• No results found

How to Craft a World-Class Work Breakdown Structure

N/A
N/A
Protected

Academic year: 2021

Share "How to Craft a World-Class Work Breakdown Structure"

Copied!
18
0
0

Loading.... (view fulltext now)

Full text

(1)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 1

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice.

How to Craft a World-Class

Work Breakdown Structure

Laura Miller, PMP

(2)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 2

Overview

• Major input to the Work Breakdown Structure (WBS) is the Scope Statement

Project Planning uses the Scope Statement as starting point

WBS is last step in defining Scope

Scope Statement will likely be updated after full WBS and Schedule creation

• The Scope Statement

Puts boundaries around the project (i.e., what’s “IN” and what’s “OUT”)

Includes description, high-level deliverables, key milestones, success criteria,

assumptions, constraints

• Work Breakdown Structure:

Sub-divides the project objective into smaller, more manageable components

Gives clear view of the work required and organizes the work activities

Serves as a basis for estimating, assigning resources, and managing/controlling the work

(3)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 3

•Please provide a benefit for building and/or using a WBS

What are the benefits of a WBS?

(4)

Benefits

• Helps to determine sequence of work

• Clarifies responsibility and assignment of work

• Creates a baseline to measure performance

• Provides an excellent tool for communication to the stakeholders

• Ensures the scope of work is covered

• Assists in controlling change

(5)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 5

Examples

Approaches

WBS Decomposition

• WBS needs to convey the decomposition of work

Can be in prose, outline form

Can be graphical in an org or hierarchical tree chart

• Generic Levels in WBS

1.0 = Project name

1.x = Subsystems or Phases

1.x.x = Major deliverables

1.x.x.x = Sub-deliverables

1.x.x.x.x = Work Packages

• Each work package has a unique identifier

• Process or Activity-Oriented

By different activities or flow

E.g., Needs Analysis, Purchasing, Testing

• Achievement-Oriented

By final state to meet objectives

E.g., Acceptance of System per Plans

• Function or Product-Oriented

By different parts of final product

(6)

Group Input

What approaches have you used to build WBS?

Has anyone used achievement-oriented approach?

Has anyone used function or product-oriented approach?

Has anyone used process or activity-oriented approach?

(7)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 7

Real-life Example

1. Business Objective: Modernize the kitchen

Description: Meet current building standards for electrical, plumbing, and HVAC. Update all fixtures and appliances.

2. Business Objective: Facilitate meal preparation

and flexibility of meal delivery

Description: Ensure 2 persons can work in the kitchen at the same time to prepare meal and can streamline delivery of meals for dining

3. Business Objective: Manage within the specified

budget

Description: Make design and execution decisions such that cost does not exceed 10% of appraised value of residence

Project Scope Objectives

Which Approach could be Selected?

• Process or Activity-Oriented

– By different activities or flow

– E.g., Needs Analysis, Purchasing, Testing

• Achievement-Oriented

– By final state to meet objectives – E.g., Acceptance of System per Plans

• Function or Product-Oriented

– By different parts of final product – E.g., Hardware, Software, Data, Service

(8)

Real-life Example

Project Scope Objectives

WBS Outline

1. Business Objective: Modernize the kitchen

Description: Meet current building standards for electrical, plumbing, and HVAC. Update all fixtures and appliances.

2. Business Objective: Facilitate meal preparation

and flexibility of meal delivery

Description: Ensure 2 persons can work in the kitchen at the same time to prepare meal and can streamline delivery of meals for dining

3. Business Objective: Manage within the specified

budget

Description: Make design and execution decisions such that cost does not exceed 10% of appraised

(9)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 9

Example, con’t

9

WBS Graphical Tree

Levels in WBS

1.0 = Project name

1.x = Subsystems/Phases

1.x.x = Major deliverables

1.x.x.x = Sub-deliverables

1.x.x.x.x = Work Packages

(10)

Let’s Practice

In Visio – decompose your scope to work packages

(11)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 11

Considerations

Sequencing

Ordering:

• Put list of activities in logical order

• Consider when the tasks should start, should be completed, or should be worked on • Check the sequence and determine if something isn’t flowing correctly and rework it

– Not only logical, but consider what is feasible and desirable

– E.g., Task # 5 starts before task # 4 is completed because it’s more feasible Constraint:

• What is keeping tasks from being started at the same time or finishing on time?

– E.g., Resource availability, Client timing for delivery of product, Certain manufacturer on short-list Dependency:

• How are tasks related and dependent on one another?

– E.g., Can task #3 get started before task #2 ends or is it dependent on task #2 being completed? • Use a network diagram to show dependency relationship, using arrows /lines to show connections

(12)

Sequencing, con’t

Example & Discussion

Click over to view the Visio of the PAINT WBS and answer the following questions. Ordering:

• What are examples of ordering on our PAINT WBS example? Constraint:

• What might keep PAINT tasks from being started or finishing on time? Dependency:

• What are examples of dependent PAINT tasks?

• Can you identify different types of dependencies? (FS, SS, FF) • What type of dependencies exist to tasks in other WBS towers?

(13)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 13

Considerations

• Duration is the time elapsed to complete the task; typically in days

• Effort is the number of hours the task will take for the assigned resource to expend

− E.g., 9 hour effort task will take 3 days in duration to complete since resource is assigned only 33% because has assignments on other tasks/projects

• Typically, consider a 5-day work week and not a 7-day calendar week or holidays for duration

− Scheduling software can be set to remove non-workdays from the calendar

Estimating

Types of Project Estimating

1. Top Down Estimating: high level estimating by comparing similar projects. 2. Bottom Up estimating: estimates at the work package level from start to finish

3. Quantitatively based estimates: based on productivity rates for a repetitive type of task As the PAINT team lead - What method of estimating would you recommend?

How could you use the other methods?

(14)

WBS Build Challenges

• When drafting initial Scope Statement, PMs are often asked to provide project-related estimates − Dates for key milestones or deliverables

− Level of required resources

o Capital / Equipment o Personnel

• Need to estimate dates and resource loads before detailed planning can begin

• Need to start project when latter phases on project not known or not yet funded

• Plan in detail only what you really know for certain through a period of time, i.e. “planning horizon” • Use placeholders to convey the major deliverables

or phases – just not the decomposition

• Additional detail is added to schedule at key points in time

• Cross industry term: “Planning Package Conversion” • Repair any breaks in scheduling standards

• Set a new Baseline

(15)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 15

• Document generated to support the WBS

• Provides a detailed description of the WBS components and assists in providing a further clarification of work, to help set expectations for stakeholders.

• It can include:

• Identifier and Component Name • Description of Work

• Resource

• Could also include:

• Milestones • Estimates • Organization Information • Quality Requirements • Acceptance Criteria • Related Activities

• Need to validate the value of creating one • Some software creates this for you

• Helpful on very large projects

WBS Dictionary

(16)

Snapshot of Project Schedule

Next Step with WBS

In MS Project – look how the “Renovate Kitchen” WBS is portrayed

Scheduling Standards include:

• Be consistent in the WBS Decomposition

• Predecessors, successors, resources & costs are applied only to Work Packages • There should be only one task without predecessor; one task without successor • Milestones are zero duration and can be the phase’s tasks successor

What are the key things to remember to do when building a WBS?

(17)

© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. 17

Guidelines

WBS Points to Remember

• Involve team members

• Use appropriate and sufficient collaboration tools

• Complete decomposition at one level before drilling down to next level

• Evaluate lowest level and verify that together, they accomplish the next level up

• Create milestones that convey a completed deliverable

• Zero Duration

• Phrase as statement of fact

• Create work packages to be easily assigned and estimated

• Best practice = 8 hours < work package < 80 hours

• Phrase as “Verb-Object” to convey activity

(18)

THE END

References

Related documents

To capture the traditional spiritual power of the Bozhe agents that is highly revered and honored by the Sabat Bet Gurage peoples, sheyikh Budalla seemed to have

The assortativity coefficients (r) are displayed. Plots of the normalized clumpiness coefficient of the 19 cubic regular graphs for the different values of α. Four classes of

Joseph Establishes T hes Tenant Laws enant Laws 2 Then Joseph said unto the people, Behold, I have bought you this day and your land for Pharaoh: lo, here is seed for you, and

Ethernet Modbus TCP OPtima Operator Station MACO Compact Racks Total Machine Control Chassis - 4 Slot Backplane - Closed Cover Temperature Card.. - Adaptive Autotune Temperature -

microscopy pictures A: Entire pronotum of male in dorsal view, insert showing frontal view of anterolaterl edge.. B: Entire pronotum of female in

interpreted the italicized language to mean that, even when the patent owner fails to introduce admissible evidence quantifying the amount of its loss, the court

coordinating preparations of proposals; extensive experience in planning, evaluating, directing, and coordinating and executing life cycle management of engineering and

While the following attempts to communicate the traditional physical demands associated with this position, Buckle will consider varying such requirements whenever necessary