Spearhead Network for Innovative, Clean and Safe Cement and Concrete Technologies
SUPERVISION ON
CONSTRUCTION SITE
Obligations of supervisor on site
Mr. Mario Ille, PhD candidate, IGH Azra Balagija, PhD candidate, IGH
CONTENT
• Introduction
• Contractor and supervisor engineer
obligations, rights and duties
• Application of valid regulations on
example of
Krk bridge
• Conclusion
INTRODUCTION
• The rights and duties relating to contractors and
supervisors in the process of construction through review of the most important Acts, Technical Regulations and Ordinance that were developed and legislate in recent years.
• Implementation of quality control of concrete on the site as one of the obligations of contractors in the
construction procedure, all in accordance with applicable regulations in the Republic of Croatia.
• Croatia is preparing to become a member of the European Union and it is necessary to adapt their
regulations to those that apply to the EU market, but it is also necessary to comply with applicable regulations.
CONSTRUCTION PARTICIPANTS
In accordance with Article 177. Physical Planning and Building Act
(NN 76/07, NN 38/09, NN 55/11, NN 90/11 & 50/12)
• Investor
• Designer
• Reviser
•
Contractor
•
Supervisor engineer
OBLIGATIONS OF CONTRACTOR
In accordance with Act contractor is obligated to buildaccording to approved main design and building permit and thereat:
• Confer performance of construction works and other works to persons who fulfill ordinance requirements for performance of these works
• Perform works in order to fulfill basic requirements and other requirements for structure
• Embed construction products and equipment in
OBLIGATIONS OF CONTRACTOR
Provide:
• proof of usability of embedded construction products
• proof of compliance of embedded equipment according to specific act
• documents of compliance of specific building parts to basic requirements for structure and from competent authority given proof of quality (testing results, records of conducted control quality procedures etc.)
• Legally dispose construction waste generated during construction on the site
• Draw up a written report of conducted works, and of the maintenance building
SUPERVISIOR ENGINEER
• In accordance with Physical Planning and
Building Act
Supervisor Engineer
is a natural
person who under a special law has the right to
use the professional title of a licensed architect
or licensed engineer and to conduct technical
supervision of construction on behalf of the
Investor.
• The supervisor engineer can not be an
employee of a person who is the contractor on
the same building
OBLIGATIONS OF SUPERVISIOR
ENGINEER
• Supervise the construction to be in accordance with
confirmed the main design, or building permit, Physical Planning and Building Act and special regulations
• Determine if a main design in terms of horizontal and vertical dimensions and purpose of the building is made in accordance with the decision on building conditions or location permit
• Determine if construction staking is performed by the person authorized to conduct affairs of state survey and real property under a special law
• Determine whether the contractor meets the
requirements for performing construction activities, regulated by special law
OBLIGATIONS OF SUPERVISIOR
ENGINEER
•
Determine the implementation of control
procedures in respect of compliance
assessment, and prove the quality of certain
parts of the building by an authorized person
• Immediately inform Investor with all the
disadvantages or irregularities perceived during
construction, and Investor, building inspections
and other inspections of the measures taken
• Compile a
final report on the building
CONSTRUCTION
BUILDING OF NEW STRUCTURE CONSTRUCTION /BUILDING RECONSTRUCTION REMOVAL OF EXISTING STRUCTURE MAINTENANCE OF EXISTING STRUCTURE Performance ofconstruction works which affect the fulfillment of basic requirements for the existing structure Performance of
construction works in order to preserve the basic requirements for the existing structure
REPAIR AND PROTECTION
• In the past few decades the need for renovation of existing structures (especially bridges) has increased. • With development of the area of repair and protection of
concrete structures the legal and technical regulations related to this area also had to pursue.
• The adoption of new rules for concrete structures
(Technical regulation for concrete structures) involved products and systems for the protection and repair of concrete structures for the first time.
• At the same time the Ordinance on conformity
assessment, documents of conformity and marking of construction products was adopted and therefore
brought the obligation to bring the approval of the
EXAMPLE OF “KRK BRIDGE” REPAIR
• It was built from 1976 until 1980
• Only six years after the opening for traffic it was
concluded that some badly done structural solutions must be repaired urgently and that concrete structure has to be protected from the chloride ingress
“KRK BRIDGE”
• The bridge connects the mainland with the
island of Krk over islet of St. Mark in the vicinity
of Kraljevica through two sea channels
• Its total length is 1309.50 m without abutment
(including the 96 m road cut on the island of St.
Mark)
“KRK BRIDGE”
• Two highest columns
(S8 & S17) are 61,44
m high
• Width of big arch is
13,00 m
BUILDING PARTICIPANTS SHEME
TECHNICAL SUPERVISION
INVESTOR
SUBCONTRACTOR CONSTRUCTION SITELABORATORY ON CONTRACTOR
BASIC DOCUMENTATION FOR QUALITY
MANAGMENT AT THE CONSTRUCTION SITE
Documentation that preceded the construction and execution:
• Building permits (with the main design as an integral part, the site permit)
• Detailed design, program control and quality assurance • Appointments of persons responsible under the Physical
Planning and Building Act
• Study on site organization with the work protection and safety and fire protection
• Record of the geodesic construction staking • Plan for quality performance
BASIC DOCUMENTATION FOR QUALITY
MANAGMENT AT THE CONSTRUCTION SITE
Documents and records generated during construction:
• Construction diary, Construction book
• Specifications of materials and construction products in the order
• Supplier Declaration of conformity, certificates of conformity of products, the certificate of factory production control, technical instructions for installation and use of products
• Records of the control activities carried out on site
• Evidence about the quality of the built-in concrete (reports of examinations conducted on the site)
• Proof of usability of concrete structure according to Technical regulations for concrete structures annex “J.2.4”
QUALITY CONTROL FOR COLUMS
REPAIR
PREPARATION WORKS FOR COLUMNS REPAIR
EMBEDING OF NEW STEEL
REINFORCEMENT
STEEL REINFORCEMENT IN ACCORDANCE TO HRN EN 10080 AND REGULATION FOR CONCRETE STRUCTURE ANNEX B MADE ACCORDING TO DESING
REINFORCEMENT EMBEDING ( FOLDING AND CONNECTION FITTINGS CONTROL )
CONSTRUCTION SITE ORGANISATION CONTRACTING SUPPLIER
CONTROL PROCEDURES BEFORE INSTALLATION
PROJECT DOCUMENTATION
GEODESIC STUDY
CASTING WITH NEW CONCRETE QUALITY MANAGMENT OF CONCRETE
CONTROL TESTING OF BUILT IN CONCRETE AND PROTECTION SYSTEM
CASTING WITH NEW CONCRETE AND PROTECTION LAYER
OVERVIEW CONCRETE SURFACE A FTER REMOVAL
DETERMINATION OF SURFACE PROPERTIES (CONTROL OF PREPARED SURFACE
STEEL REINFORCEMENT OVERVIEW
DEMOLITION OF CONCRETE COVER
HYDRO DEMOLITION OF CONCRETE
COVER ON COLUMNS AND ARCH
QUALITY CONTROL OF SURFACE
PREPARATION
The appearance of concrete surface after removal of the damaged and contaminated layer of concrete with hydro demolition
Place of testing the quality of surface preparation - Tensile strength of the surface layer of the pull-off method
APLICATION OF REPAIR PRODUCTS
ON COLUMNS
APLICATION OF REPAIR PRODUCTS
ON ARCH
CURING OF PLACED MATERIALS
The curing conditions of placed layers or elements of mortar / concrete and the procedures for quality control are given in
QUALITY MANAGMENT OF CONCRETE DURING
CONSTRUCTION
– contractor documentation and records:Program of quality performance Concrete casting records
Supervision before concreting Fresh concrete control and
supervision before casting
Supervision after casting Casting and compacting of
concrete
Supervision of precast concrete elements Regulate the management and
execution of concrete works and ensuring quality control
during the execution of concrete works (includes scaffolding,
reinforcement, casting, precast elements, geometric tolerance, supervision and repair)
QUALITY MANAGMENT OF CONCRETE DURING
CONSTRUCTION
– contractor documentation and records:Record of taking samples Uniformity of compressive strength test results
General data of construction site
Concrete data
Data about taking samples List of necessary hard
QUALITY MANAGMENT OF CONCRETE
DURING CONSTRUCTION
– documentation Institute IGH: Program of in-situ concretecontrol testing
Sample taking record
Fresh concrete data Testing results of fresh
concrete in-situ
General data of construction site
Equivalent elements of concrete structure data
QUALITY MANAGMENT OF CONCRETE
DURING CONSTRUCTION
– documentation Institute IGH: Cast in concrete testingresults assessment
Final report on conducted control procedures of concrete quality establishment
CONTROL TESTS BY TYPES OF WORK (reprofiling, grouting, the new concrete/mortar, surface protection systems)
CONCLUSION
• Croatia has established building regulations and is still evolving and adapting to market demands of the EU (Laws, Concrete Structures is used, Decrees,
Regulations, Standards)
• The obligation of all participants meet the requirements of statutory construction and current building regulations
• The design and construction going on at our mistakes are too much of contempt and misinterpretation of the
CONCLUSION
RULES THAT SHOULD BE ADOPTED
• Regulations to regulate the manner in tests
samples from the site in the laboratory
contractors or independent accredited
laboratory
• Complete work on national standards appendix
for the Performance of concrete structures HRN
EN 13670:2010 - in progress