© Oliver Wyman
INFRASTRUCTURE RISKS:
ENABLING INFORMED DECISIONS Large capital project risk management
DOHA, November 4
th, 2014
Sandro Melis – Partner Oliver Wyman
Manufacturing, Transportation and Energy
Email: sandro.melis@oliverwyman.com
Tel: 00 39 34 8895 2874
CONFIDENTIALITY
Our clients’ industries are extremely competitive. The confidentiality of companies' plans and data is obviously critical. will protect the confidentiality of all such client information.Similarly, management consulting is a competitive business. We view our approaches and insights as proprietary and therefore look to our clients to protect 's interests in our presentations, methodologies and analytical techniques. Under no circumstances should this material be shared with any third party without the written consent of .
Copyright ©
3
© Oliver Wyman 3
Project challenges and delay drivers
Delays and cost-overruns are usually driven by a combination of planning, organizational and execution challenges
Cost overruns
Delays 150 – 200% 40 – 50% 30 – 50% 20 – 30%
100 – 150% 50 – 70% 30 – 60% 15 – 25 %
Planning
• Business-driven project sizing
• Trade-offs invest- ment / operations
• Technology choices
• Equipment
specification gaps
Organisation
• Contractor
selection/ quality
• Funding gaps/
lack of liquidity
• Governance structures
• CFO involvement / lack thereof
Communication
• Information flow within project/
between project and management
• Bureaucracy
• Lack of
ownership/ blame games
Transparency and oversight
• Real-time
progress / issue reporting
• Timely quality assurance
• Delays at
commissioning
• Opportunism or even fraud on-site
Execution
• Deviation management
• Qualified labour force
• Automation and tooling
• Raw materials quality
Nuclear Power Plants
Transport infrastructure
Chemical plants Oil and gas
upstream
Source: Oliver Wyman analysis, delays reflect global industry averages within last decade
Selected typical pain points
4
© Oliver Wyman 4
Case study: Typical project delivery issues
Typically large construction projects face a variety of challenges that lead to delays and cost overruns
Risks and challenges Lessons learned
Lack of
risk awareness
• Optimistic planning and expectations, limited reflection of risks in business plan
• Lack of open communication about risks
• Blame games to avoid being risk owner
• Introduction of capital project risk management as a cornerstone to risk culture
• Usage of risk-adjusted KPIs for steering
Limited cost transparency
• Limited consideration of cost escalation over time & across technological alternatives
• Insufficient cost calculation and budgeting
• Limited incentives for cost reduction
• Forecast industry prices frequently and align with project costs to ensure long term profitability
• Define long-term budget to control expenses
• Define integrated project schedule to minimize
delaysMisaligned
tendering process, commercials and execution
• Lack of long-term partnerships
• Imbalance between price and quality focus
• Prefabrication issues resulting in rework
• Pre-screen and pre-qualify potential suppliers
• Use of framework contracts to build long-term relationships with quality suppliers
• Tighter oversight of prefabrication quality Regulatory impacts
and requirements
• Increasing specifications and functionality to adapt to growing regulations
• Increasing safety regulations
• Regulatory licensing delays
• Align industry requirements forecasting with project planning to ensure alignment with industry structure
• Establish rigorous safety policies from outset
• Manage and maintain strong regulatory relations
Ineffective organizational interfaces
• Several project views exist (e.g. financial/
technological – design/construction)
• Siloed thinking indirectly promoted
• Integrate project timeline with financial plan for a
unified project plan• Establish incentives for cooperation and risk mitigation
Lack of standard processes and capturing of experience
• Lack of standardized processes
• Limited consideration of previous project
experience• Align KPIs across businesses (e.g. number/
turnaround time of documentation changes)
• Formalize best-practice sharing across projects
5
© Oliver Wyman 5
Realizing value from risk management
Large Capital Project Risk Management approach support address and mitigation of delays and overruns risk
Increases visibility of key performance drivers
Aligns risk taking with profit and growth targets
Generates higher future returns through disciplined allocation of capital
Stabilizes performance by
protecting against downside scenarios
Promotes risk awareness
within key decision making process
Achieves risk governance and compliance as a by-
product of value creation Reduces risk through more
active and focused risk management
Reduces project
schedule slippage by
mitigating key schedule
risks
6
© Oliver Wyman 6
Example of successful results achieved in large project delivery
Oliver Wyman has recently saved >$2bn from Large Capital Projects (1/2)
US$ 2,000 MM
1US$ 450 MM US$ 1,500 MM funding
Oil production
(projects and fields)
Gasification project Power plant design, build and operate
• Re-evaulated risks and
financial projections for five oil fields (following the acquisition of an independent producer)
• Developed dynamic financial plans and mitigation measures to secure NPV uplift of $2 BN
• Built capabilities and systems to evaluate risks and inform dynamic financial planning decisions
• Project cancelled due to excessive risk, sunk cost of
$50 MM vs. expected $500 MM loss
• Developed third-party risk review to support investors due diligence
• Helped raise over $300 MM equity and $1.2 BN debt from consortium of investors
Realized NPV impact
1 Opex and Capex benefits
7
© Oliver Wyman 7
Example of successful results achieved in large project delivery
Oliver Wyman has recently saved >$2bn from Large Capital Projects (2/2)
US$ 300 MM US$ 250 MM US$ 100 MM
Nuclear Power Plant Construction
Hydro Dam Upgrade Rail network
capacity expansion
• Developed targeted mitigation activities (Training, contractor/
supplier management, procurement, quality assurance processes, …)
• Reduced expected delay by 10 months
• Identified key risks and critical path dependencies during construction of a hydro power dam
• Secured on-time delivery and go-live due to early focus of efforts on the critical
construction items and important decisions
• Created transparency around demand, operational and
capital risks which enabled the definition of appropriate
mitigation measures
• Reduced expected delay in ramp up by 24 months
• Maximized profitability through
risk-sharing in tariff design
Realized NPV impact
8
© Oliver Wyman 8
Large Capital Projects challenges
Each project lifecycle phase has distinct challenges that have a compound effect on project and operational performance
Feasibility
FEED
(Front End Engineering Design)
EPC
(Engineering, Procurement, Construction)
Operations
• Misaligned objectives leaving the project delivery at risk
• Static approval process
• Biased assessments
• Inadequate knowledge of market conditions
• Unsuitable or non- regionally specific analysis
• Compressed
timeframes resulting in incomplete analysis
• Stakeholder complexity - political, regulatory, shareholders, operations
• Ineffective organizational interfaces
• Limited consideration of long term factors
• Front End Loading (FEL) activity does not actively mitigate delivery risk
• Unrealistic planning expectations resulting in false delivery schedules
• New tech and remote areas
• Organization and contracts not designed around risk
• Avoidance of accountability with no open communication about risk & performance
• Siloed program architecture and decision making
• Insufficient cost challenge decisions and minimal regard for operational outcomes
• Limited preemptive mitigation
• Technical complexity–
physical location, technological advances, scale of projects
• High competition for limited local and global resources
• Building operational teams
• Effective commissioning and start up
• Retrospective fixes to meet operational needs
• Mitigation measures not in place
• Lack of alignment and ownership
• Scope increases
• High levels of contingency
• Incorrect prioritisation of options
• Misallocation of capital
• Over optimistic forecasting
Chal le nges Ris k s • Schedule and cost
overruns
• Scope reduction
• Inefficient use of resources
• Phased go live
• Reduced productivity and ROI
• Significant ‘fix’ costs
• High maintenance
Constrained internal and market capabilities and capacity
9
© Oliver Wyman 9
Project delays – project operational later than
planned 2
Cost overruns – CAPEX spend is greater than
expected 1
Profitability shortfall – demand uncertainty due to macro-drivers, competition, productivity development,
cost evolution 3
• Project delays
• Design/technology choices for implementation
• Timing flexibility and schedule re-sequencing
• Integrated project management data (one timeline, cost plan, business case)
• Cost overruns
• Raw material/FX hedging
• Increase efficiency productivity through training initiatives
• Minimise rework cost through forward looking quality assurance
• Alignment of KPIs to project performance to manage costs
• Profitability shortfall
• Resilience in operating model/operational excellence/
pricing and contract design choices
• Strong accountability for project management for financials
• Organisational improvements and BU incentives
2 3
Dynamic forecasting: Use risks to make informed decisions
Transparency on the risks to project value informs how to optimise performance throughout the project life cycle
Enhanced value capture
FCF over time (In US$ MM)
Mitigation activities
Original Plan – often based on optimistic assumptions in regard to project execution and market success Risked forecast – dynamically updated based on current status and forward-looking risk assessment Post mitigation forecast – considering impact of net positive investments into mitigation activities
1
Operating phase Planning and construction phase
10
© Oliver Wyman 10
Large Project Risk Management approach
Three key stages define the approach to capital project risk management, and can be applied to a variety of projects at any point in their lifecycle
Key activities Objective Project phases
• Determine key risks and analyse risk drivers
• Calculate impact of key project risks
• Develop a risk model for future usage throughout the lifecycle
• Identify and evaluate key risk mitigation options
• Develop a set of mitigation measures for future
implementation
• Develop project mitigation monitoring tool
• Operationalize mitigation actions Dynamic
Forecasting Risk assessment
and quantification
1 2 Execution and
mitigation tracking
3
• Develop perspective of engineers/ management
• Agree risk prioritization
• Determine data and
quantification requirements
• Develop risk quantification model
• Calibrate results and
prioritise risks for mitigation
• Develop risk mitigation activities
• Assessment of cost-benefit of mitigation options
– Expected NPV versus option cost
– Compare to project hurdle rate and risk appetite
• Develop governance
framework and guidebook of mitigation activities
• Develop mitigation
implementation action plan
• Assign risk
mitigation owners
• Determine operationalization of mitigation activities
timeline
• Provide effectiveness tracking platform for mitigation measures
• Integrate mitigation tracking into project operations
Organizational capability growth
11
© Oliver Wyman 11
High concentration of risk around top 3 drivers
Poor contractor
selection
Weak equipm't
supply chain
Project design
Construct.
equipm't &
materials issues
Issues w/
working docs
Slow/
costly tendering
process
Cost/
delays in decision- making
Complex cost planning
Post- poned delays
Cost/
delays - breach of
contract
Post- decision equipm't specs change
Funding/
liquidity
Other ext. Risks
Notes: Represents individual risk contribution excluding inter-risk diversification. NPV contribution as deviation from plan in the 1:10 pessimistic case
Risk assessment and quantification
Often large capital projects suffer from a high concentration of risks, implying that a few risks represent more than the majority of the overall volatility
•Delay of cooling pumps
•Delay of steam generator
• Coordination of construction works
• Poor quality of works
• Shortage of labour
• Delay of reactor vessel supply
• Works / activity sequencing
13.57047 NPV risk contribution Total risk to NPV Difference between the sum of
individual contributions and total risk
Example Nuclear Power Plant project – NPV risk contributions by factor (BN USD)
Sanitized client example
Transparency on key drivers of NPV dilution provides the basis for the development of effective mitigation strategies
12
© Oliver Wyman 12
Key drivers of deteriorating project performance
Case example: Despite significant potential cost overruns, we found delays to commissioning posed the greatest threat to the erosion of project NPV
0 100 200 300 400
Supply of pressure compensator vessel
Supply of the main circulating pump Supply of feed water line from turbine driven feed water pump to high-…
SD. Installation of turbine condersators (without water box) Supply of high pressure preheater
(HPP)-7
SA. Assembly of turbogenerator Supply of high pressure preheater
(HPP)-6
Supply of suction pipe of turbine driven feed water pump and…
Construction of containment at level till +55,6 (2nd tier of containment) Supply of steamgenerators, including
pillars
Supply of turbine condensator Supply of pipelines of emergency
core cooling system Supply of pipelines of main
circulation line Supply of polar crane Supply of reactor vessel
Optimistic case delay (days) Mean delay Pessimistic case delay (days)
Supply of high pressure preheater #6
Supply of high pressure preheater #7 capacitor
Construction 43%
Equipment 39%
Other 18%
Breakdown of costs Key drivers of project delay
FCF impact of cost vs. delays (2016)
Delays Cost
Typical drivers
• Miscalculation of cost during planning
• Price changes in steel, copper, and other commodities
• Default of contractors
• Insufficient delivery quality
Average forgone revenue of a 1 day delay = $1 MM
Impact of cost overruns Impact of project delays
13
© Oliver Wyman 13
Identification of risk mitigation measures
A detailed analysis of NPV sensitivities allows to evaluate mitigation strategies in line with their impact on the overall project value
Decrease in risk contribution
due to realization of the mitigation measures
NPV risk contribution (USD MM)
Time contribution (days)
Without mitigation measures With mitigation measures
0 50 100 150 200 250
Poor contractor selection Weak equipm't supply chain Project design Construct. equipm't & materials issues Issues w/ working docs Slow/costly tendering process Cost/delays in decision-making
Complex cost planning Post-poned delays Cost/delays - breach of contract Post-decision equipment specschange Funding/liquidity Other external risks
0 100 200 300
Sanitized client example
The analytical approach to project risk identification, quantification,
management and mitigation helped to reduced expected delays by more than
10 months
14
© Oliver Wyman 14
Note: Possible deviation of the realistic values from the calculated ones can occur even if all mitigation measures are fully realized
Risk mitigation impacts
Risk mitigation measures can be developed to bring net risk exposure levels within an acceptable tolerance range
NPV effect of mitigation measures
(Deviation from plan in pessimistic case, US$MM)
Unmitigated (Rostov-3)
Current measures
New measures implemented
by general contractor
New measures implemented by all parties involved
Residual risk (Rostov-3) C
B A
Project specific measures
Project risk appetite
Achieving a significant effect with mitigation measures in this group is possible with an aggressive pace of
implementation
D
Unmitigated NPV impact
A • Contractor under-delivery: proactively allocate less attractive tasks and improve on-site task management
• Unavailability of material: LEAN program roll-out and integration with project management systems
• Design errors: technological sequence re-ordering
• Supply chain: pressure on suppliers for on-time delivery B • Contractor under-delivery: Use of single consolidated timeline
• Design errors: develop new KPIs and incentives to improve re- planning process
• Supply chain: provide first drafts of the documents for equipment at the early staged of the delivery
C • Contractor under-delivery: use hi-tech equipment, increase financial responsibility and incentives for required quality level , as well as provide additional education to engineers
• Supply chain: increase inventory warehouse space, start mounting already available equipment and improve approval process for recovered equipment
• Complexity in cost planning: create additional items in the master data catalogue for equipment items – ensure full adequate capture
D • Contractor under-delivery: refine compensation structure and production and technical education
• Supply chain: improve overall QA and approval process
• Unavailability of materials: Develop crane facilities
• Tendering process: improve tendering process by increasing the specificity of tenders, restrict the number of suppliers for delivery, and change the weighting between cost and other factors (e.g. reliability)
• Number of risks: centralize management of equipment inventory and establish clear divisions of responsibilities and KPIs
Non-project specific
15
© Oliver Wyman 15 Risk model
Risk parameterization
Risk quantification
Key risks
Project management tool
Purpose
• Allows regular reporting on risks and associated mitigation measures
• Saves information regarding
mitigation measures and actions for their realization (mitigation
guidebook)
• Provides regular and standardized reporting platform
Use and process
• Risk model provides key risks via the dedicated export sheet
• Mitigation measures are being developed and assessed
• Mitigation measure activity plan entered into the tool and
tracked regularly
• Standard reporting available to management
• Propose to include in standard reporting
Project management tool
In order to enable full implementation of mitigation measures we use a specialized mitigation tracking tool linked to the risk model
Link between project management tool and risk
model
16
© Oliver Wyman 16
Benefits from this approach
Large project risk management can improve IRR (by 1 to 1.5%) and reduce risk cost by 15-20%
• Centralizes financial and technical operating information to provide visibility into project’s economic drivers and sensitivities
• Identifies material economic drivers and risk neutral ways to increase return using physical and financial contracts (suppliers, EPC contractors)
IRR uplift of >150 bps from baseline estimate Increased expected
IRR, with reduced variability
• Provides a framework for analyzing and interpreting the risk-return trade-offs and the cost-benefit of alternative risk mitigation strategies
• Leads to most efficient allocation of risk management resources that keep the project within investors acceptable risk taking levels
Total cost of risk reduction of 15-20% from status quo mitigation plan Greater capital
efficiency, with overall downside protection
• Clear and compelling story for investors that rigorous planning and risk analysis has been completed for the project
• Reassures potential investors that the economic business case is supported under a wide range of market scenarios
Full capital raised with 20% reduction in debt financing costs Improved investor
confidence in project economics
Source: Oliver Wyman client project results with clients on Large Project Risk Management
QUALIFICATIONS, ASSUMPTIONS AND LIMITING CONDITIONS
This report is for the exclusive use of the client named herein. This report is not intended for general circulation or publication, nor is it to be reproduced, quoted or distributed for any purpose without the prior written permission of . There are no third party beneficiaries with respect to this report, and does not accept any liability to any third party.
Information furnished by others, upon which all or portions of this report are based, is believed to be reliable but has not been independently verified, unless otherwise expressly indicated. Public information and industry and statistical data are from sources we deem to be reliable; however, we make no representation as to the accuracy or completeness of such information. The findings contained in this report may contain predictions based on current data and historical trends. Any such predictions are subject to inherent risks and uncertainties. accepts no responsibility for actual results or future events.
The opinions expressed in this report are valid only for the purpose stated herein and as of the date of this report. No obligation is assumed to revise this report to reflect changes, events or conditions, which occur subsequent to the date hereof.
All decisions in connection with the implementation or use of advice or recommendations contained in this report are the sole responsibility of the client. This report does not represent investment advice nor does it provide an opinion regarding the fairness of any transaction to any and all parties.