Overview of Sidewalk Programs
Department of Public Works
William Shreve, Director
Presenters:
Steve Staples, Chief of Roads Division
John Stevens, Chief of Capital Services
Sidewalk Repair Program
The Roads Division repairs approximately 1,500 sections of
sidewalk and replaces 850 sections annually. County-wide
inspections are performed annually, and repairs are prioritize
based on public safety risks. The condition rating guidelines
are in the following prioritization:
➢
Priority 1 – Missing concrete panel, lifted 2” or higher
➢
Priority 2 – Concrete panels lifted ½” to 2” high
➢
Priority 3 – Concrete panels with heavy cracking,
Sidewalk Repair Program
Before
Before
Sidewalk Repair Program
⚫
Existing & Proposed Site Conditions:
➢
Availability of Existing Right-of-way
➢
Sufficient Space & Whether or Not Roadway is an Open/Closed
Section
⚫
Utilities:
➢
Utility Company/Prior Rights
➢Timeliness of Utility Relocations
➢
Execution of Legal Maintenance Agreement Responsibilities
➢Legal Agreements with Home Owners Associations (HOA)
⚫
Other:
➢
Availability of Funding
➢
Timeliness of Construction Bid Process
⚫ Western Parkway Phase 2: Acton Lane to Pierce Road ⚫ Village Drive: St. Linus Drive to PD Brown Library
⚫ Valverde Drive (Linden Grove): Carthage Court to Bancroft Drive ⚫ Western Parkway Phase 3: Pierce Road North
⚫ Smallwood Drive West: Thoroughbred Court to Middletown Road
⚫ Mill Hill Road Safe Routes to School: Homecoming Lane to Davis Road ⚫ Hamilton Road Phase 1: Acton Lane to Quietfields Street
⚫ Chapel Point Road: Causeway Drive to Commerce Street
⚫ Westlake Community/St. Charles Mall: St. Patricks Drive and Route 301 ⚫ Billingsley Road: St. Patrick’s Drive to Middletown Road
⚫ Indian Head Highway/Livingston Road: Matthews Road to Wooster Road ⚫ Middletown Road: Billingsley Road to Indian Head Rail Trail
Various Pedestrian and Bicycle Facilities
Appropriated (FY14-FY21) Yearly Avg. Avg. Project Cost
Construction $336,000 $54,500 $189,000
Sidewalks funded/installed with roadway projects (4) . . . $236,700 Stand alone projects (4) ranging $200K – $600K . . . $313,000 Program projects (4) ranging $37K – $102K . . . $ 64,700
Current Project Balance $260,529
Funding available to complete 3 or 4 of the 5 smaller program projects.
The cost per linear foot is approximately $65 for sidewalks alone. However there are other associated appurtenances that drive up the project costs:
- Curb & Gutter - Stormwater Management
- Chain-link Safety Fencing - Drainage Systems - Property Acquisitions
Various Pedestrian and Bicycle Facilities
Sidewalk Improvement Program
Western Parkway Ph. 2: Acton Lane to Pierce Road
Project Description
Installed 4,200 lf. of sidewalk and 3,810 lf. of hiker/biker paths along Western Parkway from Acton Lane to Pierce Road. This project was funded through the roadway
Sidewalk Improvement Program
Village Drive: St. Linus Drive to PD Brown Library
Project Description
Construct 460 lf. of sidewalk to connect to existing sidewalk on St. Linus Drive to PD Brown Library. ($30,700)
Project Status/Schedule/Timeline
Sidewalk Improvement Program
Valverde Drive: Between Carthage Court and Bancroft Drive
Project Description
Construct 326 lf. of sidewalk to connect to existing sidewalk omitted from Linden Grove development due to proposed 150’ right-of-way Cross County Connector Phase 6
Sidewalk Improvement Program
Western Parkway Ph. 3: Pierce Road - Mattawoman Beantown Road
Project Description
Construct approximately 1,390 lf. of hiker/biker trail from Pierce Road in conjunction with the Western Parkway roadway improvements. This project is funded through the
roadway improvement project. ($90,350)
Project Status/Schedule/Timeline
Sidewalk Improvement Program
Smallwood Drive: Thoroughbred Court to Middletown Road
Project Description
Construct approximately 792 lf. of sidewalk from Thoroughbred Court to Middletown Road to connect existing sidewalks. ($89,500)
Sidewalk Improvement Program
Mill Hill Road: Homecoming Lane to Davis Road
Project Description
Construct 1,585 lf. of sidewalk from the North Point Subdivision to connect with the existing asphalt path on Davis Road. The project is being 100% funded by the
FHWA/MDSHA Safe Routes to School program. ($370,890)
Project Status/Schedule/Timeline
Sidewalk Improvement Program
Hamilton Road Ph. 1: Acton Lane to Quietfields Street
Project Description
Construct approximately 2,900 lf. of sidewalk from Acton Ln. to Quietfields St. as part of 6,000 lf. sidewalk/hiker/biker trail project. This project is funded as a stand-alone project.
($328,000)
Sidewalk Improvement Program
Project Description
Construct 900 lf. of shared hiker/biker trail from Causeway Dr. to Commerce Street. ($101,700)
Project Status/Schedule/Timeline
Currently assessing right of way acquisitions and stormwater management options.
Estimated start of construction – July 2022 (pending availability of funding).
Sidewalk Improvement Program
Westlake Community: St. Patricks Drive and Md. Route 301
Project Description
Construct 3,275 lf. of sidewalk and hiker/biker trail to establish an interconnected
sidewalk network in the vicinity of St. Charles Mall. This project is recommended to be funded as a stand-alone project. ($212,800)
Sidewalk Improvement Program
Billingsley Road: St. Patrick’s Drive to Middletown Road
Project Description
Construct sidewalks along Billingsley Road from St. Patrick’s Drive to Middletown Road to connect existing sidewalks. This project is recommended to be funded as a stand-alone project. ($81,250 and $494,000)
Project Status/Schedule/Timeline
➢ St. Patrick’s Dr. (1,250 lf.): Procurement to start construction in April 2021.
Sidewalk Improvement Program
Project Description
Construct 2,100 lf. of sidewalk along Indian Head Hwy. and Livingston Road to connect existing sidewalks. This project is recommended to be funded as a stand-alone project.
($136,500)
Middletown Road: Indian Head Rail Trail to Billingsley Road
Sidewalk Improvement Program
Project Description
Construct approximately 5,280 lf. of hiker/biker trail along Middletown Rd. from Indian Head Rail Trail to Billingsley Road. ($449,000)
Project Status/Schedule/Timeline
Hiker/biker trail to be constructed with Middletown Road Phase 3 project. Feasibility study for roadway project is currently underway to determine roadway alignment and
Charles County Government
Department of Public Works
(301) 932-3440 [email protected] 10403 Audie Lane, La Plata, MD 20646
MD Relay Service: 7-1-1
Presented By:
Equal Opportunity Employer
It is the policy of Charles County to provide equal employment opportunity to all persons regardless of race, color, sex, age, national origin, religious or political affiliation or opinion, disability, marital status, sexual
orientation, genetic information, gender identity or expression, or any other status protected by law.