• No results found

ASSENT Prequalification Document

N/A
N/A
Protected

Academic year: 2021

Share "ASSENT Prequalification Document"

Copied!
95
0
0

Loading.... (view fulltext now)

Full text

(1)

Page 1 of 95

ASSENT

Al Shafar Steel Engineering

Prequalification Document

(2)

Page 2 of 95

I N D E X

Introduction … … … … … 4

Al Shafar Group … … … … … 6

Quality Policy … … … … … 7

Market Sectors & Products … … … … 8

Construction & Site Services … … … … 9

Legal Status … … … … … 10 Branch Office … … … … … 15 Registrations … … … … … 17 ISO Certifications … … … … 35 Engineering Capabilities … … … … 38 Manufacturing Facility … … … … 40

Quality Control & Quality Assurance … … … … … 49

General Description of Work Flow Procedures … … 50

Engineering Design Output Design Review Design Validation Design Changes Software R F I ‘ s Pre-Production Planning Example … … … … … … 54 Material Preparation Identification

Handling, Storage and Stacking Consumable Storage

Fabrication Drawings Beam Processing

Beam Preparation Equipment Plate Processing

(3)

Page 3 of 95

Plate Processing Equipment Assembly

Welding

Curving and Straightening Non-Destructive Testing

Surface Preparation and Painting Delivery of Finished Product

Attachments … … … … … … 59

Process Control Procedures Inspection and Test Plan (Sample) Welding Procedure Specifications Health Safety & Environment … … … ….. ……. … .. ... 76

Our Projects … … … … … 77

Organization Chart … … … … … 87

Manpower List … … … … … … 88

Equipment List … … … … … … 93

(4)

Page 4 of 95

Introduction

ASSENT, a member of the long-established AL Shafar Group of Companies, is one of the Middle East's leading companies in the field of structural steel design, engineering, fabrication, painting and erection of all types of steel projects.

Having a fully covered and insulated area over 50,000 square-metres, allows ASSENT to be able to produce a very large volume of fabricated steel, ranging from 8,500 to 10,000 tons per month. This plant is equipped with the latest technology of CNC, blasting and other types of equipment to ensure the quality, speed of production accuracy, and proper control.

The Workshop is equipped with four (4) Automatic CNC beams and plates processing lines in an area of 66m x 180m, for sizing, comprising of :

‐ CNC Beam Sawing Lines ‐ CNC Beam Drilling Lines ‐ CNC Coping Equipment ‐ CNC Plates Processing Lines ‐ CNC Angle Masters

‐ CNC Profiling Machines

All raw material is pre-blast before processing using three (3) automatic blasting machines capable to of processing 3000 tonnes/month each (total 9000 tonnes/month)

The fabrication area covers an area of 145m x 178m, fully equipped with all necessary welding equipment, overhead cranes varying from 5 to 15 tonnes in capacity etc… In total the facility is equipped with 89 overhead travelling cranes.

Post-blasting, after fabrication is done through two (2) 10-turbine blasting machines capable of processing in excess of 8000 tonnes/month

All blasting is done to Sa 2 1/5

All painting is done under controlled conditions under cover in an area of 60m x 145m

An additional area of 72m x 240m has been dedicated to raw material project storage and can accommodate up to 40,000 tonnes of steel sections

In addition to the production capabilities described above, all the engineering and quality control is carried out in-house, with the additional independent third party testing of welds, in compliance with approved specific project ITP (Inspection and Test Plans), undertaken by Internationally Recognised and Approved Testing Agencies.

(5)

Page 5 of 95

ASSENT’s products and services are available for all types of steel projects. The Senior Management Personnel have a wealth of experience in all areas from high-rise towers to storage sheds; from oil and gas projects to large-scale commercial buildings; from hangars to showrooms and moreover all types of prefabricated residential houses, office complexes and labour camps.

ASSENT's quality control and assurance program comply with the international requirement, which closely governs all engineering, manufacturing and construction standards. We also apply strict health, safety and environmental policies to safeguard the protection of all employees and subcontractors. We always work with the aim of having a zero-accident environment.

After sales supports facilities in Abu Dhabi,

ASSENT main facilities are located in Dubai Industrial City, at a convenient location at about 100 km from Abu Dhabi, and is in a position to provide all necessary after-sales services required within and around Abu Dhabi area.

Such services include:

– Stock of spare parts: In case additional structural members or related accessories, such items can easily and conveniently be provided on short notice.

– Repair facilities: The workshop facilities are within short distance of Abu Dhabi. Any repairs can be accommodated within the workshop facilities or at the client’s premises depending on the nature of the repairs

– Technical support: Can be made available either at Main Dubai Facilities or Abu Dhabi Office

Satisfy Abu Dhabi regulations concerning Local Agency Requirements

ASSENT is a fully registered Limited Liability company registered in Dubai and fully compliant with all Legal and Local Agency Requirements of the United Arab Emirates.

Please refer to the “Legal Status section” of this document for copies of the Industrial License, Chamber of Commerce Registration and Commercial Register as well as Registrations with other Authorities.

(6)

Page 6 of 95

Al Shafar Group

A reputation for high quality and reliability

Al Shafar Steel Engineering (ASSENT) is the most recent addition to Al Shafar Group of Companies, which was established in 1989, and in a period of 20 years has now grown to incorporate a total of 18 companies (including ASSENT), all related to different aspects of the construction and related manufacturing industries.

Al Shafar Group currently employs approximately 25,000 people overall.

Through its 20 years in existence, Al Shafar Group has earned the respect and loyalty of its “repeat” clients such as Government Agencies, Dubai Police and others, through the quality of its products as well as its transparency and reliability in its business approach.

For additional information on Al-Shafar Group of companies, please visit the web site http://www.alshafar.com

(7)

Page 7 of 95

Quality Policy

Our Vision

We are confident in our strategies for growth in the Structural Steel Projects

Engineering, Manufacturing, Painting and Erection within the United Arab Emirates

and other Gulf Countries.

Our Mission

Our mission is to be the most effective and respected manufacture of industrial products

by practicing our strategy which is based on improving quality productivity.

Our Quality Policy

To realize our vision and mission we shall exert every effort to achieve the following in

all our activities:

 To have a close working relationship with all our Clients / Customers on all aspects of engineering, quality and service to expedite the contract;

 To be aware of the latest technological aspects related to our scope of works and to continually evaluate this technology and its potential impact on manufacturing capability and company quality requirements;

 To continually strive to satisfy the requirements of our Clients & Customers by completing the projects in compliance with their specifications, contract and quality requirements;

 Gaining the confidence and trust of our supervising bodies, employees, stakeholders, customers, and the public through strict adherence to all applicable laws, regulations, best practices, international standard for quality management system ISO 9001:2008;

 Continually improving the effectiveness of our Quality Management System through periodic monitoring and review of its performance and suitability ; and

 Protecting our environment by effectively utilizing our resources and reducing / preventing the pollution that may be associated with ASSENT activities through effective waste management activities; and

 Communicating our Policy to all our employees, stakeholders, partners, customers, interested parties and the public.

This Policy provides the framework and sets the basis for establishing and reviewing our objectives at the relevant functions of ASSENT. It will be reviewed periodically for continuing stability and suitability.

(8)

Page 8 of 95

Market Sectors & Products

The following is an indication, but is not limited to, of the market sectors serviced and the types of structures undertaken by ASSENT.

The flexibility, expertise and equipment allows the company to customize and provide the right products or mix of products as required by the clients’ projects.

Market Sectors

Structures

Heavy Industries Oil & Gas Pipe Racks

Petrochemical Rectangular Platforms

Aluminum Smelters Circular Platforms

Fertilizer Plants Pipe Supports

Cement Plants Main Workshop Structures Raw Material Storage Buildings Floor Gratings Staircases Handrails Ladders Temporary Structures

Infrastructure Bridges Steel Bridges

Power & Desalination

Heavy Duty Building Structures

Airports & Seaports Platforms

Railways Equipment Support Structures

Passenger Terminals

Cargo Terminals

Aircraft Hangars

Buildings Segment Residential / Commercial Hi-rise Towers

Shopping Malls Tower Crowns

Leisure Centres Atrium Structures

Multi-storey Car Parks

Roof Structures

(9)

Page 9 of 95

Construction & Site Services

ASSENT aims to provide a complete, integrated solution for customers including site installation and services. We employ a highly qualified construction team, and can provide construction equipment capable of installing 4,000 tons of steel per month.

ASSENT is part of AL Shafar Group Of Companies, The parent company ASGC (AL Shafar General Contracting) is a well established and well reputed company in the field of general contracting and registered and qualified in Steel Erection

Manpower Strength is around 12,000 and equipped with a long fleet of site construction equipments, cranes, lifting and access equipments and scaffolding.

This gives us clients the privilege of offering our clients very competitive prices for complete package of supply and erection.

(10)

Page 10 of 95

(11)

Chamber of Commerce

(12)

Commercial Register

(13)

Abu Dhabi Commercial License and

Chamber of Commerce Certificate

(14)
(15)
(16)
(17)
(18)
(19)
(20)
(21)
(22)
(23)
(24)
(25)
(26)
(27)
(28)
(29)
(30)
(31)
(32)
(33)
(34)
(35)
(36)
(37)
(38)

Design and Engineering

The engineering section employs a team of designers and detailing engineers equipped with the latest and most advanced software for both of these disciplines. All work is closely monitored to ensure that it conforms to all project specifications and standards.

The engineering department services are available for: Completing design for statical systems and connections Composing general-arrangement drawings and

foundation details Shop drawings Material take-off

Construction and assembly drawings

Full and close co-ordination with the customer's engineers.

(39)

Design and Engineering Cont…

The Drafting office is also fully computerized and utilizes the following main software packages:

Package Description Specifications / Code

AutoCad Preparation of GA Drawings &

Fabrication Drawings – Miscellaneous Works

N/A

Strucad 3D Modelling – Detailing of

Connections – Automatic

Generation of Fabrication Drawings, Production & Material Listings

N/A

Tekla - Xsteel 3D Modelling – Detailing of Connections – Automatic

Generation of Fabrication Drawings, Production & Material Listings

(40)

Manufacturing Facilities & Equipment

The plant facility is divided into the following areas:

Area Name: Inventory Stock Area Dimensions: 50m x 172m

Details: Material handling by 2 No’s of Gantry Cranes, 10 ton each.

Area Name: Open yard for Heavy Fabrication Dimensions: 50m x 172m

(41)

Area Name: Project Stock Area Dimensions: 238m x 75m

Details: Handling of material by 15 No’s of over head cranes, each has capacity of 10 tons.

Area Name: Pre-Blasting Area

Details: In feed Conyers - 44m length for feeding the material to pre-blasting through shot blasting machine, out feed Conyers - 24 m length to feed this material to the CNC beam/plate sizing bays.

Pre-Blasting Machines

Brand: Geitart Model: GW 2500

Width (mm) 2500

Height (mm) 600

Speed (m/min) 0.6 to 10

Brand: Geitart Model: GW 2500

Width (mm) 2500

Height (mm) 600

Speed (m/min) 0.6 to 10

Brand: Geitart Model: GW 2500

Width (mm) 2500

Height (mm) 600

(42)

Production Lines Area Name: Production Line 1

Details: CNC Sizing Bay S01, S02 for fully automatic cutting, drilling and copying for Section profiles and plates for Heavy weight structures.

Heavy Fabrication Bay F01 Length 120m, width 23m equipped with 5 no’s x 15 tons capacity over head cranes

2 no’s x 30 tons ground trolleys

Heavy Fabrication Bay F02 Length 120m, width 23m equipped with 5 no’s x 15 tons capacity over head cranes

2 no’s x 30 tons ground trolleys

Production Bay 1 : CNC Machines

Machine: CNC Band Saw Machine Brand: FICEP Model: 1260 LBH Technical Specifications: Sawing capacity at 90° (mm) 1250 x 600 Sawing capacity at 45° (mm) 800 x 600 Sawing capacity at 60° (mm) 500 x 500 Mitering angles +45°/-60°

Machine: CNC Drilling Machine

Brand: FICEP Model: 1203 DF Technical Specifications: Web height (mm) 1220 Flange width (mm) 510 Thicknes s (mm) 100 Diameter (mm) 50 3 axis drilling.

Machine: CNC Thermal Coping

Brand: FICEP Model: 1201 RC Technical Specifications: Volume of sections to be processed (mm) 1220 x 600 x 800 Coping stroke (mm) + 400 / - 400 Controlled axes (no.) 5 + 1

Machine: CNC Drilling &

Thermal Cutting Brand: FICEP Model: TIPO A31

Technical Specifications:

Length (mm) 6000 Width (mm) 3100 Thickness (mm) 130

2 drill heads + 2 thermal cutting heads

(43)

Production Lines Area Name: Production Line 2

Details: CNC Sizing Bay S03, S04 for fully automatic cutting, drilling and copying for Section profiles and plates for Medium weight structures.

Medium Fabrication Bay F03 Length 120m, width 23m equipped with 5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys

Medium Fabrication Bay F04 Length 120m, width 23m equipped with 5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys

Production Bay 2 : CNC Machines

Machine: CNC Band Saw Machine

Brand: FICEP Model: 1260

LBH Technical Specifications: Sawing capacity at 90° (mm) 1250 x 600 Sawing capacity at 45° (mm) 800 x 600 Sawing capacity at 60° (mm) 500 x 500 Mitering angles +45°/-60°

Machine: CNC Drilling Machine

Brand: FICEP Model: 1203 DF

Technical Specifications: Web height (mm) 1220 Flange width (mm) 510 Thicknes s (mm) 100 Diameter (mm) 50 3 axis drilling.

Machine: CNC Thermal Coping

Brand: FICEP Model: 1201 RC

Technical Specifications: Volume of sections to be processed (mm) 1220 x 600 x 800 Coping stroke (mm) + 400 / - 400 Controlled axes (no.) 5 + 1 Machine: CNC Punching& Thermal Cutting Brand: FICEP Model: TIPO

B251 Technical Specifications: Length (mm) 6000 Width (mm) 2540 Thickness (mm) 100 Punching Thickness (mm) 25 Drilling Thickness (mm) 130 Plasma Thickness (mm) 60 Thermal Cutting Thickness (mm) 130

1 drill + 1 thermal cutting + 1 punching + 1 plasma

(44)

Production Lines Area Name: Production Line 3

Details: CNC Sizing Bay S05, S06 for fully automatic cutting, drilling and copying for Section profiles and plates for Medium weight structures.

Medium Fabrication Bay F05 Length 120m, width 23m equipped with 5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys

Medium Fabrication Bay F06 Length 120m, width 23m equipped with 5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys

Production Bay 3 : CNC Machines

Machine: CNC Band Saw Machine

Brand: FICEP Model: 1260

LBH Technical Specifications: Sawing capacity at 90° (mm) 1250 x 600 Sawing capacity at 45° (mm) 800 x 600 Sawing capacity at 60° (mm) 500 x 500 Mitering angles +45°/-60°

Machine: CNC Drilling Machine

Brand: FICEP Model: 1203 DF

Technical Specifications: Web height (mm) 1220 Flange width (mm) 510 Thicknes s (mm) 100 Diameter (mm) 50 3 axis drilling.

Machine: CNC Drilling Machine

Brand: FICEP Model: 1203 DF

Technical Specifications: Web height (mm) 1220 Flange width (mm) 510 Thicknes s (mm) 100 Diameter (mm) 50 3 axis drilling. Machine: CNC Punching& Thermal Cutting Brand: FICEP Model: TIPO

B251 Technical Specifications: Length (mm) 6000 Width (mm) 2540 Thickness (mm) 100 Punching Thickness (mm) 25 Drilling Thickness (mm) 130 Plasma Thickness (mm) 60 Thermal Cutting Thickness (mm) 130 1 plasma + 1 punching

(45)

Production Lines Area Name: Production Line 4

Details: CNC Sizing Bay S07, S08 for fully automatic cutting, drilling and copying for Section profiles and plates for pipes structures and Light weight structures.

Production Bay 4 : CNC Machines

Machine Name: CNC Angle Processing Machine Brand: FICEP Model: A 164

Technical Specifications:

Angles 410 M/mm2 (mm) 160 x 160 x 19 Punching Diameter (mm) 32

Machine Name: CNC Pipe Processing Machine Brand: HGG Model: SPC 1000-6t

Technical Specifications:

Length (mm) 20000 Weight (ton) 2.5

Machine Name: Press Brake Brand: Gizelis S.A. Model: G. Bend 3290

Technical Specifications:

Bending Force (tons) 290

Width (mm) 3100

Thickness (mm) 12

Machine Name: Shearing Machine Brand: Gizelis S.A. Model: G. Cut CNC 3010

Technical Specifications:

Width (mm) 3100

(46)

Production Lines

Area Name: Production Line 5 Built Up Assembly Line Dimensions:48m x 75m

Details: Specialist workshop for heavy / medium assembly of built-up Girders / Columns / Trusses and Boxes

Fully automated using hydraulic jacks system and gantry automatic welding lines.

Production Bay 5 : CNC Machines

Machine Name: Built Up Assembly Machine Brand: CMM Model: BWF 2000 Technical Specifications: Web height (mm) 2000 Flange width (mm) 700 Length (mm) 18000 Speed (m/min) 0.3 to 6

Machine Name: Plate Cutting Machine Brand: ESAB Quantity: 3

Technical Specifications:

Length (mm) 28000

(47)

Area Name: Post-Blasting Dimensions: 238m x 18m

Details: 115m in feed Conyers & collecting this material from all fabrication bays to post blast before painting.

60m out feed Conyers to feed this material to the painting area.

Brand: Geitart Model: CM 3100

Width (mm) 3000

Height (mm) 1500

Speed (m/min) 0.6 to 4

Brand: Geitart Model: CM 3100

Width (mm) 3000

Height (mm) 1500

Speed (m/min) 0.6 to 4

Area Name: Painting Area Dimensions:120m x 20m (no’s x 3)

Details: Equipped with 5 no’s over head cranes 10 ton capacity each, CNC ground trolley for swift movement.

Each Bay is having 1 x 10 tons ground trolley

Machine Name: Spray Painting Machine Brand: Graco Model: NXT Xtreme King 70:1

(48)

Area Name: Generators Area

Details:

Machine Name: Generator Brand: Caterpillar Model: 500 kVA Quantity: 3 Model: 365 kVA Quantity: 3 Model: 455 kVA Quantity: 3 Model: 410 kVA Quantity: 1

Area Name: Gas Station Area Details:

Argon Tank 4500 kg

CO2 Tank

Oxygen Racks 3

Acetylene Racks 2

CO2 tanks, Argon Tanks 100 no’s of gas outlets for 100 MIG Welding Machines

(49)

Quality Control & Quality Assurance

Meeting the essential requirement of ISO 9001:2008

ASSENT has established and implemented ISO 9000 based procedures and has a complete ISO compliant QA Manual that includes all the following procedures:

(50)

Index to the General Description of Work Flow Procedures

The purpose of the following section is to describe in general each activity executed during a project.

Index

 Engineering  Software  R F I ’ s

 Pre Production Planning  Example

 Identification

 Handling Storage and Stacking  Fabrication Drawing

 Beam Processing  Plate Processing  Assembly  Welding

 Curving and Straightening  Non Destructive Testing  Surface Preparation

(51)

Engineering

All Technical information received from the client such as drawings, project specifications, bills of quantity, agreed scope of work and any other pertinent information is forwarded to the Design Department who review all relevant documentation to establish the design parameters. Any clarifications and requests for information are communicated to the client in writing.

Should circumstance arise were the requested information is not available then the Design Department clearly detail any and all assumptions they have made. This information is forwarded to the client.

Design Output

The design output is expressed in the following formats :

 Computer generated calculations prepared on propriety software

 Design sketches containing all the necessary information to allow drafting to generate general arrangement drawings

The General Arrangement drawing package shall consist of but not be limited to:  Anchor Bolt Layout

 Roof Framing Plan  Elevations

 Connection Details (if requested) Design Review

During the Design Sketch and calculation stage, the activities of the individual designer are monitored by the Design Department Supervisor

On completion of the calculations the designer details in writing all parameters used in the calculation, the Design Supervisor verifies that the design parameters are correct as per contract documentation.

Should the contract require the formal submittal of the design calculations to the client then the Design Supervisor forwards the package to the Engineering Manager for Approval. All General Arrangement drawings developed from design sketches are reviewed by the drafting department for drawing accuracy and signed as checked then the package is forwarded to the Design Department for review by the Designer against his design sketches to determine if they have been correctly interpreted. The design package is then forwarded to the client for review and comment.

(52)

Design Validation

All design packages, as detailed in the contractual requirements are forwarded to the client for review comment and approval prior to the start of fabrication. Should any comments or status codes be applied to the submitted design package other than approved, these comments are addressed and another submittal is made to the client. This process is repeated until the design is acceptable to the client.

Design Changes

When a change or modification to the design is required, the originator of the change documents the required modification and forwards written instructions to the relevant departments. Depending on the source of the change notice, the information is transmitted as follows :

 Internal Change notice Information to be forwarded to the Design Supervisor for review and action

 External (Client) notice Information to be forwarded to the Design Supervisor for review and action

All change notices either in the form of commented drawings or written instructions are filed in the Project File for future reference.

Software

ASSENT has standardized the computer software used in order to ensure compatibility with clients and other third parties involved in the project:

 Microsoft Office General Office

 Primavera / Microsoft Project Planning

 Autocad 2D Drafting

 Strucad 3D modeling and drafting

 Tekla - Xsteel 3D modeling and drafting

 Staad Pro 2D & 3D Design

 Master Key Connections Design

 ProKon Connections Design

 PMS system Production Tracking & Monitorng

RFI ‘ s

If during the review, engineering design, or drafting cycles, additional information or clarifications are required, a formal RFI is raised and issued to the client. The issue and return of the RFI is recorded.

(53)

Pre-Production Planning

On award of the contract the Planning Department review the overall structure to establish the following :

 Overall production requirements per week and month

 Sequence of contract execution in order to support the clients program  Priority for each sub structure

 Engineering and Drafting planning  Procurement planning

The 3D modeling & drafting systems utilized by ASSENT produce a full Bill of Quantities during the "3 D" modelling phase of the drafting cycle. This information is transferred to the Stru M.I.S evolution Software Program where the pre-determined priority ratings for each Sub-structure are automatically assigned to the individual item

This allows the Stru M.I.S evolution Software Program to automatically generate a detailed (item by item) production program which is then grouped together to give the daily production requirements for all fabrication activities.

Due to the modular format of the Stru M.I.S evolution Software Program the individual module and the relevant information required to control a specific activity can be downloaded onto the computer system of any associate company. This allows them to conduct their area of the operation in parallel with the overall project requirements.

(54)

Example

Material Preparation

The relevant material preparation modules of the Stru M.I.S evolution Software Program is forwarded to the relevant departments and all the production scheduling information downloaded.

The engineering department also issues the plates and beam shafts drawings in the format required to program the CNC equipment used in the material preparation.

As the material is processed in accordance with the production schedule, the Stru M.I.S evolution Software Program is regularly updated by the computer system controlling the CNC equipment or by manual entry periodically through the shift. This updated information allows monitoring the progress of the contract piece by piece.

This example is applicable to each individual stage of the fabrication process.

Identification

All material received either from the mill or merchants stock is inspected on receipt for:  Completeness of order

 Compliance with Purchase Order requirements  Transport Damage

 Identifiable to valid mill certificate

As the material is processed through the preparation stage of the fabrication process the heat number of the individual piece is logged onto the cutting schedule against its unique position / item number. This information is then transferred to the Stru M.I.S evolution Software Program providing material trace-ability for each individual piece back to the mill certification

Handling, Storage and Stacking

Steel plates and sections are either delivered to the preparation facility on a JIT basis or stored and stacked in a ASSENT designated area. All material is stored and stacked in such a manner as to prevent distortion twisting or bending.

Consumable Storage

All welding rods painting and blasting material are stored in accordance with the anufacturer's recommendations.

(55)

Fabrication Drawings

Material preparation drawings are issued to the Preparation Facility in electronic format and are identified by phase substructure and cutting schedule.

The assembly drawings are issued either in electronic format or paper copy again they are identified by phase substructure and assembly schedule

Beam Processing

During the cutting operation each beam is marked with it's item / position number to allow identification and trace-ability through the rest of the fabrication process.

After the beam has been marked and cut, and depending on the requirements, the beam is either moved directly to the transit lay-down area or processed thorough the CNC drill station.

Beam Preparation Equipment

Please refer to the list of equipment attached.

Plate Processing

Plates are processed using various methods depending on thickness contract requirements and end usage

If the thickness of the plate is 12 mm or less, the plates can be sheared to the required size, however the end usage and contract requirements are also considered before work is detailed to these machines.

Once the plate has been cut to the correct size and shape the final operation is producing the holes. This can be done either by drilling or punching. Again thickness, hole dia, and contract requirements are considered before allocating the work to the various machines During the cutting operation, each plate is marked with it's item / position number to allow identification and trace-ability through the rest of the fabrication process.

All cut edges can be dressed to remove burrs, dross and irregularities. Holes are dressed as required to provide a smooth contoured surface.

(56)

Plate Processing Equipment

Please refer to the list of equipment attached.

Once the preparation of the material has been completed the material is then ready for assembly.

Assembly

When the material has passed it's inspection, it is released to the assembly / welding yard were it is segregated in the lay down yard prior to release to assembly.

The material is assembled in accordance with the fitting schedule issued by Stru M.I.S evolution Software Program.

The material is assembled in accordance with the fabrication drawings in such a manner that they are not bent, twisted or otherwise damaged, and any deformation is within the stated tolerances.

All items, after assembly, are fully dimensionally checked, any deviations are corrected immediately.

The results of the dimensional check are logged onto the Stru M.I.S evolution Software Program.

Welding

All welding operations are carried out in accordance with ASSENT’s approved welding procedures by independently qualified welders.

All procedures and welder qualifications are in accordance with AWS D 1.1 (2010) as well as British standard BSEN 15614-1:2004 and BSEN 287-1:2004.

During the welding operation all welders are continually monitored to ensure that the welding parameters, as detailed in the relevant procedure, are adhered to and that the level of workmanship is maintained.

All items, after completion of welding are visually inspected against the requirements of AWS D 1.1 (2010) for compliance. Any visual discontinuity is marked and repaired immediately. Only when the item has been fully passed and accepted will it be released to blasting and painting

All welding inspections are entered onto the Stru M.I.S evolution Software Program.

(57)

Curving and Straightening

When it is necessary to curve or straighten components one of the following methods may be used:

 Mechanical - taking care not to cause indentations or changes in cross section  Local Application of Heat - ensuring that the temperature does not exceed 650°C Non-Destructive Testing

Non destructive testing is carried out in accordance with the contract requirements, all NDT inspections are conducted by an independent 3rd party specialist company with AWS D1.1(2010) acceptance standards used for determining the acceptability of the weld.

The results of all NDT examinations are entered on the Stru M.I.S evolution Software Program.

Surface Preparation and Painting

The surface preparation / blast cleaning produces the required anchor pattern and cleanliness level as detailed by the paint manufacturer to ensure paint adhesion to the surface.

The Painting Inspector carries out profile checks at the start of each blasting run to ensure that the required profile and cleanliness levels are met.

All material once blasted are primed within 4 hours to prevent rust bloom. The painting operation is conducted ony if the following conditions are met: (as specified by the paint manufacturer)

 The surface temperature shall be at least 3 degrees centigrade above the dew point and the Relative Humidity (RH%) shall not exceed 85%.

 Visual checks on the surface shall be carried out to ensure none of the following point exist oil, grease, dirt, loose paint, rust and other surface contamination.

 There is protection from adverse weather conditions, such as wind that may blow sand, or other foreign bodies on the painted surface or it may disrupt the paint pattern or cause dry spray.

 Paint stripe-coating shall be applied to all welds and corners if required.

 Primers, intermediate coats and top coats shall be contrasting colours, if more than one application is required to achieve the required film thickness, then the same colour should be used. Reference to Client's specifications must be made before implementation.

 Finished coatings shall be free of runs, drips, dry spray etc. Areas that are cracked, damaged or below minimum thickness shall be repaired prior to dispatch

(58)

All defective areas are to be cleaned with solvents, detergents or clean water as required All repair areas blast cleaned to the metal surface, with the edges being feathered back at least 50 mm beyond the clean metal surface. For areas less than 1000 mm2, brush coating may be acceptable, but with reference to Client's specifications , areas greater than 1000 mm2 the paint shall be applied as to the original specification.

Painted items shall be handled with proper care so that damage to the paint is minimised. Structural steel items shall not be handled until paint has thoroughly dried.

Care shall be taken to avoid abrasions and other damage.

Nylon / Canvas slings shall be used for handling the coated steelwork or when steel slings are to be used, they shall not be choked with wood to avoid / limit contact with coated steelwork.

Delivery of Finished Product

Each piece of steelwork shall be distinctly marked with Item No and bar code before dispatch in accordance with the fabrication drawing . Steelwork shall be stacked on timbers in order to provide easy handling

All attachments and fittings shall be securely attached. Loose plates and smaller items shall be either boxed or wired together and then wired to larger parts.

Floor plates shall be bundled for shipment

Bolts, Nuts and Washers shall be packed in strong bags with the Nuts and Washers assembled on the Bolts.

The client should be informed of the time of delivery and delivery notes shall accompany all deliveries.

The sequence of shipment shall be such as to expedite erection and minimise field handling of material

(59)

SAMPLE DOCUMENTATION ONLY

PROCESS CONTROL PROCEDURE

Document No. ASSENT-QMS-P09

(60)

1.0 PURPOSE

The purpose of this procedure is to identify and define the steps to be taken for controlling and monitoring the workmanship, fabrication and surface preparation activities in order to meet the specified quality requirements

2.0 SCOPE

This procedure outlines the responsibilities, method to control workmanship and fabrication activities to achieve the required quality during the fabrication of all structural steel products.

3.0 TERMS AND DEFINITIONS

ASSENT Al Shafar Steel Engineering L.L.C

QC Quality Control

ITP Inspection and Test Plan

WPS Welding Procedure Specification

PQR Procedure Qualification Record

NDE Nondestructive Examination (Third Party Testing)

4.0 RESPONSIBILITIES 4.1 QA Manager

To develop and implement the management of the Quality Procedures which will govern the standard of quality on the contract

4.2 Material Control Engineer

Ensures that applicable procedures for procurement of material, receipt, checking quality of material coordinating with QC Engineer, storage and issue of material, comply with the Contract requirements.

4.3 QC Engineer

Commissioning and overseeing third party inspection services (NDT) and ensuring that all relevant shop floor inspections and checks are conducted and documented. Coordinating inspection of purchaser supplied materials. Coordinating the collation and storage of all project specific quality records and documentation;

4.4 QC Inspector

To ensure that all welding and fabrication activities which are undertaken conform to the approved procedures, and to notify the QC engineer of any non-conformances. To conduct patrol inspections to monitor the welding parameters, consumables and techniques being used are in accordance with the approved procedures to conduct visual and weld dimensional checks for conformance to requirements.

(61)

4.5 Dimensional Checker

To ensure that the overall dimensions of a specific piece or item of a structure comply with those stated on the drawing.

4.6 Fabrication Workshop Supervisor

To compile and issue cutting schedules in conjunction with the Project Coordinator and Drawing office. Verify that all cutting schedules are completed and all the items listed are within the specified tolerances. Deploy the workforce for maximum efficiency and ensure the standard of workmanship meets requirements. Raise orders to purchase in conjunction with the Materials Controller to ensure adequate stock levels are maintained.

4.7 Discipline Foreman (Cutting Fabrication Welding Painting)

Each discipline foreman is directly responsible to the Fabrication Workshop

Supervisor. They are responsible for the level of workmanship, shop floor organization and control of their individual discipline.

5.0 PROCEDURE 5.1 Identification

5.1.1 Traceability of Steel

All steels materials received, ex-mils or from Merchant’s stock, shall have a valid material (Mill) certificate

The material shall be received into stock with the manufacturers heat number marked on to the item, this heat number traceability shall be maintained on cutting list for each item.

5.1.2 Fabrication/Shop Drawings

The fabrication / shop drawings shall be prepared by our in-house drafting department all drawings shall be checked and signed as Checked by ASSENT Draughts men for accuracy prior to issue to the Client for Approval, if contractually required

Fabrication & Shop drawings shall show all the necessary details and dimensions to enable fabrication of components to proceed, and will be controlled in accordance with the Document Control Procedure "ASSENT-QMS-P01"

A latest controlled copy of fabrication / shop drawings shall be issued to the Fabrication Workshop Supervisor and QC Engineer.

5.2 Marking

5.2.1 All Steel material received into stock shall be marked with the manufactures heat number ref Material Control Procedure "ASSENT-QMS-P16".

5.2.2 All material used in the fabrication shall maintain full traceability.

5.2.3 The Fabrication Supervisor shall make a requisition to the Material Control Engineer for material to be issued to Fabrication Shop, by means of beam and plate cutting schedules.

5.2.4 Steel sections will be marked prior to cutting and shaping as detailed in the fabrication drawings and cutting schedules.

5.2.5 QC Inspector shall randomly check individual parts to ensure correct marking prior to cutting, shaping or drilling and sign the cutting schedule to record his check

(62)

5.3 Cutting and Shaping, Bending and Bolt Holes

5.3.1 Beams will be cut in accordance with Beam Cutting Schedule.

5.3.2 Cutting and shaping of steel may be carried out by shearing, sawing, grinding, machine flame cutting except that where machine flame cutting is impractical, hand flame cutting may be used.

5.3.3 Deformation and burrs resulting from cutting shall be corrected and ground smooth. 5.3.4 Where cutting surfaces are required to transfer compressive loads by bearing (e.g.

column on base plates), they shall be milled to provide an adequate bearing surfaces. 5.3.5 Holes may be made by drilling and punching. Slotted holes shall be made by one of

the following methods:

 Punch in one operation

 Formed by drilling two holes and completed by gas cutting and grinding 5.3.6 Holes in steel plates over 10 mm thick shall be drilled. The diameter of the holes for

bolts (other than anchor bolts) shall not exceed nominal bolt diameter by more than 1.6 mm unless otherwise specified by Client.

5.3.7 Tolerance of the holes shall be in accordance with the approved drawings and Client’s specifications.

5.4 Machining

The thickness of elements shown on the drawings as requiring machining shall mean the minimum thickness after the machine operation.

5.5 Dressing

Cut edges shall be dressed to remove burrs, dross and irregularities. Holes shall be dressed as required to remove burrs and protruding edges.

Sharp edges shall be dressed, but a 90 deg. rolled, cut, sheared or machined edge is acceptable without further treatment.

5.6 Assembly 5.6.1 General

All components shall be assembled in a manner such that they are not bent, twisted or otherwise damaged. (Ref Inspection and Test Plan ASSENT-QMS-18). Drifting of holes to align the components shall be permitted, but must not cause damage or distortion to the final assembly.

5.6.2 Curving and Straightening

When it is necessary to curve or straighten components, one of the following methods may be used (or as stated in the project specifications):

 Mechanical means, taking care of indentations or change of cross sections;  The local Application of heat, ensuring that the temperature is carefully

controlled, by using crayon type temperature stick and does not exceed 650 deg. Centigrade;

These operations will be monitored and recorded by the Quality Control Engineer or Inspector After curving or straightening, welds within the area of curving or straightening shall be visually inspected. Welds which are to be subject to Non-destructive Examination shall have these tests carried out after curving or straightening.

(63)

5.7 Welding 5.7.1 General

All welder qualification certification and weld controls will be in accordance with Weld Control "ASSENT-QMS-21".

The size of all structural fillet welds shall be as stated on the approved fabrication drawings, all welds shall be dressed smooth, free from porosity, cracks, holes and finished to match adjacent surfaces.

All pre-qualified WPS shall be made available to the Client for his review and approval prior to commencement of welding activities or new WPS with PQR carried out if no current qualification is available for the required process.

5.7.2 Preparation of Base Metal

Preparation of base metal shall be in accordance with the approved WPS. Surfaces and edges to be welded shall be free from loose scale, slag, rust, grease, and any other foreign matter.

Joint surfaces shall be free from laminations and tears. NDE shall, if a project requirement shall be carried out on weld preparation to ensure no laminations are present prior to welding.

Preparation of edges by gas cutting shall, wherever practicable, be done by a mechanically guided torch.

5.7.3 Assembly

The parts to be jointed by fillet welds, separation between facing surfaces of lap joints and butt welds, shall be in line with approved WPS.

The parts to be jointed by groove welds shall be brought into correct alignment. The members to be welded shall be held in the correct positions by bolts, clamps, wedges, guy lines, struts or other suitable devices, or by tack welds until welding has been completed. The use of jigs and fixtures is recommended where practicable. Suitable allowances shall be made for war page and shrinkage.

In assembling and joining parts of a structure of built-up members and in welding reinforcing parts to members, the procedure and sequence shall be exercised to minimize distortion and shrinkage.

Dimensional check for the assembly before welding shall be carried out by the Dimensional Checker, and these inspections will be recorded on the form (Form # ASSENT-QMS-P17F04) further to this inspection the work will be monitored by inspection on a continuous basis through random patrol inspections recorded on form Daily Patrol Inspections (Form # ASSENT-QMS-P17F05)

5.7.4 Electrodes and Automatic Coils

Electrodes and automatic Coils shall be procured, stored, issued and controlled in accordance with ASSENT’s procedure Welding Consumable Control “ASSENT-QMS-P22".

(64)

5.7.5 Preheat and Interpass Temperature

Minimum Preheat and Interpass Temperature shall be exercised as detailed in the approved WPS.

5.8 Inspection

These activities shall be controlled in accordance with procedure of Inspection and Testing "ASSENT-QMS-P18" and governed by the Test and Inspection Plan

All items forming part of the welded assemblies will be checked for freedom from distortion and straightness, dimensional accuracy and conformity to the drawings and for compliance with project specifications and ITP to ensure that the manufacturing process is correctly implemented.

NDE inspection of welds shall be carried out in accordance with the requirements stated in the project specifications and ITP

On completion of welding and testing, final inspection of assembled pieces shall be made by QC Engineer or nominee prior to being dispatched for blasting and painting. The results and report numbers of all inspections carried out during fabrication shall be recorded in the fabrication check-list (Form # ASSENT-QMS-P17F02)

5.9 Surface Preparation, and Painting

All surface preparation, pruning and top coating, will be in accordance with the ASSENT’ s procedure of Paint Control " ASSENT-QMS-23".

6.0 RETENTION PERIOD OF RECORDS:

Record No. Retention Period

NDT Request and Report Log ASSENT-QMS-P17F01 One Year

Fabrication Check List ASSENT-QMS-P17F02 One Year

Release for Painting ASSENT-QMS-P17F03 One Year

Daily Dimensional Control Reports ASSENT-QMS-P17F04 One Year

Patrol Inspection Reports ASSENT-QMS-P17F05 One Year

Daily Painting Inspection Report --- One Year

Plate Sizing & Cutting Check List --- One Year

Beam cutting Schedule --- One Year

(65)
(66)
(67)
(68)
(69)
(70)
(71)
(72)
(73)
(74)
(75)
(76)

Environment, Health & Safety

ASSENT EHS STATEMENT

ASSENT’s Environment, Health and Safety (EHS) Policy and Management System is committed to:

 Develop, implement and manage Environmental, Health and Safety policies and work processes at all ASSENT facilities.

 Provide a safe and healthy work place and environment, to avoid injury or damage to our employees, contractors, visitors and the public, the environment and

company assets.

 Comply with applicable EHS regulatory requirements at each location.

 Audit EHS activities at regular intervals at each facility to monitor its effective implementation and to take corrective actions, wherever required.

 Create a proactive EHS culture through awareness, training and motivation, to achieve continual improvement in EHS performance.

(77)

List of Current Projects by ASSENT

PROJECT TITLE END USER ROLE SCOPE OF WORK TONNAGE

Western Range DSO 

Iron Ore ‐ SMPP  Arcelor Mittal  SUBCONTRACTOR    SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 3,300  LR2 Refinery Project  Laffan Refinery  Company Limited 2  SUBCONTRACTOR    SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 4,500  Sadara Desalination 

Plant  Marafiq  SUBCONTRACTOR

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL

1,200 

Abu Dhabi Plaza  Aldar  SUBCONTRACTOR

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL

12,000  Al‐Zour North Power 

Plant  HHI  SUBCONTRACTOR

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 9,400  BHS Link Bridge  Backbone  Dubai Aviation  Engineering Projects  Corporation  SUBCONTRACTOR SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 585  CMT Expansion  Dubai Aviation  Engineering Projects  Corporation  SUBCONTRACTOR SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 1,900  Louvre Abu Dhabi  Tourism  Development &  Investment Company  SUBCONTRACTOR  SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 3,500  Western Range  DSO 

Iron Ore ‐ Buildings  Arcelor Mittal  SUBCONTRACTOR 

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 1,800  Ras Abou Fontas 2  Desalination Plant  Qatar Electricity and  Water Company  SUBCONTRACTOR  SUPPLY &  FABRICATION OF  STRUCTURAL STEEL 800  KOC Telemetry 

Project  Kuwait Oil Company  SUBCONTRACTOR 

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL

1,096 

SSAGS  Shell  SUBCONTRACTOR 

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL

3,200 

West Qurna 1   Exxon Mobil  SUBCONTRACTOR 

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL

10,000 

Badra Oil Filed  Gazprom  SUBCONTRACTOR 

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL

4,500 

Rabigh 2  Saudi Aramco  SUBCONTRACTOR 

SUPPLY &  FABRICATION OF  STRUCTURAL STEEL

12,000 

(78)

List of Completed Projects by ASSENT

PROJECT TITLE END USER ROLE SCOPE OF WORK TONNAGE

Maaden Alumina 

Refinery  Maaden  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL  5,000  Shah Gas PKG 2  Al Hosn Gas  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  900  Rumaila Field  British Petroleum  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  400  Booster Station 171   Kuwait Oil Company  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  5,000  Qusahwira Field  ADCO  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  3,500  Shah Gas PKG 1  Al Hosn Gas  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  900  Western Range  DSO 

Iron Ore  Arcelor Mittal  SUBCONTRACTOR 

FABRICATION OF  STRUCTURAL STEEL  760  Qurayyah Power  Plant  Hajr Electricity  Company  SUBCONTRACTOR  FABRICATION OF  STRUCTURAL STEEL  12,750  Shah Sulphur Station 

and Pipeline  Al Hosn Gas  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL  5,300  Green Anode Plant & 

Rodding Shop  EMAL  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL  4,000  Aktau Desalination 

Plant  Maek Kazatompron  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL  170  RRE 7 Expansion  TAKREER  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  1,300  Shah Gas PKG 4  GASCO/Al Hosn gas  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  9,400  BOROUGE III – O & U  BOROUGE  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  12,550  Bab Thamama  ADCO  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  6,400  South Yoloten   Turkmengas  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  8,000  Maaden Rolling Mill  Maaden  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  8,000  RRE 1 Expansion  TAKREER  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  17,500  Gas Sweetening  Qatar Petroleum  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  4,150  The One Tower  Al Mazroei  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  1,000  RRE 3   TAKREER  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  7,550  Booster Station 132   Kuwait Oil Company  SUBCONTRACTOR  FABRICATION OF 

STRUCTURAL STEEL  4,500  Sohar II & Barka III  Oman Power and 

Water Company  SUBCONTRACTOR 

FABRICATION OF 

(79)

Sample Projects

Project Name: Booster Station 132  Location: Kuwait  Client: Kuwait Oil Company  EPC Contactor: SK Engineering & Construction     

(80)

Project Name: Gas Sweetening Facilities  Location: Qatar 

Client: Qatar Petroleum  EPC Contactor: Petrofac 

(81)

Project Name: Qurayyah Power Plant  Location: Saudi Arabia  Client: Hajr Electricity Co.  EPC Contactor: Samsung C&T Corporation               

(82)

  Project Name: South Yoloten Field Development  Location: Turkmenistan  Client: Turkmengas  EPC Contactor: Petrofac      Project Name: Louvre Museum  Location: UAE  Client: Tourism Development Investment Company  EPC Contactor: Waagner Biro 

(83)

Project Name: Borouge 3 Utilities & Offsites  Location: UAE  Client: BOROUGE  EPC Contactor: Hyundai Engineering & Construction  Project Name: Shah Gas Development Pkg 4  Location: UAE  Client: Al Hosn Gas  EPC Contactor: Samsung Engineering 

(84)

List of Projects Executed by ASSENT Senior Management

ASSENT is a recent addition to Al-Shafar Group of Companies, but has the advantage of a Senior Management Members who have a large experience in the structural steel fabrication business in the Middle East and in particular, the UAE and GCC countries, in all major market sectors and in particular the Oil & Gas and Petrochem Sectors.

As an indication of the background and experience of the management in these fields, we are pleased to attach the list of projects been executed by ASSENT’s Senior Management Team

S1  Project Title  Client End User Location Steel Tonnes  Year

1  Yansaleb Olefin   Technip‐ Italy SABIC Saudi 9,200   2006 2  Common Sulphur Project  Al Jaber Energy Qatar Gas Qatar 4,800   2006 3  Taweelah Extension‐ GAS  Trubine Building  Arabian  Construction  Co.  Siemens Power Abu Dhabi 800   2006 4  RGX6‐ RASGAS Onshore  Expansion‐ Train 6 & 7  Chiyoda‐  Technip Joint  Venture  RASGAS Qatar 13,832   2006

5  OGD‐ III  Bechtel  GASCO Abu Dhabi 21,400   2005

6  Dubai Airport Expansion  Phase II‐ Duty Free  Expansion  DCA  Dubai Civil  Aviation  Dubai 2,500   2005 7  Dubai Airport Expansion  Phase II‐ Cargo Mega  Terminal  DCA  Dubai Civil  Aviation  Dubai 6,500   2005 8  Dubai Aiport Expansion‐ Phase II  Cargo Mega Terminal ULD  Structure  SD Middle East Dubai Civil  Aviation  Dubai 4,000   2004 9  Dubai Aiport Expansion  Ohase II‐ CUC  Group Five Dubai Civil  Aviation  Dubai 1,000   2005 10  Sohar Refinery Project  JGC   JGC Abu Dhabi 828   2004         11  AX 149‐ Structural Steel  works for the  Dubai Airwing  Dar Al  Handasah  Dept. of Civil  Aviation  Govt.of Dubai  Dubai 21,000   2004 12  Mall of the Emirates  Develop  WP 4150‐ Snow Centre  Al Nabodah  Laing O'  Rourke  Mall of Emirates Dubai 4,250   2004 13  Umm Al Nar IWPP  Arabian  Construction  Co.  IWPP Abu Dhabi 4,300   2004

14  Amran Cement Plant  IHI  Armant Cement Yemen 1,340   2004 15  Arzew Desalination Plant  Hitachi Zosen Algeria 

Government 

Algeria 450   2004

16  Kestrel Boiler Supports  CMI  DUBAL Dubai 450   2004 17  Sahara Mall Interchange  Athena SA/  NCTC  Government of  Sharjah  Sharjah 170   2003 18  Sajja/ Dhaid Interchange  China Harbor  Engineering  Government of  Sharjah  Sharjah 290   2003

(85)

S1  Project Title  Client  End User  Location  Steel Tonnes  Year  19  Kestrel Project‐ Phase II  DUBAL  DUBAL Dubai 8,500   2003 20  Gas Metering Skids  Alderly FZE ARAMCO Saudi 

Arabia 

80   2003

21  Al Udied Package 4 Hangar  Qatar ACC Qatar MOD Qatar 400   2003 22  GAMCO Hangar  Al Hamed 

Development  & 

Construction 

GAMCO Abu Dhabi 2,000   2003

23  Sharjah Cement  IHI  Sharjah Cement Sharjah 1,250   2001 24  Al Bateen Airbase‐  MW2273  Sideco Gen.  Contracting  DMW‐ Dubai Abu Dhabi 550   2001 25  Ruwais Upgrading Facilities  Technip‐ Abu  Dhabi  GASCO Ruwais 1,450   2000 26  Al Taweelah A2 Power  Station  Arabian  Construction  Co.  Abu Dhabi Water  &   Electricity  Abu Dhabi 3,000   1999 27  Hawiyah Gas Plant  JGC  Corporation  Saudi Aramco KSA 2,500   1999 28  Aramco R & D Laboratory  Jaffar Al  Hamood Est.  Saudi Aramco KSA 850   29  OGD‐2 Package 1,2,3,4,5  Technip/  Bechtel  ADNOC Abu Dhabi 1,200   1999 30  ASAB Gas‐ Gather & Inj  Project  Mannesmann  Demag AG  ADCO Abu Dhabi 1,440   1999 31  TD‐ 48 DCA Expansion  HMR JV  Dubai Civil  Aviation  Dubai 16,500   1998 32  Codor Project‐ Pipe Rack  Alstom Power Dubai Aluminum 

Co.  Dubai 1,125   1998 33  Codor Project‐Boiler  Supports  CMI‐ Belgium Dubai Aluminum  Co.  Dubai 805   1998 34  Ras lafan‐ Qatar Gas  William Hare  Ltd.  Qatar Gas Qatar 1,400   1997 35  Oman LNG Building  Bhawan Engg.  Co.  Oman LNG Oman 800   1997

19  Kestrel Project‐ Phase II  DUBAL  DUBAL Dubai 8,500   2003 20  Gas Metering Skids  Alderly FZE ARAMCO Saudi 

Arabia 

80   2003

21  Al Udied Package 4 Hangar  Qatar ACC Qatar MOD Qatar 400   2003 22  GAMCO Hangar  Al Hamed 

Development  & 

Construction 

GAMCO Abu Dhabi 2,000   2003

23  Sharjah Cement  IHI  Sharjah Cement Sharjah 1,250   2001 24  Al Bateen Airbase‐  MW2273  Sideco Gen.  Contracting  DMW‐ Dubai Abu Dhabi 550   2001 25  Ruwais Upgrading Facilities  Technip‐ Abu  Dhabi  GASCO Ruwais 1,450   2000 26  Al Taweelah A2 Power  Station  Arabian  Construction  Co.  Abu Dhabi Water  &   Electricity  Abu Dhabi 3,000   1999

(86)

S1  Project Title  Client  End User  Location  Steel Tonnes  Year  27  Hawiyah Gas Plant  JGC  Corporation  Saudi Aramco KSA 2,500   1999 28  Aramco R & D Laboratory  Jaffar Al  Hamood Est.  Saudi Aramco KSA 850   29  OGD‐2 Package 1,2,3,4,5  Technip/  Bechtel  ADNOC Abu Dhabi 1,200   1999 30  ASAB Gas‐ Gather & Inj  Project  Mannesmann  Demag AG  ADCO Abu Dhabi 1,440   1999 31  TD‐ 48 DCA Expansion  HMR JV  Dubai Civil  Aviation  Dubai 16,500   1998 32  Codor Project‐ Pipe Rack  Alstom Power Dubai Aluminum 

Co.  Dubai 1,125   1998 33  Codor Project‐Boiler  Supports  CMI‐ Belgium Dubai Aluminum  Co.  Dubai 805   1998 34  Ras lafan‐ Qatar Gas  William Hare  Ltd.  Qatar Gas Qatar 1,400   1997 35  Oman LNG Building  Bhawan Engg.  Co.  Oman LNG Oman 800   1997

(87)
(88)

Manpower List – Category: Staff

ASSENT OFFICE STAFF

Department  Designation  Number  Total 

Executive's Office  Managing Partner  1        Executive Assistant  1              Operations  General Manager  1              Finance  Finance Manager  1        Chief Accountant  1        Accountants  3              HR & Administration  HR & Admin Manager  1        HR Executive  1        PRO  1        Receptionist  1        Document Controller  1        Transport‐in‐Charge  1        Camp Boss  2              Sales and Estimation  General Sales Manager  1        Area Sales Engineer  3        Estimation Engineer  3        Steel Detailer  1        Marketing Executive  1        Sales & Marketing Assistant  1              10  Project Management  Projects Director  1        Contracts Manager  1        Project Managers  4        Project Engineers  5        Site Engineer  2        Construction Manager  1        Quantity Surveyor  1        Document Controller  1              16  Engineering  Engineering Manager  1        Design Engineer  6        Steel Detailers  20        Steel Checkers  6    

(89)

   CNC Programmer  1       Document Controller  2             36  IT  IT Manager  1       IT Engineers  2       Attendance Officer  1                         Procurement   Procurement Auditor  1       Sr. Procurement Officer  1       Procurement Executive  1       Procurement Officer  1       Custom Coordinator  1             Inventory & Warehouse  Inventory & Warehouse Manager  1       Material Planner  1       Material Expeditor  2       Store Foreman  1       Storekeepers  8       Store Clerk  1             14  Production  Head of Production  1       Production Engineer  2       Assistant Engineer (MPS)  1       Welding Foreman  9       CNC Programmers  2       CNC Foreman  1       Production Coordinator  1       MPS Supervisor  1       MPS Chargehand  1       MPS Foreman  1       Blasting & Painting Foreman  1       Blasting Foreman  1       Painting Supervisor  3       Painting Foreman  3       Fabrication Foreman  15       Erection Foreman  1       Site Formean  1       Preparation Foreman  1       Office Clerk  1       Charge hand  8       Erection Charge hand  1       Document Controller  1             57 

(90)

Facilities/Maintenance  Facility Manager  1       Maintenance Manager  1       Maintenance Supervisor  1       Maintenance Foreman  3       Maintenance Engineer  1       Electrical Foreman  3             10  QA/QC  QA/QC Manager  1       QC Engineers  4       QC Inspector (Painting)  2       Document Controller  2             Printing  Area  Printing Officer  1             HSE   HSE Manager  1       Safety Supervisor  1       Safety Officer  1       Asst. Safety Officer  2       Site HSE Officer  1       Company Nurse  3             Dispatch/Delivery  Dispatch Supervisor  1       Dispatch Clerk  1       Driver ‐ Heavy Truck  3       Driver  10       Document Controller  3       Dispatch Foreman  1             Office Staff Total   196 

References

Related documents

Results suggest that the probability of under-educated employment is higher among low skilled recent migrants and that the over-education risk is higher among high skilled

In this PhD thesis new organic NIR materials (both π-conjugated polymers and small molecules) based on α,β-unsubstituted meso-positioning thienyl BODIPY have been

Community hospitals provide a wide range of services, covering the whole spectrum of care provision, from pre- ventative [20, 21] and primary care [22, 23], through to

working class. Bernard; Champaign IL: Human KiMtics PubliShers Inc.. Soccer in America continued to grow within the working class and along ethnic divisions into the early 1890's.

On the other hand, the study of these equations fits nicely into the the larger context of (stochastic) partial differential equations, in particular Hamilton-Jacobi, heat

18 Francee Anderson, Sylvia Bremer and Dorothy Cumming received their training, and their start in their profession, at Sydney’s three major schools of elocution, Lawrence Campbell’s

Prereq or concur: Honors standing, and English 1110 or equiv, and course work in History at the 3000 level, or permission of instructor.. Repeatable to a maximum of 6

It is recognized universally that menstrual disturbances may accompany and even may precede thyroid dysfunction .In the present study thyroid status of patients presenting