• No results found

Module 10 - Managing Construction and Completions PowerPoint Presentation_Rev1

N/A
N/A
Protected

Academic year: 2021

Share "Module 10 - Managing Construction and Completions PowerPoint Presentation_Rev1"

Copied!
102
0
0

Loading.... (view fulltext now)

Full text

(1)

Welcome to WorleyParsons Project Management

Process (WPMP) Training

(2)

Introduction

 Welcome  Safety Moment  Emergency Procedures  Introductions  Learning Objectives  Learning Outcomes

 Agenda—Module 10 Construction Management and Completions

(3)

Introduction

On completion of this module, you will have:

 A basic understanding of what the Construction and Completions

functions provide to complete an EPCM project

 An understanding of the methodologies and tools that will enable

you to work with Construction and Completions to successfully deliver a project

(4)

Introduction

 Understand the reasons for requiring Construction and

Completions involvement early in project planning & TIC Estimate

 Plan and incorporate constructability reviews and construction

lessons learnt into project design and contracting

 Address design strategy opportunities for design standardization,

modularization and pre-assembly

 Understand typical Construction and Completions organization

charts and associated roles and responsibilities On completion of this module, you will be able to:

(5)

Introduction

 Have a basic understanding of the key processes used by

Construction and Completions

 Understand the needs of Construction, including AFC drawings

and materials being available on time, and how this determines Engineering and Procurement priorities

 Have a basic understanding of the typical progress reporting

provided by Construction and Completions

 Understand the importance of HSE in Construction and

On completion of this module, you will be able to: Learning Outcomes (continued)

(6)

Agenda

 Introduction

Overview

 Roles and Responsibilities

 Project Planning

 Constructability and Commissionability

 Site Organizations and Resource Management

 Communication and Team Work

 Issue Resolution

 Quality Management

(7)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

(8)

Overview

 What is Construction

 What is Completions

(9)

Agenda

 Introduction

 Overview

Roles and Responsibilities

 Project Planning

 Constructability

 Site Organization and Resource Management

 Communication and Team Work

 Issue Resolution

(10)

Roles and Responsibilities

 Establish management processes and controls that result in a

successful project

 Responsible for total project delivery

(11)

Roles and Responsibilities

 Safety Management and promotion of HSE culture

 Construction Management Planning

 Cost Management

 Time Management

 Quality Management

 Contract Administration

(12)

Roles and Responsibilities

 Safety Management and promotion of HSE culture

 Completions Management Planning, Development & Execution

 Cost & Time Management

 Quality Management

 Site Operator Interfaces

 Site Administration after Construction

 Operator training

 Interim Facilities Turnover to the Customer/Operator, pending formal project Turnover by the Project manager

(13)

Agenda

 Introduction

 Overview

 Roles and Responsibilities

Project Planning

 Constructability

 Site Organization and Resource Management

 Communication and Team Work

 Issue Resolution

(14)

Project Planning

 The project schedule should be driven from the back end

 Early Construction and Completions involvement is absolutely

necessary

 Project WBS must meet with the minimum Contracting and

Construction requirements

 Identify issue of key deliverables

(15)

Project Planning

 Construction Manager completes pre-mobilization details with

Construction Team

 Project and Construction Managers ensures that the Construction

team do not mobilize too early

 Project and Construction Managers ensure that the mobilization

plan is based on an assured flow of ongoing work

(16)

Project Planning

 When do you hold a pre-mobilization meetings

 What are the Project Manager’s responsibilities

(17)

Project Planning

 What is the difference between Brownfield vs Greenfield

construction projects

 What expected delays on Brownfield projects may influence

the estimate

(18)

Project Planning

 Environmental impact of job

 Successful scheduling

 Site safety

 Availability of materials

 Logistics (road transport, shipping schedules, resources, etc)

 Inconvenience to public caused by construction delays

 Preparing tender documents

(19)

Project Planning

Construction Manager is responsible for:

 Completing construction preliminary planning

Keeping Project Manager informed about issues and progress

Making recommendations to Project Manager where issues

and needs may impact on planning by other disciplines

 Documenting the outcome of preliminary planning in a

Construction Management Plan (CMP)

(20)

Project Planning

Detailed Construction Planning

Issue to project team Customer approval

Revise at Approved for Construction (AFC) stage

EX ECU TE Review CMP D EFINE Draft CMP

(21)

Project Planning

As Project Manager you are responsible for:

 Ensuring CMP is prepared according to overall project

requirements

 Reviewing and approving the CMP

 Issuing the CMP to the customer

(22)

Project Planning

 Reviewing Construction Management Plan (CMP)

 Determining responsibilities at the site—Customer and other

stakeholders

 Reviewing Mobilization Plan and considering the support services

requirements for mobilization

 Reviewing the Contracts Plan and confirming the contracts strategy

 Determining the project layout for all temporary facilities

 Obtaining necessary licenses and permits

(23)

Project Planning

 Establishing utilities for and at the site

 Establishing facilities at the site—for example, transport and

storage, accommodation, sanitary arrangements, fire and other hazard protection

 Developing site administration procedures

 Developing a HSE plan for the site

 Setting up site offices and services

(24)

Agenda

 Introduction

 Overview

 Roles and Responsibilities

 Project Planning

Constructability

 Site Organization and Resource Management

 Communication and Team Work

 Issue Resolution

 Quality Management

(25)

Constructability

 Ensures that BOD covers all construction cases i.e. Fabrication

location, transportation and installation techniques

 When is Construction Team input required in a project

 What questions does constructability address

Can it be constructed and how best to do it efficiently

Can it be maintained

Can it be operated

Construction Team Input into Execution Planning and

Design

(26)

Constructability

 Safety, including safety in design

 Interfaces with operations and other contracts

 Ability to pre-assemble as much as possible off site or on the ground prior to erection  Installation access  Transportability  Ease of construction  Standardization  Ease of Commissioning

Constructability Reviews

(27)

Constructability

 Cost effectiveness

 Fabrication, Installation and Completions methodologies to reduce schedule

 A check that design cases cover ‘Construction Phases’ as appropriate

and not just operating conditions

(28)

Constructability

 Inputs to ALL Plans including BOD and project schedule

 Specific constructability checklists across all functions, scope and

disciplines

 Action lists for changes to design and procurement

 Early planning for proper activity sequencing including

Completions

 Identifying any unusual factors affecting construction

 Identifying any unusual costs not identified by normal estimating

methods

(29)

Constructability

 Identifying staffing requirements, facilities, warehousing,

documentation, information flow, quality, safety, cost and schedule

 Identifying heavy lift/rigging plans requirements and development

of cost options for major and complex lifts

(30)

Constructability

 Methodology – Pre-assembly

 Methodology –modularization

 Early definition

 Module grade levels

 Module configuration

 Module sizing

 Module contents

(31)

Constructability

 What are five examples of benefits that constructability gives to a

project?

 What would each benefit mean for a project’s schedule and costs?

(32)

Agenda

 Introduction

 Overview

 Roles and Responsibilities

 Project Planning

 Constructability

Site Organization and Resource Management

 Communication and Team Work

 Issue Resolution

 Quality Management

(33)

Site Organization and Resource Management

 Mechanical / Piping / Structural Superintendent

 Electrical and Instrumentation Superintendent

 Civil and Earthworks Superintendent

 Scaffolding Superintendent

Site Organization – Roles

The organization structure is dependant on the size, contracting strategies and complexity of the project and may differ than what is typically shown in the charts

 Document Controller

 Field Engineering

 QA/QC Inspector

 Senior Planner/Scheduler

 Senior Cost Engineer

(34)

Sample Project Organization Chart

Comm Org Chart Const Org Chart WorleyParsons Project Sponsor Customer Project Manager Project Quality Manager Administrative Assistant

HSE Manager Procurement Manager Project Engineer Manager Engineering Manager Construction Manager Project Controls Manager Commissioning Manager Lead Cost Engineer Prime Contract Administrator Lead Planner Lead Estimator Project Accountant Purchasing Supervisor Materials Management Supervisor Vendor Inspection Coordinator Contracts Supervisor MCS Supervisor Lead Document Controller WorleyParsons Project Manager

(35)

Sample Construction Site Organization Chart Project Controls * Construction Manager Construction Management HSE Manager * Construction Engineering * Construction Inspection * Contract Administration * Contracts Administrator Contracts Engineers Cost Eng Planning Eng Estimating Eng Reports Eng Superintendents Supervisors ? Civil ? Structural ? Mechanical Resident Engineer Field Engineers Document Control Site Services * Project Quality Manager Materials Management * Project Manager Materials Controller Warehouse Field Purchasing Office Services Human resources Industrial Relations Accounting Safety Advisors Training Security Environment Community Inspectors ? Civil ? Structural ? Mechanical ? Electrical ? Instrumentation

(36)

Sample Completions Site Organization Chart Completions Manager Commissioning Superintendent Permit To Work Coordinator Handover/ Turnover Coordinator Punchlist Coordinator Commissioning Planner Senior Commissioning Discipline Technicians Commissioning Discipline Technicians Operations Representative WorleyParsons Project Manager Commissioning Engineer -Electrical -Instrument -Process -Mechanical Completions Manager Commissioning Superintendent Permit To Work Coordinator Handover/ Turnover Coordinator Punchlist Coordinator Commissioning Planner Senior Commissioning Discipline Technicians Commissioning Discipline Technicians Operations Representative WorleyParsons Project Manager Commissioning Engineer -Electrical -Instrument -Process -Mechanical

(37)

Site Organization and Resource Management

 Construction Staffing Plan

Preliminary plan to be developed at FEED to form basis of CM Labor estimate

Project, Construction and HR Managers to formulate proposed construction organization resource plan

 Obtaining suitably experienced staff, subcontractors

Project, Construction, Procurement and HR Managers to source

 Demobilization

(38)

Agenda

 Introduction

 Overview

 Roles and Responsibilities

 Project Planning

 Constructability

 Site Organization and Resource Management

Communication and Team Work

 Issue Resolution

 Quality Management

(39)

Communication and Team Work

 As a Project manager encourage a Positive project culture

 Mutual trust and team respect

 Team work

Coordination

Cooperation

Communication

Compromise, and

(40)

Communication and Team Work

 Ensure Construction and Completions Managers are included in

key project meetings

 Project meetings to be held on site at regular intervals during

Construction phase

 Have engineering spend time on the construction site to conduct

follow on engineering

 Have a well-defined and adequately resourced Field Engineering

group to manage on-site engineering queries linking back to the Home Office

 Construction and Completions to be included in project team

Home Office and Site Office Communication and

Teamwork

(41)

Communication and Team Work

 Regular on-the-job meetings

 Ensure work is organised according to schedule

 Ensure that the Site logistics plan supports all phases of the

project

 Monitoring and expediting the processing of shop drawings,

samples and other submittals for approval in a timely manner

Coordination

Your role as Project Manager is to provide support and guidance to the Construction and Completions Management Teams

(42)

Communication and Team Work

 Settling money issues promptly

 Submission of progress and final payment applications using the

contract’s established procedure

 Communications between the Construction Contractor and the

Engineer is being facilitated through WorleyParsons

 Nurturing relationships being conducted between WorleyParsons

Construction Management Team and Construction Contractors’ authorized representatives

Cooperation

(43)

Agenda

 Introduction

 Overview

 Roles and Responsibilities

 Project Planning

 Constructability

 Site Organization and Resource Management

 Communication and Team Work

Issue Resolution

(44)

Issue Resolution

 What is the effect of saving up issues for resolution later

Problem

 What should Project Managers do about resolving issues

(45)

Agenda

 Introduction

 Overview

 Roles and Responsibilities

 Project Planning

 Constructability

 Site Organization and Resource Management

 Communication and Team Work

 Issue Resolution

(46)

Quality Management

 Project procedures

 Quality processes used at project level

 Continuous improvement

 Audit program

(47)

Quality Management

 Reporting deficiencies that may affect delays in completion of work

 Issuing of Non-conformance Reports and Corrective Action

Requests to the Construction Manager

 To accurately reflect the project Quality Plan expectations and

desired outcomes

Construction Contractor’s Responsibilities for Quality

Control

(48)

Quality Management

 Ensures the status of inspection and test is known at all times

 Provides documentary evidence of the satisfactory completion of

required tests

(49)

Quality Management

 Checklists provide a verification record of a test

OR

the completion status prior to a non-reversible step

 An inspector produces a Defect List when they find defects or

requirements for rework

(50)

Quality Management

 A Construction Contractor may request inspection clearance from

the Site Inspector

 Where the inspector finds defects a punch list must be attached to

the Inspection Release Certificate

 Punch list

Can only be cleared by the site supervisory team and forms

part of the contract quality records

Indicates the category of the punch list items and dates by

which they will be completed

(51)

Quality Management

 Construction Contractors must provide a Manufacturer’s Data

Report (MDR)

 MDR contains

Documentary evidence of inspection and test activities

‘As-built’ status of work

Compliance status with relevant standards, codes and

specifications

(52)

Agenda

 Introduction

 Overview

 Roles and Responsibilities

 Project Planning

 Constructability

 Site Organization and Resource Management

 Communication and Team Work

 Issue Resolution

 Quality Management

(53)

Protocols for Construction Site Visits

 Is project-specific and covers legalities and that Customer requirements are addressed and who controls security and access

 Oversees project security measures

 Is reviewed by WorleyParsons Executive Project Management and the Customer

 Ensures that correct Inductions and Orientations are conducted i.e.

Permanent Construction Personnel

Visitors

(54)

Protocols for Construction Site Visits

 Minimum PPE requirement

Safety boots

Hard hat

Safety glasses

Long trousers

Long sleeve shirts

High visibility vest or clothing

 Additional PPE requirement

Mono-goggles

Gloves

Hearing protection

Fire retardant clothes

(55)

Agenda, continued

Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

(56)

Health, Safety and Environment (HSE)

 Safety is the Number One Concern of Construction work as it is

conducted in high risk areas

 Zero Harm applies to all projects

 Promotion of safety culture

(57)

Health, Safety and Environment (HSE)

 Risk analysis

Project Risk assessment

Construction Risk Assessment

Job hazard Analysis (JHA)

 Contractor selection

Based on proven safety commitment and performance

Documented proof of a Company Health and Safety Program

Development of a Project specific OHS&E Management Plan

(58)

Health, Safety and Environment (HSE)

 Other strategies

Safety in design

Plans and preparation for emergency conditions

Periodic controlled audits on performance

Quick and firm response if sub-standard performance found

Recognition of safety performance and commitment

Follow-up of OSH&E performance at contract close-out

 Proactive involvement of key Construction Contractors

Involve Contractors in regular on site HSE meetings

(59)

Health, Safety and Environment (HSE)

 Training and Inductions of Contractor personnel

 Site Safety policies and Procedures

Develop a written safety policy of commitment to national and

state safety laws and regulations

Produce a comprehensive suite of safety procedures for use

on site

Ensure that adequate safety equipment is available

(60)

Health, Safety and Environment (HSE)

 Ensure a positive culture of relationships and communication by:

Early analysis of project scope to identify key risk areas

Early involvement of key Construction Contractors

Clear communication of safety approach, programs, roles and responsibilities

HSE incident reporting

Regular Job Start meetings

Toolbox meetings

Job Hazard Analysis (JHA), Safe Working Instructions

Take 5

Continuous Improvement activities

Site notice board

(61)

Health, Safety and Environment (HSE)

 Project Environmental Plan

All personnel are responsible for environmental observance

and accountability

 Impact of unforeseen environmental problems

Ensure contingencies are in the budget for unforseen

problems

Resolve issues expediently

Insurance concerns and project lenders liabilities

(62)

Agenda, continued

 Health, Safety and Environment (HSE)

Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

 Change Management

(63)

Industrial Relations

 What is the purpose of the Industrial Relations (IR) Strategy

To manage Industrial relations during Define and Execute phases to minimize time lost due to Industrial disputes

The Industrial Relations must be jointly managed by the Project and Construction Managers throughout the Project lifecycle

 What are the requirements of the IR Plan

Where there is a need to have one within a project area

To reflect our global requirements of managing IR

That it be a sub-section of the PEP

 Who is in the IR Team

(64)

Industrial Relations

 Jointly responsible for policies, procedures and principles

contained in the IR approach with the Construction Manager

 Workplace consultative committees

Management of Construction Contractor Industrial

Relations

(65)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

(66)

Risk Management – Construction

 Risk Management Workshops

Ensure that both Construction and Completions participate to

capture activity risks

 Planning and review process

The process to capture all activities so that they can be

performed in a safe and timely manner

All activities should be aligned with the OneWay to Zero Harm

philosophy

(67)

Risk Management – Construction

 Maximize Customer satisfaction

 Minimise risk

Contractual/commercial exposures such as process and

performance guarantees, warranties, liabilities

Labor productivity risks for lump sum projects

Supervisory quality

Staff availability, morale, competency, retention

HSE & security

(68)

Risk Management – Construction

The hierarchy of control is the systematic strategy used to:

 Elimination

 Substitution

 Engineering

 Administration

 Personal protection equipment

(69)

Health, Safety and Environment (HSE)

 Continuous education and training in safety and safety awareness

 Strict safety requirements and experienced safety supervision

 Regular safety inspections and audits to verify compliance

 Requirements of the Construction Safety Case

 Requirements of Operational Safety Case

 Permit to Work System (requires Permit Holders)

(70)

Health, Safety and Environment (HSE)

 Excavation Procedure

 Works executed under an approved Work Instruction

 Construction HAZID Workshops and Risk Analysis Workshops

 Customer presence for tie-ins and shutdowns.

 Close interaction between construction and commissioning phases

(71)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

Construction and Field Procurement

 Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

(72)

Construction and Field Procurement

 Market conditions

 Division of work

 Project Schedule (and other KPIs)

 Quality of scope definition

 Customer staffing model for the project

(73)

Construction and Field Procurement

 Lump sum

 Reimbursable

 Cost plus fixed fee

 Unit rate

 Mixed strategy

 Day work

(74)

Construction and Field Procurement

 Key decisions and operational directions

Construction Manager participates in key decision and

operational directions including assisting in the compilation of SoW, Tender reviews and Construction Contractor selection

 Site requisitions

These are primarily used where a service is not covered by a

project office issued contract or purchase order

 Program for site purchasing

The Project Procurement Management Procedure will confirm

the limits set for site purchases

(75)

Construction and Field Procurement

 Materials Management

Inspection and expediting

Materials receipt, quality control and inspection, identification

and resolution of deviations, item identity/tagging, and quarantine

Warehousing

Issue control

Material reconciliation

MARIAN

(76)

Construction and Field Procurement

 The construction team administer the construction Contractors

activities on site

 Vendor representations

Construction and Completions interface with Engineering

office to establish vendor timing to site and arrange visit via Procurement

► Contracts placed by the Customer

• Encourage a Customer to relinquish control of the Contractor

for the full duration of the Contract

(77)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

(78)

Construction Control and Reporting

 Construction progress against the budget and schedule

 Contractor reporting of all contracts involving works at a

construction site

(79)

Construction Control and Reporting

 Construction KPIs

Meet project health and safety requirements

Meet project schedule

Meet project budget

Meet project quality objectives

Minimize environmental impact during construction

Minimize inconvenience to local community and landowners

Meets the Customers expectations

(80)

Construction Control and Reporting

► Construction Forecasts

Baseline schedule is used to monitor progress

Schedule critical paths is update weekly

► Contractor Performance Measurement

Earned hours by task are calculated by the actual progress

achieved

Performance against the budget is monitored comparing

actual vs earned hours

(81)

Construction Control and Reporting

 Report Format

Reports must follow format as agreed between the Project Manager and the Customer

 Construction Site Reports

Safety Incidents, near misses and hazard identification

Progress, summary of activities, key deliveries at site

Details about these reports are listed in the Progress Measurement Construction Guideline, PCP-0005

Numbers of personnel on site, broken down by Construction

Contractor and construction work, supplier, material and equipment

Areas of concern

(82)

Construction Control and Reporting

 Construction Project Meetings

Construction Contractor progress meetings are convened

weekly

Shorter duration projects may require meetings twice a week

Project Manager should attempt to participate in progress

meetings at least once per calendar month.

Agenda

Minutes

(83)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

Document Management

 Completions – Commissioning and turnover to the Customer

(84)

Document Management

 Specific constructability checklist

 Construction Management Plan

 HSE Management Plan

 Environmental Management Plan

 Drawings

(85)

Document Management

 Formal, documented procedure

 Procedure covers receipt, issue, transmittal and recording of

drawings, specification and other documents

 Includes documents issued to or received from Contractors

 Documents must be uniquely numbered and registered

 Document Controller is responsible for document management

and control

(86)

Document Management

 A document and drawing library must be maintained at the

Construction site office

Document Review and Sign-off

Document Control Registers

 Document Control Registers must be maintained for all drawings,

(87)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

 Document Management

Completions – Commissioning and turnover to the Customer

(88)

Completions – Commissioning and turnover to the Customer

 Pre-commissioning is now referred to as Commissioning Stage 1

Historically referred to as pre-commissioning

 Commissioning has four stages

Commissioning Stage 1 — Mechanical Completion

Commissioning Stage 2 — Function Testing

Commissioning Stage 3 — System Commissioning

Commissioning Stage 4 — Start-up and Ramp-up

(89)

Completions – Commissioning and turnover to the Customer

 Commissioning Stage 1 – Mechanical Completion

Features of this phase will include:

Single discipline activity.

Static or un-energized checking of equipment and components to ensure specification compliance and correct installation.

Includes device installation checks.

Calibration checks.

Includes cable insulation and continuity checks.

Includes motor rotation checks using rotation instruments

Piping hydro-testing (usually completed in the fabrication yard) and flushing.

(90)

Completions – Commissioning and turnover to the Customer

Preparation of site teams for introduction of power and upcoming live plant testing.

First fill lubrication of equipment

Alignment checking

Preservation and warehousing.

Acceptance of Red line As Built Documents.

Inspection, agreement of the Mechanical Completion Punch List.

Entry of all punch list items into CMT.

(91)

Completions – Commissioning and turnover to the Customer

 Commissioning Stage 2 – Function testing

Single discipline activity.

Energized function testing.

Completions phase Permit to Work system is in place.

Inspection and agreement of the Stage 2 Punch List.

Entry of all punch list items into CMT.

(92)

Completions – Commissioning and turnover to the Customer

Customer Operations participation in these activities is now mandatory

 Commissioning Stage 3 – System commissioning

Transformation from static checking to live testing

Dynamic testing of complete systems and sub systems

Completions and placing into service the utility systems.

Confirmation that systems are ready to start up or accept

product

Inspection and agreement of the Stage 3 Punch List

A Pre-Start Safety Review (PSSR)

Entry of all punch list items into CMT.

(93)

Completions – Commissioning and turnover to the Customer

All work will be completed by system or area previously identified and included in the completions schedule

 Commissioning Stage 4 – Start-up and ramp-up

Introduction of product (or inert medium, followed by product)

Start up and ramp up to operating operational status

Inspection and agreement of the Stage 4 Punch List

Entry of all punch list items into CMT

Turnover of process systems

(94)

Completions – Commissioning and turnover to the Customer

Completions, continued

Operation & Performance Testing

Interim Turnover to the Customer

Interim Facilities Turnover

(95)

Completions – Commissioning and turnover to the Customer

► Commissioning and Turnover Documentation

Facilities Turnover Meeting MOM

Turnover Certificates

Facilities Turnover Punch List

Commissioning Dossier

Outstanding Works Plan

Site Administration Records and Reports

Deliverables as per Commissioning Execution Plan

(96)

Completions – Commissioning and turnover to the Customer

 Management of mechanical completion and function testing

activities and interfaces between various stages

 CMT selected during BOD and implement during FEED

 Selection of CMT depends on size and complexity of project and

Customer preference

(97)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

(98)

Change Management

 Approved procedures are in place and personnel are trained

 Compliance to procedures

 Construction Team are integrated into Management of Change

process

(99)

Change Management

Management of Project Change Procedure <insert hyperlink to

PCP-0010>

Site Queries Procedure <insert hyperlink to FCP-0016>

Site Based Contract Administration Procedure <insert hyperlink

to FCP-0011>

Key Procedures

(100)

Agenda, continued

 Health, Safety and Environment (HSE)

 Industrial Relations

 Risk Management – Construction

 Construction and Field Procurement

 Construction Control and Reporting

 Document Management

 Completions – Commissioning and turnover to the Customer

 Change Management

(101)

Summary and Feedback

 Review Learning Objectives and Outcomes

 Summary – review topics

 Questions

(102)

Module 10 Managing Construction and Completions

References

Related documents

&#34; Now you can start drawing generation for main positions by clicking the button Apply (in the dialog window Automatic &lt; Outputs on the right

Metode ini menyajikan dua buah grafik yang disebut spektrum, yaitu spektrum kapasitas (capacity spectrum ) yang menggambarkan kapasitas struktur berupa

Hugh play of light and shadow contrast in the luminaire Inside of leaves white on all metal versions of the luminaire Frosted glass leaves combines luminance with reflection

From the perspective of this Reference Architecture, a portal providing information and functionality to a patient is no different to any other consumer of health information –

and phone number: Mailing address: Website: SIC Code &amp; Description of Operations (including how company generates revenue): Federal Tax ID: Annual revenue: Year

case study community could balance local demand with different renewable energy supply- 278. side

The variables included in the multiple imputation model to estimate the outcome (delivery or not) were the IVF unit, the woman’s age at the aspiration date, the number of

The rates in term of n are known to be the optimal one for the deconvolution with known error (see Fan (1991) and Butucea (2004)).. Extending the proof of Neumann (1997), we can