INDEX
INDEX ...2
ATTACHMENTS: ...3
ATTACHMENT 1: ENGINEERING ORGANISATION MATRIX...3
ATTACHMENT 2: PROCEDURES INDEX AMENDMENTS AND REVISIONS ...3
AMENDMENTS AND REVISIONS ...4
1. PURPOSE ...5
2. SCOPE ...5
3. APPROACH TO PROJECT EXECUTION...5
3.1 PROJECT OBJECTIVES ...5
3.2 PROJECT STRATEGY ...6
3.3 PROJECT ORGANIZATION AND RESPONSIBLITIES...6
3.4 CONTRACTOR AND COMPANY COOPERATION...7
3.4.1 COOPERATION ...8
3.4.2 FACILITIES AND SERVICES ...8
3.4.3 BLOCK VISA ...8
3.5 HEALTH, SAFETY AND ENVIRONMENTAL (HSE)...8
3.6 QUALITY MANAGEMENT IN PROJECT EXECUTION ...13
3.7 RISK ASSESSMENT AND MANAGEMENT ...13
4. EXECUTION OF THE WORK ...14
4.1 CONTRACT DOCUMENTS REVIEW...14
4.2 DETAILED ENGINEERING AND DESIGN ...14
4.3 DISCIPLINE ACTIVITIES...15
4.3.1 FIELD AND PLATFORMS DESIGN ...15
4.3.2 ONSHORE PIPELINES DESIGN ...20
4.3.3 OFFSHORE SEALINES DESIGN...21
4.3.4 SUBMARINE COMPOSITE CABLES & SUBSEA UMBILICALS ENGINEERING ...25
4.3.5 ENGINEERING INTERFACES ...27
4.3.6 CONSTRUCTABILITY...27
4.3.7 PRELIMINARY DESIGN VERIFICATION...28
4.3.8 ENGINEERING ORGANIZATION MATRIX ...28
4.4 PROJECT CONTROLS...29
4.4.2 WORK BREAKDOWN STRUCTURE ...29
4.4.3 PLANNING AND SCHEDULING ...30
4.4.4 PROGRESS MEASUREMENT...31
4.4.5 PROJECT REPORTING...32
4.5 PROCUREMENT ...33
4.6 CONSTRUCTION MANAGEMENT ...34
4.7 OFFSHORE TRANSPORT AND INSTALLATION...37
4.7.1 INSTALLATION ENGINEERING ...37
4.7.2 INTERFACES...39
4.7.3 OFFSHORE TRANSPORTATION OF FACILITIES ...40
4.7.4 OFFSHORE INSTALLATION ...40
4.8 ONSHORE CONSTRUCTION AND INSTALLATION ...44
4.8.1 ONSHORE ONSITE TEMPORARY FACILITIES...44
4.8.2 ONSHORE PIPELINE CONSTRUCTION / INSTALLATION WORKS ...44
5. INDEX OF PROCEDURES ...47
ATTACHMENTS:
ATTACHMENT 1: ENGINEERING ORGANISATION MATRIX
AMENDMENTS AND REVISIONS
Amendment
and revision
Date
Page
Description
X1 23.04.2011 Interdisciplinary Check GS
A 26.04.2011 Issued for COMPANY comments / Approval GS
1. PURPOSE
This document, Work Execution Plan and Procedure (WEPP), provides a general statement on
the CONTRACTOR’s plan to execute the PROJECT in order to achieve the CONTRACT
Requirements, Objectives and Goals.
This document is intended to be a strategic planning set of documents that defines the
objectives, plans, requirement and information necessary for project execution as required by
OOK Contracts n. 6600026283, Schedule B, Paragraph 4.8. and by IK Contracts n.
6600026284, Schedule B, Paragraph 4.3.
Detailed processes are described in other relevant Plans and Procedures referenced in this
document and CONTRACT Schedule “B”. The various Plans will evolve throughout the
PROJECT, equally the Project Organisation will adapt to meet the specific needs prevailing at
each stage of the execution.
The SAIPEM Project Director leads the WEEP preparation with the involvement of all involved
parties.
2. SCOPE
This WEPP applies to the entire scope of work of the OOK CONTRACT 6600026283 and the IK
CONTRACT 6600026284.
3.
APPROACH TO PROJECT EXECUTION
3.1 PROJECT
OBJECTIVES
The Project Management team will provide their best efforts and expertise in order to achieve
the following Project Objectives. The individual Plans and Procedures lay down the detailed
framework for their achievement.
HSE
Achieve HSE goals in a manner that meets COMPANY and CONTRACTOR
high performance standards and an outstanding performance in personnel
safety and environmental respect
Quality
Provide works in accordance with the CONTRACT requirements and
accurately documented for future reference
Technology
Design and construct facilities using available technology, with recognition
of experience gained on previous project as appropriate.
Schedule
Deliver a Quality Product within the specified Project Schedule
3.2 PROJECT
STRATEGY
The key element of the CONTRACTOR Project Strategy is the utilisation of Saipem Group
resources to best meet the Project requirements, including
Engineering located at Saipem offices
Local fabrication and logistics support thought STAR & Snamprogetti existing yards
located near Damman
Saipem offshore installation fleet with Heavy Lift /Lay Barges Castoro 2, Castoro 8
Outsides Kingdom Saipem fabrication yard in Indonesia
3.3 PROJECT ORGANIZATION AND RESPONSIBLITIES
CONTRACTOR fulfils the scope of work through the deployment of a dedicated Project
Management Team, led by a fully dedicated Project Director, Project Managers and Project
Team.
The Project Team is made up of key personnel, all specifically dedicated to the project as task
force.,
The Project Work Scope will be subdivided in five main Work Packages, each, assigned to a
dedicated Project Manager; The Main Work Packages are:
EPCI Onshore Works
EPC Structures
EP Pipelines and Cables
Structures Construction
Sealines & Cables Construction,
The Task Force also includes for following staffs: Procurement, QA/QC, HSE, Contract
Administration, Project Control and Human resources, providing services and support to Work
Packages Project Managers and reporting directly to the Project Director.
The details of CONTRACTOR Project Organization OOK and IK and the definition of roles and
responsibilities are given in the following documents:
Project Team Organization
Project
Quality
Plan.
Project Office:
The CONTRACTOR Project Management Team will be located at the Design Office in the
Saipem Branch office in Sharjah (UAE) next to the COMPANY PMT office for effective
communication.
Project Work Sites:
The Project will be executed at the following sites:
UAE at SAIPEM Sharjah:
o Project Management,
o Field and Platform Design,
o Procurement (platforms and subcontracts)
o Offshore Transportation and Installation Engineering,
Italy at SAIPEM Fano:
o Offshore Sealines Design (including flow assurance, wall thickness sizing and
corrosion for the entire pipeline system)
o Submarine Cables and Umbilical Engineering
o Purchase and Vendors inspection of Sealines and subsea valves, Cables and
Umbilicals (battery limit defined later on)
In
Kingdom:
o Onshore Pipelines Design
o Fabrication in STAR yard, prefabrication in Snamprogetti yard (refer section 4.6)
o Sealines Pipe coating,
o onshore and offshore Construction sites
Indonesia:
o Fabrication of Tie-In Topsides in Saipem Karimun yard (Indonesia) (refer section
4.6)
3.4.1 COOPERATION
The Project will be executed in a co-operative environment between COMPANY and
CONTRACTOR Project Team resident at Project Office in Sharjah UAE and then at Sites in
order to accelerate the decision making process, which is an essential element of this Project
Execution Plan.
Integration at the working level of CONTRACTOR and COMPANY Project Team in Sharjah
UAE first and eventually at Site will be a vital ingredient to the success of the Project.
3.4.2 FACILITIES AND SERVICES
Facilities and Services for Company Project Management Team in Design Offices and
Fabrication Office will be as per Contract Schedule B.
CONTRACTOR will prepare and submit to COMPANY the proposed Office Lay out at each
location.
3.4.3 BLOCK
VISA
CONTRACTOR will follow the Block Visa procedure for its activities in kingdom.
CONTRACTOR will establish the plan of personnel to be mobilised in Kingdom for the
performance of the Project. CONTRACTOR will issue to COMPANY the Statement Of
Manpower Requirements providing with the following information: Contractor details, Contract
details, number of expatriates by nationality required to perform the job. The well-known to
Contractor block visa procedure includes the following steps:
Submit Statement of Manpower Requirements to COMPANY Project Manager
After approval, submission to Aramco Contract department
Submission to Aramco Government Relation office
Preparation of special documents for Labour Office
Submission to Labour Office
Submission to Ministry
After approval Visa allocation for each nationality
Receive work Visa from labour office
3.5 HEALTH, SAFETY AND ENVIRONMENTAL (HSE)
number of other HSE documents (e.g. Hazard Identification and Risk Assessment Plan,
Emergency Response Plan, Event Reporting and Investigation Procedure, HSE Audit Plan,
HSE Requirements for Subcontractors Procedure, Waste Management Plan, etc.), which will
generate the fundamentals of the Project HSE Management System and will be applicable at all
project locations and throughout its lifetime. The Project HSE Management System so
developed and implemented will be meant to ensure that no Harm to People, no Damage to the
Environment, and no Damage to or Loss of Asset will occur throughout the project duration.
These objectives will be pursued in a number of ways, a few of which being pointed out here
below:
Hazard Management
CONTRACTOR will ensure that risk assessments are timely performed by each part of its
project organization to suitably and sufficiently cover their full scope of work. This means
that no work activity will commence, unless appropriate control measures have been
physically implemented (not necessarily on project basis) and all involved parties have been
made aware of them.
Consideration for the Environment
CONTRACTOR will act in full respect of the applicable environmental legislation and will
encourage the reduction of environment emissions, including noise, to a minimum and
improvement of waste management through its ZERO Pollution target and policies.
Health and Welfare
CONTRACTOR will pursue schemes and initiatives for the improvement of the occupational
health and welfare of employees
Training and Competence
CONTRACTOR will promote and implement training and awareness programmes
throughout the project duration and will ensure that all individuals have received adequate
HSE training in order to perform their work safely and efficiently.
Incident Prevention, Reporting and Investigation Actions
In line with SAIPEM CORPORATE and COMPANY requirements, CONTRACTOR is
committed to prevent any kind of Accident / Incident during the entire project lifetime.
However, should any undesirable event occur, the reporting, investigating, analysing and
record-keeping of Accident / Incident reports is an important element of CONTRACTOR’s
HSE Management System.
Therefore, CONTRACTOR is committed to reporting and investigating all Accidents /
Incidents, even where no injuries or significant damage have occurred.
These investigation reports will be analysed to determine where the HSE improvement
efforts need to be emphasised. All reports and investigations must include a determination
of the root causes of the incident and corrective actions to be undertaken to prevent
recurrences.
Incident is a general term. An Incident can be an Accident or a Near Miss, but all of them will
be subjected to the same reporting and investigation procedure.
Lessons Learned, both good and bad, will be shared with the COMPANY and all Third
Parties involved in the project execution works.
Monitoring and Review
HSE initiative will be monitored using Leading Indicators techniques to provide a clear
measure of their effectiveness. CONTRATOR will regularly perform internal audits and all
finding will be reviewed and timely followed-up.
Targets
CONTRACTOR will set targets for the Project activities against a similar set of key
indicators reflecting the HSE objectives.
The list of HSE documents that CONTRACTOR will prepare the Project SOW are listed in
Section 5 of this document and will include the following:
Waste Management Plan for the Fabrication, Onshore and Offshore Activities (IK)
Environmental Monitoring Program for the Offshore Activities (IK)
Loss Prevention Plan for Fabrication Activities (IK)
Hazard Identification and Risk Assessment (HIRA) Plan for Fabrication Activities (IK)
Emergency Response Plan (ERP) with MEDEVAC for Fabrication Activities (IK)
Oil Spill Contingency Plan for Fabrication Activities (IK)
Loss Prevention Plan for Onshore Activities (IK)
Hazard Identification and Risk Assessment (HIRA) Plan for Onshore Activities (IK)
Emergency Response Plan (ERP) with MEDEVAC for Onshore Activities (IK)
Oil Spill Contingency Plan for Onshore Activities (IK)
Loss Prevention Plan for Offshore Activities (IK)
Hazard Identification and Risk Assessment (HIRA) Plan for Offshore Activities (IK)
Emergency Response Plan (ERP) with MEDEVAC for Offshore Activities (IK)
Oil Spill Contingency Plan for Offshore Activities (IK)
Loss Prevention Plan for Fabrication Activities (OOK)
Hazard Identification and Risk Assessment (HIRA) Plan for Fabrication Activities (OOK)
Emergency Response Plan (ERP) for Fabrication Activities (OOK)
H2S Contingency Plan (TBC)
Project Event Reporting and Investigation Procedure
Project HSE Training and Induction Plan
Project HSE Requirements for Subcontractors
Project HSE Audit Plan
Project Health Plan
Project HSE Incentive Scheme
In addition to the above, CONTRACTOR will undertake a series of actions including the
following:
HSE Audit of STAR Fabrication Yard prior to commencing project activities.
HSE Audit of KARIMUN Fabrication Yard prior to commencing project activities.
HSE Audit of the main Vessels involved in the offshore operations (Castoro 2, Castoro 8,
etc.) prior to commencing the activities.
HSE Induction and Training of project personnel in KSA, Sharjah and KARIMUN. The
process will be coordinated with the project assigned HSE Coordinators at STAR and
KARIMUN Fabrication Yards. The HSE Induction and Training will be given to personnel
as they join the project teams and prior to commencing work. It will be done in
accordance with the Project HSE Induction and Training Plan approved by COMPANY.
Preparation of Risk Assessments applicable to the project activities. The process will be
coordinated with the project assigned Operational Management, HSE Coordinators and
relevant Masters of the Vessels involved. The process will be an ongoing one,
throughout the lifetime of the project, as additional Risk Assessment (review) sessions
may be required during the work execution phases, depending on various potential
changes. Review with COMPANY the Risk Assessments.
HSE Audits of Project HSE Management System, work sites and HSE performance at all
project locations. The HSE Audits will include Health, Medical and Catering Facilities &
Services audits, Safety audits and Environmental Protection & Waste Management
audits. Internal and / or Subcontractor HSE Audits will be conducted on a monthly basis
at all project locations according to the Project HSE Audit Plan (which will include a
Project HSE Audit Schedule) approved by COMPANY.
HSE Inspections of work sites at all project locations. Daily random HSE inspections will
be conducted at each work site, aimed at checking the compliance with the Project HSE
Standards during certain tasks execution phase. Thorough Weekly HSE inspection will
be conducted at each work site.
Organize regular Lessons Learned sessions at the end of work phases. These sessions
will be coordinated with and agreed upon with COMPANY and CONTRACTOR PMT.
The aim will be to share Lessons Learned, both good and bad, with all project teams.
Thoroughly Coordinate and Risk Assess SIMOPS (as applicable). The main target
should be to avoid, if possible at all, any SIMOPS, but, should the need for SIMOPS
occurs, they are to be thoroughly and timely analyzed and Risk Assessed. The relevant
Risk Assessment is to be approved by COMPANY and CONTRACTOR management,
and green light to proceed with work is to be given accordingly.
Weekly HSE & Welfare Meeting at each project work site. Weekly HSE & Welfare
Meeting will be held at each project work site. The schedule for each worksite will be
approved beforehand by COMPANY and CONTRACTOR relevant management. The
meeting will be minuted and the MoM will be distributed to COMPANY and
CONTRACTOR management.
Conduct Emergency Drills at each project work site. An Emergency Drills schedule will
be developed for each project work site and subjected to COMPANY approval prior to
entering into force.
Hold Lessons Learned meeting with the relevant personnel, if applicable, after
conducting each Emergency Drill. Lessons Learned meetings will be held only if
negative aspects (e.g. too long mustering time, improper evacuation of the affected work
areas, inadequate response, in terms of both timing and actions, of the Emergency
Response Team, inadequate behaviour of personnel, etc.) have been highlighted during
the drill.
Establish and monitor a two-way open and effective communication system (e.g. HSE
and Welfare Meetings, Toolbox Talks, Safety Bulletins, Safety Alerts, Safety
Stand-Downs, Safety Handbooks, Newsletters and relevant HSE Information) as part of the
HSE Awareness Program to promote active information, involvement and co-ordination
between work force, HSE personnel and management. This process will be aimed at
enhancing the positive safety culture within the entire project organization.
Implement an HSE Incentive Scheme program at project level, applicable to each work
site and facility. This program will be aimed at recognizing and rewarding good HSE
performance throughout the project.
Annual HSE Management System Review. A Management Review will be carried out on
an annual basis and will address the status of implementation of the HSE Management
System, outstanding issues, review of the status of suppliers HSE System, persistent
non compliances and a review of trends.
Moreover, CONTRACTOR does confirm that the project dedicated Loss Prevention Plans
(please refer to the aforementioned list of HSE documentation) will address the following:
Schedule “D” of the IK Contract
COMPANY Construction Safety Manual
COMPANY Marine Safety Instructions
Other applicable project standards and specifications
With reference to the Attachment V of Schedule “B” of the OOK Contract, CONTRACTOR will
prepare an Emergency Response Plan (ERP) with MEDEVAC for Fabrication Activities to
address all items included in the Attachment.
3.6 QUALITY MANAGEMENT IN PROJECT EXECUTION
During All phases of the Project (Engineering, Procurement and Construction) quality assurance
is addressed as follows:
A Project Quality Manager will be assigned full time to the Project and will be
responsible for monitoring the development and implementation of the Project Quality
System
30 days after Contract award the Project Quality Manager, on the basis of the scope of
the Project, develops a specific Project Quality Plan
Specific project procedures will be prepared and approved in line with Contract
requirements and CONTRACTOR Project execution practices
Project Quality Manager in close cooperation with the Project Director and relevant
Project Managers will develop a Project Quality Audit Schedule
Schedule Q of OOK and IK Contract shall be reviewed and implemented as requested
by the Contract throughout all Project execution life
3.7 RISK ASSESSMENT AND MANAGEMENT
Risk and Opportunity Management Plan is a process composed of four essential steps,
identification, qualification, quantification and follow up / monitoring, with the lowing approach:
Full integration of the Risk Management into the overall Project Management Process.
Pro-active and early identification, evaluation and management of risks in all phases and
at all levels of the project. Anticipation and management of risks are always preferred to
corrective actions.
Continuous control & monitoring of the risks and opportunities and detailed associated
reporting.
Promote communication to facilitate problem-solving
During the risk identification process, specific attention will be given to all “Lesson Learned” by
CONTRACTOR in the execution of past Projects in Saudi Arabia.
An essential feature for the correct application of the method is the assignment of each
identified risk to a nominated individual.
identified. The nominated owner collaborates with the Risk Engineer and Project Managers to
further identify and evaluate risks, to propose and implement appropriate risk mitigation actions.
Each Risk Owner is then responsible for monitoring the progress of his risk in collaboration with
the Risk Engineer.
4.
EXECUTION OF THE WORK
4.1 CONTRACT DOCUMENTS REVIEW
The review of the technical documentation enclosed in the Contract Documents is a key activity
for the successful completion of the project. The main objectives of this activity are:
Check the documentation to define missing information, data and criteria;
Review design solutions against contractual design criteria to verify completeness and
consistency;
Establish a comprehensive documentation for the critical design and field activities that
can be on the critical path for the project implementation, such as field surveys; such
field activities may also include the collection of existing documentation at SAUDI
ARAMCO premises;
Identify the CONTRACTOR’s corporate applicable engineering and procurement
Projects procedures, complete of document specimen for Client review and approval
prior any massive detailed engineering activity (these specimen will be used as guideline
for the entire project);
Establish a project Vendor List selecting the most suitable IK and OOK Vendors for
project purposes;
Set-up to project requirements, if necessary, the internal work procedures and tools such
as, but not limited to, drafting manual, document register, co-ordination procedure, etc.;
Define technical engineering interfaces and set-up procedures and work plan to be used
for the interface engineering;
Identify areas where contractual scope of work has to be updated and modified as per
conclusions of activities above; proposed solutions, backed-up with all the necessary
documentation, will be discussed and agreed with COMPANY Representative and used
for detailed engineering activities accordingly.
4.2 DETAILED ENGINEERING AND DESIGN
During the detail engineering, CONTRACTOR activities are tailored towards the issue of the
necessary documentation for procurement of itemized equipment and bulk materials, and,
subsequently, the issue of the construction drawings and documentation to build-up the facilities
in accordance to the contractual specifications, requirements and Company Standards.
The main objectives to be met throughout the completely engineering process in order to fulfil
all the contractual requirements can be summarized as follows:
Engineering for Procurement:
Perform the detailed Engineering in order to issue technical documentation for material
procurement (enquiry, technical evaluation of the bids, purchase orders, etc.) concerning all
items including the critical items.
Engineering for Construction:
Perform the detailed Engineering in order to:
complete the Procurement activities
assure the availability of technical documentation and fabrication drawings for the
execution of the Structural, Mechanical, Electrical and Instrumentation and other related
works
Assure the availability of technical documentation (IFC Drawings, etc.) and materials on
site as planned to support smooth execution of construction.
Engineering during Construction:
Ensure that works are performed according to the Project Documentation and the materials are
in compliance with the technical specifications.
Resolve any problems (if any) caused by modifications during construction and/or
non-conformity/re-work.
Prepare and issue the pre commissioning procedure
Obtain the “Mechanical Completion certificates”.
4.3 DISCIPLINE
ACTIVITIES
The activities, which will be carried out by the various disciplines involved in the execution of the
Project, are summarized here below.
4.3.1.1 Process
Engineering
Prepare and issue of PFD’s
Prepare and issue, in collaboration with the other involved disciplines, the P&IDs.
Prepare and issue the fire protection drawings.
Cooperate with the other involved disciplines to define and prepare the technical
specifications and data sheets for equipment, packages, instrumentation, electrical and
DCS.
Complete the HAZOP study as required.
Prepare and issue the cause and effect diagrams.
Support the Technical Departments for Bids Technical Evaluation.
Revise technical documents according to ordered material.
Issue the preliminary edition of the following documents relevant to the scope of work:
o PRECOMMISSIONING GENERAL SPECIFICATIONS
o PROJECT RECORD BOOKS
Resolve any NON CONFORMITY during construction.
Organize and carryout all the activities relevant to the pre-commissioning (Auxiliary
systems only).
Assure technical assistance during pre-commissioning.
Issue the “AS BUILT” Documentation.
4.3.1.2 Machinery
and
Packages
Cooperate with Process Department to finalize the P&ID’s.
Cooperate with involved Departments to finalize mechanical specifications.
Define the items and packages specifications.
Issue data for Classification of Hazardous Locations.
Issue the Preliminary Electric Load List.
Issue the Material Purchasing Specifications, General Specifications, etc.
Define the layout of Machinery and Packages.
Check and approve the supplier’s Construction Drawings and support Inspection
Department for Workshop tests.
Revise technical documentation to fully comply with purchased equipment.
Carry out the Detailed Engineering according to the Vendor’s engineering.
Provide the Construction Department with quantities, drawings, etc.
Cooperate to the following documents:
o FIELD QUALITY CONTROL PLAN
o PRECOMMISSIONING GENERAL SPECIFICATIONS
o PROJECT RECORD BOOKS
Assure the technical assistance during the construction activities.
Resolve any NON CONFORMITY during construction.
Assure technical assistance during pre-commissioning.
Issue the “AS BUILT” Documentation.
4.3.1.3
Piping and mechanical equipment engineering
Cooperate with Process Department to define the P&ID’s.
Cooperate with involved Departments to define the mechanical Specifications.
Issue project piping specifications.
Issue technical specification for Painting, insulation and anti-corrosive coatings.
Issue the Plot Plans, prospective views, sections.
Define the piping system layout.
Issue data for Classification of Hazardous Locations.
Perform the Stress Analysis.
Issue the Material Purchasing Specifications, General Specifications, etc.
Issue Requisition for Quotation, and Technical Evaluation of material to be purchased.
Check and approve the Supplier’s Construction Drawings.
Carry out the Detailed Engineering to fully comply with the purchased materials.
Define and issue the technical documentation required for construction activity (Piping
Layouts, DWG’s required for piping prefabrication and erection, piping isometric
drawings etc.).
Provide the Construction Department with quantities, drawings, particular specifications,
etc.”
Cooperate to the following documents:
o FIELD QUALITY CONTROL PLAN
o PRECOMMISSIONING GENERAL SPECIFICATIONS
o PROJECT RECORD BOOKS
Assure technical assistance during the Construction activities.
Resolve any NON CONFORMITY during construction.
Assure technical assistance during pre-commissioning.
Issue the “AS BUILT” Documentation.
4.3.1.4 Electrical
Engineering & Cathodic Protection
Cooperate with involved Departments to define mechanical specifications.
Finalize and confirm ETAP Studies (Load Flow, Short Circuit current, Grounding
System)
Define cable runs, protection coordination studies and diagrams, relay protection and
one line diagrams.
Define in detail the cathodic protection system and the Anode Ground bed Locations.
Issue the Material Purchasing Specifications, General Specifications, etc.
Issue Requisition for Quotation, and Technical Evaluation of material to be purchased.
Check and approve the supplier’s Construction Drawings and support Inspection
Department for Workshop tests.
Revise technical documentation to fully comply with purchased materials.
Carry out the Detailed Engineering according to the purchased material.
Define and issue the technical documentation required for construction activity (Cable
run and road crossing details, lighting systems, cable interconnection diagram).
Provide the “Construction Department” with quantities, drawings, etc.
Cooperate to the following documents:
o FIELD QUALITY CONTROL PLAN
o PROJECT RECORD BOOKS
Assure the technical assistance during the construction activities.
Resolve any NON CONFORMITY during construction.
Assure technical assistance during pre-commissioning.
Issue the “AS-BUILT” Documentation.
4.3.1.5 Instrumentation
and automation engineering
Cooperate with Process Department to define P&ID’s.
Cooperate with involved departments to define mechanical specifications.
Define
cable
runs.
Issue technical specification and data sheets of instruments.
Issue data for Classification of Hazardous Locations.
Issue the Preliminary Electric Load List.
Issue the Material Purchasing Specifications, General Specifications, etc.
Issue Requisition for Quotation and Technical Evaluation of material to be purchased.
Check and approve the supplier’s Construction Drawings and support Inspection
Department for Workshop tests.
Revise technical documentation to fully comply with purchased materials.
Carry out the Detailed Engineering according to the purchased material.
Define and issue the technical documentation required for construction activity (Cable
run and road crossing details, instrumentation and RTUs, cable interconnecting diagram,
instrument primary and secondary connection sketches).
Provide the Construction Department with quantities, drawings, etc.
Cooperate to the following documents:
o FIELD QUALITY CONTROL PLAN
o PRECOMMISSIONING GENERAL SPECIFICATIONS
o PROJECT RECORD BOOKS
Assure the technical assistance during the Construction activities.
Resolve any NON CONFORMITY during construction.
Issue the “AS BUILT” Documentation.
4.3.1.6 Structural
Engineering
Issue all deliverables for the strengthening of structures, as defined in the scope of work.
Perform design calculations of all the structures.
Implement the 3D Tekla™ model of the structure and export it into PDS for the purpose
of interface checks.
Extract from 3D Tekla™ model the 2D General Arrangement drawings.
Issue the fabrication Drawings and Material Take-Offs.
Cooperate to the following documents:
o FIELD QUALITY CONTROL PLAN
o PROJECT RECORD BOOKS
Assure the technical assistance during the Construction activities.
Resolve any NON CONFORMITY during construction.
Issue the “AS-BUILT” Documentation.
4.3.2 ONSHORE PIPELINES DESIGN
Detailed engineering, which includes the site surveys activities and the procurement support,
will be executed in accordance with the following general sequence:
The onshore pipeline detailed engineering will be sub-contracted to an ARAMCO approved
GES/Engineering Firm operating in the Kingdom of Saudi Arabia having a valid engineering
licence and with a proven experience in pipeline design (for gas and liquid hydrocarbons
transportation).
Site surveys and Project data collection of the existing facilities will be included in the Sub
Contractor scope of work and constitute the primary and early design activities to be performed:
Site survey in Abu Ali (for the MV composite cable route and connection)
Pipeline Topographic Survey (along the proposed route: shore tie-in with offshore
pipeline, pipeline corridor crossing, pipeline route definition for the alignment sheets
preparation, interface with Wasit Gas Plant)
Geotechnical investigation (scraper facilities area, beach valve station, soil resistivity
measurement for cathodic protection system design)
4.3.3 OFFSHORE
SEALINES
DESIGN
4.3.3.1
Flow Assurance Engineering
The following main activities will be carried-out:
Preparation of the Flow Assurance Design Basis according to the performed status of
the Preliminary Design (Company provided) and the input data collection.
Fluid property characterization
Implementation of Simulation Models for the following transport systems:
o Arabiyah
Production
System:
pipelines
gathering network from Arabiyah WHPs
to the onshore arrival at WGP via Arabiyah TP;
o Hasbah Production System: pipelines gathering network from Hasbah WHPs to
the onshore arrival at WGP via Hasbah TP;
o MEG Injection System from WGP to Arabiyah and Hasbah TPs via the IIP;
o Elemental Sulfur Solvent Injection System from WGP to Hasbah WHPs via the
IIP and the Hasbah TP.
The following battery limits will be considered for the flow assurance analysis:
o The simulation models for both Arabiyah and Hasbah pipelines gathering
networks will be implemented for the overall transport system including the infield
flowlines and the export trunkline, from the X-Mas Tree onboard each satellite
well head platform up to the delivery point at the onshore receiving trap
(upstream the onshore treatment plant);
o The simulation model for MEG Injection System will be implemented from the
onshore launching trap (downstream the onshore MEG regeneration plant) up to
the injection points along Arabiyah and Hasbah trunklines (i.e. at the onshore
beach valve stations, at the trunklines subsea tie-in and onboard each TP);
o The simulation model for Elemental Sulfur Solvent Injection System will be
implemented from the onshore launching trap (downstream the onshore plant) up
to the injection points at Hasbah WHPs (at well-heads, upstream the choke
valves).
Performance of the following simulations for both Arabiyah and Hasbah Production
Systems:
o Steady state transport simulations.
o Transient
simulations.
Development of the Hydrate Management Strategy for both Arabiyah and Hasbah
Production Systems.
Performance of the following simulations for MEG Injection System:
o Steady state simulations to verify the MEG system capability to transport the
MEG design flowrate.
o Transient simulations for identification of high pressure transients.
Performance of the following simulations for Elemental Sulfur Solvent System:
o Steady state simulations to verify the Elemental Sulfur Solvent system capability
to transport the design flowrate.
o Transient simulations for identification of high pressure transients.
Preparation of process input data (P, T, density, velocity profiles, etc.) for interfacing with
other disciplines such as pipeline mechanical and corrosion design, material selection
and receiving process (e.g. flow rate and temperature at the onshore plant) and for any
other external interfaces to the Contractor Scope of Work.
Preparation of the following deliverables covering used input data, methodology, results
and recommendations for each performed activity:
o Steady State Thermo-Hydraulic Analysis for Arabiyah Production System;
o Transient Analysis for Arabiyah Production System;
o Steady State Thermo-Hydraulic Analysis for Hasbah Production System;
o Transient Analysis for Hasbah Production System;
o Hydrate Prevention Strategy for Arabiyah and Hasbah Production Systems;
o Steady State Thermo-Hydraulic Analysis for MEG and for Elemental Sulfur
Solvent Injection Systems;
o Transient Thermo-Hydraulic Analysis for MEG and for Elemental Sulfur Solvent
Injection Systems.
4.3.3.2
Subsea Rigid Pipelines Detailed Design
The detailed design engineering of rigid pipelines will include the following main activities:
Preparation of the Offshore pipelines design basis, including all the main data required
for the different engineering activities and the relevant criteria
Pipelines routing; verifying the compliance of the surveyed corridors to any given
constraint/crossings, adjusting and optimizing the routes taking into consideration all
surveys data
Pipelines wall thickness analysis;
Pipelines on-bottom stability analysis;
In-service buckling analysis
Walking
assessment;
Spool/riser
design;
Pipelines free-span analysis;
On-bottom roughness analysis and intervention works definition;
Intervention works design;
Crossing design;
Shore approaches and shore crossing design;
Preparation of Issue for Construction drawings (alignment sheets, platform approach,
spool and riser layouts etc.)
4.3.3.3
Offshore Pipeline Cathodic Protection Design
The cathodic protection design will include the following main activities:
Preparation of the cathodic protection philosophy for offshore pipelines; identifying all the
main data and criteria, design methodology and interface with other cathodic protection
systems
Preparation of the cathodic protection design report
Development of the anodes specification and drawings
Preparation of the material requisition and material take off for anodes
Preparation of the anode installation specification and drawings
Technical evaluation and follow on of the suppliers
4.3.3.4
Subsea Flexible Pipelines and Subsea Structures Detailed Design
The subsea flexible pipelines and subsea structures design will include the following main
activities:
Definition of the MEG injection valve skid configuration
Valve skid detailed design
Valve protection cover design
Alignment frames design
Preparation of the specifications for order (technical specification, scope of work, MTO
and data sheets);
Technical evaluation and follow-on of the selected Vendor engineering, manufacturing,
testing and delivery activities of the required subsea items;
Assist the fabrication contractor during fabrication and test of the structures and the
relevant piping;
4.3.3.5
Materials Engineering
The material engineering will include the following main activities:
Review of the Company specifications for carbon steel and clad linepipe, bends and
flanges and identification of additional requirements
Preparation of the Material requisition for linepipes, bends and flanges
Development of the negotiations with the vendors and Technical bid evaluations
Follow on of the suppliers
4.3.3.6
Pipelines Coating Engineering
The pipeline coatings engineering will include the following main activities:
Preparation of the requirements for internal coating laboratory testing
Review of the Company specifications for pipeline internal and external coatings and
identification of additional requirements
Development of additional coating specification as required
Preparation of the Material requisition for internal, external, concrete coating for
linepipes, bends and flanges
Development of the technical negotiations with the vendors and Technical bid
evaluations
Follow on of the suppliers
The corrosion engineering will include the following main activities:
Preparation of the requirements for corrosion inhibitor compatibility tests
Review and development of corrosion management philosophy
Preparation of material selection report
4.3.4 SUBMARINE COMPOSITE CABLES & SUBSEA UMBILICALS ENGINEERING
The submarine composite cables and umbilicals engineering will be carried out by the
CONTRACTOR in close liaison with the COMPANY to finalise the design and will include the
following main activities:
Preparation of the Submarine Composite Cables & Umbilicals Material Requisition
package including:
o Definition of the Scope of Supply,
o Definition of design, manufacturing and testing requirements functional lines and
structures,
o Definition of the documentation and certification to be produced by the Suppliers
o Definition of submarine composite cables and umbilicals load out, transportation
and installation requirements
Submarine Composite Cables and Umbilicals Bid Technical Evaluations and preparation
of the BTE reports to the COMPANY
Review and updating of the Design Basis relevant to the submarine composite cables
and umbilical system including:
o The basic design data
o The design criteria
Starting point for the development of the design criteria will be the documentation
developed during FEED, including any follow-up from the endorsement phase.
To ensure that the design of the submarine composite cable and umbilical
systems meet the specified requirements, the basic engineering design data
relevant to the submarine composite cables and umbilicals present in the ITT
documents will be verified and updated as necessary with the data collected from
Pre-Engineering survey on existing facilities.
All data used in the submarine composite cables and umbilicals design including
the environmental, meteocean, seabed soil data will be provided with references
to their sources and will be part of the revised Design Basis produced in
agreement with the COMPANY and kept updated throughout the development of
the project.
As part of this activity, the design criteria, functional and technical requirements
for the submarine composite cables and umbilicals, the ancillary equipment
(J-tube pull in head, hang off assembly, bend restrictors and J-(J-tube centralisers) and
for the topside termination enclosures (topside electrical splice cases and
on-shore splitter box, fibre optic junction boxes, topside umbilical termination unit for
sulphur solvent injection) will be developed for use in the Detail Design.
Starting point for the development of the design criteria will be the corresponding
ITT documentation, including any follow-up from the endorsement phase.
As far as concern the submarine composite cables, the subsea umbilicals and the
related ancillary equipment design, manufacturing, testing installation and
pre-commissioning, the Saudi Aramco material specifications and international
standards will be considered as the primary design codes
Detail design including:
o Review and assessment of the power cores sizing and fiber optic budget.
o Review and assessment of the sulphur solvent injection lines sizing.
o Review and assessment of the submarine composite cables and subsea
umbilicals design and project documentation performed and generated by the
relevant Suppliers.
o Review and assessment of the submarine composite cables and umbilicals
routing report
o Assessment of seabed stability and allowable span for the submarine composite
cables and umbilicals.
o Review and assessment of the submarine composite cables and umbilicals
onshore and platforms approaches.
o Interfaces and installability assessment of the submarine composite cable and
umbilical systems equipment
o Definition of all technical and functional interfaces
o Definition of the submarine cables and umbilicals mechanical completion
(pre-commissioning) requirements and all necessary equipment, tools consumables
and personnel.
Follow-up of the selected Suppliers detail design, fabrication, testing, offshore services
and documentation supply activities.
4.3.5 ENGINEERING
INTERFACES
Overview
The effective control of Interfaces is considered to be one of the key issues to ensure the
successful execution of the Project. Accordingly, CONTRACTOR organization includes senior
personnel to ensure that both Internal and External Interfaces are closely monitored and well
managed.
External Interfaces
External Interfaces are under the responsibility of the Interface Manager.
Internal Interfaces
Internal Interfaces are under the responsibility of the respective Project Managers.
Key Interface Points
Management and resolution of External and Internal Interface requires good co-ordination and
communication between the concerned parties.
For this reason, the interfaces will be discussed during internal co-ordination meetings and
specific meetings as necessary. To manage internal interfaces, CONTRACTOR will develop, at
the beginning of the project, interface matrix between engineering centers, engineering
disciplines and between engineering center and construction sites .
The External Interfaces Register will be maintained and continuously updated as the work
progresses. The Register will be reviewed during the Interface meetings organised on a regular
basis and it will be updated and issued to COMPANY
CONTRACTOR will issue the Plan for Interfaces Coordination defining the plans and
procedures to be followed for the management and control of the External interfaces.
4.3.6 CONSTRUCTABILITY
CONTRACTOR will develop a Constructability Program to optimize engineering, detail design,
engineering planning, procurement and safety objectives.
The constructability objectives are to ensure safety, to take an active part in environmental
concerns, to enhance quality (reliability, operability and maintainability), and to optimize overall
schedule and costs by utilizing construction knowledge and experience in planning, design,
procurement, and field operations.
The activities are applied to all personnel involved in the Project with the intent that all
engineering, procurement, and construction activities and all disciplines responsible for
executing these activities will incorporate constructability to achieve overall project objectives.
No constructability suggestion should be implemented if it increases total project cost or extends
the schedule. Suggestions should only be considered that result in lower overall cost or
shortened schedule. A suggestion could result in an increase in engineering hours but yields
construction savings that more than offset the increase in engineering.
CONTRACTOR will ensures that the construction experiences and previous project lesson learn
shall be taken into consideration in every stage of the project – management, engineering,
procurement and construction – in order to achieve the project goals.
Key activities:
Organize spew-out and brainstorming sessions to identify the most critical
construction issues – the ones that strongly affect overall time, cost and quality;
Build an action plan to turn the critical issues into opportunities;
Organize follow-up sessions to update the action-plan;
Organize Sequencing meetings to identify the best construction sequence using
visual aids;
Update the Constructability guidelines according to the methodology evolution.
4.3.7 PRELIMINARY DESIGN VERIFICATION
CONTRACTOR will perform the verification of the COMPANY provided Preliminary Design as
per Contract requirement Schedule H section 1.4.
During the 120 days Verification Period, CONTRACTOR will review and evaluate the
Contractual COMPANY provided Preliminary Design to verify for any conflict with drawing,
specifications and applicable Standards. Any conflict will be notified to COMPANY and a report
will be issued within 120 days from Contract effective date.
Depending on the extent of the findings and their impacts, the Verification Period shall be
extended, as agreed with COMPANY, to complete the review in order to allow the detailed
design, engineering development in accordance with the FACILITIES performance
specifications.
4.3.8 ENGINEERING ORGANIZATION MATRIX
The CONTRACTOR organisation for the performance of the overall engineering Scope of Work
will be as per Attachment 1 to this WEPP Engineering Organization Matrix.
4.4 PROJECT
CONTROLS
The Project Control Manager, as part of CONTRACTOR Project Management Team, shall be
responsible for all project control activities.
For planning and scheduling, PRIMAVERA software (P 6) will be used.
The activity will be carried out as described in relevant Project Control Procedures to suit the
Scope of Work foreseen for both the Contracts 6600026283 (OOK) and 6600026284 (IK).
00-ZA-E-09800 Work Breakdown Structure
00-ZA-E-09801 Planning and Scheduling
00-ZA-E-09803 Progress Measurement
00-ZA-E-09804
Project
Reporting
4.4.1 OVERVIEW
The Planning and Control are cross processes involving all the various stages (Design,
Procurement, Fabrication, Transportation, Installation and Pre-Commissioning) of the Project.
The aim is to assure the best support to the Project Management, by the use of professional
techniques and procedures, and by the latest computer technology and software, for monitoring,
analysing, and taking, if necessary, the right corrective actions, in order to reach all the
Contractual objectives.
The purpose of the Reporting is to inform the CONTRACTOR Project Management Team and
COMPANY PMT on the status of the Project, on the scored Progress, to describe the activities
in progress and forecasted, highlighting the problems and the areas of concern.
CONTRACTOR will develop the Project Control Procedures and contained tools (Software and
Reporting) for monitoring of the Project. Once approved by the COMPANY, they will be
regularly updated and issued to COMPANY in compliance with established cut-off dates
(Project Reporting Procedure), across the whole Project life.
4.4.2 WORK
BREAKDOWN
STRUCTURE
The definition of the WBS (Work Breakdown Structure) of the Project is the first step of the
Project Control System setup. The WBS is a hierarchical structure splitting up the Project, which
allows the monitoring of the scope of work at the synthesis/detail rate required by the various
involved parties. One of the key activities of the WBS development process is the weighting of
the breaking down elements in accordance to the Contractual Pricing Breakdown.
In order to suite CONTRACTOR Organization and Scope of Work pertinence, the WBS will be
developed and implemented with the purpose of guarantee the appropriate overall consolidation
and also to ensure the development of the Overall Schedule.
The WBS will be developed as follows:
1st Level – Phases (Design, Procurement, Fabrication, Mobilization, Installation and
Pre-Commissioning)
2nd Level – Onshore and Offshore Facilities (i.e ARBI-4 Wellhead Deck , 12” Gas
Flowline ARBI-9, etc)
3rd Level – Disciplines for the Offshore Structures (i.e Electrical, Instrumentation, etc)
and Components for Pipelines (i.e. Cables, Flowlines, CRA Cladded Pipes, etc)
4.4.3 PLANNING
AND
SCHEDULING
Development of the Schedule is the step following the definition of the WBS.
At this stage, the CONTRACTOR Lead Planning Engineer acting as coordinator of various
Planning Engineers working for each of the 5 Main Work Packages, by interfacing with the
Project Managers, Engineering, Procurement, Onshore Fabricator, Operations and
Pre-Commissioning department/expertises identifies activities and develops the schedule for
activities to be directly performed by CONTRACTOR at various levels, by following a pyramidal
top-down logic consistent with the WBS. For activities to be subcontracted, after having
identified the span period for execution of the Subcontracts, a detailed schedule is required from
potential subcontractor and verified for consistency with the Overall Schedule
Level 1: Project Milestones and Key Dates
Contractual Milestones and Key Dates. Summary of one Page
Level 2: Project Summary Schedule by Phases and Sub-Phases.
Contractual Milestones and Key Dates. Start and completion dates by Phases (Engineering,
Procurement, Onshore Fabrication, Transportation and Installation, Hydro-testing &
Pre-Commissioning) and sub-phases: Discipline/ Equipment for Engineering and Procurement;
Work Disciplines and Structures such as Jackets, Topsides, Pipelines, Cables, Facilities and
whatever other Structures foreseen in the Scope of Work for Fabrication; Work
Areas/Structures, Pre/Post Surveys Spreads, Shore Approaches Spread, Offshore Operations,
Transportation Spreads, Diving Support Spread, Modifications Support, Cable Spread vessel
and whatever other Spread foreseen for Transportation and Installation and
Hydro-testing/Pre-commissioning. Summary of 10-15 Pages.
Level 3: Critical Path Method (CPM) Detailed Work Schedule
At this level, activities are sized to allow estimation of duration and identification of logical links
and sequences. In addition, resources/manhours requirement shall be evaluated at this level.
Level 4: Detailed Deliverables Schedule
List of Document for Engineering (Master Document Register); List of Material to be procured by
discipline/Type of material for Procurement (Procurement Status Report / Material Status
Report). Discipline Pre-Fabrication steps for Onshore Fabrication (Fabrication Production
Control).
The level four Detailed Deliverables will be grouped to be compatible with level three. These
lists will be managed using Spreadsheets/databases formats. WBS for Schedule development
will be included in “Project Planning & Scheduling” Procedure.
Estimation of time, allocation to approximated period, responsible for execution of the activities,
the contractual Milestones and the Contractors/SAIPEM Key dates (ex: Barges availability, etc)
are some of the key elements to be considered.
During level four development process, network analyses and optimisation of resources are
carried out by SAIPEM Planning Engineer until a satisfactory result is attained.
Once completed the development, SAIPEM will submit the whole Planning package to
COMPANY. Upon approval the Planning package, composed by Project Schedules, Progress
“S” Curves and Histogram will be frozen to become the baseline for monitoring of the
performance.
4.4.4 PROGRESS
MEASUREMENT
A Progress Monitoring System is set up based on the WBS that has been developed in
consistence with the Contract Pricing Breakdown, at the required level of detail.
The methodology, structure, logic, steps of progress linked to specific events and samples
adopted to develop the System to measure the progress for each Work Package and entity in
accordance to the WBS, will be produced within the “Progress Measurement System”
Procedure and submitted to COMPANY for approval.
The followings Level 4 specific Tools for Progress Measurement will be used:
‘Master Document Register’ for Design Deliverables and Installation Engineering
progress calculation, managed by Database EIM (Engineering Integrated Management)
‘Material Status Report’ for Post Order Activities for Procurement progress calculation,
‘Fabrication Production Control’ for Onshore Fabrication progress calculation, managed
by Database FAB&MAN
These above-mentioned are univocally linked to the network activities and constitute the
database for updating programs and calculating the progress with a bottom-up approach at
various level of the WBS
.
4.4.5 PROJECT
REPORTING
The system for Progress Reporting will be described through the Procedure “Project Reporting”
and submitted to COMPANY for approval. It will contain proposed Calendar of Cut-Off dates
and formats for Weekly and Monthly Reports to be also approved by COMPANY. It will be
regularly issued by the Project Manager across the whole Project life, in respect of the above
Progress Reporting Calendar. These Reports, whose indexes are approved by the COMPANY,
will contain the Schedules, Curves, Histograms, etc. updated at the established cut-off dates,
together with other narrative and reporting parts, highlights, area of concerns, analyses, and
any specific information that will be agreed through the Project Procedures between SAIPEM
and the COMPANY
CONTRACTOR will prepared and distributed an internal Flow Chart for the purpose of
coordinate the operative sites (FANO/Pipeline & Cable Design, DAMMAM/Onshore Engineering
& Construction and the Fabrication Sites) in the process of consolidating the
Information/Narrative, Graphs (Barcharts/Histograms/Progress Curves),
Consolidated reporting is reviewed within the Weekly Internal coordination meeting on Monday
and approved by the Project Director
Progress “S” Curves
Resources, quantities and weight points are associated to each baseline activity. Weighting of
level 3 an 4 activities will be described in the “Progress Measurement” Procedure and is done
on the basis of contract values, budgeted costs, man-hours or Quantities (steps of progress
linked to specific events), the Baseline Progress ‘S’ Curves are drawn at the contractual
required level of detail.
The Curves are then frozen and represent the reference for the following scored Progress
Values
Resource Histograms
Resource Histograms, Baseline and Actual are produced by discipline in accordance to
COMPANY requested level of detail for Engineering and Onshore Fabrication Phases
4.5 PROCUREMENT
The Project Procurement Manager, as part of CONTRACTOR Project Management Team, will
be responsible for all procurement activities for the Project including:
The timely delivery of the equipment and materials, fully in compliance with project
designs, specifications, quality requirements, and at the construction site fully protected
and properly documented to fully support the construction schedule.
The timely delivery of all Vendor Documentation to allow detailed engineering to proceed
in accordance with the project schedule.
CONTRACTOR will develop Project Procurement Plan describing applicable procurement flow
and procedures.
The Procurement Team will take advantages of the worldwide procurement network that
Saipem have since long time established.
The CONTRACTOR’s general strategy for purchasing will be to competitively bid.
For several Project commodities such as Steel Structures, Piping and Electrical Material, if
proved competitive, it is CONTRACTOR standard Purchasing policy to procure materials on the
basis of what are called Master Agreements or Project Agreements, i.e. pre negotiated price
lists which will allow CONTRACTOR to place actual Purchase Orders without having to pass
through the usual path foreseeing Inquiry/Bidding/Evaluation of Vendors bids.
CONTRACTOR may decide to proceed with single source negotiation. Single source
negotiations and Master/Project Agreements application or will be always carried out in the
respect of contractual requirements such as application of the Regulated Vendor List and Saudi
Manufacturers Participation requirement.
Single source negotiation will be managed on “case by case” basis.
CONTRACTOR will expedite each purchase order in order to control the scheduled, forecast
and actual date. The Project Material Coordinator (PMC) is responsible for checking and
monitoring Expediting and Shipping Departments or Agency performance and inspection.
CONTRACTOR will appoint expediters responsible for the following activities:
carry out the first expediting action in respect of Vendor in order to ascertain that the
order has been received and taken over;
summon and attend the kick-off meetings
request from vendors a detailed construction schedule, check it and when needed
request the necessary changes;
request from vendors of main equipment an up-to date and detailed Monthly Status
Report and progress for each activities (design, procurement, materials manufacturing
and test).
issue on periodic basis the A.S.O (Actual Status of the Purchase Order) to inform the
Project Management about the status of the PO
ascertain that materials are available for shipment and all requested contractual
documents are received. Receive shipping documents and check them for
completeness;
CONTRACTOR PMC will closely monitor expediting reports and will provide instruction in order
to recover or mitigate any delay.
The Quality Procurement Manager will be responsible to organise inspections according to
approved QA/QC plans and contractual obligations.
4.6 CONSTRUCTION
MANAGEMENT
The overall fabrication scope of work for platforms and sealine items will be split among the
three CONTRACTOR fabrication Yards as follows:
FACILITIES DESCRIPTION SAIPEM KARIMUN Indonesia STAR KSA SNAMPROGETTI Fab Yard KSA NOTES ARBI 4 – 5 – 6 – 7 – 8 – 9
WELL HEAD DECKS X X(note)
Some prefabrication will be executed in SnamProgetti Yard ARBI-TP-1 TIE-IN PLATFORM: TOPSIDE X ARBI-TP-1 TIE-IN PLATFORM: JACKET AND PILES
X X(note)
Part of JKT (Boat landing, etc) will be fabricated at SnamProgetti Yard ARBI TP-2 INTERMEDIATE
INJECTION PLATFORM: TOPSIDE
X X(note)
Some prefabrication will be executed in SnamProgetti Yard ARBI TP-2 INTERMEDIATE INJECTION PLATFORM: JACKET X X(note)
Part of JKT (Boat landing, etc) will be fabricated at SnamProgetti Yard ARBI BRIDGE SUPPORT
JACKETS X X(note)
Some prefabrication will be executed in SnamProgetti Yard
ARBI FLARE
X X Will be decided based on
the Yards work-load ARBI BRIDGES
X X Will be decided based on