AND REROOF

REMOVE AND REPLACE DOOR

REPAIR DETERIORATED CONCRETE TANK WALL REINFORCE WALL AND TIE INTO ROOF DIAPHRAGM

REMOVE AND REPLACE EXISTING DETERIORATED BRICK VENEER REMOVE AND REPLACE CONCRETE MASONRY VENEER

CUT & POINT ALL BAD CONCRETE MASONRY UNIT MORTAR JOINTS, REPAINT

CUT & POINT ALL BAD BRICK MORTAR JOINTS, CLEAN, AND APPLY WATER REPELLENT REMOVE AND REPLACE CAST STONE AND WINDOWS

REPAINT ROOF FRAMING

PREPARE AND PAINT ALL EXPOSED HOLLOWCORE STEEL CONNECTIONS LEGEND

BUILDING NO. 1

VERIFY IF CONCRETE TANK REPAIRS ARE NECESSARY BEHIND BRICK VENEER DURING REPLACEMENT REMOVE AND REPLACE STEEL ROOF DECK, REPAINT ROOF FRAMING, AND REROOF

REMOVE AND REPLACE DOOR

REPAIR DETERIORATED CONCRETE TANK WALL REINFORCE WALL AND TIE INTO ROOF DIAPHRAGM

REMOVE AND REPLACE EXISTING DETERIORATED BRICK VENEER REMOVE AND REPLACE CONCRETE MASONRY VENEER

CUT & POINT ALL BAD CONCRETE MASONRY UNIT MORTAR JOINTS, REPAINT

CUT & POINT ALL BAD BRICK MORTAR JOINTS, CLEAN, AND APPLY WATER REPELLENT REMOVE AND REPLACE CAST STONE AND WINDOWS

REPAINT ROOF FRAMING

PREPARE AND PAINT ALL EXPOSED HOLLOWCORE STEEL CONNECTIONS LEGEND

(10)

EVALUATION OF EXISTING FACILITIES

Building No. 1 Structural Issues (1953 Original

Construction)

(11)

EVALUATION OF EXISTING FACILITIES

Building No. 1 Structural Issues (1971 Addition)

(12)

EVALUATION OF EXISTING FACILITIES

Building No. 1 Structural Issues (1996 Addition)

(13)

EVALUATION OF EXISTING FACILITIES

Building No. 3 (Chemical Feed – Structural Repairs)

(14)

EVALUATION OF EXISTING FACILITIES

Recarbonation System

(15)

EVALUATION OF EXISTING FACILITIES

Building No. 3 (Chemical Feed)

(16)

EVALUATION OF EXISTING FACILITIES

Backup Generator Automatic Transfer Switch

(17)

EVALUATION OF EXISTING FACILITIES

High Service Pumping

(18)

EVALUATION OF EXISTING FACILITIES

Building No. 5 (Garage)

(19)

EVALUATION OF EXISTING FACILITIES

Clearwell

(20)

EVALUATION OF EXISTING FACILITIES

Electrical and Controls Upgrades

• MCC Upgrades

• Plant Controls/PLC Upgrades

(21)

TECHNICAL MEMORANDUM NO. 3

Plant Process and Code Evaluation

(22)

PLANT PROCESS AND CODE EVALUATION

• Capacity of Unit Processes

• Current plant capacity = 12.0 MGD

• Unit Process Design Standard Deficiencies

• 10 States Standards

• Hydraulic Test

• Confirm hydraulic model

Evaluation reviewed the following:

Unit Process Rated

Capacity, MGD

Aeration 11.5/14.3

Detention Tanks 10.4(1)

Solids Contact Units 17.5

Recarbonation Tank 1.9

Filters 13.1

Clearwell Transfer Pumps 12.2

High Service Pumps 15.1

Lime Residuals Dewatering 12.0

NOTE: (1)Detention tanks and detention times not applicable

(23)

PLANT PROCESS AND CODE EVALUATION

• Building Code Compliance

• Structural, Architectural, Electrical, Mechanical, and Hazardous Materials

• Only areas where improvement recommended

• Distribution Department Space Needs

• Office Space Needs: 2,060 sq. ft

• Equipment Storage/Garage Needs: 4,440

Evaluation reviewed the following:

(24)

TECHNICAL MEMORANDUM NO. 4

Facility Improvements and Alternatives Evaluation

(25)

FACILITY IMPROVEMENTS & ALTERNATIVES EVALUATION

Alternatives Evaluated and Recommended Improvements

Improv. No. Improvement Description Project Cost

1 Aerator/Detention Tank Improvements $1,090,000

2 Cover Solids Contact Units $1,354,000

3A Recarbonation System Improvements – Convert to PSF System $3,195,000 3B Recarbonation System Improvements – Upgrade Existing System $890,000

4 Filter Improvements $1,077,000

5 High Service Pumping Improvements $1,032,000

6 Clearwell Improvements $225,000

7 Metering Improvements $1,467,000

8 Miscellaneous Projects to Comply with 10 States Standards $334,000 9 Upgrades to Comply with Ground Water Under the Influence Standards $1,213,000

10 Sulphate Reduction N/A

11 Building No. 1 Structural Repairs $1,120,000

(26)

FACILITY IMPROVEMENTS & ALTERNATIVES EVALUATION

Alternatives Evaluated and Recommended Improvements (continued)

Improv. No. Improvement Description Project Cost

12 Miscellaneous Structural and Architectural Repairs $337,000

13 Miscellaneous Process Repairs $1,017,000

14 Mechanical Improvements $1,020,000

15 Electrical Improvements $952,000

16A Space Needs Improvements – Combined Distribution Office and Garage $2,578,000 16B Space Needs Improvements – Separate Distribution Office and Garage $2,464,000

(27)

IMPROV. 16A & 16B - DISTRIBUTION OFFICE AND GARAGE

(28)

FACILITY PLAN & NEEDS ASSESSMENT

Recommended Capital Improvements Plan

(29)

RECOMMENDED CAPITAL IMPROVEMENTS PLAN 0 – 5 YEARS

Improv. No. Improvement Description Project Cost CIP Year

8.e/c/ Relocate Chlorine Feed Lines out of Ferric Room $4,000 1

11.a. Building No. 1 Structural Repairs $565,000 1

11.b. Relocate/new MCC 1 $641,000 1

15.c. Replace ATS $285,000 1

3A.c. New 30-Ton Vertical CO2 Storage Tank $562,000 2

5.a. Replace HSP No. 3 (Includes isolation valves, check valve, and VFD installation) $301,000 2

15.d. SCU#1 Mixer VFD $20,000 2

6.a. Replace Clearwell Valve Structure $44,000 3

6.b. Clearwell Access Hatch Improvements $43,000 3

6.c. Repaint Transfer Pumps and Piping $11,000 3

6.d. Clearwell Tank Cap Waterproofing $144,000 3

8.f. Backwash Reclaim Tank Improvements $38,000 3

8.g. Filter 5-8 Effluent Box Hatch Improvements $22,000 3

12.a. Building No. 2 Structural Repairs $12,000 3

12.b. Building No. 3 Structural Repairs $116,000 3

12.c. Building No. 4 Structural Repairs $59,000 3

12.e. Building No. 6 Structural Repairs $59,000 3

13.f. Replace Backwash Reclaim Pump $43,000 3

13.c. Clean and Recoat West Reservoir $619,000 4

16A. Space Needs Improvements - Combined Distribution Office and Garage $2,776,000 5

CIP Year

Total Project Cost

1 $1,495,000

2 $883,000

3 $580,000

4 $630,000

5 $2,776,000

TOTAL $6,364,000

(30)

RECOMMENDED CAPITAL IMPROVEMENTS PLAN 5 – 10 YEARS

Improv. No. Improvement Description Project Cost

4.b. Replace Air Backwash Blower $145,000

7.b. Filter Air Backwash Metering $35,000

4.c. Miscellaneous Filter Improvements (Repainting and Valve Stem Replacements) $136,000 5.a. Replace HSP No. 2 (Includes isolation valves, check valve, and VFD installation) $288,000

5.b. Replace Process Valves for HSP Nos. 1, 4, and 5. $396,000

5.c. Install VFDs on HSP Nos. 1, 4, and 5. $222,000

5.d. Repaint Piping & Pumps $32,000

8.e. Ferric Chloride Feed System Improvements $100,000

12.d. Building 5 Structural-Architectural Demolition $135,000

14.a. Building No. 1 – Mechanical Repairs - Filter Room Dehumidifier $356,000

14.b. Building No. 1 – All Other Mechanical Improvements $311,000

14.c. Building No. 3 - Mechanical Repairs $356,000

14.d. Building No. 4 - Mechanical Repairs $44,000

14.f. Building No. 6 - Mechanical Repairs $207,000

15.a. Replace MCC Buckets $438,000

TOTAL $3,201,000

(31)

RECOMMENDED CAPITAL IMPROVEMENTS PLAN 10 – 15 YEARS

Improv. No. Improvement Description Project Cost

2a. Install Covers on SCUs $1,777,000

2b. Install Overflows on SCUs $182,000

3B.a. Existing Recarbonation Tank Improvements $33,000

3B.b. New Pressure Solution Feed System $499,000

3B.c. Replace 14 Ton CO2 with 30 Ton $755,000

13.a. Lime and Soda Ash Level Sensor Replacement $56,000

13.b. Lime and Soda Ash Bin Cleaning and Repainting $111,000

13.d. Repair and Repaint SCU #3 $405,000

TOTAL $3,818,000

(32)

RECOMMENDED CAPITAL IMPROVEMENTS PLAN 15+ YEARS

Improv. No. Improvement Description Project Cost

1 Aerator/Detention Tank Improvements $1,828,000

3A.a. New Recarbonation Tank and Feed Building $3,905,000

7.a. SCU Influent Metering $247,000

7.c. Filter Effluent Metering $2,167,000

9.a. Install Turbidimeters $319,000

9.b. Install Filter-to-Waste Piping, Valves, and Controls $1,268,000

9.c. Filter-to-Waste Tank $448,000

TOTAL $10,182,000

(33)

RECOMMENDED CAPITAL IMPROVEMENTS PLAN

CIP

Years Total Project Cost

0 - 5 $6,364,000

5 - 10 $3,201,000

10 - 15 $3,818,000

15+ $10,182,000

TOTAL $23,565,000

20-Year CIP Summary:

(34)

Facility Plan and Needs Assessment

A.C. Ward Water Treatment Plant, West Des Moines Water Work

QUESTIONS?

Lance Aldrich, P.E. – [email protected]

Jenny Ruddy, P.E. – [email protected]

(515) 233-0000

References

Related documents

The use of combined microscopic and molecular data resulted in the identification of the Microsporidia as Glugea atherinae Berrebi, 1979, a species that was

Install roof insulation to match existing gypsum board roof deck thickness at existing steel roof deck, secure insulation to steel deck with mechanical fasteners and plates, and cover

remove the vacuum head and rinse recovery tank with clean water.. Replace the ball plug on

AIS must include the ability to define data workflow logic in the same environment and must make both the data logic and the workflow logic and information available for use

See also Intonation, page 384; Parts, Euphonium, page 393; Tuning Slides, page 403; Tuning/Tuning Note Considerations, page 404 Th ree-Quarter-Size Baritone: See Instrument Family

Using a computable model, we have simulated household bills under three conditions (a) a base case involving existing average cost tariff structures; (b) a time- of-use tariff with

Engineering and Technology (DUET) Gazipur, Bangladesh Saad Andalib Department of Computer Science American International University–Bangladesh (AIUB) Dhaka, Bangladesh Saiful

Have manufacturer review work involved in handling, installation, protection, and cleaning of insulation and accessories, and submit written reports in acceptable format to verify