ID Description Dur u Start Finish
2011-2016 Building Program
Montessori Community School (QSCB - $15.5 M)
MS02 Design Phase 390 07JUN11* 30JUN12
MS03 Bid & Award Project 58 01JUL12 27AUG12
MS01 Construction (New) - Contract Duration 302 28AUG12 25JUN13
MS01GC Construction (New) - GC's Schedule Duration 317 28AUG12 10JUL13
MS01IH Construction (New) - In-House Schedule Duration 317 28AUG12 10JUL13
MS01CP Construction (New) - Earned Value Projection 318 28AUG12 11JUL13
MS04 Commissioning of School / Owner to Occupy 45 26JUN13 09AUG13*
Sullivan's Island (Carry Over 26.4 M)
SI02 Design Phase 648 07JUN11* 15MAR13
SI02F Design Phase - Foundation Package 36 13AUG12* 17SEP12
SI03A Bid & Award Demo 29 27MAR12* 24APR12
SI03F Bid & Award Building - Foundation Package 36 18SEP12 23OCT12
SI03 Bid & Award Building 39 16MAR13 23APR13
SI01A Demo of Existing Bldg - Contract Duration 67 24APR12 29JUN12
SI01F Foundation Construction - Contract Duration 114 23OCT12 13FEB13
SI01 Bldg Construction - Contract Duration 466 23APR13 01AUG14
SI04 Commissioning of School / Owner to Occupy 30 17JUL14 15AUG14*
Memminger Elementary School (Wave 1 - $22 M)
MM02 Design Phase 433 01JAN11* 08MAR12
MM03 Bid & Award Project 68 09MAR12 15MAY12
MM01 Construction - Contract Duration 421 15MAY12* 09JUL13
MM01GC Construction (New) - GC's Schedule Duration 421 15MAY12* 09JUL13
MM01IH Construction (New) - In-House Schedule Duration 423 15MAY12 11JUL13
Design Phase Bid & Award Project
Construction (New) - Contract Duration Construction (New) - GC's Schedule Duration Construction (New) - In-House Schedule Duration Construction (New) - Earned Value Projection
Commissioning of School / Owner to Occupy
Design Phase
Design Phase - Foundation Package Bid & Award Demo
Bid & Award Building - Foundation Package Bid & Award Building
Demo of Existing Bldg - Contract Duration
Foundation Construction - Contract Duration
Bldg Construction - Contract Duration Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project
Construction - Contract Duration
Construction (New) - GC's Schedule Duration Construction (New) - In-House Schedule Duration
ID Description Dur u Start Finish
MM01CP Construction (New) - Earned Value Projection 430 15MAY12 18JUL13
MM04 Commissioning of School / Owner to Occupy 45 02JUL13 15AUG13*
Buist Academy (Wave 1 - $35.7 M)
BA02 Design Phase 497 01JAN11* 11MAY12
BA03 Bid & Award Project 37 27MAY12 02JUL12
BA001 Retrofit/Pile Pack Const. - COMPLETE 245 10JAN12* 10SEP12
BA01 New Building Construction - Contract Duration 354 02JUL12* 20JUN13
BA01GC New Building - GC's Schedule Duration 367 02JUL12* 03JUL13
BA01IH New Building - In-House Schedule Duration 369 02JUL12 05JUL13
BA01CP New Building - Earned Value Projection 366 02JUL12 02JUL13
BA04 Commissioning of School / Owner to Occupy 50 21JUN13 09AUG13
Charleston Progressive ES (Wave 1 - $18.6 M)
CP02 Design Phase 487 01JAN11* 01MAY12
CP03 Bid & Award Project 61 07JUN12* 06AUG12
CP01 Construction - Contract Duration - West Wing 421 06AUG12 30SEP13
CP01A Construction - Contract Duration - N & E Wing 347 06AUG12 18JUL13 CP01GC Construction -GC's Schedule Duration West Wing 421 06AUG12* 30SEP13 CP01GCAConstruction -GC's Schedule Duration N & E Wing 347 06AUG12* 18JUL13 CP01IH Construction-InHouse Schedule Duration-West Wing 421 06AUG12 30SEP13 CP01IHA Construction-InHouse Schedule Duration- N&E Wing 347 06AUG12 18JUL13 CP01CP Construction- Earned Value Projection- West Wing 425 06AUG12 04OCT13 CP01CPAConstruction- Earned Value Projection-N & E Wing 351 06AUG12 22JUL13
CP04 Commissioning of School / Owner to Occupy 20 01OCT13* 20OCT13
James Simons Montessori School (Wave1 - $27.4 M)
JS02 Design Phase 595 01JAN11* 17AUG12
JS022 CM @ Risk Selection Complete 0 27FEB12*
Construction (New) - Earned Value Projection Commissioning of School / Owner to Occupy
Design Phase Bid & Award Project
Retrofit/Pile Pack Const. - COMPLETE
New Building Construction - Contract Duration New Building - GC's Schedule Duration New Building - In-House Schedule Duration New Building - Earned Value Projection
Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project
Construction - Contract Duration - West Wing Construction - Contract Duration - N & E Wing
Construction -GC's Schedule Duration West Wing Construction -GC's Schedule Duration N & E Wing
Construction-InHouse Schedule Duration-West Wing Construction-InHouse Schedule Duration- N&E Wing
Construction- Earned Value Projection- West Wing Construction- Earned Value Projection-N & E Wing
Commissioning of School / Owner to Occupy
Design Phase CM @ Risk Selection Complete
ID Description Dur u Start Finish
JS01 New Bldg Construction - Contract Duration 308 18SEP12* 22JUL13
JS01GC New Bldg Construction - GC's Schedule Duration 308 18SEP12* 22JUL13 JS01IH New Bldg Constructn - In-House Schedule Duration 308 18SEP12 22JUL13 JS01CP New Bldg Construction - Earned Value Projection 304 18SEP12 18JUL13
JS04 Commissioning of School / Owner to Occupy 40 23JUL13 31AUG13*
Montessori/Springfield Support Fac.(Wave 2- $6M)
MSS02 Design Phase 404 27FEB12* 05APR13
MSS025 Bid & Award Project - Early Site 31 11FEB13* 13MAR13
MSS03 Bid & Award Project - Building 49 11MAY13 28JUN13
MSS11 Relocation of Portables 38 01DEC11* 07JAN12
MSS022 Construction - Contract Duration Early Site 192 14MAR13 21SEP13
MSS01 Construction - Contract Duration Building 350 28JUN13* 12JUN14
MSS04 Commissioning of School / Owner to Occupy 60 13JUN14 11AUG14*
Harborview Elementary School (Wave 2 - $26.5 M)
HV002 Design Swing Campus 319 17JUN11* 30APR12
HV0013 Design - Demo & Ground Modifications 156 09DEC11* 12MAY12
HV02 Design - Building 515 17JUN11* 12NOV12
HV0022 Bid & Award Swing Campus 15 01MAY12 15MAY12
HV0023 Bid & Award - Demo & Ground Modifications 47 17JUN12* 02AUG12
HV03 Bid & Award - Building 92 13NOV12 12FEB13
HV001A Mikell Drive Road Improvements 199 16JAN12* 01AUG12
HV001 Prep Swing Campus 79 15MAY12 01AUG12
HV003 Construction - Demo & Ground Modifications 103 02AUG12 12NOV12
HV01 Bldg Construction (Rebuild) - Contract Duration 489 12FEB13 15JUN14
HV04 Commissioning of School / Owner to Occupy 60 16JUN14 14AUG14
New Bldg Construction - Contract Duration New Bldg Construction - GC's Schedule Duration New Bldg Constructn - In-House Schedule Duration New Bldg Construction - Earned Value Projection
Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project - Early Site Bid & Award Project - Building Relocation of Portables
Construction - Contract Duration Early Site
Construction - Contract Duration Building Commissioning of School / Owner to Occupy
Design Swing Campus
Design - Demo & Ground Modifications Design - Building
Bid & Award Swing Campus
Bid & Award - Demo & Ground Modifications Bid & Award - Building
Mikell Drive Road Improvements Prep Swing Campus
Construction - Demo & Ground Modifications
Bldg Construction (Rebuild) - Contract Dura Commissioning of School / Owner to Occupy
ID Description Dur u Start Finish
Career & Technology Academy (Wave 2 - $49.7 M)
WC0013 Design - Early Site & Permitting 134 16DEC11* 27APR12
WC02 Design Phase - Building 338 04SEP11* 06AUG12
WC0023 Bid & Award - Early Site 21 06JUN12* 26JUN12
WC03 Bid & Award - Building 79 09AUG12* 26OCT12
WC003 Construction - Early Site 142 09JUL12 27NOV12
WC01 Construction (New) - Contract Duration 571 18DEC12* 11JUL14
WC01GC New Bldg Construction - GC's Schedule Duration 571 18DEC12 11JUL14 WC01IH New Bldg Constructn - In-House Schedule Duration 571 18DEC12 11JUL14 WC01CP New Bldg Construction - Earned Value Projection 571 18DEC12 11JUL14
WC04 Commissioning of School / Owner to Occupy 33 12JUL14 13AUG14*
St. Andrews Math & Science ES (Wave 3 - $33.1 M)
SM002 Design Swing Campus 103 30DEC11* 10APR12
SM0013 Design - Demo & Ground Modifications 306 10JAN12* 10NOV12
SM02 Design Phase - Building 631 04JUN11* 23FEB13
SM0022 Bid & Award Swing Campus 17 11APR12 27APR12
SM0023 Bid & Award - Demo & Ground Modifications 60 11NOV12* 09JAN13
SM03 Bid & Award - Building 33 22MAR13* 23APR13
SM001 Construct Swing Campus 78 27APR12 13JUL12
SM003 Construction - Demo & Ground Modifications 129 09JAN13 17MAY13
SM01 Bldg -Construction (Rebuild) - Contract Duration 561 23APR13 04NOV14
SM04 Commissioning of School / Owner to Occupy 59 05NOV14 02JAN15
Chicora Elementary School (Wave 3 - $28 M)
CH12 Aquire Land 141 16MAR12* 01MAR13
CH02 Design Phase 545 07JUN11* 30JUN13
CH03 Bid & Award Project 112 01JUL13 20OCT13
Design - Early Site & Permitting Design Phase - Building Bid & Award - Early Site
Bid & Award - Building Construction - Early Site
Construction (New) - Contract Duration New Bldg Construction - GC's Schedule Du New Bldg Constructn - In-House Schedule New Bldg Construction - Earned Value Proj Commissioning of School / Owner to Occupy
Design Swing Campus
Design - Demo & Ground Modifications Design Phase - Building
Bid & Award Swing Campus
Bid & Award - Demo & Ground Modifications Bid & Award - Building
Construct Swing Campus
Construction - Demo & Ground Modifications
Bldg -Construction (Rebuild) - Contra Commissioning of School / Owner to Occupy
Aquire Land Design Phase
ID Description Dur u Start Finish
CH01 Construction (Rebuild) - Contract Duration 493 20OCT13 24FEB15
CH04 Commissioning of School / Owner to Occupy 35 25FEB15 31MAR15*
Jennie Moore Elementary School (Wave 3- $34.4 M)
JM024 Early Site - Design 523 20OCT11* 25MAR13
JM0265 Swing Campus - Design 118 05NOV12* 02MAR13
JM02 Design Phase - Building 602 15JAN12* 07SEP13
JM025 Early Site - Bid & Award 36 26MAR13 30APR13
JM0266 Swing Campus - Bid & Award 38 03MAR13 09APR13
JM03 Bid & Award - Building 41 08SEP13 18OCT13
LM001 Abatement & Demolition of Old Jennie Moore 35 03JUN13* 07JUL13
JM026 Early Sitework Construction 170 30APR13 16OCT13
JM027 Construct Swing Campus 98 09APR13 15JUL13
JM028 Bldg -Construction (Rebuild) - Contract Duration 607 18OCT13 16JUN15
JM04 Commissioning of School / Owner to Occupy 60 17JUN15 15AUG15
Laing Middle School (Wave 4 - $39.1 M)
LM02 Design Phase 647 10JAN12* 17OCT13
LM03 Bid & Award Project 40 18OCT13 26NOV13
LM003 Completion of Old Jennie Moore Demolition 0 07JUL13
LM002 Completion of Jennie Moore Swing Campus 0 28JUL13*
LM01 Construction (Rebuild) - Contract Duration 568 26NOV13 16JUN15
LM04 Commissioning of School / Owner to Occupy 60 17JUN15 15AUG15
Burke Career Technology Center (Wave 4 - $5 M)
BM02 Design Phase 300 08MAY13 03MAR14
BM03 Bid & Award Project 60 04MAR14 02MAY14
BM01 Construction - Contract Duration 365 02MAY14 01MAY15
BM04 Commissioning of School / Owner to Occupy 75 02MAY15 15JUL15*
Construction (Rebuild) - Contract Duration
Commissioning of School / Owner to Occupy
Early Site - Design Swing Campus - Design
Design Phase - Building Early Site - Bid & Award Swing Campus - Bid & Award
Bid & Award - Building
Abatement & Demolition of Old Jennie Moore Early Sitework Construction
Construct Swing Campus Bldg -Construction (Rebuild) - Contract Duration
Commissioning of School / Owner to Occupy
Design Phase Bid & Award Project
Completion of Old Jennie Moore Demolition Completion of Jennie Moore Swing Campus Construction (Rebuild) - Contract Duration
Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project Construction - Contract Duration
ID Description Dur u Start Finish
James Island Charter HS (Wave 4 - $25 M)
JI02 Design Phase 336 03DEC12* 03NOV13
JI03 Bid & Award Project 60 04NOV13 02JAN14
JI01 Construction (Improvements) - Contract Duration 516 02JAN14 01JUN15
JI04 Commissioning of School / Owner to Occupy 75 02JUN15 15AUG15*
CCSD Emergency Operation Center (Wave 4- $2.5 M
CO02 Design Phase 240 01FEB14 28SEP14
CO03 Bid & Award Project 60 29SEP14 27NOV14
CO01 Construction (IT Relocation)- Contract Duration 200 27NOV14 14JUN15
CO04 Commissioning Op.Center / Owner to Occupy 62 15JUN15 15AUG15*
N. Charleston Creative Arts ES (Wave 5- $27.1 M)
NC02 Design Phase 432 03JAN13 10MAR14
NC03 Bid & Award Project 59 11MAR14 08MAY14
NC01 Construction (Rebuild) - Contract Duration 552 08MAY14 10NOV15
NC04 Commissioning of School / Owner to Occupy 53 11NOV15 02JAN16*
Murray LaSaine ES (Wave 5 - $10 M)
ML02 Design Phase 330 12FEB13 07JAN14
ML03 Bid & Award Project 61 08JAN14 09MAR14
ML01 Construction (Renovation) - Contract Duration 420 09MAR14 02MAY15
ML04 Commissioning of School / Owner to Occupy 75 02MAY15 15JUL15*
Angel Oak ES (Wave 5 - $9.3 M)
AO02 Design Phase 330 12FEB13 07JAN14
AO03 Bid & Award Project 61 08JAN14 09MAR14
AO01 Construction (Renovation) - Contract Duration 420 09MAR14 02MAY15
AO04 Commissioning of School / Owner to Occupy 75 02MAY15 15JUL15*
Design Phase
Bid & Award Project Construction (Improvements) - Contract Duration
Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project Construction (IT Relocation)- Contract Duration
Commissioning Op.Center / Owner to Occupy
Design Phase
Bid & Award Project Construction (Rebuild) - Contract Duration
Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project Construction (Renovation) - Contract Duration
Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project Construction (Renovation) - Contract Duration
ID Description Dur u Start Finish
Springfield (Wave 5 - $33.1 M)
SP02 Design Phase - Building 415 19APR12* 13SEP13
SP021 Design Phase - Early Site 29 11NOV13* 09DEC13
SP031 Bid & Award Early Site Package 36 10DEC13 14JAN14
SP03 Bid & Award Building Package 85 08MAR14* 31MAY14
SP011 Construction - Early Site - Contract Duration 176 14JAN14 08JUL14
SP01 Construction - Building - Contract Duration 380 31MAY14 14JUN15
SP012 Demolition of Existing Springfield 60 11JUN15* 09AUG15
SP013 Fine Grading & Site Work @ Old Springfield Site 120 10AUG15 07DEC15
SP04 Commissioning of School / Owner to Occupy 60 15JUN15 13AUG15
Pinehurst ES -Roof & Wing (Wave 7 - $15.3 M)
PE02 Design Phase 366 02APR14 02APR15
PE03 Bid & Award Project 61 03APR15 02JUN15
PE01 Construction (Renovation) - Contract Duration 366 03JUN15 02JUN16
PE04 Commissioning of School / Owner to Occupy 74 03JUN16 15AUG16*
Stono Park Elem School (Wave 7-$26.6 M) ON HOLD
ST02 Design Phase 365 29JUL13 28JUL14
ST03 Bid & Award Project 61 29JUL14 27SEP14
ST01 Construction (Rebuild) - Contract Duration 600 27SEP14 18MAY16
ST04 Commissioning of School / Owner to Occupy 75 19MAY16 01AUG16*
2011-2016 Building Program - Contingent Projec
Athletic & Weight Rm Improvements ($4 M)
AA01 Advance Design & Permitting 1 01NOV13 01NOV13
AA03 Design Phase 366 01NOV13 01NOV14
AA04 Bid & Award Project 60 02NOV14 31DEC14
AA02 Construction - Contract Duration 519 31DEC14 01JUN16
Design Phase - Building Design Phase - Early Site
Bid & Award Early Site Package Bid & Award Building Package Construction - Early Site - Contract Duration
Construction - Building - Contract Duration
Demolition of Existing Springfield Fine Grading & Site Work @ Old Springfield Site Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project Construction (Renovation) - Contract Duration
Commissioning of School / Owner to Occupy
Design Phase
Bid & Award Project Construction (Rebuild) - Contract Duration
Commissioning of School / Owner to Occupy
Advance Design & Permitting Design Phase
Bid & Award Project Construction - Contract Duration
ID Description Dur u Start Finish
AA05 Commissioning / Owner to Occupy 75 02JUN16 15AUG16*
Carolina Bay- Aquire Land ($3.5 M)
CB01 Land & Road Improvements 1 01AUG16* 01AUG16
Azalea Bus Lot ($7.5 M)
AR02 Design Phase 180 01AUG15 27JAN16
AR03 Bid & Award Project 60 28JAN16 27MAR16
AR01 Construction (Renovation) - Contract Duration 130 27MAR16 03AUG16*
District 3 Bus Lot ($3.3 M)
DB02 Design Phase 180 01AUG15 27JAN16
DB03 Bid & Award Project 60 28JAN16 27MAR16
DB01 Construction - Contract Duration 130 27MAR16 03AUG16*
Ingleside Campus- Aquire Land ($3.5 M)
IC01 Land Purchase 1 01DEC16* 01DEC16
Commissioning / Owner to Occupy
Land & Road Improvements
Design Phase Bid & Award Project
Construction (Renovation) - Contract Duration
Design Phase Bid & Award Project
Construction - Contract Duration