Using the Advancement Degree of Difficulty (AD 2 ) as an input to Risk Management

N/A
N/A
Protected

Academic year: 2021

Share "Using the Advancement Degree of Difficulty (AD 2 ) as an input to Risk Management"

Copied!
16
0
0

Loading.... (view fulltext now)

Full text

(1)

James W. Bilbro

JB Consulting International Huntsville, AL

Management

Multi-dimensional Assessment of Technology Maturity Technology Maturity Conference

Founders Inn & Spa, Virginia Beach, VA September 8-12, 2008

(2)

4. TITLE AND SUBTITLE

Using the Advancement Degree of Difficulty (AD2) as an input to Risk Management

5a. CONTRACT NUMBER 5b. GRANT NUMBER

5c. PROGRAM ELEMENT NUMBER

6. AUTHOR(S) 5d. PROJECT NUMBER

5e. TASK NUMBER 5f. WORK UNIT NUMBER

7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES)

JB Consulting International,4071 Panorama Dr. SE,Huntsville,AL,35801

8. PERFORMING ORGANIZATION REPORT NUMBER

9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 10. SPONSOR/MONITOR’S ACRONYM(S)

11. SPONSOR/MONITOR’S REPORT NUMBER(S)

12. DISTRIBUTION/AVAILABILITY STATEMENT

Approved for public release; distribution unlimited

13. SUPPLEMENTARY NOTES

See also ADM002183. Presented at the Technology Maturity Conference held in Virginia Beach, Virginia on 9-12 September 2008. U.S. Government or Federal Rights License.

14. ABSTRACT

15. SUBJECT TERMS

16. SECURITY CLASSIFICATION OF: 17. LIMITATION OF

ABSTRACT

Same as Report (SAR)

18. NUMBER OF PAGES

15

19a. NAME OF RESPONSIBLE PERSON a. REPORT

unclassified

b. ABSTRACT

unclassified

c. THIS PAGE

unclassified

Standard Form 298 (Rev. 8-98) Prescribed by ANSI Std Z39-18

(3)

Academy of Program/Project & Engineering Leadership

2

Advancement Degree of Difficulty (AD2) is a method of systematically dealing with aspects beyond TRL.

It is a “predictive” description of what is required to move a system, subsystem or component from one TRL to another.

It provides information in the form of:

• Liklihood of occurrence of an adverse event. Risk

• Cost to ensure that such an event does not occur.

• The time required to implement the necessary action. Impact

(4)

Academy of Program/Project & Engineering Leadership

3

• AD consists of a set of questions in 5 specific areas:

– Design and Analysis – Manufacturing

– Software Development – Test

– Operations

• The questions are asked about each element in the product WBS structure from the top level system down to the

individual component.

• The questions are not directed toward the element itself, rather toward the issue of:

– Do you have the resources – people, skills, tools, facilities, etc. to design, manufacture, test and operate it?

(5)

5-41140

The levels of risk associated with AD

2

are described in terms of the experience base of the developers.

i.e., have they done this before?

(6)

5-41140

Requires new development outside of any existing experience base. No viable approaches exist that can be pursued with any degree of confidence.

Basic research in key areas needed before feasible approaches can be defined.

Requires new development where similarity to existing experience base can be defined only in the broadest sense. Multiple development routes must be pursued.

Requires new development but similarity to existing experience is sufficient to warrant comparison in only a subset of critical areas.

Multiple development routes must be pursued.

Requires new development but similarity to existing experience is sufficient to warrant comparison on only a subset of critical areas. Dual development approaches should be pursued in order to achieve a moderate degree of confidence for success. (desired performance can be achieved in subsequent block upgrades with high degree of confidence.

Requires new development but similarity to existing experience is

sufficient to warrant comparison in all critical areas. Dual development approaches should be pursued to provide a high degree of confidence for success.

Requires new development but similarity to existing experience is

sufficient to warrant comparison across the board. A single development approach can be taken with a high degree of confidence for success.

Requires new development well within the experience base. A single development approach is adequate.

Exists but requires major modifications. A single development approach is adequate.

Exists with no or only minor modifications being required. A single development approach is adequate.

9 8 7

1 2 3 4 5 6

90%

80%

70%

0%

10%

20%

30%

40%

50%

RISK

(7)

Academy of Program/Project & Engineering Leadership

(8)

Academy of Program/Project & Engineering Leadership

(9)

*De Meyer, et al Relating AD2 to Project Uncertainty: from Variation to Chaos*

Variation:

Cost, time and performance levels vary randomly, but in a predictable range.

Foreseen Certainty:

A few known factors will influence the project but in predictable ways.

Unforeseen Uncertainty:

One or more major influence factors cannot be predicted.

Chaos:

Unforeseen events completely dominate the project’s target, planning and approach.

(10)

Academy of Program/Project & Engineering Leadership

(11)

Academy of Program/Project & Engineering Leadership Level Likelihood Probability of Occurrence

1 Not Likely ~10%

2 Low Likelihood ~30%

3 Likely ~50%

4 Highly Likely ~70%

5 Near Certainty ~90%

DOD Likelihood Descriptions

Relating AD

2

to a 5X5 Risk Matrix

(12)

Academy of Program/Project & Engineering Leadership Level Technical

Performance

Schedule Schedule

1 Minimal or no consequence to technical performance

Minimal or no impact Minimal or no impact

2 Minor reduction in technical performance or supportability, can be tolerated with little or no impact

on the program

Able to meet key dates.

Slip <*month(s)

Budget increase or unit production cost

increases.

<**(1% of Budget)

3 Moderate reduction in technical performance or supportability with

limited impact on program objectives

Minor schedule slip. Able to meet key milestones with no schedule float

Slip <*month(s)

Sub-system slip<*month(s) plus available float

Budget increase or unit production cost

increases.

<**(5% of Budget)

4 Significant degradation in technical performance or major shortfall in

supportability; may jeopardize program success

Program critical path affected Slip <*month(s)

Budget increase or unit production cost

increases.

<**(10% of Budget)

5 Severe degradation in technical performance. Cannot meet KPP or

key technical/supportability threshold; will jeopardize program

success

Cannot meet key program milestones Slip <*month(s)

Budget increase or unit production cost

increases.

>**(10% of Budget)

DOD Consequence Descriptions

(13)

5-41140

Requires new development outside of any existing experience base. No viable approaches exist that can be pursued with any degree of confidence.

Basic research in key areas needed before feasible approaches can be defined.

Requires new development where similarity to existing experience base can be defined only in the broadest sense. Multiple development routes must be pursued.

Requires new development but similarity to existing experience is sufficient to warrant comparison in only a subset of critical areas.

Multiple development routes must be pursued.

Requires new development but similarity to existing experience is sufficient to warrant comparison on only a subset of critical areas. Dual development approaches should be pursued in order to achieve a moderate degree of confidence for success. (desired performance can be achieved in subsequent block upgrades with high degree of confidence.

Requires new development but similarity to existing experience is

sufficient to warrant comparison in all critical areas. Dual development approaches should be pursued to provide a high degree of confidence for success.

Requires new development but similarity to existing experience is

sufficient to warrant comparison across the board. A single development approach can be taken with a high degree of confidence for success.

Requires new development well within the experience base. A single development approach is adequate.

Exists but requires major modifications. A single development approach is adequate.

Exists with no or only minor modifications being required. A single development approach is adequate.

9 8 7

1 2 3 4 5 6

90%

80%

70%

0%

10%

20%

30%

40%

50%

RISK

90%

70%

10%

30%

50%

5

4

1

2

3

(14)

Academy of Program/Project & Engineering Leadership

5X5 Risk Matrix

(15)

Academy of Program/Project & Engineering Leadership

14

• The AD2 assessment provides the basis for the

development of the Technology Development Plan and for improved accuracy of the development of program/project cost, schedule and risk.

Summary

(16)

Academy of Program/Project & Engineering Leadership

15

Website: www.jbconsultinginternational.com

Bibliography:

De Meyer, Arnould, Loch, Christoph H., and Pich Michael T., “Managing Project Uncertainty: From Variation to Chaos,” MIT Sloan Management Review, pp. 60-67, Winter 2002.

Risk Management Guide for DOD Acquistion 6th Edition Version 1.0 August 2006.