Advanced Project Financing
Structuring Risk
Second Edition
Richard Tinsley
Contents
P r e f a c e t o 2 n d E d i t i o n
P r e f a c e t o 1 s t E d i t i o n
A u t h o r b i o g r a p h y
L i s t o f c a s e s t u d i e s
L i s t o f e x h i b i t s
I n t r o d u c t i o n
Project Finance’s origins Project Finance defined Project-Finance structuringOff balance sheet (OBS)
1. Deconsolidation
2. Portfolios
3. Defeasance
4. Non-recourse
5. Completion test and option conditions
6. Limited recourse Advantages Capital shortage Risk transfer Deal sequestration Ratings management
Securitised Project Financings Better [equity] returns Consortium control Tailoring
Covenant busting Flexibility
Workouts Privacy Project validation Simple arithmetic Disadvantages Documentation Extra cost Too long Lender control Higher insurance costs Higher legal bills Greater Risk to lenders Recourse
Summary
Chapter 1: Structuring stages
Technical feasibility stageFinancial feasibility stage Market feasibility stage
Approach to banks
Approach to bond underwriters Board paper
Takeout (re)financing Piercing the sovereign ceiling Use in mergers and acquisitions
Equity/mezzanine Project concept Summary
C h a p t e r 2 : F u n d i n g S o u r c e s
Local-currency funding Banks Bilateral Agencies Multilaterals 1. PRI Developers Mezzanine Merchant financing Islamic lending Public-private partnerships (PPPs) Leasing Commodity-based lending Equity SummaryC h a p t e r 3 : C a s h f l o w s
Modelling aspects Interest bases Spreads Reserve Styles Cashflow controls Operations summary Operating cashflowsGross revenues Opex Financing reports Financing costs Capex Modelling cashflows Approaches Typical sensitivities Liquidated damages (LDs) Model periodicity Input sheet Model shortcomings Summary
C h a p t e r 4 :
F i n a n c i a l A d v i s e r s
Advantages and disadvantages Need for an adviser
Advisory costs
Who are the Financial Advisers? Summary
C h a p t e r 5 :
C r e d i t R a t i o s
Debt Service Cover Ratio (DSCR) Residual/Tail
Interest Cover Ratio (ICR) Principal Cover Ratio (PCR) Present value (PV) ratios Loan Life Ratio (LLR) Project Life Ratio (PLR) Residual Life Ratio (RLR) Debt:Equity ratio (D:E) Payback
Discount rate Leveraged IRR Choice of discount rate Multi-tranche ratios Accounting ratios Telecoms Summary
C h a p t e r 6 :
R i s k
S y s t e m s
Insurance Statistical Risk modellers Benchmark Checklist Contractual/Jigsaw Project Finance SummaryC h a p t e r 7 :
S e c t o r P r o f i l e s
Sector features Analysis by sector Power cashflows Tollways cashflows Railways cashflows Resources cashflows Telecoms cashflows Satellites cashflows Prisons/hospitals cashflows Airports/ports cashflowsWater [supply]/Waste water [sewage] cashflows Stadiums/theme parks cashflows Summary
C h a p t e r 8 :
S t r u c t u r e s
Risk 1. Contract 2. Trigger 3. Financed 4. Studied 5. Avoided Risk division Document matrix Interest Principal Drawdown styles 1. Certification 2. Benchmarks 3. Anticipated-cost-to-complete 4. Up-Front -- banks 5. Up-Front -- bonds SPV CompanyUnincorporated joint venture (UJV) Partnership Trusts Mezzanine Subordinated debt Working capital Bridge loans Multi-tranche Commodity funding
Contract structures Supplier credits Buyer credits Pre-export financing 1. Prepayment 2. Advanced payment Leasing 1. Leveraged leasing 2. Wrap lease 3. [Bermuda] Captives 4. Double-dip 5. Hire purchase 6. Lease tranches Trigger structures Deferral
1. Inverse order of maturity 2. Current order of maturity
3. Banked deferral Clawback Mandatory prepayments Equity kickers Financed structures Equity 1. Dividend reserve 2. Subordinated debt
3. Convertible debt/initial public offering (IPO) Securitisation
1. Collateralised loan obligation (CLO)
2. Revenues Joint financing Study structure Ratings 1. Methodology 2. Default 3. Deal Pricing 4. Covenants 5. Terms 6. Pricing Avoided
Off balance sheet (OBS)
1. Deconsolidation 2. Diamond 3. Defeasance 4. Derivatives 5. Puts/calls/indemnities 6. Comfort letters Summary
C h a p t e r 9 :
D u e d i l i g e n c e
Systematic reviewThe feasibility process Selection of experts/engineers Customary reviews
Traffic studies
Construction cost audit Power
Resources
Telecoms subscriber studies Common sense
C h a p t e r 1 0 :
S u p p l y R i s k
Contract structures Supply agreements Supply undertakings Tolling contracts Supply assurance Trigger structures Insurance Hedging Financed structures Collateral Study structures Supply studies 1. Traffic 2. Telecoms 3. Water4. Oil and gas
5. Mining
6. Power
7. Processing
Weighting
1. Borrowing base [Reserve-based lending]
2. Physical tail 3. Depletion protection Summary
C h a p t e r 1 1 :
M a r k e t R i s k
Market-price Contract structures Sales contracts Take-or-payCapacity [availability] contracts Throughput agreements Buy-back contracts Minimum-quantity contracts Market-preference contract Requirements contract Tolling agreements Advanced sales contracts Production payments Contract monetisation
Market-price hedging Contract base pricing
Additional sales contract options Force majeure
Priority
Capacity [availability] charges Trading-company Customer Trigger situations Hedging Contract-for-differences (CFD) Make-up/deficiency agreements Insurances Study techniques Market forecasts Summary
C h a p t e r 1 2 :
F o r e i g n E x c h a n g e ( F X ) R i s k
What percentage to structure? Contract structures Forward contracts Parallel loans Barter [countertrade] Trigger structures Currency swap
Exchange rate agreements Study
Purchasing-power parity Exchange rate forecasts Avoided Natural hedge Commodity lending CPI lending FX tariff Summary
C h a p t e r 1 3 :
O p e r a t i n g R i s k – T e c h n i c a l c o m p o n e n t
Contract structures Technology management Quality assurance Technology guarantee Trigger structuresFleet assurance [shared spares] Business interruption insurance Technology insurance Financed structure Performance bond Study structures Independent certification Alternative technology Technology curve Summary
C h a p t e r 1 4 :
O p e r a t i n g R i s k – C o s t c o m p o n e n t
Contract structures Cost guarantee Sales contracts Trigger structures Economic test Financed structures Cost subordination Study structure Cost curves Avoided Waiver SummaryC h a p t e r 1 5 :
O p e r a t i n g R i s k – M a n a g e m e n t c o m p o n e n t
Contract structures Management contract Labour contracts Training agreements Trigger structures Key-person insurances Study Personal screen SummaryC h a p t e r 1 6 :
E n v i r o n m e n t a l R i s k
Emissions Catastrophe Contextual Contamination Sustainability Contract structures Environmental management Rehabilitation management Trigger structures Rehabilitation release Emergency response Environmental warranty Environmental insurances Financed structures Rehabilitation guarantee Pollution-control bonds Rehabilitation reserve StudyEnvironmental impact Statement (EIS) Environmental plan Equator compliance Avoided Regulatory waiver Physical waiver Regulatory purchase/trade 1. sulphur 2. carbon Summary
C h a p t e r 1 7 :
I n f r a s t r u c t u r e R i s k
Contract structuresInfrastructure contract Government commitments Pooled infrastructure agreements Financial Structure
Tax-fee status Studies
Transport [freight] studies Avoided f.o.b offtake Summary
C h a p t e r 1 8 :
F o r c e M a j e u r e
R i s k
Acts of nature Acts of man(kind) Acts of government Impersonal acts Trigger structures Deferral Insurance Negotiation Studies Risk Manager Safety measures SummaryC h a p t e r 1 9 :
C o m p l e t i o n R i s k
Completion test (Type 1) Contract structures
Turnkey Construction Contract (TCC) (Type 2) Multi-party contracts
Partnering charters/alliance contracting Trigger structures Liquidated damages (LDs) Delay-in-startup (DIS/DSU) 1. Force majeure 2. Change of a law 3. Efficacy 4. General provision Financed structures Default agreement Bonding/guarantees 1. Retention 2. Performance bonds 3. Maintenance bond Completion guarantee Completion undertaking Overrun-standby facilities Debt:Equity subscription
Study approach
Independent completion engineer Completion tests
Sector completion protocols Tollroads/bridges Rail/light rail Ports/airports Prisons/hospitals
Water supply/sewage treatment Power
Telecoms Oil and gas Mining Summary
C h a p t e r 2 0 :
E n g i n e e r i n g R i s k
Design/calculations Trigger structure Insurance Study Independent certificationC h a p t e r 2 1 :
P o l i t i c a l R i s k
Definitions1. War and insurrection (W&I)
2. Currency inconvertibility and transfer (CIT) 3. Expropriation and creeping expropriation
a. Regulatory creep
b. Financial creep
c. Physical creep
4. Landowner/indigenous peoples’ disturbances
5. Terrorism and sabotage
6. Wilful breach of contract/Deprivation
7. Change of government 8. Corruption 9. Unions 10. Environmental activists 11. Approvals/bureaucratic risk 12. Conflict of authority
13. United States of America (USA)
14. Religious fundamentalism/ethnic tension 15. Interest withholding tax increases
16. Change in law
17. Partisanship
18. Xenophobia
19. Political independence of the courts 20. Regional blocs
Government supports Direct undertaking Offtake guarantee
Direct assurance to the lender Counter indemnities
Contract structures Concession agreement Cofinancing Multi-party structures Market tie Countertrade [Barter} Trigger structures
Political risk insurance (PRI) Currency inconvertibility agreements Partial Risk Guarantees (PRG) Partial Credit Guarantees (PCG) Foreign-exchange (FX) devaluation Debt:equity swaps
Tax indemnification Financed structures
War and insurrection residual Cash escrow
Prepaid PRI premiums Study sources
Prince chart Avoided
Offshore proceeds account Summary
C h a p t e r 2 2 :
P a r t i c i p a n t R i s k
Sponsor pre-completion (Type 1) SPV
1. Company
2. Unincorporated joint venture (UJV)
3. Partnerships 4. Trusts Trigger structures Deficiency agreement Share pledge Board control Call option Study route Bankruptcy remoteness Avoided Pre-assignment Summary
C h a p t e r 2 3 :
I n t e r e s t - R a t e R i s k
Contract structures Supplier credits Leasing Hedging/swaps Trigger structures Alternate funding Interest-protection agreement Interest make-up agreement Back-ended interest SummaryC h a p t e r 2 4 :
S y n d i c a t i o n R i s k
RolesChoice of banks and placements parties
Pricing Disclosure Contract structures Club underwriting Broad syndication UN syndication Study structures Information memorandum Avoided Equator syndicate Syndicate Excel model
Project Development Plan (PDP) Loan administration Summary
C h a p t e r 2 5 :
L e g a l R i s k
Legal regime Concept of law Enforcement The courts Solicitors/lawyers Contracted structures Direct agreements Legislation Trigger structures Title insurance Study structures Title searches Legal opinions Due-diligence ‘books’ AvoidedParallel security structure Offshore security structure Pre-transfer agreements Summary
A p p e n d i x 1 :
D i f f e r i n g D e f i n i t i o n s
Mergers & Acquisitions (M&A) Project Financiers
Summary
A p p e n d i x 2 : T y p i c a l o w n e r - c o n t r o l l e d i n s u r a n c e p r o g r a m m e ( O C I P )
Section 1 Owner’s project company insurance coverages – construction phase
1. Contractors-all-risk etc including delay-in-start-up (DIS/DSU)
2. Marine cargo and delay in start-up (DIS/DSU)
3. Umbrella/excess liability – construction
4. Workers’ compensation and employer’s liability
5. Business auto liability
6. Any other statutorily required coverages
Section 2 Contractor’s insurance requirements – construction phase
1. Contractor equipment
2. Marine liability 3. Aircraft liability
4. Workers’ compensation and employer’s liability
5. Business auto liability
6. Professional errors and omissions (E&O) –design liability 7. Umbrella excess liability – construction
8. Liquidated damages/efficacy (to be provided by equipment supplier)
9. Any other statutorily required coverages 10. Any other elective coverages
Section 3 Owner’s project company insurance coverages – operational phase
1. Industrial all-risk property damage
2. Operational boiler and machinery coverage
3. Industrial all-risk – loss of profits 4. Business auto liability
5. Third-party liability primary cover 6. Umbrella/excess liabilities
7. Any other statutorily required insurance coverages 8. Any other elective [insurance] covers