• No results found

February 4, Estimate

N/A
N/A
Protected

Academic year: 2021

Share "February 4, Estimate"

Copied!
5
0
0

Loading.... (view fulltext now)

Full text

(1)

(617) 799-5832 (508) 758-9777 Cost Estimator: Miyakoda Consulting 300 Black Mallard Road Bridgewater, MA 02324

Architect:

Marion, MA 02738 P.O. Box 1290 Turowski2 Architecture, Inc.

313 Wareham Road

Delaney-Vogel Elementary School Partial Roof Repair

Wrentham, MA

February 4, 2016

(2)

1 The project consists of roof replacement to Delaney-Vogel Elementary School 2 Replace existing asphalt roof shingles and EPDM

3 Estimate is based on drawings dated January 20, 2016 from Turowski2 Architecture 4 Detailed quantity takeoff from these documents where possible

5 Experience with similar projects of this nature 6 Unit rates using recent bid results

7 The project will be publicly bid to Roofing Contractors under Chapter 149

8 Our costs assume that there will be at least three subcontractors submitting unrestricted bids in only painting sub trade

9 The Total Construction Cost reflects the fair construction value of this project in a competitive bidding market 10 Unit rates are based on current dollars

11 An allowance for escalation to start of construction at a rate of 5% per year has been carried in the Main Summary. Start of construction has been carried as June 2016

13 General Conditions and Requirements value covers Sub-Contractor's bond, site office overheads, and building permit applications

14 Overhead and profit markup is calculated on a percentage basis of direct construction costs. The value covers Contractor's bond, insurance and profit

15 Design and Pricing Contingency markup does not include allowance for unforeseen design issues, design detail development and specification clarifications. THIS IS NOT A CONSTRUCTION CONTINGENCY (FOR CHANGE ORDERS)

16 Design fees and other soft costs 17 Interest expense

18 Owner's project administration 19 Construction of temporary facilities 20 Relocation expenses

21 Printing and advertising

22 Site or existing condition surveys and investigations 23 Utility company back charges

24 Police details and street/sidewalk permits 25 Work beyond the boundary of the site 26 Testing & commissioning

(3)

ELEMENT QUANTITY UNIT UNIT RATE TOTAL

7

8 02 06 00 Selective Site Demolition and Removals 9 Remove existing roof system:

10 Low slope roof type #1 including insulation 21,606 SF $2.00 $43,212

11 Low slope roof type #2 including insulation 3,130 SF $2.00 $6,260

12 Medium slope roof type #3 insulation to remain 6,023 SF $1.75 $10,540

13 Medium slope roof type #4 no insulation 21,619 SF $1.75 $37,833

14 Remove existing wood framed window & louver (21' L x 5'0" H) 1 LOC $1,190.00 $1,190

15 Note 3: Remove existing HVAC equipment 28 EA $35.00 $980

16 Note 3: Remove existing HVAC equipment (larger) 6 EA $500.00 $3,000

17 Note 4: Remove roof drains 7 EA $35.00 $245

18 Allow for cutting and patching 1 LS $5,000.00 $5,000

19 02 06 00 Selective Site Demolition and Removals Subtotal $108,261

20

21 04 10 00 Masonry (Filed Sub Bids Not Required)

22 Allow for chimney repairs 1 LS $15,000.00 $15,000

23 Flashing 260 LF $200.00 $52,000

24 Repointing at existing chimney 1,500 SF $15.00 $22,500

25 Allow for scaffolding 1 LS $7,500.00 $7,500

26 04 10 00 Masonry (Filed Sub Bids Not Required) Subtotal $97,000

27

28 06 10 00 Carpentry

29 Perimeter blocking 3,287 LF $5.00 $16,435

30 Blocking at new window wall 62 LF $6.50 $403

31 Allow for rough carpentry 41 LOC $100.00 $4,100

32 06 10 00 Carpentry Subtotal $20,938

33

34 07 20 00 Insulation

35 Insulation included with roofing $0

36 07 20 00 Insulation Subtotal $0

37

38 07 50 00 Roofing (Filed Sub Bids Required)

39 Ridge at roof type #3 54 LF $9.00 $486

40 Ridge at roof type #4 113 LF $9.00 $1,017

41 Replace asphalt shingles 27,642 SF $8.00 $221,136

42 Type 1: New PVC roofing and tapered insulation 21,606 SF $17.00 $367,302

43 Type 2: New PVC roofing 3,130 SF $15.00 $46,950

44 Ice and water shield 4,086 SF $0.50 $2,043

45 Replace pipe boots 27 EA $35.00 $945

46 Flashing 2,858 LF $15.00 $42,870

47 New roof drains 4 LOC $350.00 $1,400

48 Connection to new roof drains 4 LOC $75.00 $300

49 Allow for step flashing as required; premium 1 LS $5,000.00 $5,000

50 07 50 00 Roofing (Filed Sub Bids Required) Subtotal $689,449

DETAILED ESTIMATE

Wrentham Delaney Vogel Elem School Roof Repair 4 February 2016.xlsx Printed 2/4/2016

(4)

51

52 07 72 00 Roof Accessoriea

53 Roof hatch 1 EA $3,500.00 $3,500

54 Ladder 1 EA $1,500.00 $1,500

55 07 72 00 Roof Accessoriea Subtotal $5,000

56

57 07 92 00 Joint Sealants (Filed Sub Bids Not Required)

58 Allow for joint sealant 1 LS $7,500.00 $7,500

59 07 92 00 Joint Sealants (Filed Sub Bids Not Required) Subtotal $7,500

60

61 08 50 00 Window

62 Window frame replacement 1 EA $3,150.00 $3,150

63 08 50 00 Window Subtotal $3,150 64 65 08 80 00 Glazing 66 Window replacement 105 SF $60.00 $6,300 67 08 80 00 Glazing Subtotal $6,300 68 69 08 90 00 Louvers 70 Louver 1 EA $1,050.00 $1,050 71 08 90 00 Louvers Subtotal $1,050 72

73 22 00 00 Plumbing (Filed Sub Bids Not Required)

74 P1: Remove the exist roof drain strainer, flashing collar & bolts 7 EA $75.00 $525 75 P2: Extend 2" cast iron VTR to min. 24" above proposed roof elev. 1 EA $130.00 $130 76 P3: Extend 3" cast iron VTR to min. 24" above proposed roof elev. 3 EA $132.00 $396 77 P4: Extend 4" cast iron VTR to min. 24" above proposed roof elev. 19 EA $134.00 $2,546

78 P5: Remove & dispose of exist. scupper type roof drain 1 EA $35.00 $35

79 P6: Extend 6" PVC VTR to min. 24" above proposed roof elev. 3 EA $136.00 $408

80 New roof drains at existing locations 7 EA $250.00 $1,750

81 New roof drain 1 EA $500.00 $500

82 Cast iron piping 10 LF $65.00 $650

83 Insulation to horizontoal piping above floor 1 LS $750.00 $750

84 New scupper drain 1 EA $600.00 $600

85 Miscellaneous plumbing allowance 1 LS $1,800.00 $1,800

86 Permits Included

87 22 00 00 Plumbing (Filed Sub Bids Not Required) Subtotal $10,090

88

89 23 00 00 HVAC Subtotal (Filed Sub Bids Not Required)

90 K-1 Remove centrifical roof mtd exhaust fan 19 EA $500.00 $9,500

91 K-2 Remove air cooled condensing unit 4 EA $1,000.00 $4,000

92 New attic ventilation, louver and new exhaust fan 1 LS $5,000.00 $5,000

93 Reinstall roof mtd exhaust fans 19 EA $1,000.00 $19,000

94 Reinstall air cooled condensing unit 4 EA $1,800.00 $7,200

95 Miscellaneous HVAC allowance 1 LS $10,000.00 $10,000

(5)

DETAILED ESTIMATE

97

98 26 00 00 Electrical (Filed Sub Bids Not Required)

99 Reconnect exhaust fans 19 EA $350.00 $6,650

100 Reconnect air cooled condensing units 4 EA $1,000.00 $4,000

Miscellaneous electrical items 1 LS $3,500.00 $3,500

102 26 00 00 Electrical (Filed Sub Bids Not Required) Subtotal $14,150

103

104 32 12 16 Asphalt Paving

105 Patch existing asphalt paving 47 SF $25.00 $1,175

106 Sawcut existing bit conc walkway 19 LF $15.00 $285

107 32 12 16 Asphalt Paving Subtotal $1,460

108

109 33 41 00 Storm Utility Drainage Piping

110 Subsurface Infiltration Chambers 1350 CF 1,350 CF $42.00 $56,700

111 6"PVC Pipe 9 LF $60.00 $540

112 4"PVC Pipe 7 LF $55.00 $385

113 Trenching and backfill 16 LF $35.00 $560

114 Connect to existing downspout 1 EA $50.00 $50

115 Subsurface Infiltration Chambers 740 CF 740 CF $72.00 $53,280

116 Trenching and backfill Subtotal $111,515

117 118 Subtotal $1,130,563 119 120 Design Contingency 10.00% $1,130,563 $113,056 121 122 Subtotal $1,243,619 123

124 General Conditions and Requirements 3 MONTHS $30,000 $90,000

125 Insurance 1.10% $1,333,619 $14,670 126 GC Bonds 0.65% $1,348,289 $8,764 127 Permits 1.50% $1,357,053 $20,356 128 Fee 3.00% $1,377,409 $41,322 129 Escalation to June 2016 2.50% $1,418,731 $35,468 130 131 TOTAL $1,454,199 132

133 Deduct Alternate #1: No Reroof to Type #1 Roof -$389,000 134 Deduct Alternate #2: No Reroof to Type #2 Roof -$50,000 135 Deduct Alternate #3: No Window Replacement at South Wall -$11,000 136

137

Wrentham Delaney Vogel Elem School Roof Repair 4 February 2016.xlsx Printed 2/4/2016

References

Related documents

Juvenile Court has contracted with Family Resource Center of Northwest Ohio to provide services to families enrolled in the program, and in 2013, the IMPACT

The$first$schism$within$Popolo$Viola$coincided$with$the$end$of$the$excitement$ stage$ and$ the$ beginning$ of$ the$ movement’s$ formalization$ stage.$ The$ division$ followed$

When aggregating feeding route into patients re- ceiving oral (normal or soft diet) versus non-oral nutrition/ fluids (tube feeding, parenteral fluids or none), one third of

• Increase of silane content in functionalization leads to higher pullout bond strength; 16.. • Functionalization with TEOS enhance fibre–matrix interfacial properties;

The ticket office i n the Center for the Performing Arts handles tickets for all College of Fine A rts events, including music and theatre performances in the Center, plus

Top Causes for Poor Application Performance •  Application Turns •  TCP •  Layer 7 Bottlenecks •  Congestion (network) •  Processing Delay to p 5... Causes

The association between RAI treatment failure and various clinical parameters includ- ing age, sex, height, weight, body mass index (BMI), thyroid gland volume, and isthmus length

If the restoring force/ torque acting on the body in oscillatory motion is directly proportional to the displace- ment of body/particle and is always directed towards