• No results found

PRINCE2_LESSON_13.pdf

N/A
N/A
Protected

Academic year: 2021

Share "PRINCE2_LESSON_13.pdf"

Copied!
32
0
0

Loading.... (view fulltext now)

Full text

(1)

Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS Limited. All rights reserved. PRINCE2® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. AXELOS® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.

The Swirl logo™ is a trade mark of AXELOS Limited, used under the permission of AXELOS Limited. All rights reserved. Copyright 2014, Simplilearn, All rights reserved.

Lesson 13—Directing a Project Process

PRINCE2

®

Foundation

(2)

● Identify who is responsible for the Directing a Project process ● State the purpose and objective of Directing a Project process

● Identify and describe the activities in the Directing a Project process

Objectives

After completing this lesson, you will be able to:

(3)

According to PRINCE2® methodology, the Project Board is responsible for making all the decisions in the project.

● Depending on the size and complexity of the project, the Project Board can control the project

formally via written reports and a signed stage approval.

● The Project Board can also exercise control informally by verbal communication of information and

decisions.

(4)

The purpose of the Directing a Project process is to enable the Project Board to be accountable for the project’s success by making key decisions and exercising overall control while delegating day-to-day management of the project to the Project Manager.[1]

(5)

Objective of Directing a Project

The objective is to ensure that:

● there is authority to initiate the project and deliver the

project’s products;

● management direction and control are provided throughout

the project’s life, and the project remains viable throughout its life;

● corporate or programme management has an interface to the

project; and

(6)

Directing a Project—Overview

(7)

Directing Project activities are Project Board oriented. It comprises the following activities:

Directing a Project—Activities

● Authorise initiation ● Authorise the project

● Authorise a Stage or Exception Plan ● Give ad-hoc direction

(8)

While authorising the initiation, the Project Board performs the following actions:

● Reviews and approves the Project Brief and the Project Product Description ● Confirms the customer’s quality expectations and the acceptance criteria ● Verifies that the outline Business Case demonstrates a viable project ● Reviews and approves the Stage Plan for the initiation stage

● Obtains or commits the resources needed by the Stage Plan for the initiation stage ● Informs all stakeholders and the host locations that the project is being initiated ● Authorises the Project Manager to proceed with the initiation stage

(9)

The following is the activity summary of Authorise Initiation:

Authorise Initiation

Figure 13.2. Authorise initiation: activity summary. Copyright © AXELOS Limited 2013. Material is reproduced under licence from AXELOS. All rights reserved.

(10)

The second activity that is performed during Directing a Project is to authorise the project.

● The Project Manager requests for authorisation to deliver the project.

● The Project Board must confirm that an adequate and suitable Business Case exists and that it

demonstrates a viable project.

● If the project is not authorised by the Project Board, it should be prematurely closed. ● While authorising the project, the Project Board also confirms that the Quality, Risk,

Communication and Configuration Management Strategy are sufficient.

● It also reviews and approves the Benefits Review Plan.

(11)

The following is the activity summary of Authorize the Project:

Authorise the Project

Figure 13.3. Authorise the project: activity summary. Copyright © AXELOS Limited 2013. Material is reproduced under licence from AXELOS. All rights reserved.

(12)

One of the important activities of Directing a Project process is to authorise a Stage or Exception Plan.

● During the project, the tolerances may be forecast to exceed for different reasons, and an

exception is raised.

● If an exception has occurred during the stage, the Project Board may request the Project Manager

to produce an Exception Plan for the Project Board’s approval.

● Deviations from the Project Plan may require corporate or programme management approval. ● Deviation within Work Packages is managed by the Project Manager using the Controlling a Stage

process.

(13)

The following is the activity summary of Authorize a Stage or Exception Plan:

Authorise a Stage or Exception Plan

Figure 13.4. Authorise a Stage or Exception Plan: activity summary. Copyright © AXELOS Limited 2013. Material is reproduced under licence from AXELOS. All rights reserved.

(14)

In response to an escalated issue, the Project Board seeks advice from corporate or programme management, or takes decision regarding:

Give Ad Hoc Direction

Asks Project Manager to prepare Exception Plan or provide guidance

Problem/concern

Approves, defers, rejects or asks for more information and checks whether exception report is required

Request for change

Grants a concession; defers, rejects or asks for more information; checks

(15)

The following is the activity summary of Give Ad Hoc Direction:

Give Ad Hoc Direction

Figure 13.5. Give ad hoc direction: activity summary. Copyright © AXELOS Limited 2013. Material is reproduced under licence from AXELOS. All rights reserved.

(16)

Authorized closure is the last activity undertaken by the Project Board and may require endorsement from corporate or programme management.

● Steps are taken to review the original and current versions of the Project Initiation Documentation

to understand the project’s initial baseline and current strategies and controls.

● The End Project Report is prepared by the Project Manager and reviewed by the Project Board. ● The Project Board confirms who receives each follow-on action recommendation summarised in

the End Project Report, as well as the Lessons Report.

● The Project Board reviews and gains approval for the updated Benefits Review Plan.

(17)

The following is the activity summary of Authorise a Project Closure:

Authorise a Project Closure

Figure 13.6. Authorize project closure: activity summary. Copyright © AXELOS Limited 2013. Material is reproduced under licence from AXELOS. All rights reserved.

(18)

Directing a Project Process—Exercise

Which role is responsible for each of the activities of the Directing a Project process? Write activities and roles responsible.

Q

How are the seven themes applied within the Directing a Project process?

Q

The following questions are designed to test your comprehension of this process. Please solve them as a group activity.

(19)
(20)

a. b. c. d. QUIZ

Which process enables the Project Board to exercise overall control of a project?

Directing a Project Starting up a Project Initiating a Project Controlling a Stage 1

(21)

QUIZ

a. b. c. d.

Which process enables the Project Board to exercise overall control of a project?

Answer: b.

Explanation: Project Board exercises control over the project using the Directing a Project

process. 1 Directing a Project Starting up a Project Initiating a Project Controlling a Stage

(22)

a. b. c. d. QUIZ

Which is a purpose of the Directing a Project process?

Prepare a solid foundation for the project

Establish the prerequisites for the initiation of a project Assign Work Packages

Enable the Project Board to exercise overall control of a project 2

(23)

QUIZ a. b. c. d. Answer: a.

Explanation: The purpose of the Directing a Project process is to enable the Project Board

to be accountable for the project’s success by making key decisions and exercising overall control while delegating day-to-day management of the project to the Project Manager.

Which is a purpose of the Directing a Project process?

Prepare a solid foundation for the project

Establish the prerequisites for the initiation of a project Assign Work Packages

Enable the Project Board to exercise overall control of a project 2

(24)

a. b. c. d. QUIZ

When does the Directing a Project process start?

On completion of the Starting up a Project process On completion of the Initiating a Project process When the Starting up a Project process commences After the project has been authorised

(25)

QUIZ a. b. c. d. Answer: b.

Explanation: The Directing a Project process starts on completion of the Starting up a

Project process and is triggered by the request to initiate a project. When does the Directing a Project process start?

On completion of the Starting up a Project process On completion of the Initiating a Project process When the Starting up a Project process commences After the project has been authorised

(26)

a. b.

QUIZ The production cost forecast should be reviewed by the Project Board during the Directing a Project process to determine whether the project should continue.

False True 4

(27)

a. b. QUIZ

Answer: a.

Explanation: All Project Board decisions are made during the Directing a Project process. This

includes review of the production cost forecast by the Project Board.

The production cost forecast should be reviewed by the Project Board during the Directing a Project process to determine whether the project should continue.

False True 4

(28)

a. b. c. d. QUIZ

What process is triggered by the Project Manager's request to initiate a project?

Initiating a Project Directing a Project

Managing a Stage Boundary Starting up a Project

(29)

QUIZ a. b. c. d. Answer: c.

Explanation: When the Project Manager requests to initiate a project, it can be approved

only by the Project Board in line with the activities in the Directing a Project process.

What process is triggered by the Project Manager's request to initiate a project?

Initiating a Project Directing a Project

Managing a Stage Boundary Starting up a Project

(30)

● The purpose of the Directing a Project process is to enable the Project Board

to be accountable for the project’s success.

● The Directing a Project process starts on completion of the Starting up a

Project process and is triggered by the request to initiate a project.

● Directing a Project activities are Project Board-oriented.

● The activities include authorise initiation, authorise the project, authorise a

Stage or Exception Plan, give ad-hoc direction and authorise the project closure.

Summary

Here is a quick recap of what we have learnt in this lesson:

(31)

Thank You

Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS Limited. All rights reserved. PRINCE2® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. AXELOS® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under the permission of AXELOS Limited. All rights reserved.

(32)

[1] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Directing a Project, Purpose.

Reference

References

Related documents

Quality: We measure quality (Q in our formal model) by observing the average number of citations received by a scientist for all the papers he or she published in a given

The PROMs questionnaire used in the national programme, contains several elements; the EQ-5D measure, which forms the basis for all individual procedure

Directions: Through the following activity, you will be working with a group of students to determine which events, or "footsteps", were MOST important in pushing the

An analysis of the economic contribution of the software industry examined the effect of software activity on the Lebanese economy by measuring it in terms of output and value

Upon a thorough review of the published literature pertaining to multiple self-inflicted gunshot wounds to the head, 81 cases document two gunshot entrance wound defects,

For each font and color of applied vinyl used for lettering, contractor shall cut two (2) samples of lettering to match the font, height, width ratio and color. The letters to be

In this research the researcher argues that the ‘administrative shift’ of the day to day activities of the National School Nutrition Program, management of funds and procurement

Examples of assigning an appropriate facet to blog posts include the case for an initial topic keyword “smoking” and a facet “passive smoking” , where those blog posts and