• No results found

ITP for Fire Fighting System

N/A
N/A
Protected

Academic year: 2021

Share "ITP for Fire Fighting System"

Copied!
7
0
0

Loading.... (view fulltext now)

Full text

(1)

INSTALLATION

(ALL METALLIC GROOVED/THREADED PIPING)

VIJAY ARABIA FIRE AND SECURITY SYSTEMS

(Contract No:

PLL/P5QA01/PROJ/WO/096)

MECHANICAL WORKS

DOCUMENT REVIEW STATUS

Status 1 : Work May Proceed

Status 2 : Revise & Resubmit. Work May Proceed Subject To Incorporation of Comments Indicated

Status 3 : Revise & Resubmit. Work May Not Proceed

Status 4: Review Not Required. Work May Proceed

Permission to proceed shall not constitute acceptance or approval of design details,

calculations, analyses, test methods, or materials developed or selected by contractor

and shall not relieve contractor from full compliance with contract technical

specification and requirements.

___________________ _________________

Overseas

Bechtel,

Inc.

Date

ITP NO: 25045-C5100-16-ITP-50, Rev 0

0 03.09.08 Issued for approval 0

Guhan S. U. Roy R. Roy N.R. Das

REVIEWED BY

REV DATE DESCRIPTION

PREPARED BY Project Engineer QA Manager Construction Manager APPROVED BY Project Manager

(2)

1. 2. Submittals Pipe Cleaning 25045-C5100-16-3GS-M-008 Rev 2 25045-C5100-16-3PS-D-02572 25045-C5100-16-3PS-A-13955 25045-C5100-16-3PS-M-13915 25045-C5100-16-3GS-M-50 25045-16-3PS-02551 & 25045-C5100-16-3PS-A-13915 Method Statement Drawing Material Physical cleanness

• Approval by OBI Code 1 or Code 2 • Approval by OBI Code 1 or Code 2

• Tested and certified

• Mill test reports certified by manufacturer for chemical and physical properties.

• Free from dirt and foreign material.

• The pipe end Cap/Seal will not be removed until the pipe is to be installed.

• At openings for branches in pipe, all material, which falls into the pipe, will be removed before Grooving/Threading in the branch fittings.

• Internal and external part of pipe and pipe fittings will be clean and free from oil, rust, scale, and other material that would be detrimental to either the weld or the base metal when heat is applied.

• After each day’s work, the open ends of all pipes being installed shall be sealed.

Each Area Each Area Material Test Reports, Material Inspection Report R W R S R S

(3)

3. 5. Identification, Labeling, Handling and stocking of pipe, fittings & valves Fabrication 25045-C5100-16-3PS-M-13915, 25045-16-3PS- 02572,25045-16-3PS-02551 25045-16-3PS-D-02572 25045-16-3PS-A-13955 25045-16-3PS-M-13915 External coating Stocking Drawing marking Pipe cutting Grooving Fit-up and joining preparation.

• As per material specification, size, schedule, etc.

• Pipe and fittings, valve etc. will be tagged or label.

• External coating free from any kind of visible damage.

• 10” dia pipe & 8” and smaller dia pipe

racked 2 sections and 4 section maximum respectively.

• All fittings and valves kept in a covered dry storage area until ready for installation.

• Grooved joints number marking in isometric drawings by piping engineer. • By circular saw and by grinding.

• By machine cutting/grinding and grooving. • As per approved AFC

• Provision for suitable support to avoid distortion. Each Area Each Area Material Inspection Report Fit-up Inspection Report W W W W S S

(4)

6. Installation 25045-16-3PS-D-02572 25045-16-3PS-A-13955 25045-16-3PS-M-13915 NFPA 13,NFPA 14,NFPA 15 and NFPA 16 Clearance for Installation Supporting Valves and Instruments Flow line elevation & Slope

• Visual inspection and clearance. • Covering of spool ends

• Completion of hydraulic testing on pre fabricated spools, if applicable.

• Completion of painting activities where necessary.

• Completion of grooving if necessary.

• Type as per AFC drawing.

• Permanent pipe supports installed. • Temporary supports engaged if providing

of permanent supports not possible. • All temporary supports replaced by

permanent support before mechanical clearance.

• As per AFC drawing and P & ID. • As per AFC drawing or direction by

Engineer. Each Area Each area Hydrostatic W W W W S S S S S

(5)

7. Pressure testing

NFPA 13,14,15,16 and NFPA 25.

Test Pressure Test pressure as specified in specification,

AFC Drawing.

No Leak or Pressure Drop.

Hydrostatic pressure test procedure will be submitted later.

Each Area test report.

(6)
(7)

References

Related documents