HV Submarine Cable Systems Design, Testing and Installation

Robert Donaghy

Senior Consultant Engineer, ESB International

CIGRE Ireland Technical Seminar 6th October 2010

(2)

Presentation Overview

• Applications

• Design

• Testing

• Installation

• Examples

(3)

Submarine Cable Applications

• Interconnections

between grid systems

• Island connections

• Off-shore wind and wave

power connections

(4)

Development of Submarine Cables

• 60-70s MV 3-core XLPE & EPR

• 1980s Large s/c core fluid filled up to 400kV

• 1990s 3-core dry type XLPE designs up to 145kV

• 2000- Long length XLPE 3-core & single core up

to 400kV

(5)

Submarine Power Cable Types

Rated Voltage Uo

33 kV ac 150 kV ac 420 kV ac 320 kV dc 450 kV dc

Insulation XLPE, EPR XLPE Oil/paper or

XLPE

Extruded Mass

Impregnated

Typical application

Supply of small islands,

connection of offshore WTG

Supply to large islands, offshore platform export cables

Crossings of rivers, straits with large

transmission capacity

Long distance connections of offshore

platforms or wind parks

Interconnection of power grids over long distances

Max. length 20-30 km 70-150 km <50 km >500 km >500 km

Typical rating 30 MW 180 MW 700MW / 3

cables

1000 MW / cable pair

600 MW / cable

(6)

HV Cable Construction

Conductor

Sheath

Fibre Optic Cores Armour

Outer Serving

Insulation

(7)

Single Core Three Core

Pros

Lighter weight Smaller Diameter Longer lengths

Possibly fewer factory & field joints Higher current rating

Improved security, can add a 4th cable Voltage rating up to 400 kV and greater Reduced repair costs and spares

Cons

Higher magnetic field Greater installation costs

Individual seabed trenching increases costs Protection costs increased

Sheath current must be considered

Pros

Reduced magnetic field

Lower sheath circulating currents and voltages Lower installation costs

One trench on seabed Lower protection costs

Includes optional Fibre Optic Cable

Cons

Lower current rating Heavier

Large diameter

Security of cable system decreased

All three phases have to be repaired after a fault

(8)

Electrical Design

• Voltage level (U

0

/U)

• Rated transmitted power (kVA)

• Short circuit current (kA) & duration (s)

• Load factor

• Maximum losses allowed

(9)

Transmission Capacity Limits

0 MW 200 MW 400 MW 600 MW 800 MW 1000 MW 1200 MW

0 km 50 km 100 km 150 km 200 km 250 km 300 km 350 km 400 km Un=400 kV

Un=132 kV Un=150 kV Un=230 kV

Cable Length Power*

* With compensation, based on 3-core 1,000mm² conductor, 400kV is 1-core 1,200mm² (ref. Nexans)

(10)

Key Design Data

• Ambient temperature (seabed & land)

• Burial depth

• Particular burial/protection requirement at shore approach (deeper burial, directional drill pipe…)

• Axial spacing of cables

• Thermal resistivity of seabed & land

• Length of submarine cable

• Water depths

(11)

Connections to Floating Platforms

• Application specific

• Mechanical performance: movements and vibrations

• Hang-off arrangements on platform

• Corrosion protection and grounding conditions

(12)

Route Survey

• Hydrographic & geophysical survey

• Sea bed bathymetry

• Tide data Level, met ocean data

• Locate existing cables & obstacles

• Multi-beam echo sounder

• Side scan sonar

• Sub-bottom profiling

• Core Sampling

Profile along cable route

• Water depth profile

• Corridor width

• Risk of damage to cables

• Burial depth/protection requirement

• Shore landing point selection

• Environmental assessment

• Consents, Foreshore Licence

(13)

Sea Bed 3D Bathymetric Profile

Proposed Cable

Existing Cable

(14)

Shore Landing

• Near shore civil works

• Directional drill, pulling through pipes

• Mechanical protection of cables

• Space for Sea/land transition joint

• Parallel routing of cables

• Environmental considerations

– Sand dune movements

– Erosion concern

(15)

• Factory Joints

• Repair Joints

• Terminations

• Transition Joints

Accessories

(16)

Testing

• Prequalification / Development Tests

• Type Tests

• Routine Tests

• Sample Tests

• After-Installation Tests

(17)

CIGRE WG B1-27

• Test recommendations for long AC extruded submarine cables 150 - 500 kV (now also to cover 36 - 150kV)

• Addresses particular requirements of submarine cable systems:

– Water tightness of conductor and under metallic sheath – Armouring

– Mechanical forces during installation of cable and joints – Water tightness of rigid joints

– Delivery lengths and weights

– Routine tests of cable and joints – challenges in testing long

lengths

(18)

CIGRE WG B1-27 Recommendations

• More stringent approach Partial Discharge measurement in factory joints

• Extended frequency range for ac tests: 10 – 500 Hz

• External water pressure test of rigid sea & repair joints

• Scheme for mechanical tests for repair joints

• Tests for visual inspection of submarine cables

• Range of approval for type tests modified: factory joints, mechanical testing etc

• Prequalification and Extended Qualification

• Factory joints still to be qualified

(19)

Cable Laying Vessels

In the old

days…

(20)

Cable Laying Vessels

Now…

(21)

Cable Laying

(22)

Cable Laying Vessels

Shallow draft barges

(23)

Protection

Dropped objects

Anchoring

Fishing

(24)

1/4

Soft Hard

m

Penetration of smaller anchors &

fishing gear vs. soil hardness

1/2 1

3/4

1 T anchor

500 kg anchor 400 kg anchor 200 kg anchor

Otter trawl Beam trawl

(25)

2.5 m

Cable buried in hard to soft sediments to 0.5 – 3.0m

Embedment by water jetting

(26)

Protection

Embedment

(27)

Cork Harbour Project

One of the first 220kV XLPE submarine projects in the world

• Two circuits: Single core 1 x 1,600mm² copper, 570MVA rating

– 3.5km length: Aghada-Raffeen 220kV – 4.5km length: Glanagow-Raffeen 220kV

• Continuous manufacturing lengths up to 4.5km

• Shallow water: 10 metres (1st crossing), 30 metres (2nd crossing)

• Crossing main shipping channel of major port

• Submarine cable embedment by water jetting

(28)

4.6km

3.3km

Legend

220kV Submarine Cable 220kV Land Cable

6km

1.4km 3km

0.5km

(29)

Picture Area

Cork Harbour 220kV: Feb 2010

Cable Laying Vessel

Cable shore landing

(30)

SEAI Wave Energy Test Site

2 x 15km 20kV subsea cables

2 x 7km 20kV subsea cables

(31)

Ireland – Wales East West Interconnector

186km Marine Route 45km Land Cable in Ireland 30km in Wales

Converter Stations at Woodland & Deeside

(32)

Thank you

for your attention

References

Related documents

Nature has made the man superior to the woman in terms of rationality and spiritedness; the man not only rules over the female for her own good, but for the good of society as

1). Flat to LOS b/c the play is not a wide outside play. If play goes wider then pursuit angle is deeper. Shuffle at 45 degree angle to 2x2 and attack BC outside in... STOPPING

motivation from both parents and teachers was the cause of less participation of students in class, Lack of confidence also discouraged students to participate in class,

The blog fails, though, to state the extent to which building improvements have successfully proceeded over the past few years, the value they’ve added to our building or the speed

In this paper, we present a coordinated Multiple Un- manned Aerial Vehicles (UAVs) system in order to ef- ficiently explore an unknown environment using poten- tially

Hasil penerapan E-module berbasis Problem Based Learning dan data yang diperoleh menunjukan peningkatan kemampuan berpikir tingkat tinggi dan penurunan

This research aims at understanding how citizen science has been studied by scholars and layout research agenda for future research related to citizen science in the field

0 1 2 3 Organization &amp; Time Management Audience cannot understand presentation because the information is not sequenced logically; students have significant trouble