• No results found

TOYO 1-55

N/A
N/A
Protected

Academic year: 2021

Share "TOYO 1-55"

Copied!
435
0
0

Loading.... (view fulltext now)

Full text

(1)

TOKYO JAPAN Ibro Emghneeiung Cobs ISSUED

|

FEB. 10,89

3.7 Casing Design Pressure

(1) Casing design pressure except for double casing or multi-stage pumps should be higher than the maximum discharge pressure (MDP), except that the thickness of the pump casing is to be suitable for the MDP plus allowances for head and speed increase.

(2) Hence, the maximum discharge pressure (MDP) is decided according to the following formula:

MDP (kgf/cm2G) = Shutoff head (D x Sp.Gr.

+ MaJt_ Buction preBBUre

10 (kgf/cm2G)

If the pump head curve has a peak point, the shutoff head should be replaced with a peak head.

Further to the above, the maximum discharge pressure may be equal to setting pressure of a relief valve provided that the relief valve is equipped at the pump discharge.

(3) When the MDP exceeds 1.1 times pump rated discharge pressure, it will affect potentially the design pressure of equipment and systems at

down-stream of the pump. In this case, the design pressure of the subject equipment and systems should be adjusted accordingly.

3.8 Total Head of Vertical Sump Pumps

For vertical sump pumps, the following points should be taken into account

(2)

(1) It should be clearly stated on the inquiry specification (i.e. data sheet), that the discharge pressure and total head is designated at the point of discharge nozzle.

(2) When pumps are tested in performance at Vendor's shop and the discharge pressure is measured at the point of * in Fig. 9, the pump performance

should be corrected accordingly.

FORM A-G30.014

TOKYO JAPAN

Tbso Emoinbbxing Corp. ISSUED

|

FEB.10,89

pTEC

i

—►

r

L Fig. 9 Vertical Sump Pump

3.9 Bearing Material for Vertical Pumps

(1) Material for radial bearings of vertical pumps should be carbon, which has the strong recommendation from past experience.

(2) For low temperature service such as liquid ammonia or liquid propane gas (LPG), this requirement is mandatory,

(3) For water service, cast iron, niresist or bronze is applicable,

3.10 Insulation for Vertical Pumps

Vercial pumps for low temperature service are usually provided with cold insulation around their barrel to protect the pumps from being jacked up due to freezing. In this case, the designer should take care of baseplate size and position of anchor bolts to be properly fit with the insulation

(Fig. 10). ‘ fQ sucT.

(3)

FORM A-G30.0 14

0

TOKYO |^J JAPAN

Ibro Enoinbbxing Cokr

ISSUED FEB.10,89

ENGINEERING MANUALS

DESIGN CONSIDERATIONS FOR CENTRIFUGAL PUMPS

TEM

4 1 4 1 E

PAGE 9 OF 13

3.11 Equalizing Piping for Vertical Pumps

Vertical pumps handling saturated liquid such as LPG and liquid ammonia should be furnished with equalizing piping at pump suction in order to get ventilation. This piping should have enough size to vent gas released and should rise continuously to a suction vessel. The equalizing piping is preferably separated from flushing piping from/to mechanical seals.

(4)

(1) A starting torque curve of automatically started pumps has a different shape from that of manually started pump as shown in Fig. 11.

(2) The designer should clearly identify the pump which is automatically started and inform a motor manufacture of this fact. If necessary, the starting torque curve should be sent to the motor manufacturer.

Remark: In Fig. 11, the cross point of the torque curves gives us an idea of operating speed.

®-DISCHARGE VALVE

OPEN (AUTOMATIC)

©---DISCHARGE VALVE

SHUT (MANUAL)

Fig. 11 Pump Starting Torque Curve

(3) It is recommended that output power rating of drivers should cover the power required by the automatically started pump at the end of curve.

3.13 Shaft Seals

(1) Mechanical seals will be used for flammable or toxic service. API Standard 610 calls for use of the mechanical seals for all services.

(2) Gland packings can' be used for services of cooling water, steam condensate or other water.

(3) The mechanical seals, which are used for the service containing slurry, are externally flushed with clean liquid.

(4) For high temperature services, the mechanical seals are usually provided with a cooler in a flushing line or they are of bellow type.

(5)

FORM A-G30n 14

TOKYO JAPAN' Ibro ErfOiXEEitiNG Corf ISSUED

|

FEB.10,89

(5) For vacuum services, the followings are criteria of selection of the mechanical seal type:

2

- 0.4 kgf/cm G and above: single

mechanical seal with quenching

2

- under 0.4 kgf/cm G : Double

mechanical seal

(6) Recently a tandem or a double mechanical seal becomes popular in use for low temperature hydrocarbon. The double mechanical seal needs an

expensive sealing system consisting a reservoir, pumps and coolers. (Refer to Attachment (4) in detail.)

Non-seal pumps can be optionally replaced with such special application.

Picking Packing

Fore* Fore*

Connection A (rater to appropriate primary M«* piping arrangement}

Tandem Seals

(6)

tandsm sasl piping arrangarnom)

Connection B (relerto appropriate mmflarr *asl piping arrangement)

aaureunoar bueKng (mechanical eaal

matrtrtv* buaWng) or euaMvy Mdtogdwtos

Fig. 12 Pump Shaft Seals

3.14 Limited End Float Couplings

When a driving motor is equipped with sleeve bearings, a coupling between the motor and a pump should be of limited end float type. This type of coupling prevents a rotor of motor from moving more excessively than limited by motor end play. For further details, refer to Engineering Manual TEM-4047E.

FORM A.-G300 (4

TOKYO JAPAN

(7)

ISSUED

|

FEB. 10,89

3.15 Resonance Vibration of Large Vertical Pumps with Motor Speed

(1) If a frame of large sized vertical pumps has an resonance in natural

frequency with Z x operating speed (2=1,2...), such pumps do

potentially encounter vibration.

(2) During detailed design stage, the resonance frequency should be checked to be far from the revolutional speed and at the test it should be

examined by hammering, etc.

3.16 Thrust Balancing and Shaft Sealing

(1) Thrust froce around an impeller with a balance holes will become different from that without balance holes as shown in Fig. 13.

(2) When the impeller is provided with balance holes and suction pressure is higher than 15 to 20 barG, the thrust force loading impeller opening cannot be properly balanced, which results in overloading to the thrust bearing. Thus, in this case the impeller will not be furnished with the balance holes at all.

(3) When the suction pressure of pumps is very close to liquid vapor pressure, flushing liquid, i.e. self liquid, in a stuffing box is possibly vaporized by heat generated at the part of matings of a mechanical seal provided that the box pressure is equal to the suction pressure. In this case, the impeller will not be furnished with the balance holes, either.

(4) The box pressure, in such a.case that no balance hole is furnished, is nearly equal to pump discharge pressure. Flushing liquid to the

mechanical seal will be circulated to "pump suction, which is called "Reverse Flushing" (API Plan No. 13).

(8)

COMBINED THRUST FORCE

WITHOUT BALANCE HOLE.

COMBINED THRUST FORCE

WITH BALANCE HOLE

Fig. 13 Thrust Force around Impeller

FORM A-G3OJ0 14

F

PUMP DA fA SHEET

Attachment V2

7

(9)

9 1D 11 12 13 /Vo/e:

X

;

wwMfiMvf-J 'to cbfiMjt '

1 -2proc_

(10)

rr^fcr-rgtTiJi ;^/^T%fTiirii>rrrg- tc n -mc&i

r

PUMP DATASHEET Attachment 1-2 (14J1B) I 2 3 4

(11)

5

6

1-2proc_ ^

SiZlixa, Jn (yC^Mj^ ■

TOKYO 0 JAPAN

Toyo Engineering Corp.

TITLE: CHECK OF VENDOR’S PRINT FOR ROTATING MACHINERY

DATA SHEETS FOR CENTRIFUGAL PUMPS & EXPECTED PERFORMANCE CURVE TIME OF CHECK AT THE TIME OF THE FIRST ISSUE OF VENDOR’S DATA SHEETS AND PERFORMANCE CURVES.

(12)

CHECK ITEMS AND POINTS

CHECK

ABC

REMARKS

(1) Check if data designated by Vendors are coincident with inquiry spec.

(2) Check if all data are filled in by vendors.

(3) Check if all latest revisions are identified with mark.

(4) Check if the pump case mounting, foot, centerline or vertical is in compliance with the applicable spec.

(5) Check if case split is in accordance with applicable spec.

(6) Nozzle rating and facing

- Check if suction nozzle has the same rating as discharge nozzle for one- or two-stage pumps.

- Check if a flat face is applied to cast iron casings.

(7) Check if nozzle size of 1-1/4, (2-1/2), 3-1/2, (5), 7 or 9 inch is not used.

(8) Check if overhung impellers of two stages or double suction is not used corresponding to the requirement of applicable spec.

(9) Impellers

- Check if design tip diameter of impellers is not equal to max. or min diameter for the case.

- Check if 5 % margin is available in total head to that developed by an impeller of the max. diameter for the fixed speed horizontal pumps.

(10) Check if wearing clearances axe as per applicable spec, or standard.

□ □

(13)

O

□ □

MEMO WORK NO.

REQ. NO. VENDOR DOC. NO. 2 1 0 REV. TOKYO 0 JAPAN Toyo Engineering Corf.

TITLE: CHECK OF VENDOR’S PRINT FOR ROTATING MACHINERY

DATA SHEETS FOR CENTRIFUGAL PUMPS & EXPECTED PERFORMANCE CURVE

WORK FLOW CHART

CHECK ITEMS AND POINTS

(11) Check if hydrodynamic bearings are required in accordance with applicable spec, or standard (12) Check if ball thrust bearings are of duplex single row 40-deg. angular contact type as per API 610 Standard when applicable.

(13) Check rating life of bearings, if necessary, by vendor’s calculation sheet. (14) Couplings

- Check if a flexible coupling are used for horizontal pumps or vertical pumps with a thrust bearing as per spec. - Check if a rigid coupling is used

for vertical pumps with no thrust bearings. - Check if a spacer coupling is provided and its space length is as per spec. (15) Check if rotating direction is coincident with an outline drawing and electrical load list. (16) Materials

- Check compliance of requirement regarding materials as per applicable spec, and standards. - Check if hardness of wearing rings is correctly

appointed as per applicable specification. - Check if hardness of sleeves is correctly appointed

(14)

to type of shaft seals. - Check if any components include materials prohibited from

being used in the inquiry spec. - Check if the materials for low temperature service are in compliance with applicable spec, or standards. (17) Check pump speed according to motor pole

&

frequency (slip

&

speed reducer) (18) Check if NPSHR has margin to NPSHA appointed as follows; - min. 0.6 m margin between NPSHR

&

NPSHA as a guideline for horizontal pumps. - NPSH margin for the pumps used for Add Gas Removal

units according to licenser’s spec.

REMARKS

TOKYO 0 JAPAN Toyo Engineering Core.

TITLE: CHECK OF VENDOR’S PRINT FOR ROTATING MACHINERY

DATA SHEETS FOR CENTRIFUGAL PUMPS & EXPECTED PERFORMANCE CURVE

WORK FLOW CHART

CHECK ITEMS AND POINTS

A

(19) Check pump rated BHP according to the equation using rated flow, head, spec, gravity and pump efficiency designated by vendor.

CHECK B REMARKS

c

(20) Minimum continuous flow

- Check if the min. continuous flow is greater than normal flow.

(15)

operation with the flow under the min continuous flow.

(21) Max. operating pressure:

- Check if max. operating pressure is equal to or higher than max. suction pressure + shutoff pressure (with test

tolerance) for fixed speed pumps.

- Check if max. operating pressure is equal to or higher than max. suction pressure + shutoff pressure at max. continuous speed (with test tolerance) ter variable speed pumps

- Check if max. operating press, is within piping spec. & flange rating.

- Check necessity of a relief valve at suction line to protect the pump from overpressure during stand-by.

D

(22) Check if case design temp, is higher than pumping temp. + 10 deg.C. as per applicable spec.

0

(23) Check if case design press, is higher than max. operating press, appointed.

(24) Hyd. test press.

(16)

Applicable high pressure pumps

(25) Check if impeller tip speed vs. material is as per the following guideline;

Cast Iron Bronze Cast Steel 18-8SS Niresist Nodular iron 13% Cr Steel Ref. TEG1-1211-105 TOKYO 0 JAPAN

Toyo Engineering Corp.

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINE

TWO ISSUED PAGE

TITLE: CHECK OF VENDOR’S PRINT FOR ROTATING MACHINERY

DATA SHEETS FOR CENTRIFUGAL PUMPS & EXPECTED PERFORMANCE CURVE

WORK FLOW CHART

CHECK ITEMS AND POINTS

A

(26) Check if suction specific speed is 1900 (rpm,m3/m,m) or smaller for impellers with no inducer or 3000 or smaller for the impeller with an inducer.

(17)

CHECK

B

C

REMARKS

(27) Mechanical Seals:

- Check if type of mechanical seals is in compliance with the inquiry spec, and applicable standards.

- Check if face materials are properly selected according to applicable standards and vendor’s past experience. Especially both faces of tungsten carbide or silicon carbide are to be selected for caustic or slurry services.

- Check if the sealing pressure is positive in any operating cases. Otherwise, check the protection for the seal against vacuum pressure.

D

(28) Auxiliary Piping

- Check if seal piping plan is coincident with type of mechanical seals selected.

- Check if materials of process piping are equal to or better than case material.

- Check if cooling water piping is planned as per requirement of cooling for bearing housings, seal cooling inserts,

pedestal cooling and so on.

- Check if seal quenching is properly appointed for such services as heavy/crude oil, solidified liquid, caustic service, ammonium solution, vacuum service and so on.

(18)

- Check if the external flushing sources, if any, are available in such pressure as being supplied suitably to seals or wearing rings without being vaporized.

- Check if the balance line (chamber), if available, is sized properly so that the chamber pressure is within the max. allowable pressure with leakage flow appointed by vendor.

D

(29) Casing Tapped Openings:

- Check if vent and drain system is as appointed in PO conditions and is compatible with process P & ID.

- Check if the terminal points, if any, have the same pressure rating as main nozzles, or higher.

Applicable to the multi-stage pumps.

(30) Check if pump automatic start and/or stop is correctly appointed as per P & ID.

(19)

icia::

TOKYO 0 JAPAN Toyo Engineering Corf.

TITLE: CHECK OF VENDOR’S PRINT FOR ROTATING MACHINERY

DATA SHEETS FOR CENTRIFUGAL PUMPS & EXPECTED PERFORMANCE CURVE

WORK FLOW CHART

(20)

The incipient cavitation does potentially occur at around 50% of BEP. TOKYO

9b

JAPAN

Toyo Engineering Corf.

TITLE : P&ID Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD related manuals : TEG1-6221-106

PREL. Q □ □ □ 0 □ □ □ □ □ □ □ □

(21)

MEMO WORK NO. P&ID DWG NO. 2 1 0 REV. TOKYO ^ JAPAN

Toyo Engineering Corf.

TITLE : P&ID Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD related manuals : TEG1-6221-106

PREL. □ 0 □ □ □ □ □ □ □ □ □ □ □ . □ □ □

(22)

WORK NO.

P&ID DWG NO.

MEMO

TOKYO JAPAN

Toyo Engineering Corp.

TITLE : P&ID Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD related manuals : TEG1-6221-106

ISSUE STAGE

PREL □ □ □ □ 0 □ □ □

CHECK ITEMS & POINTS

(19) Confirm surge-protection for centrifugal pumps with a Q-H curve having a peak point (for example, "Sundyne" pumps), and that the system is so arranged to enable to

(23)

start the standby machine properly in such a case. (20) Confirm the necessity of warming-up for high

temperature pumps and cooling-down for low temperature pumps, and the suitability of systems. (21) Appointment and confirmation of straight length of

suction piping for centrifugal compressors, gas expanders, double suction pumps, etc.

(22) Confirmation and indication of a flow control system for reciprocating pumps

(23) Confirmation of the necessity of installing minimum flow orifices for high pressure pumps such as BFW pumps, and indication of vendor’s scope of supply for the subject orifices.

(24) Necessity of block valves around compressors, and interlock devices for their opening and closing (25) Confirm the suitability of branch-points of the

compressor kickback (bypass) line.

(26) Confirm the suitability of the destination where the pump reverse line returns, and of the flow control method of the reverse line.

9. Confirm the presence of special contaminants in liquid or gas handled.

(1) Presence of hydrogen sulfide or chlorine contents (2) Presence of slurry contents

10. Treatment of Vent and Drain:

(1) Indicate the basic planning of the vent and drain for rotating machines in aspect of process design.

(2) Indicate actual design conditions of vent and drain based on vendors’ information.

11. Related to Maintenance:

(1) Are flanges and short pipes suitably installed for equipment maintenance? Are the positions of block valves appropriate for utilities connections, and vent and drain?

12. Hot Insulation and Cold Insulation using Steam Trace, Jacket and so on.

(1) Are the steam trace and jacket provided for the rotating machines clearly shown?

(2) When materials for the steam trace are within vendor’s scope of supply, is it specially mentioned?

REMARKS WORK NO. P&ID DWG NO. MEMO

TOKYO >C/ JAPAN

(24)

TITLE : P&ID Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD related manuals : TEGl-6221-106

PREL.

MEMO WORK NO.

P&ID DWG NO.

(25)

ftgRft-auintew) NO.

TWC 1-1211-105E

REV.

0

t FORM A-<530.022-A (91113 TOKYO 0 JAPAN Toyo Engineering Corf.

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINERY

(26)

ISSUED PAGE

TITLE : Divisional Screening for Key Points of Engineering of Rotating Machinery

TIME OF CHECK: Immediately before the first return of principal vendor prints for the major equipment

Supplement : The screening may be conducted two tunes on presence of the major equipment with different

engineering phase each other. Pending matters shall be reported within six months after placing the ordering of the subject equipment. The screening meeting in this concern may be held only when it is considered effective.

RELATED MANUALS: Equipment design PROJECT MONTHLY REPORT

WORK FLOW CHART

CHECK ITEMS AND POINTS

A

Order for Equipment

Is the progress of engineering for rotating machines expectedly smooth?

Is there any equipment for which no order has yet been placed? What is the reason? Expected tune of placing the order?

CHECK

___

c

REMARKS

(27)

_^_

Obtaining approval application Drawings of Major Vendor prints

- What are the spare parts with high importance? Has orders been placed for them yet?

- How about the situation of issue of vendor prints? No significant adverse effects given to other disciplines?

As for the equipment which is subject to precise design-review, has the design-review been completed and properly recorded?

_x_

Check of the Above

If the above review has not yet be completed, its schedule, agenda and reviewers are to be decided.

□ □

□ □

□ □ □

□ □

- Aren't there any equipment, design, portions and sub-order which are not based on the actual proven experience of the purchaser's and/or vendor’s?

- When “yes” to the above query, how did you examine a technical evaluation to them?

(28)

□ □ □

□ □ □

□ □ □

Return of Approval Drawings of Major Vendor Prints

- Have you read the job close-out report of similar process and plant?

When there were problems in the past five years on the same vendors as adopted, are they fed back to current engineering?

D

MEMO WORK NO.

REQ. NO. ITEM NO. VENDOR DOC. NO.

2

1

0

REV. FORM A-G30.015-V2 (9905) TOKYO

0

japan

(29)

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINERY

TWC 1-1211-106E ISSUED FEB. 15/96 PAGE 2/3

title : Divisional Screening of Key Points of Engineering of Rotating Machinery

WORK FLOW CHART

CHECK ITEMS AND POINTS

A

- Aren't there any critical points for the plant guarantee?

CHECK

_____

c

REMARKS

Oder for Equipment s Obtaining application Major Vd

- Have you checked if there are not any operational problems for compressors and turbines? Aren't there any particular problems during start-up and shutdown?

• Different gases handled from specified one

■ Different suction pressure, temperature and discharge pressure

(30)

• Seal differential pressure

• Field test run before commissioning

• Change of steam supply conditions

Check of the Above

- Aren't there any operational problem due to improper Q-H characteristic and limited operation range of the pump?

- How are the critical speed and the operational stability of turbo compressors and turbines?

□ □

O

□ ; □ □ □

- How do you treat with the pulsation analysis of reciprocating compressors?

- Are items and procedures appropriate for shop-testing?

- Which tests and inspection will be witnessed as a design engineer?

(31)

□ □ □ □ □ □ □ □

_±_

Return of Approval Drawings ofMajar Vendor

Prints

- Have you finished the compatibility check of Process P&ID (AFD) with Equipment Vendors’ Prints? When will be done if not

finished? Were there any problems to do so?

- Was the check performed by using the check list entitled as P&ID Screening Meeting (design of Rotating Machinery)?

Refer to TWC No.

1-1211-105E.

MEMO WORK NO.

REQ. NO.

' HEM NO.

VENDOR DOC. NO.

(32)

TOKYO

0

JAPAN

Toyo Engineering Corf.

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINERY

TWC 1-1211-106E

ISSUED FEB. 15,'96

PAGE 3/3

TITLE : Divisional Screening of Key Points of Engineering of Rotating Machinery

WORK FLOW CHART

CHECK ITEMS AND POINTS

CHECK

ABC

REMARKS

Order for Equipment

Obtaining approval application Drawings of Major Vendor prints

(33)

Return of Approval Drawings of Major Vendor Prints

Have you checked the tie-in conditions of speed control governor for steam turbines and anti-surge control systems for centrifugal compressors in the above check?

Have you finished the compatibility check of foundation drawings regarding anchor plans with the latest vendors’ drawings? When will you do it if not finished?

Have you conducted a screening check for compatibility of rotating direction between driven equipment and drivers based on each individual outline drawing? If not, complete it and report in three months before the shipment of equipment In case of steam turbines, however, incompatibility causes a fatal problem. Check carefully, therefore, when checking each outline drawing of both equipment.

• Review the JOB EXECUTION PLAN again Are there any outstanding dispute or changes from it?

How about the follow-up of particular job instructions/orders from the management and the pending matters?

- How about the follow-up of pending matters with the client if any?

- Aren’t there any vendors problematical for the execution of engineering? What are they in particular?

(34)

- Haven't the client claimed demand beyond the contract?

- Aren't there any additional claim of a sizable amount submitted from vendors?

- What was the achievement related to cost like huge cost-reduction?

- What was the achievement leading to the technical innovation or enhancement?

- Is the technical know-how registered and stored in the files properly? □ □ □ □ □ □ □ □

P

□ □ □ □ □ □ □ □ MEMO

(35)

WORK NO. REQ.NO, ITEM NO. VENDOR DOC. NO. FORM A-G30.015-1/2 (9305)

ENGINEERING MANUAL CONTROL SHEET

ORIGINATING DEPARTMENT

NO.

TW)

1

1211—106E

REV.

0

(36)

TITLE:.

PREPARATION OF DATA-SHEETS FOR ROTATING MACHINERY

TIME OF CHECK: AT THE^TtME OF.THE FIRST ISSUE OF DATA SHEETS FOR EACH TYPE OF ROTATING MACHINERY

NOTE: The date sheet will be used for defining the purchaser’s requirements & specifications of rotating machinery to be purchased..

This check list shall be used for the first issue of each type of rotating equipment..

CHECK ITEMS AND POINTS

1.

Check if the correct form is applied.. Check if

the data sheet can be integrated in data base

system.

2.

Check if the data sheet is checked

&

approved as

per department/team instruction(TMS1-CD003).

3. Check if the equipment item no., service & no.

required of equipment are coincident with

equipment list issued by project department.

4. Check if name of customer, site location, unit

name

&

capacity are correctly specified.

5. Check if the previous experience of similar

plant, or previous installation data with same

customer is referred..

6. Check if the measuring units used in the data

sheet are as per contract.

7. Check the following points regarding process

data

(a)

For compressors,

interstage pressure

'&

temperature

shall be clearly indicated, in case of the

limitation on the same.

(b) Reasonable allowance shall be available

between rated

&

normal points.

(c) For major equipment, check process information

of . pressure, temperature, flow rate

A

gas

composition with reference to material balance

&

utility balance.

(d) Specific operating condition/case, which is

different than normal operating condition, shall

be clearly specified, if any.

(e) Allowable leakage

&

.how to recover the

leakage shall be specified, if,required. Check if,

it is specified in data sheet, how to recover the

leakage or not.

(f) In case of volumetric type of

compressor, check if oil-free compressor

is absolutely/r.eally required or , not.

(37)

(g) Requirement regarding, the operating range

*

shall be clearly specified, if applicable.

(h) Normal, minimum flow range shall be clearly

specified, if applicable.

(i) NPSHA shall be checked from suction pressure

&

vapor pressure. This value shall be approximately

same as NPSHA indicated in data sheet.

TWO

ISSUED

PAGE

MEMO 1 0 rev!

FORM A-G30.01S-1/2 (9807) • 0 TOYO ENGINEERING CORF.

TITLE:

PREPARATION OF DATA-SHEETS FOR ROTATING MACHINERY

TIME OF CHECK: AT THE TIME OF THE FIRST ISSUE OF. DATA SHEETS FOR EACH TYPE OF

ROTATING MACHINERY

NOTE: The data sheet will be used for defining the purchaser’s requirements & specifications of rotating machinery to be purchased.

This check list shall be used for the first issue of each type of rotating equipment

CHECK ITEMS AND POINTS

(j) For vertical pumps, check if the

reference point of pressure, head &

NPSHA is clearly indicated or not.

(k) Check if data sheet is coincident

with process data sheet.

(1) Check if the issued process data are

registered in input/output control sheet &

properly filed as per job filing code.

8. Following points with reference to process P &

I Diagram shall be checked & specified in addition

to process data, if required:

(a) Vendor’s scope of supply.

(b) Start-up operation & switching over to

stand-by machine.

(38)

(d) Pump minimum flow.

(e) Priming &.method of priming.

(f) Warming up for pump & turbine.

(g) Auto start-stop.

(h) Settling out pressure for centrifugal

compressor.

(i) Buffer gas source & flushing fluid to shaft

seal.

(j) Type of driver.

9. If required, the maximum suction and/or

discharge pressure

&

temperature shall properly be

specified, considering special operating, case.

10. Check if the type of rotating equipment as

specified by process licenser, or process

department, can be used or not. The possibility of

an alternative type can be checked.

11. If required, the expected values of power

requirement, steam consumption & fuel consumption

with limitation shall be specified.

12. Check if utility' supply and return conditions

are clearly specified for each item.

13. Check if handling fluid can be used for shaft

seal and/or self-lubrication of bearings.

14. Following points shall be checked regarding

construction :

(a)

Type

(horizontal/vertical/type

of

support/casing split/etc.). *

(b) Nozzle orientation

&

flange rating.

(c) Type of seal, flushing fluid & type of buffer

gas.

(d) Material of main parts.

(e) Termination points of vents & drains.

(f) Others.

15.

Results

of

screening

meeting

with

instrumentation & electrical department shall be

considered.

16. Excess requirement,

&.

information to be

specified by vendor, shall be not filled.

17. Emergency

&

safety design shall be

considered for power/ steam failure,

(specifically for shaft seal lubrication, .

etc.).

TWO

(39)

PAGE

FORM A-G30.015-2/2 (9607)

0 Toyo Engineering Corf.

TITLE:

PREPARATION OF DATA-SHEETS FOR ROTATING MACHINERY

TIME OF CHECK: AT THE TIME OF THE FIRST ISSUE OF DATA SHEETS FOR EACH TYPE OF ROTATING MACHINERY

’ NOTE: The data sheet will be used for defining the purchaser’s requirements & specifications of.rotating machinery to be purchased.

This check list shall be used for the first issue of each type of rotating equipment.

CHECK ITEMS AND POINTS IS. 19. 20.

TWC

ISSUED

PAGE

FORM A-G30.015-2E (9807)

0Toyo Engineering Corf.

ENGINEERING MANUAL CONTROL SHEET

ORIGINATING DEPARTMENT

l'/szj'M'tmn-r

(eipc)

NO.

TWC 1—1211 —250E

REV.

0 P

(40)

i

FORM A-G30.02Z-A (9609)

TITLE:

ITB AND CONTRACT REVIEW FOR ROTATING EQUIPMENT DESIGN TIME OF CHECK: IMMEDIATELY AFTER PROJECT LAUNCHING MEETING WHERE RELEVANT

PARTS OF THE ITB / CONTRACT ARE DISTRIBUTED AND EXPLAINED TO THE ASSIGNED ENGINEERS BY THE PROJECT.

NOTE: Results of the check shall be reported In the Discipline Job Execution Plan with this Check Listfilledjjjx

CHECK ITEMS AND POINTS

1. Special Features of the Contract, especially for the following points: (a) Type of Contract (Turn key, Lump Sum, etc)

(b) Project Schedule ( Mile Stones for E and P )

(c) Contractor's Organization / Formation for E.P.C Execution (d) Guarantee Items, Conditions and Figures

(e) Penalty Clauses

(0 Contractor's Scope of Work and Supply (g) Noise and Environmental Requirements

2. Special Features of the Plant, especially for the following points: (a) Experienced process or not

(b) Capacity of the similar plants experienced (c) Reference reoords and Capability of Licenser (d) Lioense contracted by Client or Contractor

(e) Existence of unique rotating equipment not handled in the past (0 Special Site Conditions

(41)

(g) Special Utility Conditions

3. Client Project Organization / Formation, especially for the following points: (a) Involvement of Client Hired Consultant

(b) Client and / or Consultant Resident at TOYO (c) Client's Approval on Documents / Drawings (d) Client's Approval on Vendor Selection

4. Applicable Codes, Standards and Local Regulations, especially for the following points:

(a) Clear Definition of the applicable Codes, Standards and Local Regulation with status of Edition

(b) Availability of these Documents

5. Statutory Approval ( Subject and Schedule ), especially for the following area:

(a) Building Approval

(b) Explosion Protected Electrical Components (c) Pressure Vessel Registration / Nameplate

6. Specific requirements for Project Language and Measuring Unit 7. Specific requirements for extent of CAD application and specific requirements for Software / Version

8. Client’s specific requirements for QC, QA execution

9. Specific requirements for Training, especially for the following points:

TWC

ISSUED

PAGE

MEMO 1 0 REV. FORM A-G3D.015-1/2 (9807)

0

Toyo Engineering Corp.

TITLE:

ITB AND CONTRACT REVIEW FOR ROTATING EQUIPMENT DESIGN

TIME OF CHECK: IMMEDIATELY AFTER PROJECT LAUNCHING MEETING WHERE RELEVANT

PARTS OF THE ITB / CONTRACT ARE DISTRIBUTED AND EXPLAINED TO THE ASSIGNED ENGINEERS BY THE PROJECT.

NOTE: Results of the check shall be reported in the Discipline Job Execution Plan with this Check List filled up.

CHECK ITEMS AND POINTS

(a) Location of the Training (Vendors’ Shop / Site) (b) Language

(c) CD-ROM and / or Video Tape 10. Client’s special requirements for Test and Inspection

(a) Shop Performance Test of Compressor (b) Shop Performance Test of Gas Turbine (c) String Test

(42)

(d) Site Acceptance / Performance Test 11. Applicable Engineering Specifications

(a) Client’s Standard Specifications or TES

(b) Extent of application of Clients Specification for Piping, Electrical and Instrumentation to the Packaged Units

(c) Client's Specifications for Local Panel, Redundant PLC( etc. (d) Procedure for Client’s Approval of Deviations

12. Project Vendor List

-(a) Existence of Contractual Client’s Approved Vendor List (b) Procedure for Client's Approval of Additional Suppliers (c) Contractual Requirements for Uniformity of the Suppliers of Electrical Equipment, Devices and / or Instruments

13. Scope of Spare Parts and Operational Consumables

(a) Consumable Spare Parts, Capital Spare Parts Two Years Spare Parts

(b) Spare Rotor for Compressor, Steam Turbine, Gear, etc (with Mechanical Running Test)

(c) Initial Charge of Lube Oil, Refrigerant and Desiccant, etc (d) Other Special Items

TWC

ISSUED

PAGE

FORM A-G30.01S-2/2 (0807)

0 Toyo Engineering Corf.

TOKYO

JAPAN

Toyo Engineering Corp.

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINE

TWC I-1211-101E

ISSUED DEC.15,'95

PAGE 1/3

TITLE

: Rotating Machinery/Piping/Civil Engineering Coordination Meeting

TIME o f CH ECK

: Within two weeks after the issue of preliminary plot plan

(43)

RELATED MAN UALS; tegi-121 1-202, Design of foundation for centrifugal

tegi-1632-201,

Design of foundation for rotating machines

tegi-13 13-002,

Design standards for piping around compressors

and turbines

TEGl-1313-003,

Pump piping

WORKFLOW CHART

CHECK ITEMS AND POINTS

<For large rotating machines (compressors, medium and large turbines,and large centrifugal pumps with a forced lubrication system)>

- Type of drivers and driven equipment, and the position, orientation and size of main nozzles

- Requirement for minimum straight pipe length of main piping

- Any special consideration to the piping for normal maintenance of rotating machines (such as necessity of spool pieces)

- Location of ancillary equipment (lube Oil systems, overhead tanks, local gauge boards, etc.)

- Elevation of ancillary equipment such as oil reservoirs, seal oil traps and overhead tanks

- Requirements for piping slope and no pocket in piping

- Cable-distance from the central control room to a local control panels (Restriction is available in case of gas turbine drive.)

- Indoor or outdoor installation

- Requirements for ventilation of side wall and air-conditioner in the case of the indoor-installation

- Necessity of winterization for piping

- Requirements for location ofkey-valves and key-instruments concerning start-up, normal and shutdown operation.

- Presence of emergency isolation valves and vent valves controlled from the remote position

REMARKS

MEMO WORK NO. REQ.NO. DOC.NO. 2 1 0 REV. FORM A-G30.D15-1/2 (0305)

(44)

TOKYO JAPAN

Toyo Engineering Corp.

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINE

TWC

1-1211-101E

ISSUED

DEC.

15,*95

PAGE 2/3

TITLE : Rotating Machinery/Piping/Civil Engineering Coordination Meeting

WORK FLOW CHART

CHECK ITEMS AND POINTS

CHECK

ABC

REMARKS

- Type of baseplates (Common, Separate, Sole)

■ Delivery condition at the time of shipping from vendor’s work

shop, and the scope of field assembling

- Requirements for crane and hoist (necessity, objective, parts and

lifting weight, allowance in duty, and lifting height)

- Space for removal of internals (internal casings, tube bundles of

heat exchangers, heaters, filters) at the time of maintenance

- Expected size of large parts, floor-loads and floor space of workshop at the time of field-maintenance

- Equipment installation methods and procedures

- Pull-out procedures for field-maintenance and dropout area

(45)

- Gravity points and magnitude of static loads and dynamic loads of the equipment, direction of the loads and the allowable values of foundation amplitude for design of foundation

- Reaction doe to thermal expansion and pressure-load when using bellows joints to be taken into account of the loads of foundation and equipment nozzles.

- Designation of grouting type

- Shape (grand, elevated, mezzanine and so on) of foundation, type

of foundation bolts and suppliers of them

- Suppliers of liner plates and shim plates

- Suppliers of insert plates

□ □

□ □ □ □ □ □

□ □ □ □

MEMO WORK NO. REQ. NO. DOC. NO.

(46)

FORM A-G30.015-1/2 (9305)

TOKYO JAPAN

Tovo Engineering Corf.

title : Rotating Machinery/Piping/Civil Engineering Coordination Meeting

WORKFLOW

CHART

CHECK ITEMS AND POINTS

CHECK

A B C

REMARKS

- Necessity and method of noise protection, and suppliers of protective devices against noise?

- Piping material specification of ancillaiy piping

- Vendor’s scope of supply for piping

• Special flanges and suppliers of them

- Suppliers of insulation materials

- Compliance with laws and local regulations

- Particularity (party in charge, scope and schedule) of pulsation analysis and vibration analysis

- Confirmation on the requirements in the related TEG listed. <Other equipment

- Nozzle orientation of large fans, blowers and pumps

- Location of equipment-installation and type of foundation (grand, mezzanine or elevated fiame?)

- Vibration-proof measures for rotating machine installed on steel structure

(47)

of intake pits of large water intake pumps

- Check on possibility of water hammering and its countermeasure

□ □

□ □

□ □

□ □ D

□ D

□ □

□ □ □ □ □

□ □

MEMO WORK NO, REQ. NO. DOC. NO. FORM A-G30.015.iy2 (9305) TOKYO JAPAN

(48)

Toyo Engineering Corf.

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINE

TWC

1-1211-102E

ISSUED DEC.15,’95 PAGE 1/3

TITLE : Rotating Machinery/InstnimerLtatiori Coordination Meeting

TIME OF CHECK: Before the issue of requisition for large rotating machines

RELATED MANUALS: P/C STANDARD :

A6.004-1 INSTRUMENT SYMBOLS

A6.027-1 CONNECTION TYPE AND SIZE OF INSTRUMENTS

A6.028-1 SCOPE OF SUPPLY AND TERMINAL SPEC OF INSTRUMENTS.

A6.005-I LOCAL GAGE BOARD

FORMAT [INSTRUMENT AND CONTROLS DATA SHEET] .

Applicable engineering spec. Applicable API standards

WORKFLOW

CHART

CHECK ITEMS AND POINTS

CHECK

ABC

REMARKS

Confirmation on items of rotating machine equipped with instrumentation

- Confirmation on the outline of instrumentation around equipment and the scope of equipment-vendor’s supply based on typical P&ID

(49)

- Identification of a terminal point (such as at a junction box) of each instrument and its location

- Objective, construction and installation-location of local control panels (or local gauge boards) which the equipment-vendor will supply.

- Planning of the purchaser’s local control panels, which will be installed near rotating machines, and their objective

- Identification of instruments which will be supplied by the equipment-vendor to be mounted on the purchaser’s panel.

• Identification of instruments which will be supplied by the purchaser to be mounted on vendor’s local panel or gauge board.

- Particulars of vibration monitoring systems and their installation points

• Type-selection and supplier of the vibration monitoring systems

• Necessity of signal linkage between the vibration monitors and DCS

(50)

- Suppliers of barriers for intrinsically safe instruments

□ □

MEMO WORK NO.

REQ. NO. ITEM NO. VENDER DOC. NO.

2

1

0

REV. FORM A-G3Q.015-1/2 (9305) TOKYO JAPAN

Toyo Engineering Corp.

ENGINEERING WORK CHECK SHEET

DESIGN OF ROTATING MACHINE

TWC 1-1211-102E

ISSUED DEC.15,'95

PAGE 2/3

title

: Rotating Machmery/Instrumentation Coordination Meeting

(51)

WORKFLOW CHART

MEMO WORK NO. REQ. NO. ITEM NO. VENDER DOC. NO. FORM A-G30.015-1/2 (9305) TOKYO JAPAN

Toyo Engineering Corp.

ENGINEERING

WORK

CHECK SHEET

DESIGN OF ROTATING MACHINE

TWC 1-1211-102E

(52)

PAGE 3/3

TITLE : Rotating Machmery/Instrumentation Coordination Meeting

WORKFLOW • CHART

CHECK ITEMS AND POINTS CHECK

ABC

REMARKS

- Connection type and size of wiring and tubing

- Type and size of screws for instruments

- Necessity of cable glands and their supplier (usually by the purchaser)

- Dial size of pressure gauges and thermometers, and measuring systems used for instruments

• Designation of material of thermocouples according to temperature range

- Specific requirements for RTD (Pt-100, 3-wire system, etc.)

- Direction of action for switch contacts and solenoid valves (normal action and action upon abnormal conditions) and action upon power- or signal-failure.

- Safety measure at instrument-air failure, and action of control valves at the time of air- or signal-failure (FO^FC or FL)

- Appointment of electric power source for instrumentation . (AC110V, DC24V, etc.)

- Designation of vendors for instruments and vendor list

- Appointment of hazardous area classification and explosionproof construction of electrical instruments

- Necessity of certificates for intrinsically safe or explosionproof instruments

(53)

- Basic planning for preparation of an engineering specification applicable to instrumentation for rotating machines.

- Tag numbering of instruments and appointment of the number diversified to each item

- Information required to the purchaser and documents to be submitted by equipment-vendors for design of instrumentation

D □ □ O

□ □

□ □

□ □

□ □

ODD

MEMO WORK NO. REQ. NO. ITEM NO. VENDER DOC. NO. FORM A-Q3Q.015-1/2 (9305) TOKYO 0 JAPAN

(54)

TITLE : Rotating Machinery/Elcctrical Design Coordination Meeting

TIME OF CHECK: Before the issue of requisition for rotating machines

RELATED MANUALS :

TEG1-1211-001

[INTERFACE OF ROTATING MACHINES AND

THEIR DRIVERS]

FORMAT [ELECTRICAL LOAD LIST],

[MOTORDATA SHEET]

[DATA SHEET FOR GD2]

WORKFLOW CHART

CHECK ITEMS AND POINTS CHECK

ABC

REMARKS

<General>

- Will the driving motor be purchased with main equipment? (This should be discussed more specifically in case that the main

equipment will be purchased at a separate area from that of the electric motors.)

- Which electric items (oil pump drivers, turning motors, heaters, etc.) will be purchased with equipment from equipment-vendors?

- Appointment of hazardous area classification.

- Are there any items subject to automatic power input after instantaneous voltage drop? How long is the. time-duration of the instantaneous drop? Will it be necessary to check and examine the strength of equipment?

- Is there any emergency power source? AC or DC? How about time lag in supply?

- Which motors will be backed up with the emergency power source? (items to be determined by equipment-designer)

(55)

- Definition of GD2 (unit, conversion by rotating speed) and use of

standard form for one to appoint it for large size electric motors.

- Starting method and starting torque of the electric motors. (Are any special requirements available for them?

- Items subject to automatic starting (items to be detennined by equipment design side).

□ □ □ □ □

□ □

□ □

□ □

□ □

P

MEMO WORK NO. REQ. NO. ITEM NO. DOC. NO. 2 1 0 REV. FORM M330.01S-1/2 (9305) TOKYO 0 JAPAN Toyo Engineering Corf.

(56)

WORKFLOW

CHART

CHECK ITEMS AND POINTS

CHECK

ABC

REMARKS

- Are there any items of frequently intermittent use?

- Are there any items possibly driven by a WVF motor?

- Are there any items possibly subject to substantial cost-reduction by reducing rated output of the motor?

<In case that electric motors are not purchased with the driven equipment from equipment-vendors>

- Confirmation on use of forms “ELECTRICAL LOAD LIST’ to appoint specifications of each item of electric motor.

- Where will the electric motor be mounted on a baseplate or an equipment? How about the route of shipment?

a. In case of the common baseplate and vendors for both driven equipment and drivers are located in the same area.

b. In case of separate baseplates.

c. In case that both vendors are located in separate areas.

- Who is responsible for packing of electric motors for delivery from equipment-vendor’s shop to the site?

- Check if the contracted motors are required tor shop testing of driven equipment.

- Preliminary delivery schedule of electric motors in case that they are shipped to the equipment-vendor’s shop. (Final arrangement will be made separately in this regard.).

- Who is responsible for machining, mounting and shipment for a coupling-half at the motor-end?

(57)

especially for electric motors with sleeve bearings.

- Check items of electric motor requiring a sliding rail (which is within the scope of motor-vendors).

- Make use of a typical starting torque curve of driven equipment. Determine items requiring a particular starting torque curves.

- Issue schedule of preliminary motor outline drawings tor design of equipment, and the same of certified ones.

□ □ □ □ □ □ □ □ □ □ □ □ □ □ a □ □ o n MEMO WORK NO. REG. NO. ITEM NO. DOC. NO. FORM A-G30.015-1/2 (9305) TOKYO 0 JAPAN Toyo Engineering Corf.

(58)

TITLE : Rotating Machineiy/Electrical Design Coordination Meeting

WORKFLOW

CHART

CHECK ITEMS AND POINTS

A

- Check items for which lube oil is supplied from equipment side to an electric motor. □ CHECK

_____

c

REMARKS

- Do basic planning and scheduling oh supply conditions of the lube oil (amount of oil, supply pressure, temperature, heat duty, low pressure alarm and trip sets, type of oil) and on scope of oil piping and instrumentation.

• Make mutual understanding for the range of expected rotating speed of electric motors considering slip speed of induction motors.

□ □

<In case electric motors are purchased with the driven equipment from equipment-vendors including the case of canned motor or magnetic driven pumps>

- Availability of Engineering Spec, applicable to electric motors or, unless available, expected issue-date of the spec.

- Confirm a form of data sheet applicable to the electric motors.

- Confirm, the following specifications of particular application to jobs:

(59)

• Hazardous Area Classification

• Protection System

• Applicable Code

• Position of Terminals Box (Viewed from Opposite Coupling End)

• Type of cable entry, applicable threads and scope of vendor’s supply

• Ventilation and Cooling System

• Requirement of Space Heaters

• Is action of thermostats NORMAL OPEN or NORMAL CLOSE? □ □ □ □ □ □ Q O □ □ □ □ □ □ □ □ □

<In. the case of reciprocating compressors directly coupled with a □ □

driving motor>

(60)

machining?, and supply schedule of gage plates from equipment □ manufacturer

- Allowable limit of speed variation on the electric motors and the same on equipment side (if any).

MEMO WORK NO.

REQ. NO. ITEM NO. DOC. NO.

FORM A-G30.015-1/2 (8SD5>

TOKYO 0 JAPAN

Toyo Engineering Corf.

TITLE : Rotating Machinery/Electrical Design Coordination Meeting

WORKFLOW CHART

CHECK ITEMS AND POINTS

A

Confirm procedures for analysis of speed variation and for determination of GD2 for equipment and electric motors.

CHECK

"~B~“

C

REMARKS

- Issue schedule of the start torque curve, the crank effort diagram (rotation angle vs. torque curve) and GD2

<In the case of vertical pumps 'with a rigid coupling>

(61)

electric motor.

- Machining of the motor-shaft-end is to be in compliance with the □ instructions from the equipment-vendor. Finishing of the end face

is to be within the specified tolerances.

<In the case of"Sundyne Pump”>

- Supplier of spline-couplings (usually the equipment-vendor □ □

provides it to a motor-vendor).

<In the case of double-ends shaft motors>

Double-ends shaft motors are required to have insulated

construction against static current on a rotor. Check what kinds of measures arc to be taken?

□ □

<In the case of variable speed motors>

- When adopting VWF motors, obtain a torque fluctuation curve on the motors and confirm with the equipment-vendor to assure that no resonance will occur in the speed control range. Make planning and scheduling to ensure the above.

P □

WORK NO, REQ. NO. ITEM NO. MEMO

TITLE: Plot Plan Screening Meeting (Rotating Machinery)

TIME OF CHECK: Preliminary, AFP, AFD

Security Level 2

TWC ISSUED PAGE

Unless stamped "CONTROLLED" , any hard copy from the TEC-STANDARD SYSTEM is handled as "Non-control led" .Therefore, users should-confirm that the copy is relevant version.

(62)

Pre. ( ) ( ) ( ) ( ) ( ) ( ) C ) () () () () () () () () () MEMO 1 0 REV.

twc1211104e.doc 0 Toyo Engineering Corf

TITLE: Plot Plan Screening Meeting (Rotating Machinery)

TIME OF CHECK: Preliminary, AFP, AFD

Security Level 2 TWC ISSUED PAGE Pre. ( )

(63)

( ) ( ) ( > ( ) t) ( ) ( ) ( ) twc1211104e.doc

0 Toyo Engineering Corp.

TOKYO

9b

JAPAN

Toyo Engineering Corp.

TITLE : P&1D Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD related MANUALS : TEG1-6221-106

PREL. □ □ □ □ □ □ □ □ □

(64)

□ □

MEMO WORK NO.

P&ID DWG NO. 2 1 0 REV. TOKYO 0 JAPAN

Toyo Engineering Corp.

TITLE : P&ID Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD related manuals : TEG1-6221-106

PREL. □ □ □ □ □ □ □ □ □ 0 □ □ □

(65)

memo work no.

P&ID DWG NO.

Q/x

TOKYO JAPAN

Toyo Engineering Corp.

TITLE : P&ID Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD RELATED MANUALS : TEG1-6221-106

ISSUE STAGE

PREL. □ □ □ □ □ □ □ □

(66)

CHECK ITEMS & POINTS

(19) Confirm surge-protection for centrifugal pumps with a Q-H curve having a peak point (for example, "Sundyne" pumps), and that the system is so arranged to enable to start the standby machine properly in such a case, (20) Confirm the necessity of warming-up for high

temperature pumps and cooling-down for low temperature pumps, and the suitability of systems. (21) Appointment and conformation of straight length of

suction piping for centrifugal compressors, gas expanders, double suction pumps, etc.

(22) Confirmation and indication of a flow control system for reciprocating pumps

(23) Confirmation of the necessity of installing minimum flow orifices for high pressure pumps such as BFW pumps, and indication of vendor’s scope of supply for the subject orifices.

(24) Necessity of block valves around compressors, and interlock devices for their opening and closing (25) Confirm the suitability of branch-points of the

compressor kickback (bypass) line.

(26) Confirm the suitability of the destination where the pump reverse line returns, and of the flow control method of the reverse line.

9. Confirm the presence of special contaminants in liquid or gas handled.

(1) Presence of hydrogen sulfide or chlorine contents (2) Presence of slurry contents

10. Treatment of Vent and Drain:

(1) Indicate the basic planning of the vent and drain for rotating machines in aspect of process design. (2) Indicate actual design conditions of vent and drain based

on vendors1 information.

11. Related to Maintenance:

(1) Are flanges and short pipes suitably installed for equipment maintenance? Are the positions of block valves appropriate for utilities connections, and vent and drain?

12. Hot Insulation and Cold Insulation using Steam Trace, Jacket and so on.

(1) Are the steam trace and jacket provided for the rotating machines clearly shown?

(2) When materials for the steam trace are within vendor’s scope of supply, is it specially mentioned?

REMARKS

WORK NO. P&lbDWQNO.

(67)

TOKYO ^ JAPAN Toyo Engineering Corf.

TITLE : P&ID Screening Meeting (Design of Rotating Machinery)

TIME OF CHECK: □ Preliminary □ AFP □ AFD RELATED MANUALS : TEGl-6221-106

ISSUE STAGE

CHECK

PREL.

AFP

AFD CHECK ITEMS & POINTS

□ 13, Screening of Vendors’ P&ID for Main Rotating Machine:

The Vendors1 P&IDs for main rotating machines are to be

A I B I C

□ □

REMARKS

subject to the themes of screening.

(1) Confirm the following item, 14.

(2) Examine preventive analysis against power failure.

n

(68)

14. Vendors’ Information:

(1) Confirm tie-in conditions with vendors.

(a) Connection size, rating, etc. Enter reducers, spec-break if necessary.

(b) Line spec for piping which is represented in vendor’s P & 1 Diagram, but is within the purchaser's scope of supply. Pay particular attention to extraction and/or leak-off steam piping for steam turbines taking into consideration of partial operation of the steam turbines.

(c) Compatibility of vendor’s control systems and instrumentation with the purchaser’s.

(d) Connections of all utility lines with the purchaser’s ,and their sizes and line spec. A supplier of all block valves for utility lines.

(2) Confirm such a requirement as piping slope and no pocket

in piping which is within the purchaser’s scope of supply.

(69)

□ □

□ □

15. Planning for Pre-commissioning Operation:

(1) Examine and confirm pre-commissioning procedure in aspect of the rotating machine.

(a) Cleaning of piping, especially the necessity of pickling for compressor suction piping, and the procedure of blow-out for such piping

(b) Necessity and procedure of oil flushing

(c) Procedure for nitrogen and/or gas purging

(d) Rotating machines used for piping-flushing, and protection measures for shaft-seals of theirs

(2) Examine and confirm field testing procedure.

(a) Procedure for solo running test for each steam turbine(*l)

(b) Procedure for compressor mechanical running test(*2)

(70)

machines, especially for centrifugal compressors, and instrumentation required for the test

0

□ A suppliers of special flanges if any. (*l)Be careful about high pressure steam turbine. (*2)Air, N2, actual gas, etc.

16. Winterization:

Confirm if winterization is properly taken around the rotating machines (hot insulation, steam trace, drain-system, etc.).

(71)

WORK NO. P&ID DWG NO.

MEMO

TOKYO JAPAN

Toyo Engineering Corf.

TITLE : Divisional Screening for Key Points of Engineering of Rotating Machinery

TIME OF CHECK: Immediately before the first return of principal vendor prints for the major equipment

Supplement : The screening may be conducted two times on presence of the major equipment with different

engineering phase each other. Pending matters shall be reported within six months after placing the ordering of the subject equipment. The screening meeting in this concern may be held only when it is considered effective.

RELATED MANUALS: Equipment design PROJECT MONTHLY REPORT

WORK FLOW CHART

CHECK ITEMS AND POINTS

A

Order far Equipment

- Is the progress of engineering for rotating machines expectedly smooth?

- Is there any equipment for which no order has yet been placed? What is the reason? Expected time of placing the order?

a

CHECK

___

(72)

c

REMARKS

_i_ Obtaining approval application Drawing of Major Vender prints

- What are the spare parts with high importance? Has orders been placed for them yet?

- How about the situation of issue of vendor prints? No significant adverse effects given to other disciplines?

- As for the equipment which is subject to precise design-review, has the design-review been completed and properly recorded?

_i_

Check of the Above

- If the above review has not yet be completed, its schedule, agenda and reviewers are to be decided.

□ □

□ □

□ □ □

(73)

- Aren’t there any equipment, design, portions and sub-order which are not based on the actual proven experience of the purchaser’s and/or vendor’s?

- When “yes” to the above query, how did you examine a technical evaluation to them?

- Have any past troubles concerned been fed back to the design?

□ □ □

□ □ □

□ □ □

_±_

Return of Approval Drawings of Major Vendor Prints

- Have you read the job close-out report of similar process and plant?

- When there were problems in the past five years on the same vendors as adopted, axe they fed back to current engineering?

n

MEMO WORK NO. REG. NO.

(74)

ITEM NO. VENDOR DOC. NO. 2 1 0 REV. FORM A-G 30.015-1/2 (9305) TOKYO 0 JAPAN

Toyo Engineering Corp.

TITLE : Divisional Screening of Key Points of Engineering of Rotating Machinery

WORK FLOW CHART

Order for Equipment

Obtaining application! Major Va

_si_

Check of the Above

_±_

Return of Approval Drawings of Major Vendor

Prints

CHECK ITEMS AND POINTS - Aren't there any critical points for the plant guarantee? - Have you checked if there are not any operational problems for

compressors and turbines? Aren't there any particular problems during start-up and shutdown?

• Different gases handled from specified one

(75)

■ Security of buffer gas supply for sealing (if necessary) * Seal differential pressure

* Field test run before commissioning • Change of steam supply conditions

- Aren't there any operational problem due to improper Q-H characteristic and limited-operation range of the pump? - How are the critical speed and the operational stability of turbo

compressors and turbines?

- How do you treat with the pulsation analysis of reciprocating compressors?

- Are items and procedures appropriate for shop-testing?

- Which tests and inspection will be witnessed as a design engineer? - What is the current issue stage of Process P&I Diagram?

- Have you finished the compatibility check of Process P&ID (AFD) with Equipment Vendors’ Prints? When will be done if not finished? Were there any problems to do so?

- Was the check performed by using the check list entitled as P&ID Screening Meeting (design of Rotating Machinery)?

REMARKS

Refer to TWO No, 1-1211-105E.

MEMO WORK NO. REQ. NO, ITEM NO. VENDOR DOC. NO. FORM A-G30.015-1/2 (9305) TOKYO 0 JAPAN

Toyo Engineering Corp.

TITLE : Divisional Screening of Key Points of Engineering of Rotating Machinery

WORK FLOW CHART

CHECK ITEMS AND POINTS CHECK

ABC

REMARKS

(76)

> Obtaininj application Major Vei

Return of Approval Drawings ofMkj or Vendor Prints

- Have you checked the tie-in conditions of speed control governor for steam turbines and anti-surge control systems for centrifugal compressors in the above check?

- Have you finished the compatibility check of foundation drawings regarding anchor plans with the latest vendors' drawings? When will you do it if not finished?

- Have you conducted a screening check for compatibility of rotating direction between driven equipment and drivers based on each individual outline drawing? If not, complete it and report in three months before the shipment of equipment In case of steam turbines, however, incompatibility causes a fatal problem. Check carefully, therefore, when checking each outline drawing of both equipment.

- Review the JOB EXECUTION PLAN again. Are there any outstanding dispute or changes from it?

- How about the follow-up of particular job instructions/orders from the management and the pending matters?

- How about the follow-up of pending matters with the client if any?

- Aren’t there any vendors problematical for the execution of engineering? What are they in particular?

(77)

- Haven't the client claimed demand beyond the contract?

- Aren't there any additional claim of a sizable amount submitted from vendors?

- What was the achievement related to cost like huge cost-reduction?

- What was the achievement leading to the technical innovation or enhancement?

- Is the technical know-how registered and stored in the files properly? P □

□ □ □

□ □ □ □ □ □

u nu

□ □ □ □ □ □ □ □ □ n □

p p □

p □

MEMO WORK NO. REQ. NO. ITEM NO. VENDOR DOC. NO. FORM A-G30.015-1)2 (9303)

TITLE:

PREPARATION OF REQUISITION

TIME OF CHECK: THE FIRST PREPARATION OF THE REQUISITION FOR EACH TYPE OF ROTATING MACHINERY.

References

Related documents

On this account, semantic information and cues inherent to the native accent of the speaker speed up word recognition, but are not used as a strict cue to restrict lexical search to

4.2.19 When specified on the purchaser‟s PIP ELSSG01D Data Sheet, an interlock shall be provided to prevent opening of the breaker compartment door unless the breaker is in

stock transport order : at goods receipt the transported quantity is posted in the receiving plant from stock in transit into unrestricted-use stock (or stock in quality

The Company cautions you that forward-looking statements are not guarantees of future performance and that its actual financial position, business strategy, plans and objectives

This section discusses previous research in the area of term dependencies, specifically: query operators to match term-dependencies in documents, the selection of term combinations

In any of your Application Firewall profiles, you configure general settings for the Cookie Consistency security check in the pane that opens when you open a profile. The

The Vendor shall take all necessary precautions and exercise due caution so as not to damage the premises or properties of others. The Vendor’s signature on the bid sheet certifies

Mere is that way [masculine] on and off the field. But Mere can’t say that she’s lesbian. In 20xx, her uncle found out that she was lesbian. … She got chased from her home and went