• No results found

E6 Trondheim-Stjørdal, the Trondheim section.

N/A
N/A
Protected

Academic year: 2021

Share "E6 Trondheim-Stjørdal, the Trondheim section."

Copied!
8
0
0

Loading.... (view fulltext now)

Full text

(1)

Tendering processes

E6 Trondheim-Stjørdal,

the Trondheim section.

www.vegvesen.no/e6ost

ENGLISH

(2)

1 INTRODUCTION

1.1

Prequalification

The Norwegian Public Roads Administration, Mid-Norway Region has planned a process for awarding a contract for implementation of the main work on the Western surface work zone of the Trondheim Section, as a design build contract. This work is part of the E6 Trondheim – Stjørdal project. This information pamphlet provides a general description of the contract as it is now planned.

1.2

National Transportation Plan

The Storting White Paper on the National Transportation Plan (NTP) presents the main features of the government’s transportation policy. NTP has a 10-year plan period, but is revised every four years.

The Nidelv bridge – Grillstad sub-project (Trondheim sec-tion) is discussed in NTP for the period 2002 – 2011: ”The earnings in the E6 Trondheim - Stjørdal toll-road project are significantly higher than expected, and work is therefore underway on plans to expand the project to also include the end sections in Trondheim and Stjørdal. If this meets with approval, the Nidelv bridge - Grillstad project could be implemented in the final part of the ten-year period. For the time being, this project expansion is being based on partial road financing by an expansion of the toll-road project E6 Trondheim - Stjørdal, cf. Storting Proposi-tion No. 124 (1986-1987) and Storting ProposiProposi-tion No. 42 (1994-1995).”

NTP for the period 2006 – 2015 confirms that implementa-tion of the E6 Trondheim - Stjørdal project may take place in the final part of the ten-year period.

In the background material for the National Transportation Plan 2010-2019 from the public transportation agencies, the assumption is that the E6 Nidelv bridge – Grillstad sub-project (Trondheim section) will commence before 2010. The plan is still for the project to be partially toll-road financed as a part of the E6 Trondheim – Stjørdal toll-road project. The project is to be completed in the first four-year period.

1.3

Resolutions relating to

implementation and

financing

The Storting has thus far not passed a final resolution regarding implementation and financing of the E6 Trondheim - Stjørdal project. Completion of the Ministry of Trans-port and Communication proposition to the Storting is underway and it is expected that the proposition will be considered in the Storting during the course of the autumn session of 2008.

1.4

Authorities

The Storting is the budgetary authority and makes decisions on national road network building projects. The Minister of Trans-portation and Communication implements the decisions of the Storting. The Minister

Contents

1 INTRODUCTION

1.1 Prequalification

1.2 National transportation plan

1.3 Resolutions relating to implementation

and

financing

1.4 Authorities

1.5 The procurement procedure and contract

signing

1.6 The purpose and meaning of the information

2 PROJECT DESCRIPTION

2.1 General information about the

E6 Trondheim - Stjørdal project

2.2 Description of end section in Trondheim:

Nidelv bridge – Grillstad.

2.3 Western surface work zone - general contract

2.4 Structures

2.5 Area development plans

2.6 Special issues

2.7 Project goals

3 COMPETITIVE DIALOGUE - FACTS

3.1 Description of the procurement procedure

3.2 Brief description of implementation of the

procurement procedure

(3)

is responsible to the Storting for building, operation and maintenance of the national road network.

The Norwegian Public Roads Administration, Mid-Norway Region is the local governmental road authority. The Nor-wegian Public Roads Administration, Mid-Norway Region will represent the State in the procurement process and be a contractual party as the representative of the State in the implementation of the project. The Norwegian Public Roads Administration, Mid-Norway Region has carried out the preparatory planning for the project, and will carry out land acquisition and other facilitation of the project. The Norwegian Public Roads Administration, Directorate of Public Roads is the central authority for national roads and shall authorize building plans where this follows from the prevailing design engineering regulations. Corresponding authority approval must be secured from the Norwegian National Rail Administration for structures which affect any nearby railway.

The Municipality of Trondheim is the local authority, and is the planning and building authority in accordance with the Planning and Building Act. This also applies to municipal cables/lines and other infrastructure, over which the Mu-nicipality of Trondheim has approval authority.

1.5

The procurement procedure and

contract signing

A contract regarding detailed engineering and implemen-tation of the Western surface work zone in the Trondheim Section will be entered into in accordance with the rules for competitive dialogue in the Act of 16 July 1999 No. 69 relating to public procurement and the Regulations of 7 July 2007 No. 402 relating to public procurement (”the Procurement Regulations”).

The contract award will take place after a competition which includes the following main steps:

• prequalification

• invitation to participate in dialogue phase

• submission of outline proposal

• dialogue phase

• invitation to tender

• tender phase

• signing of contract

Chapter 3 contains a more detailed description of the procurement procedure.

Public announcement of the competition will be sent to the Official Journal of Norway and to the Official Journal of the European Communities as soon as the basis for im-plementation is in place. The public announcement will be an invitation to apply for prequalification.

1.6

The purpose and meaning of the

information

The information in this information pamphlet is only meant to be a basis on which to consider participation in and, potentially, the preparation of a prequalification applica-tion. The information is to be construed as guidelines and preliminary, and will be replaced by the information which will be published following pre-qualification and selection of relevant tenderers. Accordingly, the information pro-vided in this document can not subsequently be invoked in connection with the final contract.

2 PROJECT DESCRIPTION

2.1

General information about the E6

Trondheim - Stjørdal project

The original development of E6 along the stretch Trondheim – Stjørdal has had a very long period of planning, followed by implementation in several stages. In 1986-1987 a resolu-tion was adopted for this stretch of E6 to be developed in four phases from 1988-1994. The first part was completed in 1988, whereas the entire stretch between the remaining end sections was finished in 1995. In 1994-1995, a new collection system was adopted, and the building of the end sections was postponed indefinitely due to insufficient financing. A new bridge over the Nidelva river (”Pirbrua” - the Pier Bridge) was originally a part of the northern relief road in Trondheim, but is now being built as a separate project under the E6 Trondheim - Stjørdal project organisation. It is the end sections in Trondheim and Stjørdal municipalities, respectively, which now are to be built, thus completing

(4)

the E6 Trondheim – Stjørdal project. By completing the E6 Trondheim – Stjørdal project, a better link between Stjørdal and Trondheim will be achieved. Trondheim Airport Værnes is located at Stjørdal, and with the completion of the project, the travel time from Værnes to the Trondheim city centre will be reduced.

If one looks at Trondheim alone, the city will gain a new primary thoroughfare from the east as well as a greater effect of the ring road around the city. Today, it is the two-lane Innherred road which is the main approach, and there are considerable traffic flow and environmental challenges associated with this. The current road passes through major residential areas, and is not dimensioned for the present-day traffic volume. The northern relief road is now under construction, and construction of the Nidelv bridge - Grillstad section, will make the ring road system around Trondheim more complete.

In Stjørdal, the realisation of this project will facilitate better local development of downtown Stjørdal, as well as greatly improving the flow of traffic on E6 and E14 past Stjørdal.

2.2

Description of the end section in

Trondheim: Nidelv bridge – Grillstad.

The end section in Trondheim includes building approx. 4.5 kilometres of new or improved four-lane E6 along the stretch from the Nidelv bridge – Grillstad. This also includes a 2.4 km long tunnel from Møllenberg to Strindheim, of which approx. 2 km is in rock, and an intersection on three levels at Strindheim with its own ramp tunnels, also in rock. A cross-connection to Håkon VII street is also included. The project also includes measures to improve the overloaded situation in and around the Innherreds road.

2.3

Western surface work zone - general

contract

The contract includes design engineering and building of the new E6 from Pirbrua to approx. 30 metres within the entry point of the rock tunnel under Møllenberg. Detailed design engineering and reconstruction of Dyre Halses street, Skippergata and Losgata, as well as reestablishment of

Kirkegata and Gamle Kongevei are also included. In this context, several concrete structures, as well as necessary re-routing of cables, lines and pipes, are included.

The intention is to have a separate contract for preparatory work at Nyhavna with temporary roads and diversion of the railway line. Furthermore, the plan is that the handling of presumed moving and securing of buildings and setting them up again over the part of the tunnel in soil will be carried out under a separate contract, and a separate, final landscaping project is planned for implementation under a separate contract.

2.4

Structures

The following main concrete structures are included

in the project:

Tunnel in soil (drawing K101) assumed from profile

P20 to profile P288

A new railway crossing for E6 (drawing K101) from

P-25 to P20.(Part of tunnel in soil)

Trough in front of tunnel in soil (drawing K102).

New pedestrian culvert under the railway (drawing

K103).

Temporary railway bridge for re-routed railway

(dra-•

wing K104). Applies only to demolition for this con-tract.

Temporary bridge over Innnherreds road (drawing

K105).

New railway bridge over Skippergata (drawing

K106).

New technical room with pumping station, transformer

and office for operation of tunnel construction work (drawing K107).

Underpass under Dyre Halses street (drawing K108)

Retaining walls (drawing K109).

Rebuilding of railway platform (stop) in accordance with

new requirements and with length approx. 110m

For the structures cf. Drawing K101 (portion under the railway), K103 and K106, construction plans exist which are very close to being approved by the Norwegian National Rail Administration as the appropriate authority. These plans will be made available to the general contractor.

(5)

2.5

Area development plans

The following area development plans apply to the Western surface work zone of the Trondheim section:

Zoning plan for E6, Nidelv bridge – Grillstad, Sub-plan

1, Nyhavna/Lower Møllenberg district, approved 23 November 2006.

Zoning plan for E6, Nidelv bridge – Grillstad, Delplan

2, Rock tunnel Lower Møllenberg – Strindheim, ap-proved October 2006

Zoning plan for E6 East/Northern relief road, new

bascule bridge over Nidelva (river), approved March 2007

2.6

Special issues

Preliminary plans for implementation of Western surface work zone affect many buildings and residents at Møl-lenberg

Buildings which must be temporarily moved or torn

down

Buildings which must be vacated for some periods of

time

Buildings under preparation for being secured /

un-•

derpinned / having foundations redone

Buildings which receive special follow-up with regard

to settlement damage

Buildings which to some extent are affected by the

construction work

Stringent requirements will be implemented in order to ensure that consequences for buildings and residents at Møllenberg are no greater than necessary. Reduction of planned consequences will be implemented as one of several award criteria for the general contract.

Geological and geotechnical investigations have been un-dertaken as a basis for design engineering and execution of the general contract. Very demanding soil conditions with quick clay and excess pore pressure against the bed-rock have been documented in the area where the tunnel in soil is to be built. Reports from all investigations which have been undertaken will be presented as part of the basis for the contract and tendering. If, during the course of the dialogue phase, a need for supplementary investigations and documentation is identified, this will insofar as possible be coordinated and carried out by the Norwegian Public Roads Administration before the tender phase. The results from any supplementary investigations will be distributed to all tenderers.

Work which entails a risk of disturbing sensitive soil masses and/or changes in the pore pressure require comprehensive planning and control while the work is carried out, in or-der to avoid unacceptable conditions along the way. The contractor must through design engineering and execution ensure that disturbance of quick clay is avoided, as this can have catastrophic results.

Blasting in quick clay areas requires special care, and must be planned in detail. It is expected that the contractor plans and performs monitoring of vibrations and pore pressure for this kind of work.

The design engineering and implementation must take into account that the construction is taking place in densely built-up areas and show due consideration for noise and

vibrations. For limit values reference is made to NS 8176. The choice of limit values must also be evaluated with regard to construction work in areas with sensitive masses (quick clay).

The salinity of the groundwater approx. at profile P70 corresponds to that of seawater. This must be taken into consideration in the design engineering and construction of concrete structures, and where relevant, in the use of permanent steel structures.

Design engineering and approval by the competent author-ity for work on water and sewage lines and cables has been progressed so far that it should be used as a basis in the further work. The design engineering work done within these areas will be made available for all relevant tenderers in the dialogue/tender phase for any questions and clarifica-tion (kept by the principal).

2.7

Project goals

The project objectives are divided into socio-political goals and performance goals.

Socio-political goals

The E6 Trondheim – Stjørdal project has the following goals:

Improve traffic flow on the E6 and E14 ??trunk roads

/ national highways

Reduce the number of traffic accidents, the feeling of

threatened safety and barrier effect

Reduce the current environmental impact, both locally

and globally

Create better conditions for cyclists and pedestrians

as well as local traffic

Contribute to progressive local development in Stjørdal

and Trondheim

Performance goals

HSE:

The project has the goal of avoiding undesirable incidents and thereby achieving an H-value (damage frequency) of 0 during the construction phase. This means that injuries which cause absence must not occur during the course of the entire project period.

Cost:

The entire project is to be completed within the stipulated cost framework.

Quality:

The new road network shall be built in accordance

to applicable manuals of which the most important are: Hb 017 Road and street design, Hb 018 Road construction and Hb 021 Road tunnels, in addition to the design engineering manuals.

The rock tunnel must fulfil EU tunnel directive

requi-•

rements

The project’s design guides must be used as a basis to

ensure that the new road system fits in aesthetically with the adjacent road network and otherwise with the desired visual profile

Emphasis shall also be placed on safe traffic solutions,

both for the completed road system and temporary traffic management during the construction phase, not least for cyclists and pedestrians, for whom cros-sing main roads with overpasses (rather than level

(6)

crossings) is the goal throughout the entire construction phase.

Great emphasis must be placed on quality assurance

in all phases, so that we can be sure to achieve the described quality.

Time:

No later than 2013, the entire project must be completed in accordance with the adopted development plan, with the exception of measures on the adjacent road networks.

3 COMPETITIVE DIALOGUE -

FACTS

3.1

Description of the procurement

procedure

In connection with the implementation of the Western surface work zone in the Trondheim section, the Norwe-gian Public Roads Administration intends to test the new procurement procedure ”competitive dialogue”.

”Competitive dialogue” is a procurement procedure gov-erned by the Regulations relating to public procurement, and may be relevant when awarding particularly complex projects. This is the first time for a contract project that. the Norwegian Public Roads Administration is using ”Competi-tive dialogue” as the procurement procedure. Therefore, this work has pilot project status, where the objective is to develop guidelines for the use of this procurement proce-dure, as well as for carrying out the construction work.

The procedure for competitive dialogue is governed by Section 4-2, litra c) of the Regulations relating to public procurement:

procurement procedure where the principal, in one or more rounds, carries out a dialogue with suppliers regarding alter-native solutions before competing tenders are submitted The conditions for use of the procedure are governed in Section 14-2 of the Regulations relating to public procure-ment.

The provision reads as follows:

The Principal can use competitive dialogue when award-1.

ing particularly complex contracts.

A contract is particularly complex when the principal 2.

is not able to:

(a) in accordance with Section 17-3 (requirements related to performance and the use of technical specifica-tions), third subsection - to objectively and precisely define the technical terms and conditions which can fulfil their needs and purposes, or

(b) to objectively and precisely define the legal or financial conditions in connection with a project. The Western surface work zone of the Trondheim Section presents several technical challenges of varying nature. The tunnel in soil at Møllenberg with a presumably very deep construction pit presents special challenges associated with such things as quick clay, the external environment and neighbours directly above/in very close proximity to the tunnel. There may be various solutions to tackle these challenges, which makes the project well-suited for such a procurement procedure.

There are several potential construction methods which can be used to build the tunnel in soil at Møllenberg. It is therefore useful to gain access to the competence and

E6 Trondheim - Stjørdal

(7)

experience of the various contractors / consultancy groups, who will have the opportunity to offer their own proposals for solutions.

The procurement procedure entails that each individual contractor/ consultancy group can suggest the solution that it finds most suitable. The procedure includes a dialogue phase where the Principal engages in dialogue with each individual contractor/ consultancy group about the pro-posed solution, with an eye to possibly further developing it. This will provide opportunities for creative solutions and optimal implementation. The participating contractor and consultancy groups will have no knowledge about which solutions other players have proposed. The players who go through with the entire dialogue phase will be invited to deliver a final, binding tender, which is the object of the contract award.

The contracting industry has requested implementation methods where they are challenged to be creative, and the entire industry is now being challenged to join in the work on a very interesting development project.

The preliminary progress plan calls for the basis for the tender competition for the Western surface work zone to be ready for distribution early in November 2008. It is as-sumed that it may take around nine months to complete this competition. This means that the start of construction work can be no sooner than the autumn of 2009.

The intention is that preparatory work, such as re-routing of railway tracks, cables and lines and building a temporary road connection for Pirbrua (the Pier Bridge), be carried out under a separate contract in advance (presumed start-up approx. March 2009).

3.2

Brief description of the

implementation of the procurement

procedure

All parties who are interested may apply to participate in the competition. The Norwegian Public Roads Administration will pre-qualify participants based on given criteria where, for example, emphasis is placed on the requirement for geotechnical competence in Nordic quick clay conditions. In the first phase, the tenderers will prepare outline solu-tions to satisfy the Principal’s requirements. The purpose is to identify and establish how the Principal’s requirements can best be satisfied.

The second phase, the dialogue phase, will to a large degree be characterized by which solutions the suppliers have pre-sented, and how the principal responds to these solutions. It is likely that this phase will be split into partial phases with more rounds of dialogue where some solutions and tenderers may be abandoned along the way. During the dialogue, all aspects of the contract can be discussed with the selected suppliers. This means that all aspects of the solutions can be discussed and negotiated, including technical, time-related and financial terms and conditions. It may be relevant to enter into a remuneration agreement with the contractors participating in the dialogue phase.

The Principal must ensure that all the suppliers are treated equally. In particular, the Principal must make sure that there is no differential treatment in the form of providing information which could give some contractors a better position than others. All information which comes from the Principal must be presented simultaneously and in the same manner, to all participants in the dialogue.

The Principal may not reveal to the other participants solutions or other confidential information which one participant has given to the Principal, without that participant’s consent.

When the Principal has identified the solution(s) which fulfil(s) the need, the Principal declares the termination of the dialogue. The Principal then invites the participants to submit their final tenders based on the solutions which have been presented and possibly modified in the dialogue phase. For this work, the participants will be tendering for a general contract.

When the tenders have been received, these shall be evalu-ated in relation to any minimum requirements. The manuals of the Norwegian Public Roads Administration may contain minimum requirements for structures and other considera-tions, which the contractor shall adhere to in its tender, in order for the tender to be valid.

Project-specific award criteria will be prepared, and these shall be used to determine which proposed solution will be most suitable for this project. For this competition, particular emphasis will be placed on measures associated with the environment and neighbours, in particular the buildings in the Møllenberg district.

The contract award will take place on the basis of which tender is the most economically advantageous.

Reference is made to the Regulations for detailed information. http://www.lovdata.no/for/sf/fa/xa-20060407-0402.html#14-2 )

(8)

0891-08 [email protected] - ajour pr 01.10 2008

Contact information:

Project Manager:

Harald Inge Johnsen Tel.: (+47) 91512885

E-mail: [email protected]

Postal address:

Statens vegvesen Region midt Fylkeshuset

N-6404 Molde Norway

Mark envelope: E6 Trondheim-Stjørdal

Office addresses:

Trondheim Project Office: Lademoen stasjon

Strandvegen 40, Trondheim Stjørdal Project Office: Trafikkstasjonen Tuftenvegen, Stjørdal E-mail: [email protected] Tel.: (+47) 81544040 www.vegvesen.no/e6ost

www.vegvesen.no/e6ost

References

Related documents

As a result of the petrographical and geo- chemical study of the plagioclase-rich leucocratic rocks located at the upper levels of the gabbros and isotrope gabbros of the

effect of government spending on infrastructure, human resources, and routine expenditures and trade openness on economic growth where the types of government spending are

• Spike on TWI pins when TWI is enabled • High current consumption in sleep mode • Timer 4 11-bits enhanced PWM mode.. Spike on TWI pins when TWI

Best energy yields are achieved with the PV system facing south and a tilt angle of 30% (values for Germany). Deviations from these orientation are resulting in less

In this work, we extend the stripe-decoration technique to study director distortions around disclinations in thin films of a side-chain liquid crystalline polymer using

In order to study the impact of foreign aid on exports, the report focuses on net Official Development Assistance (ODA) and within this category on two types of aid, namely bilateral

switches, secure/non-secure configurations  Multi-node faults scenarios (e.g. pipelines recovery)  Requires fault manager/dispensary.  Support for multi-node, multi-conditions