• No results found

Integration Practices

N/A
N/A
Protected

Academic year: 2021

Share "Integration Practices"

Copied!
8
0
0

Loading.... (view fulltext now)

Full text

(1)

Integration Practices

Mark Davis – General Manager Operational Excellence

November 2015

Practical lessons from recent asset

integrations

(2)

Integration activity at MMG

2

Las Bambas

Project

2014

Anvil Mining

(Kinsevere)

2012

MMG

Group Office

• Open pit copper mine

• Design 450+ktpa

concentrate

• Ownership 62.5%

• Open pit copper mine

• Design 60ktpa

cathode

(3)

1. Understand and establish ownership of the asset

2. Transfer control from current owner and position as the operator of the asset

3. Maintain/improve safety performance and operational (cost and schedule) KPIs

4. Retain and engage critical capabilities and people

5. Deliver comprehensive Beyond Integration Plans to the new Management Team

6. Position asset to deliver on M&A valuation case

Integration Objectives

3

Integration Key Principles

Focus on key areas and close out outstanding due

diligence items that could have a material impact on the

value of acquisition

Adopt a “light touch” approach and only integrate what

is mandatory, not discretionary, to support the delivery of

the project on time and on budget while providing

management control

Respect and collaboratively work alongside existing

operations and project personnel. The role of the

integration team is not to “take over” the project

Develop a strong understanding of the asset, the

(4)

Key Phases

•Internal/External communication – minimise

uncertainty and manage political/social sensitivities

Phase 2:

Integration Readiness

(8 Weeks)

Phase 1:

Pre-Assessment,

Planning & Mobilization

(12 Weeks ++)

Phase 3:

Integration Execution

(60 Days)

• Work streams and steering

committee

• Timetable, outcomes, boundaries

• Integration model, processes and

protocols & rules of engagement

• Mobilise Integration team leaders

• Arrange support and infrastructure

• WAIT FOR DEAL TO BE DONE…..

• Build knowledge (doc review, briefings,

one on ones)

• Identify and prioritise activities

• Operational goals and Integration KPIs

• Detailed Execution Plans:

•Transfer of Management Control

•Transfer of Project Management Control

•Stakeholder Assessment & Comms Plan

•Common system/process rollout

• Develop Day 1 Plan

• Develop 60 Day Plan

• Identify Management Team for Day 1

• Announce new organisational

structure

• Deploy new systems and processes

• Execute integration plans (Day 1

and Day 60)

• Monitor compliance with integration

milestones & targets

• Handover on-going beyond

integration work stream activities to

new asset Management Team

(Business as Usual)

•Engage Integration Steering Committee

•Appoint Integration GM and PMO

•Integration Steering

Committee to review and

ratify implementation

plans

•EXCO takes over from ISC

and integration responsibility

moves from the Integration

General Manager to the asset

General Manager

•Identify key integration stakeholders

•Develop and launch communication plan

Governance

(5)

5

Plan on a Page – Overall Integration

Definitive cost & schedule to complete estimate Project control gaps closed

Rem committee Approval of Rem Structure #2 Stakeholder Comms plan approved Week 1 Comms delivered

Pre-Assessments Complete & Final Integration plans developed

Change of Ownership Readiness Meeting Phase II Readiness Review • Draft Integration Plan complete

• Mobilization plan complete • Integration Budget approved • Delegation of Authority

Day 1 Comms pack delivered

Comms Plan complete Rebranding plan complete Plans complete with owner identified for trailing actions Handover to Country Manager

Pre-Assessment

Key Integration Events

Integration Execution

Project Delivery /

Ops Readiness

Stakeholder / SHEC

31 Jul

BAU

People / Culture

Change of

Ownership

16 June

Integration Readiness

Deal Capture

SPA

13 Apr

ExCo Review

SBS / Finance / Commercial

Supply / IT / Legal

30 Sep

April

May

June

July

August

September

October

= on track = area of concern

Fatal Risk Gap Analysis complete, with Action Plan

Week 2 Comms delivered Aviation Management Plan Crisis Management & Emergency process endorsed

MMG Endorsed Community Management Plan Community positioning paper

approved by Exco #1

Project health check complete Ops readiness assessment completed

Concentrate Logistics assessed, road transport plan affirmed

Funds for project completion approved

Ops reporting in place for safety , volume & cost Preliminary estimate of cost &

schedule to complete

Delegation of authority in place

Fund for project completion (2014) approved

Key personnel retention strategy

finalised Individual retention plans for key people developed SPA Governance Monitoring & Compliance in place

IT separation commenced

IT separation completed (continues into 2015) Leadership Team in place & key resource gap addressed

All employees have clarity on role and remuneration

TSA services separated BaU Planning Systems in place Financial reporting process in

place

Required insurances retained & gaps addressed Day 1 org structure approved by ExCo

TSA governance, monitoring & compliance in place

Day 1 IT & Shared Services in place Completion accounts prepared

Key contracts novated & transferred = complete = Overdue # change log CoC Stakeholder /Branding /Comms Plan Approved

Change Management Plan delivered BaU work plans completed

Close out Report & KPI results

Advisory board appointed #3

Org structure changes implemented

Planning cycle aligned with corporate planning

(6)

Key Relationships

6

Integration Principles

Protect and create value at all times.

Act as an ambassador of MMG and Las Bambas.

Adopt a “light touch” approach and only integrate what is

mandatory, not discretionary, to support the delivery of

the project on time and on budget while minimising

change.

Respect and collaboratively work alongside existing

Las Bambas and project personnel. The role of the

integration team is not to “take over” the Las Bambas

project.

Respect diversity at a country, region and asset level.

• Understand and obey requirements of the Shareholder

Purchase Agreement during the Pre-Closure period

• Maintain close connection with Deal team leader working

under Transitional Services Agreement to achieve timely

Close

• Maintain close connection with corporate function GMs back

in the Head Office

• Leverage the parent company Operating Model (no

exceptions)

• Maintain close connection with new asset GM to align

(7)

Reinforcing lessons for future integrations

7

• Apply dedicated resources of the highest level of capability

necessary to get the job done:

‒ Source internally and support with externals (for example external work stream

experts doing “back office” tasks, stress testing plans and providing PMO); and

‒ Backfill internal resources

• Prepare integration work team members on the culture of the

company doing the integration, the culture of company being

integrated, and not just the culture of the Country

• Maintain the focus on the Integration key deliverables and be

clear up front on how transition to Business As Usual will be

done

• Maintain the short (60 day) integration period to drive

(8)

Key Messages from those “integrated”

8

• Understanding local requirements and Integration planning

and delivery was enhanced by the on-boarding of senior

leaders from acquired company ahead of change of

ownership

• All stakeholders warmly welcomed the new owner’s

commitment to the country, asset, people and culture

• The number and quality of MMG people that visited site

teams was especially important, it impressed the new asset

team with their knowledge and passion for mining

• Visible and effective leadership with multiple visits into

country by senior most company leadership

References

Related documents

Unless and until the legislative appreciate the underlying theories and concepts of the law of consumer protection and the contractual remedies and its approaches, the consumers

OSH strategy on Tideway is a complex intervention with transformational intended outcomes being implemented by multiple stakeholders, over a significant period of time, within

Commissioners present for roll call: Chairman Ed Hoffman, Vice-Chair Teri Teutsch, Co-Secretary Mark Canada, Mathew Anselmo, Marla Bruder, Paul Leckband, Terry

Table 1 –Conditions where Gastrostomy feeding is considered Neurological Indications Cerebrovascular Disease Motor Neurone Disease Multiple Sclerosis Muscular Dystrophy

 Banque Misr Liban s.a.l..  Gabas Albilad Holding

39 prescription naprosyn dosage 40 does naproxen 500mg make.

Bert (2003) who submitted a report from the topic “The role of budget and budgetary Control in district council concluded that: The role of budget is achieving the

Many experts recommend that a good IPM contract include requirements for maintaining and using detailed pest sighting and pesticide use records, conducting inspections, consulting