MILLENNIUM DOME PROJECT
MILLENNIUM DOME PROJECT
Gurpreet Singh (23), Neha Ansal (35), Soham Chowdhury (59)
Agenda
Agenda
Introduction: Why Project Management
Introduction: Why Project Management
Project Scheduling
Project Scheduling
The Organizational Context
The Organizational Context
Project Selection and Portfolio Management
Project Selection and Portfolio Management
Leadership and Project Manager
Leadership and Project Manager
Scope Management
Scope Management
Project Team Building, Conflict and Negotiation
Project Team Building, Conflict and Negotiation
Risk Management
Risk Management
Cost Estimation and Budgeting
Cost Estimation and Budgeting
Project Scheduling I
Project Scheduling I
Project Scheduling II
Project Scheduling II
Critical Chain Project Scheduling
Introduction
Introduction
The
The Millennium Dome
Millennium Dome is the original name of a large dome-shaped building, originally used to
is the original name of a large dome-shaped building, originally used to
house the
house the Millennium Experience
Millennium Experience , a major exhibition celebrating the beginning of the
, a major exhibition celebrating the beginning of the third
third
millennium.
millennium.
The project was largely reported by the press to have been a
The project was largely reported by the press to have been a flop
flop
:
: badly thought-out, badly
badly thought-out, badly
executed, and leaving the government with the embarrassing question of what t
executed, and leaving the government with the embarrassing question of what to do with it
o do with it
afterwards.
afterwards.
During the 12 months it was
During the 12 months it was open there were approximately 6.5 million visitors
open there were approximately 6.5 million visitors —
— significantly
significantly
fewer than the approximately 10 million paying visitors that attended the
fewer than the approximately 10 million paying visitors that attended the Festival of
Festival of
Britain
Britain , which only ran from May to September
, which only ran from May to September ..
According to the UK
According to the UK National A
National Audit Office,
udit Office, the total cost of The Dome at t
the total cost of The Dome at the liquidation of the
he liquidation of the
New Millennium Experience Company in 2002 was
New Millennium Experience Company in 2002 was £789 million, of which £628
£789 million, of which £628 million was
million was
covered by National Lottery grants and £189
covered by National Lottery grants and £189 million through sales of tickets etc
million through sales of tickets etc . A surplus
. A surplus
of £25 million over costs meant that the full lottery grant was not required.
of £25 million over costs meant that the full lottery grant was not required. However, the £603
However, the £603
million of lottery money
Millennium Dome - Location
Located on the Greenwich
Peninsula in South East London,
England, the exhibition was open to
the public from
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
The Parameters of success in a project:
TIME: 1997-2000 COST: £750 million CLIENT ACCEPTANCE: 12 million visitors PERFORMANCE: World-class dome
Introduction: Why Project Management
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
The elements of the project were the following:
•
Unique: It was at the dome that the national exhibition was to be held as
part of the millennium celebrations.
•
Time scale: The time line was fixed- started in 1997 and ended in 2000.
•
Budget: The project was to be funded by National Lottery, visitors and
commercial sponsors and had an estimated budget of £750 million.
•
Limited resources: Fixed amount of human resources and equipments,
raw material etc. were allotted.
•
Cross-functional dimension: Involved human resources from all
domains like designing, construction, hospitality, electricity and water
boards etc.
Project Life Cycle
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
CONCEPTUALIZATION
February 1996 The Millennium Commission decides in principle to proceed
with a Millennium Exhibition.
March 1996 The site at Greenwich is selected from four short-listed options.
January 1997 The Commission announce their 'in principle' support for the
Dome. The Government decided that the project should be delivered in the
public sector.
February 1997 Millennium Central Ltd (later renamed the New Millennium
Experience Company Ltd) became operational.
Project Life Cycle
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
DEVELOPMENT
May 1997 The New Millennium Experience Company finalizes its business
plan which sets an overall cash cost of £758 million.
June 1997 The new Government confirms its commitment to the Dome.
Construction of the Dome and associated infrastructure begins.
July 1997 The Millennium Commission awards a lottery grant of £449 .
EXECUTION
April 1998 The Company issues its first Corporate Plan.
November 1998 Budget review by the Company and the Commission.
March 1999 Competition to select a user for the Dome after the Millennium
Exhibition begins.
September 1999 Tickets go on sale to the public on 22 September.
January 2000 The Dome opens to the public on 1 January. The Company
revises its forecast number of visitors from 12 million to 10 million on 28
January. The Company reverses its decision not to sell tickets at the gate.
February 2000 The Commission awards an additional grant of £60 million to
the Company on 4 February. The Company's Chief Executive Ms Jennifer
Page CBE is replaced by M. P Y Gerbeau.
Project Life Cycle
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
TERMINATION
May 2000 The Company revises its forecast number of paying visitors to
6 million in its application for an additional grant of £38.6 million submitted
on 19 May.
The Chairman of the Company (Mr Robert Ayling) resigns & is replaced.
July 2000 The number of paying visitors reaches the three million mark.
August 2000 The Commission awards an additional grant of £43 million
to the Company on 4 August. The Company revises its forecast number of
paying visitors to 4.5 million.
September 2000 The Commission awards an additional grant of £47
million to the Company on 5 September. Mr David James CBE is
appointed Executive Chairman and Accounting Officer of the Company on
5 September. Mr Quarmby steps down and becomes Vice Chairman.
The Organizational Context
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
MISSION STATEMENT
•
To create, build, and operate a national Millennium Experience which attracts,
inspires, entertains, educates and involves visitors and participants.
•
To seek, through the Experience, to influence positively each individual's view
of themselves and the world's view of this nation.
This mission statement was well in line with the objectives set forth by the
company to build in a world class exhibition dome for the millennium
celebrations.
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Executive Chairman Board of Directors Executive Directors Chief Executive Finance & Corporate Services Non Executive Directors
Site & Structure Transport CommercialDirector
Sponsorships Licence Trade Travel Operations Director Ticketing Daily Operations Challenger Director Implementation Director Production Director Greenwich content & events
Marketing & Communications
Director
Accounting Officer
Key Stakeholders
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
INTERNAL STAKEHOLDERS Chief Executive Officer Board of Directors The Millennium Commission Project Managers Functional Managers Accounting Officers EXTERNAL STAKEHOLDERS NMEC The Millennium Commission National Lottery Fund Distribution Department Governm ent, UK Department of Culture, Media and Sports Visitors Environment Groups National Audit Committee
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
The basis for selection of this project for building the Dome
was:
Past History:
The commission wanted the Millennium Exhibition of a scale and
stature comparable to that of:
•
The Great Exhibition of 1851
•
The Festival of Britain of 1951
Since, they already had such exhibition domes built earlier like
the above; they could now focus on this Dome easily as they
had past data with them which brought them higher in the
learning curve.
Financial aspect
–
Balanced Budget:
The millennium commission was approved as it would achieve a
balanced budget - costs and income of £758 million and it would
result in a 12 million paying visitors.
Leadership and Project Manager
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Ms.Jennifer Page was Chief Executive
of the London Millennium Dome project
from 1 March 1995 until she was fired
after a flawed opening night and poor
early attendance at the start of 2000.
Page was sacked as Chief Executive on
5 February 2000. She had come under
pressure after an opening night fiasco on 31 December 1999, followed
by poor attendance in January 2000 and a revolt by sponsors.
Page added to her criticism of ministers by insisting that the unexpected
decision by the Prime Minister Tony Blair to invite one million
schoolchildren to the Dome for free had had a significant impact on
its income .
Scope Management
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
The scope of the project was to build a Millennium Dome so as to conduct the
millennium exhibition. The following is the : Work Breakdown Structure (WBS):
Responsibility Matrix
Chapters1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Project Team Building
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
The major players included:
The New Millennium Experience Company
The Millennium Commission
The Department of Culture, Sports and Media
The designing and construction was outsourced to different project based
teams.
A few examples:
Civil Engineer - WS Atkins
Services Engineering - Buro Happold Consulting Engineers
Acoustic Consultant - Sandy Brown Associates
Conflict and Negotiation
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Peter Mandelson
–
Minister for Trade and Industry
was made the Dome Secretary.
Conflict of Interest:
The dome was being sponsored by a number of
companies - such as Rupert Murdoch's BSkyB
which were affected by rulings from the
Department of Trade and Industry
“My role in relation to the dome is as shareholder, not as head of the
sponsorship team."I have never been and never intend to be
involved in procuring or negotiating sponsorship deals, so no
conflict arises.” –
Peter Mandelson addressing the House of
Commons.
Risk Management
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Risk Consequence Score
Likelihood Score Impact Potential Score 1 Schedule Risk High 0.8 Medium 0.7 Serious 0.56 2 Cost Estimate Risk High 0.9 Medium 0.8 Serious 0.72 3 Market Risk, volume High 0.7 High 0.8 Serious 0.56 4 Market Risk, price High 0.7 High 0.7 Serious 0.49 5 Political Risk Medium 0.5 Medium 0.4 Moderate 0.2 6 Technical Risk Medium 0.4 Low 0.2 Minor 0.08 7 Financing Risk High 0.9 Medium 0.4 Serious 0.36 8 Promotion Risk Medium 0.4 Medium 0.4 Moderate 0.16 9 Technical Risk Medium 0.5 Low 0.2 Moderate 0.1 10 Operating Risk Low 0.3 Low 0.3 Minor 0.09 11 Integrating Risk Low 0.1 Low 0.1 Minor 0.01 12 Environmental Risk Low 0.1 Low 0.2 Minor 0.02
Overall Probability:
P
f= (0.8 + 0.9 + 0.7 + 0.7 + 0.5 + 0.4 + 0.9 +0.4 +0.5 + 0.3
+ 0.1 + 0.1 + 0.8)/13 = 0.55
Overall Consequences:
C
f= (0.7 + + 0.8 + 0.8 + 0.7 + 0.4 + 0.2 + 0.4 +0.4 +0.2 +
0.3 + 0.1 + 0.2 + 0.1)/13 = 0.26
Overall Risk Factor = P
f+ C
f–
(P
f
) * (C
f)
= 0.55 + 0.26
–
0.55*0.26
Risk Impact Matrix
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
1 Construction (Schedule Risk) The Dome might not be completed on time.
The Dome opened on schedule on 1 January 2000. The fit out of the Dome, originally to be completed by October 1999, continued up to opening day. This meant that there was limited opportunity for trial running.
2 Cost Estimate Risk
Costs might exceed the May 1997 budget.
Costs moved over the period May 1997 to September 2000. As at September 2000, the budget had increased by five per cent. 3 Visitor numbers (Market Risk, volume)
Visitor projections might be too high.
The projected number of paying visitors reduced from 12 million to 4.5 million.
4 Marketing (Promotion Risk/ Market Risk, price) Marketing might not
successfully sell the Dome to the public, particularly if there was considerable negative publicity.
The public perception of the Dome was of a 'risky purchase'. But the majority of people visiting the Dome enjoy it.
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
THE RISKS WHAT HAPPENED IN PRACTICE 6 Sponsorship
Delays in finalizing contracts, and the unattractiveness of certain zones to sponsors, might result in a failure to secure anticipated levels of
sponsorship.
The total amount of sponsorship received (cash, 'value in kind' and 'budget enhancement') was below the original budget of £175 million
7 Sale Proceeds
Buyers might not be found for the Dome, and an adequate selling price might not be achieved.
A preferred bidder for the Dome was announced in July 2000 with an offer of £105 million, but withdrew in
September. The process of finding another buyer was then restarted.
8 Political Risk
Political unrest, strike, riots, terrorism etc.
The Secretary for trade and industry, Peter Mandelson had been given the responsibility for the Millennium Dome and was charged by the opposition for conflict of interest between his two jobs. The dome was being sponsored by a number of companies - such as Rupert Murdoch's BSkyB - which were affected by rulings from the Department of Trade and Industry.
Cost Estimation and Budgeting
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Cost Sheet
Sponsorship income, compared with the Company’s forecast
Ticket sales income, compared with the Company's forecast
Actual total and paying visitors compared with the Company's
successive targets
Project Scheduling
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Gantt Chart
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Network Diagram
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
The concept of CCPM could be applied to the Millennium Dome project and
work could be completed before schedule without any delay because of the
safety and feeder buffers.
WITHOUT CCPM
The total days required to complete the project was 1128 days before applying
CCPM.
WITH CCPM
Project Closeout and Termination
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and
CHAPTER LIST
Body of the write up
Chapters
1 Introduction: Why Project Management?
2 The Organizational Context 3 Project Selection and Portfolio
Management
4 Leadership and Project Manager 5 Scope Management
6 Project Team Building, Conflict and Negotiation
7 Risk Management
8 Cost Estimation and Budgeting 9 Project Scheduling I
10 Project Scheduling II
11 Critical Chain Project Scheduling 12 Project Closeout and