VER. 07 - 09/03/13 - (Final)
Div. Samet Job Cost Description
Job Cost Accounting Code
01 General Requirements 01-000
Senior Project Executive / VP 01-100 L, LB
Group Manager 01-110 L, LB Project Executive 01-120 L, LB Project Director 01-130 L, LB Sr. Project Manager 01-140 L, LB Project Manager 1 01-150 L, LB Project Manager 2 01-160 L, LB Project Engineer 01-170 L, LB Sr. Superintendent 01-180 L, LB Superintendent 01-190 L, LB Asst. Superintendent 01-200 L, LB
Carpenter Leadman / Foreman 01-210 L, LB
Carpenter 01-220 L, LB Asst. Carpenter 01-230 L, LB General Laborer 01-240 L, LB Safety Director 01-250 L, LB Safety Manager 01-260 L, LB Project Administrator 01-270 L, LB Project Coordinator 01-275 L, LB
CAD / BIM Manager 01-280 L, LB
Senior Accountant 01-285 L, LB
Accountant 01-290 L, LB
AP Clerical 01-300 L, LB
Personal Vehicle / Equip't Expense [E] 01-400 RI Personal Vehicle / Equip't Expense [A] 01-405 RI
Mileage Expense 01-410 D
Subsistence 01-420 L, D
Photographs 01-500 D
Reprographics / Printing Expense 01-505 D
Advertising Expense 01-510 D
Postage Expense 01-515 D
CPM Scheduling 01-520 S,D
Demolition Permit / Fees 01-530 D
Driveway Permit / Fees 01-531 D
Road Closure Permit / Fees 01-532 D
Erosion Control Bond 01-535 D
Impact / Capacity Use Fees 01-540 D
Materials Testing / Inspections 01-550 S
Air Quality Testing 01-555 S
Temporary Electricity 01-560 D
Temporary Fuel Oil 01-565 D
Temporary HVAC 01-570 D
Temporary Lighting / Power Services 01-575 D
Temporary Natural-Gas 01-580 D
Temporary Telecommunications 01-585 D
Temporary Water 01-590 D
Field Offices and Sheds 01-600 D,RE
Field Office Equipment / Supplies 01-605 D
Computer / PDA / Cell Phone 01-610 D
Computer / Software Expense 01-615 D
PDA / Cell Phone 01-620 D
Copier Rental w/Maintenance 01-622 RE
Software Licenses 01-625 D
Job Tool Trailer 01-630 RE
Small Tools / Maintenance 01-635 D
Owner Trailer 01-640 RE
Temporary Toilets / Holding Tank 01-642 RE
Temporary ice / water / cups 01-644 D
Rentals - Company Owned 01-645 RI
Rentals - Third Party 01-650 RE
Fuel For Equipment 01-655 D
Hoists and Cranes 01-660 RE,S
Scaffolding Rental 01-665 RE,S
Trash Chutes 01-670 RE.S
Temporary Stairs / Ladders 01-675 RE.S
Air Scrubbers 01-680 RE,D,RI
Pumping and Drainage 01-685 RE,D
Equipment & Tool Repair 01-690 D
Tire Repair 01-695 D
Temporary Fencing 01-710 S
Temporary Partitions 01-715 D,L
Protection of Work and Property 01-720 D,L
Safety Equipment 01-725 D
Temporary Fire Protection 01-730 D
Temporary Shoring / Bracing 01-735 D,S
Site Security 01-740 D,S
Project Signage 01-750 D
Mobilization 01-760 D
Temporary Stone 01-765 D
General Clean Up 01-775 D,L
Construction Waste Management 01-780 D,L
Final Cleaning 01-785 D,S
Gowning Requirements 01-790 D
General Trades 01-795 S
Punch List 01-800 L,LB,D,S
Other Misc. General Requirements 01-805 D
Legal Expense - Reimbursable 01-815 D
Misc. Consumables 01-820 D
Meals / Entertainment 01-825 D
Background Checks 01-830 D
02 Existing Conditions 02-000
Demolition 02-180 L,LB,S
Hazardous Material Abatement 02-200 S
Mold Inspection 02-220 S
Mold Remediation 02-240 S
Permanent Utility Relocation 02-260 S
Sheeting / Shoring 02-270 S
03 Concrete 03-000
Concrete 03-020 S
Concrete Formwork 03-100 L,LB,M,S
Concrete Formwork - Foundation 03-105 L,LB,M,S Concrete Formwork - C.I.P. Walls 03-110 L,LB,M,S
Concrete Formwork - S.O.G. 03-120 L,LB,M,S
Concrete Formwork - S.O.D. 03-130 L,LB,M,S
Concrete Reinforcing 03-200 L,LB,M,S Concrete Reinforcing - Foundation 03-205 L,LB,M,S Concrete Reinforcing - C.I.P. Walls 03-210 L,LB,M,S Concrete Reinforcing - S.O.G. 03-220 L,LB,M,S Concrete Reinforcing - S.O.D. 03-230 L,LB,M,S Concrete Reinforcing - Stairs 03-240 L,LB,M,S
Concrete Accessories 03-300 L,LB,M,S
Concrete Accessories - Foundation 03-305 L,LB,M,S Concrete Accessories - C.I.P. Walls 03-310 L,LB,M,S Concrete Accessories - S.O.G. 03-320 L,LB,M,S Concrete Accessories - S.O.D. 03-330 L,LB,M,S Concrete Accessories - Stairs 03-340 L,LB,M,S
Concrete Materials 03-400 L,LB,M,S
Concrete Materials - Foundation 03-405 L,LB,M,S Concrete Materials - C.I.P. Walls 03-410 L,LB,M,S
Concrete Materials - S.O.G. 03-420 L,LB,M,S
Concrete Materials - S.O.D. 03-430 L,LB,M,S
Concrete Materials - Stairs 03-440 L,LB,M,S
Perimeter Wall Foundation Insulation 03-505 L,LB,M,S
Perimeter S.O.G. Insulation 03-525 L,LB,M,S
Stone Base - S.O.G. 03-600 L,LB,M,S
Post Tensioned Structural Concrete 03-705 S
Structural Precast Concrete 03-720 S
Hollow Core Precast Concrete 03-735 S
Tilt-Up Concrete 03-750 S
Architectural Precast Concrete 03-765 M,S
Gypcrete 03-805 S
Stamped / Stained Concrete 03-820 S
Polished Concrete 03-835 S
Concrete Superintendent 03-900 L,LB
Concrete Asst. Superintendent 03-910 L,LB
Concrete Carpenter Leadman / Foreman 03-920 L,LB Personal Vehicle / Equip't Expense 03-930 RI
Subsistence 03-940 L,LB,D 04 Masonry 04-000 Masonry 04-100 S Block 04-125 M,S Brick 04-150 M,S Masonry Reinforcing 04-205 M,S Masonry Accessories 04-220 M,S
Masonry Wall Bracing 04-240 M,S
Masonry Forms 04-270 M,S
Concrete Grout Fill 04-305 M,S
Clean Block 04-405 M,S
Clean Face Brick 04-425 M,S
Foam Insulation 04-505 M,S
Rigid Insulation 04-515 M,S
Masonry Mortar 04-605 M,S
Masonry Sand 04-625 M,S
Stone Masonry 04-705 M,S
Architectural Precast Concrete 04-730 M,S
Architectural Cast Stone 04-760 M,S
Masonry Superintendent 04-900 L,LB
Masonry Asst. Superintendent 04-910 L,LB
Masonry Carpenter Leadman / Foreman 04-920 L,LB Personal Vehicle / Equip't Expense 04-930 RI
Subsistence 04-940 D,L
05 Metals 05-000
Structural Steel 05-100 S
Structural Steel - Mat'l P.O. 05-120 M
Structural Steel Erection 05-150 S
Steel Bar Joist 05-200 M,S
Steel Deck 05-300 M,S
Light Gauge Structural Stud Framing 05-400 S
Light Gauge Truss Framing 05-450 S
Miscellaneous Metals 05-500 L,LB,M,S
Metal Stairs 05-520 L,LB,M,S
Metal Railings 05-530 L,LB,M,S
Metal Column Covers 05-800 L,LB,M,S
Expansion Joint Assemblies 05-850 L,LB,M,S
06 Wood, Plastics, & Composites 06-000
Wood Framing 06-100 M,S
Wood Framing Mat'l - Dimensional 06-110 M,S Wood Framing Mat'l - Wood Sheathing 06-120 M,S Wood Framing Mat'l - Wood Trusses 06-130 M,S Wood Framing Mat'l - Wall Blocking 06-140 M,S Wood Framing Mat'l - Misc. Blocking 06-150 M,S Wood Framing Mat'l - Roof Nailers 06-160 M,S
Finish Carpentry 06-200 M,S
Finish Carpentry - Window Stools 06-220 M,S
Finish Carpentry - Shelving 06-230 M,S
Finish Carpentry - Wood Paneling 06-240 M,S
Finish Carpentry - FRP Paneling 06-250 M,S
Finish Carpentry - Wood Windows 06-260 M,S
Finish Carpentry - Prehung Doors 06-270 M,S
Architectural Woodwork 06-400 M,S
Base / Wall Cabinets 06-410 M,S
Countertops 06-420 M,S
Custom Wood Doors 06-430 M,S
Custom Wood Trim 06-440 M,S
Wood Framing Superintendent 06-900 L,LB
Wood Framing Asst. Superintendent 06-910 L,LB Wood Framing Carpenter Leadman / Foreman 06-920 L,LB Personal Vehicle / Equip't Expense 06-930 RI
Subsistence 06-940 D,L,LB
07 Thermal & Moisture Protection 07-000
Dampproofing and Waterproofing 07-100 S
Insulation 07-210 M,S
E.I.F.S. 07-240 S
Vapor / Air Barriers 07-250 M,S
Shingle Roofing 07-310 M,S
Metal Roofing & Wall Panels 07-400 M,S
Siding 07-460 M,S
Membrane Roofing 07-500 S
TPO Membrane Roofing 07-505 S
EPDM Membrane Roofing 07-510 S
Modified Bitumen Membrane Roofing 07-515 S
Flashing and Sheet Metal 07-600 M,S
Roof Hatch 07-650 M,S
Roof and Wall Accessories 07-700 M,S
Applied Fireproofing 07-800 M,S
Firestopping 07-840 M,S
Joint Sealants & Caulking 07-900 M,S
08 Openings 08-000
Metal Doors and Frames 08-100 L,LB,M,S
Wood Doors 08-140 L,LB,M,S
Access Doors and Frames 08-310 L,LB,M,S
Coiling Doors and Grilles 08-330 S
Overhead Doors 08-340 S
Rapid Rise Doors 08-350 S
Fire Shutters 08-360 S
Special Doors 08-370 S
Curtain Wall Glazed Assemblies 08-440 S
Windows 08-500 M,S
Skylights 08-600 M,S
Finish Hardware 08-700 L,LB,M,S
Glass and Glazing 08-800 M,S
Mirrors 08-850 M,S
Louvers and Vents 08-900 L,LB,M,S
09 Finishes 09-000
Drywall, Metal Studs & Insulation 09-100 S Drywall, Metal Studs, Insulation & Acoustical Ceilings 09-200 S
Hard Tile 09-300 S
Acoustical Ceilings 09-500 S
Flooring 09-600 S
Walk Off Mat 09-610 M,S
Flooring Protection 09-620 L, LB, M, S Wood Flooring 09-640 S Resilient Flooring 09-650 S Terrazzo Flooring 09-660 S Fluid-Applied Flooring 09-670 S Carpeting 09-680 S Cork Flooring 09-690 S Rubber Flooring 09-700 S Access Flooring 09-710 S Wall Coverings 09-720 S Acoustic Treatment 09-800 S
Painting and Coating 09-900 S
Special Coatings 09-920 S
Finish Superintendent 09-975 L,LB
Finish Asst. Superintendent 09-980 L,LB
Finish Carpenter Leadman / Foreman 09-985 L,LB Personal Vehicle / Equip't Expense 09-990 L,LB,RI
Subsistence 09-995 D,L,LB
10 Specialties 10-000
Visual Display Units 10-110 M,S
Display Cases 10-120 M,S
Building Directories 10-130 M,S
Signage 10-140 L,LB,M,S
Toilet Compartments and Cubicles 10-210 L,LB,M,S
Demountable Partitions 10-220 S
Operable Partitions 10-230 S
Wall and Door Protections 10-260 L,LB,M,S
Toilet, Bath, Laundry Accessories 10-280 L,LB,M,S
Manufactured Fireplaces 10-310 L,LB,M,S
Lockers 10-510 L,LB,M,S
Postal Specialties 10-550 L,LB,M,S
Storage Assemblies 10-560 L,LB,M,S
Awnings and Canopies 10-730 S
Flagpoles 10-750 L,LB,M,S
Other Specialties 10-900 L,LB,M,S
11 Equipment 11-000
Parking Control Equipment 11-120 M,S
Loading Dock Equipment 11-130 M,S
Dock Doors / Equipment 11-135 M,S
Residential Equipment 11-300 M,S
Food Service Equipment 11-400 M,S
Audio-Visual Equipment 11-520 M,S
Laboratory Equipment 11-530 M,S
Theater and Stage Equipment 11-610 M,S
Athletic Equipment 11-660 M,S
Healthcare Equipment 11-700 M,S
Solid Waste Handling Equipment 11-820 M,S
Other Equipment 11-900 M,S
12 Furnishings 12-000
Window Treatments 12-200 S
Manufactured Casework 12-300 S
Countertops 12-360 S
Entrance Floor Mats and Frames 12-480 L,LB,M,S
Fixed Audience Seating 12-610 S
Stadium and Arena Seating 12-630 S
Telescoping Bleachers 12-660 S
Other Furnishings 12-900 L,LB,M,S
13 Special Construction 13-000
Swimming Pools 13-110 S
Fountains 13-120 S
Special Purpose Rooms 13-200 S
Vaults 13-270 L,LB,M,S
Pre-Engineered Buildings 13-340 M,S
Pre-Engineered Building Erection 13-345 S Pre-Engineered Building Insulation 13-350 M,S
Radiation Protection 13-490 S
14 Conveying Equipment 14-000
Elevators 14-200 S
Escalators and Moving Walks 14-300 S
Hoists/Cranes 14-600 S
Facility Chutes 14-910 S
Pneumatic Tube Systems 14-920 S
21 Fire Suppression 21-000
Fire Suppression / Sprinkler 21-100 S
Knox Box 21-150 M
22 Plumbing 22-000
Plumbing 22-100 S
Sub Metering 22-150 S
Process Piping 22-670 S
23 Heating, Ventilating, and A/C 23-000
HVAC 23-100 S
Fuel Systems 23-110 S
Refrigeration Equipt & Piping 23-230 S
25 Integrated Automation 25-000
Integrated Automation 25-100 S
26 Electrical 26-000
Electrical 26-100 S
Packaged Generator Assemblies 26-320 S
Site Lighting 26-560 S
27 Communications 27-000
Structured Cabling 27-100 S
Data / Telecommunications 27-200 S
Audio / Visual 27-300 S
28 Electronic Safety and Security 28-000
Security / Surveillance 28-100 S
31 Earthwork 31-000
Site Preparation / Stormwater Drainage 31-100 S
Trench and Subdrainage Systems 31-105 S
Construction Staking-3rd Party 31-110 S
Site Clearing and Grubbing 31-115 S
Construction Entrance 31-120 S
Temporary Access Stone 31-125 M,S
Rock Excavation 31-230 S
Erosion and Sediment Control 31-250 S
Termite Control 31-310 S
Site Development 31-315 S
Soil Stabilization 31-320 S
Special Foundations 31-600 S
Sitework Superintendent 31-900 L,LB
Sitework Asst. Superintendent 31-910 L,LB
Sitework Carpenter Leadman / Foreman 31-920 L,LB Personal Vehicle / Equip't Expense 31-930 RI
Subsistence 31-940 D,L,LB
32 Exterior Improvements 32-000
Asphalt Paving 32-100 S
Concrete Paving 32-130 S
Unit Paving 32-140 S
Concrete Curb & Gutter 32-160 S
Sidewalks 32-165 L,LB,M,S
Fences and Gates 32-310 S
Retaining Walls 32-320 S
Irrigation Systems 32-800 S
Landscape & Seeding 32-900 S
33 Utilities 33-000
Site Utilities 33-100 S
Water Utilities - Domestic 33-120 S
Water Utilities - Fireline 33-140 S
Water Utilities - Wells 33-160 S
Sanitary Utilities 33-300 S
Sanitary Utilities - Septic System 33-320 S
Dewatering 33-480 L,LB,M,S,RE
35 Bonds, Insurances & Closeout Services 35-000
Performance & Payment Bond 35-010 D
Builders Risk Insurance 35-020 D
Liability Insurance 35-030 D
Project Closeout Services 35-040 W
Subcontractor Bonding Program 35-050 D
Subcontractor Bonds 35-060 D
41 Material Processing and Handling 41-000
Cranes and Hoists 41-220 D
Manufacturing Equipment 41-300 D
48 Electrical Power Generation 48-000
Solar Energy Power Generation 48-140 S
49 Preconstruction Services 49-000
Director of Pre-Const. Services 49-010 L,LB Pre-Construction Project Executive 49-020 L,LB Pre-Construction Project Manager 49-030 L,LB Pre-Construction Project Engineer 49-040 L,LB
Pre-Construction CAD Operator 49-050 L,LB
Project Development Manager 49-060 L,LB
Marketing Development Manager 49-065 L,LB
Pre-Construction Administrator 49-070 L,LB
Marketing Coordinator 49-075 L,LB
Senior Project Executive / VP 49-080 L,LB
Group Manager 49-090 L,LB Project Executive 49-100 L,LB Project Director 49-110 L,LB Sr. Project Manager 49-120 L,LB Project Manager 1 49-130 L,LB Project Manager 2 49-140 L,LB Project Engineer 49-150 L,LB Sr. Superintendent 49-160 L,LB Superintendent 49-170 L,LB Project Coordinator 49-180 L,LB Safety Director 49-190 L,LB
Personal Vehicle / Equip't Expense [E] 49-200 RI Personal Vehicle / Equip't Expense [A] 49-205 RI
Mileage Expense 49-210 D
Subsistence 49-220 L,D
Photographs 49-300 D
Office Supplies 49-305 D
Reprographics / Printing Expense 49-310 D
Advertising Expense 49-320 D
Postage Expense 49-330 D
Other Misc. General Requirements 49-340 D
Telephone Expense 49-350 D
Computer/PDA/Cell Phone 49-360 D,L
Computer / Software Expense 49-370 D
PDA/Cell Phone 49-375 D
Legal Expense Reimbursable 49-400 D
Topo / Boundary Survey 49-420 S
Pond Survey 49-430 S
Phase I Environmental 49-440 S
Phase II Environmental 49-450 S
Stream / Wetland Delineation 49-460 S
Subsurface Exploration 49-470 S
Hazardous Material Survey 49-480 S
Meals & Entertainment 49-490 D
Preliminary Expense 49-800 D, S
Civil / Site / Infrastructure Design 49-810 S
Landscape Design 49-820 S
Architectural Design 49-830 S
Structural Engineering Design 49-840 S
Fire Protection Design 49-850 S
Plumbing Design 49-860 S Mechanical Design 49-870 S Electrical Design 49-890 S Envelope Consultant 49-900 S 50 Allowances 50-000 Owner Allowances 50-005 D Site Allowances 50-025 D Building Allowances 50-050 D 51 Contingency 51-000 CM Contingency 51-005 D CM Design Contingency 51-015 D Contractor Contingency 51-025 D Buyout Contingency 51-050 D 52 Owner's Contingency 52-000 Owner Contingency 52-005 D
60 Co. 1 General Requirements 60-000
Senior Project Executive / VP 60-100 L,LB
Group Manager 60-110 L,LB Project Executive 60-120 L,LB Project Director 60-130 L,LB Sr. Project Manager 60-140 L,LB Project Manager 1 60-150 L,LB Project Manager 2 60-160 L,LB
Project Engineer 60-170 L,LB
Sr. Superintendent 60-180 L,LB
Superintendent 60-190 L,LB
Asst. Superintendent 60-200 L,LB
Carpenter Leadman / Foreman 60-210 L,LB
Carpenter 60-220 L,LB Asst. Carpenter 60-230 L,LB General Laborer 60-240 L,LB Safety Director 60-250 L,LB Safety Manager 60-260 L,LB Project Administrator 60-270 L,LB Project Coordinator 60-275 L,LB
CAD / BIM Manager 60-280 L,LB
Senior Accountant 60-285 L,LB
Accountant 60-290 L,LB
AP Clerical 60-300 L,LB
Pre Con Development Manager 60-310 L,LB
Pre Con Project Executive 60-320 L,LB
Pre Con Project Manager 60-330 L,LB
Personal Vehicle / Equip't Expense 60-400 RI
Mileage Expense 60-410 D.L
Subsistence 60-420 D.L
Computer/PDA/Cell Phone 60-610 D.L
Computer/Software Expense 60-615 D, L
PDA/Cell Phone 60-620 D.L
65 Co. 2 General Requirements 65-000
Senior Project Executive / VP 65-100 L.LB
Group Manager 65-110 L.LB Project Executive 65-120 L.LB Project Director 65-130 L.LB Sr. Project Manager 65-140 L.LB Project Manager 1 65-150 L.LB Project Manager 2 65-160 L.LB Project Engineer 65-170 L.LB Sr. Superintendent 65-180 L.LB Superintendent 65-190 L.LB Asst. Superintendent 65-200 L.LB
Carpenter Leadman / Foreman 65-210 L.LB
Carpenter 65-220 L.LB
Asst. Carpenter 65-230 L.LB
General Laborer 65-240 L.LB
Safety Manager 65-260 L.LB
Project Administrator 65-270 L.LB
Project Coordinator 65-275 L.LB
CAD / BIM Manager 65-280 L.LB
Senior Accountant 65-285 L.LB
Accountant 65-290 L.LB
AP Clerical 65-300 L.LB
Pre Con Development Manager 65-310 L.LB
Pre Con Project Executive 65-320 L,LB
Pre Con Project Manager 65-330 L,LB
Personal Vehicle / Equip't Expense 65-400 RI
Mileage Expense 65-410 D,L
Subsistence 65-420 D,L
Computer/PDA/Cell Phone 65-610 D,L
Computer/Software Expense 65-615 D,L
PDA/Cell Phone 65-620 D,L
70 Co. 3 General Requirements 70-000
Senior Project Executive / VP 70-100 L,LB
Group Manager 70-110 L,LB Project Executive 70-120 L,LB Project Director 70-130 L,LB Sr. Project Manager 70-140 L,LB Project Manager 1 70-150 L,LB Project Manager 2 70-160 L,LB Project Engineer 70-170 L,LB Sr. Superintendent 70-180 L,LB Superintendent 70-190 L,LB Asst. Superintendent 70-200 L,LB
Carpenter Leadman / Foreman 70-210 L,LB
Carpenter 70-220 L,LB Asst. Carpenter 70-230 L,LB General Laborer 70-240 L,LB Safety Director 70-250 L,LB Safety Manager 70-260 L,LB Project Administrator 70-270 L,LB Project Coordinator 70-275 L,LB
CAD / BIM Manager 70-280 L,LB
Senior Accountant 70-285 L,LB
Accountant 70-290 L,LB
AP Clerical 70-300 L,LB
Pre Con Development Manager 70-310 L,LB
Pre Con Project Executive 70-320 L,LB
Personal Vehicle / Equip't Expense 70-400 RI Mileage Expense 70-410 D Subsistence 70-420 D,L Computer/PDA/Cell Phone 70-610 D,L Computer/Software Expense 70-615 D,L PDA/Cell Phone 70-620 D,L 75 JV General Requirements 75-000 Photographs 75-500 D
Reprographics / Printing Expense 75-505 D
Advertising Expense 75-510 D
Postage Expense 75-515 D
CPM Scheduling 75-520 D,S
Building Permit / Fees 75-525 D
Demolition Permit / Fees 75-530 D
Driveway Permit / Fees 75-531 D
Road Closure Permit / Fees 75-532 D
Erosion Control Bond 75-535 D
Impact / Capacity Use Fees 75-540 D
Materials Testing / Inspections 75-550 S
Air Quality Testing 75-555 S
Temporary Electricity 75-560 D
Temporary Fuel Oil 75-565 D
Temporary HVAC 75-570 D
Temporary Lighting / Power Services 75-575 D
Temporary Natural-Gas 75-580 D
Temporary Telecommunications 75-585 D
Temporary Water 75-590 D
Field Offices and Sheds 75-600 S,RE
Field Office Equipment / Supplies 75-605 D
Computer / Software Expense 75-615 D
Copier Rental w/Maintenance 75-620 RE
Software Licenses 75-625 D
Job Tool Trailer 75-630 RE
Small Tools / Maintenance 75-635 D
Owner Trailer 75-640 RE
Temporary Toilets / Holding Tank 75-642 RE
Temporary ice / water / cups 75-644 D
Rentals - Company Owned 75-645 RI
Rentals - Third Party 75-650 RE
Fuel For Equipment 75-655 D
Hoists and Cranes 75-660 S,RE
Trash Chutes 75-670 S,RE
Temporary Stairs / Ladders 75-675 S,RE
Air Scrubbers 75-680 D,RE,RI
Pumping and Drainage 75-685 D,RE
Equipment & Tool Repair 75-690 D
Tire Repair 75-695 D
Temporary Barricades 75-705 L,LB,D
Temporary Fencing 75-710 S
Temporary Partitions 75-715 D,L,LB
Protection of Work and Property 75-720 D,L,LB
Safety Equipment 75-725 D
Temporary Fire Protection 75-730 D
Temporary Shoring / Bracing 75-735 D,S
Site Security 75-740 D,S
Project Signage 75-750 D
Mobilization 75-760 D
Temporary Stone 75-765 D
General Clean Up 75-775 D,L,LB
Construction Waste Management 75-780 D
Final Cleaning 75-785 D,S
Gowning Requirements 75-790 D
Punch List 75-800 L,LB,D,S
Other Misc. General Requirements 75-805 D
Legal Expense - Reimbursable 75-815 D
Misc. Consumables 75-820 D
Meals / Entertainment 75-825 D
Background Checks 75-830 D
Surveying/Set Corners/Benchmark 75-835 S
80 JV Bonds, Insurances & Closeout Services 80-000
Performance & Payment Bond 80-010 D
Builders Risk Insurance 80-020 D
Liability Insurance 80-030 D
Project Closeout Services 80-040 W
Subcontractor Bonding Program 80-050 D
Subcontractor Bonds 80-060 D
85 Non-Reimbursables 85-000
Non-Reimbursables 85-005 D