ID Description Dur u Start Finish

2011-2016 Building Program

Montessori Community School (QSCB - $15.5 M)

MS02 Design Phase 390 07JUN11* 30JUN12

MS03 Bid & Award Project 58 01JUL12 27AUG12

MS01 Construction (New) - Contract Duration 302 28AUG12 25JUN13

MS01GC Construction (New) - GC's Schedule Duration 317 28AUG12 10JUL13

MS01IH Construction (New) - In-House Schedule Duration 317 28AUG12 10JUL13

MS01CP Construction (New) - Earned Value Projection 318 28AUG12 11JUL13

MS04 Commissioning of School / Owner to Occupy 45 26JUN13 09AUG13*

Sullivan's Island (Carry Over 26.4 M)

SI02 Design Phase 648 07JUN11* 15MAR13

SI02F Design Phase - Foundation Package 36 13AUG12* 17SEP12

SI03A Bid & Award Demo 29 27MAR12* 24APR12

SI03F Bid & Award Building - Foundation Package 36 18SEP12 23OCT12

SI03 Bid & Award Building 39 16MAR13 23APR13

SI01A Demo of Existing Bldg - Contract Duration 67 24APR12 29JUN12

SI01F Foundation Construction - Contract Duration 114 23OCT12 13FEB13

SI01 Bldg Construction - Contract Duration 466 23APR13 01AUG14

SI04 Commissioning of School / Owner to Occupy 30 17JUL14 15AUG14*

Memminger Elementary School (Wave 1 - $22 M)

MM02 Design Phase 433 01JAN11* 08MAR12

MM03 Bid & Award Project 68 09MAR12 15MAY12

MM01 Construction - Contract Duration 421 15MAY12* 09JUL13

MM01GC Construction (New) - GC's Schedule Duration 421 15MAY12* 09JUL13

MM01IH Construction (New) - In-House Schedule Duration 423 15MAY12 11JUL13

Design Phase Bid & Award Project

Construction (New) - Contract Duration Construction (New) - GC's Schedule Duration Construction (New) - In-House Schedule Duration Construction (New) - Earned Value Projection

Commissioning of School / Owner to Occupy

Design Phase

Design Phase - Foundation Package Bid & Award Demo

Bid & Award Building - Foundation Package Bid & Award Building

Demo of Existing Bldg - Contract Duration

Foundation Construction - Contract Duration

Bldg Construction - Contract Duration Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project

Construction - Contract Duration

Construction (New) - GC's Schedule Duration Construction (New) - In-House Schedule Duration

(2)

ID Description Dur u Start Finish

MM01CP Construction (New) - Earned Value Projection 430 15MAY12 18JUL13

MM04 Commissioning of School / Owner to Occupy 45 02JUL13 15AUG13*

Buist Academy (Wave 1 - $35.7 M)

BA02 Design Phase 497 01JAN11* 11MAY12

BA03 Bid & Award Project 37 27MAY12 02JUL12

BA001 Retrofit/Pile Pack Const. - COMPLETE 245 10JAN12* 10SEP12

BA01 New Building Construction - Contract Duration 354 02JUL12* 20JUN13

BA01GC New Building - GC's Schedule Duration 367 02JUL12* 03JUL13

BA01IH New Building - In-House Schedule Duration 369 02JUL12 05JUL13

BA01CP New Building - Earned Value Projection 366 02JUL12 02JUL13

BA04 Commissioning of School / Owner to Occupy 50 21JUN13 09AUG13

Charleston Progressive ES (Wave 1 - $18.6 M)

CP02 Design Phase 487 01JAN11* 01MAY12

CP03 Bid & Award Project 61 07JUN12* 06AUG12

CP01 Construction - Contract Duration - West Wing 421 06AUG12 30SEP13

CP01A Construction - Contract Duration - N & E Wing 347 06AUG12 18JUL13 CP01GC Construction -GC's Schedule Duration West Wing 421 06AUG12* 30SEP13 CP01GCAConstruction -GC's Schedule Duration N & E Wing 347 06AUG12* 18JUL13 CP01IH Construction-InHouse Schedule Duration-West Wing 421 06AUG12 30SEP13 CP01IHA Construction-InHouse Schedule Duration- N&E Wing 347 06AUG12 18JUL13 CP01CP Construction- Earned Value Projection- West Wing 425 06AUG12 04OCT13 CP01CPAConstruction- Earned Value Projection-N & E Wing 351 06AUG12 22JUL13

CP04 Commissioning of School / Owner to Occupy 20 01OCT13* 20OCT13

James Simons Montessori School (Wave1 - $27.4 M)

JS02 Design Phase 595 01JAN11* 17AUG12

JS022 CM @ Risk Selection Complete 0 27FEB12*

Construction (New) - Earned Value Projection Commissioning of School / Owner to Occupy

Design Phase Bid & Award Project

Retrofit/Pile Pack Const. - COMPLETE

New Building Construction - Contract Duration New Building - GC's Schedule Duration New Building - In-House Schedule Duration New Building - Earned Value Projection

Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project

Construction - Contract Duration - West Wing Construction - Contract Duration - N & E Wing

Construction -GC's Schedule Duration West Wing Construction -GC's Schedule Duration N & E Wing

Construction-InHouse Schedule Duration-West Wing Construction-InHouse Schedule Duration- N&E Wing

Construction- Earned Value Projection- West Wing Construction- Earned Value Projection-N & E Wing

Commissioning of School / Owner to Occupy

Design Phase CM @ Risk Selection Complete

(3)

ID Description Dur u Start Finish

JS01 New Bldg Construction - Contract Duration 308 18SEP12* 22JUL13

JS01GC New Bldg Construction - GC's Schedule Duration 308 18SEP12* 22JUL13 JS01IH New Bldg Constructn - In-House Schedule Duration 308 18SEP12 22JUL13 JS01CP New Bldg Construction - Earned Value Projection 304 18SEP12 18JUL13

JS04 Commissioning of School / Owner to Occupy 40 23JUL13 31AUG13*

Montessori/Springfield Support Fac.(Wave 2- $6M)

MSS02 Design Phase 404 27FEB12* 05APR13

MSS025 Bid & Award Project - Early Site 31 11FEB13* 13MAR13

MSS03 Bid & Award Project - Building 49 11MAY13 28JUN13

MSS11 Relocation of Portables 38 01DEC11* 07JAN12

MSS022 Construction - Contract Duration Early Site 192 14MAR13 21SEP13

MSS01 Construction - Contract Duration Building 350 28JUN13* 12JUN14

MSS04 Commissioning of School / Owner to Occupy 60 13JUN14 11AUG14*

Harborview Elementary School (Wave 2 - $26.5 M)

HV002 Design Swing Campus 319 17JUN11* 30APR12

HV0013 Design - Demo & Ground Modifications 156 09DEC11* 12MAY12

HV02 Design - Building 515 17JUN11* 12NOV12

HV0022 Bid & Award Swing Campus 15 01MAY12 15MAY12

HV0023 Bid & Award - Demo & Ground Modifications 47 17JUN12* 02AUG12

HV03 Bid & Award - Building 92 13NOV12 12FEB13

HV001A Mikell Drive Road Improvements 199 16JAN12* 01AUG12

HV001 Prep Swing Campus 79 15MAY12 01AUG12

HV003 Construction - Demo & Ground Modifications 103 02AUG12 12NOV12

HV01 Bldg Construction (Rebuild) - Contract Duration 489 12FEB13 15JUN14

HV04 Commissioning of School / Owner to Occupy 60 16JUN14 14AUG14

New Bldg Construction - Contract Duration New Bldg Construction - GC's Schedule Duration New Bldg Constructn - In-House Schedule Duration New Bldg Construction - Earned Value Projection

Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project - Early Site Bid & Award Project - Building Relocation of Portables

Construction - Contract Duration Early Site

Construction - Contract Duration Building Commissioning of School / Owner to Occupy

Design Swing Campus

Design - Demo & Ground Modifications Design - Building

Bid & Award Swing Campus

Bid & Award - Demo & Ground Modifications Bid & Award - Building

Mikell Drive Road Improvements Prep Swing Campus

Construction - Demo & Ground Modifications

Bldg Construction (Rebuild) - Contract Dura Commissioning of School / Owner to Occupy

(4)

ID Description Dur u Start Finish

Career & Technology Academy (Wave 2 - $49.7 M)

WC0013 Design - Early Site & Permitting 134 16DEC11* 27APR12

WC02 Design Phase - Building 338 04SEP11* 06AUG12

WC0023 Bid & Award - Early Site 21 06JUN12* 26JUN12

WC03 Bid & Award - Building 79 09AUG12* 26OCT12

WC003 Construction - Early Site 142 09JUL12 27NOV12

WC01 Construction (New) - Contract Duration 571 18DEC12* 11JUL14

WC01GC New Bldg Construction - GC's Schedule Duration 571 18DEC12 11JUL14 WC01IH New Bldg Constructn - In-House Schedule Duration 571 18DEC12 11JUL14 WC01CP New Bldg Construction - Earned Value Projection 571 18DEC12 11JUL14

WC04 Commissioning of School / Owner to Occupy 33 12JUL14 13AUG14*

St. Andrews Math & Science ES (Wave 3 - $33.1 M)

SM002 Design Swing Campus 103 30DEC11* 10APR12

SM0013 Design - Demo & Ground Modifications 306 10JAN12* 10NOV12

SM02 Design Phase - Building 631 04JUN11* 23FEB13

SM0022 Bid & Award Swing Campus 17 11APR12 27APR12

SM0023 Bid & Award - Demo & Ground Modifications 60 11NOV12* 09JAN13

SM03 Bid & Award - Building 33 22MAR13* 23APR13

SM001 Construct Swing Campus 78 27APR12 13JUL12

SM003 Construction - Demo & Ground Modifications 129 09JAN13 17MAY13

SM01 Bldg -Construction (Rebuild) - Contract Duration 561 23APR13 04NOV14

SM04 Commissioning of School / Owner to Occupy 59 05NOV14 02JAN15

Chicora Elementary School (Wave 3 - $28 M)

CH12 Aquire Land 141 16MAR12* 01MAR13

CH02 Design Phase 545 07JUN11* 30JUN13

CH03 Bid & Award Project 112 01JUL13 20OCT13

Design - Early Site & Permitting Design Phase - Building Bid & Award - Early Site

Bid & Award - Building Construction - Early Site

Construction (New) - Contract Duration New Bldg Construction - GC's Schedule Du New Bldg Constructn - In-House Schedule New Bldg Construction - Earned Value Proj Commissioning of School / Owner to Occupy

Design Swing Campus

Design - Demo & Ground Modifications Design Phase - Building

Bid & Award Swing Campus

Bid & Award - Demo & Ground Modifications Bid & Award - Building

Construct Swing Campus

Construction - Demo & Ground Modifications

Bldg -Construction (Rebuild) - Contra Commissioning of School / Owner to Occupy

Aquire Land Design Phase

(5)

ID Description Dur u Start Finish

CH01 Construction (Rebuild) - Contract Duration 493 20OCT13 24FEB15

CH04 Commissioning of School / Owner to Occupy 35 25FEB15 31MAR15*

Jennie Moore Elementary School (Wave 3- $34.4 M)

JM024 Early Site - Design 523 20OCT11* 25MAR13

JM0265 Swing Campus - Design 118 05NOV12* 02MAR13

JM02 Design Phase - Building 602 15JAN12* 07SEP13

JM025 Early Site - Bid & Award 36 26MAR13 30APR13

JM0266 Swing Campus - Bid & Award 38 03MAR13 09APR13

JM03 Bid & Award - Building 41 08SEP13 18OCT13

LM001 Abatement & Demolition of Old Jennie Moore 35 03JUN13* 07JUL13

JM026 Early Sitework Construction 170 30APR13 16OCT13

JM027 Construct Swing Campus 98 09APR13 15JUL13

JM028 Bldg -Construction (Rebuild) - Contract Duration 607 18OCT13 16JUN15

JM04 Commissioning of School / Owner to Occupy 60 17JUN15 15AUG15

Laing Middle School (Wave 4 - $39.1 M)

LM02 Design Phase 647 10JAN12* 17OCT13

LM03 Bid & Award Project 40 18OCT13 26NOV13

LM003 Completion of Old Jennie Moore Demolition 0 07JUL13

LM002 Completion of Jennie Moore Swing Campus 0 28JUL13*

LM01 Construction (Rebuild) - Contract Duration 568 26NOV13 16JUN15

LM04 Commissioning of School / Owner to Occupy 60 17JUN15 15AUG15

Burke Career Technology Center (Wave 4 - $5 M)

BM02 Design Phase 300 08MAY13 03MAR14

BM03 Bid & Award Project 60 04MAR14 02MAY14

BM01 Construction - Contract Duration 365 02MAY14 01MAY15

BM04 Commissioning of School / Owner to Occupy 75 02MAY15 15JUL15*

Construction (Rebuild) - Contract Duration

Commissioning of School / Owner to Occupy

Early Site - Design Swing Campus - Design

Design Phase - Building Early Site - Bid & Award Swing Campus - Bid & Award

Bid & Award - Building

Abatement & Demolition of Old Jennie Moore Early Sitework Construction

Construct Swing Campus Bldg -Construction (Rebuild) - Contract Duration

Commissioning of School / Owner to Occupy

Design Phase Bid & Award Project

Completion of Old Jennie Moore Demolition Completion of Jennie Moore Swing Campus Construction (Rebuild) - Contract Duration

Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project Construction - Contract Duration

(6)

ID Description Dur u Start Finish

James Island Charter HS (Wave 4 - $25 M)

JI02 Design Phase 336 03DEC12* 03NOV13

JI03 Bid & Award Project 60 04NOV13 02JAN14

JI01 Construction (Improvements) - Contract Duration 516 02JAN14 01JUN15

JI04 Commissioning of School / Owner to Occupy 75 02JUN15 15AUG15*

CCSD Emergency Operation Center (Wave 4- $2.5 M

CO02 Design Phase 240 01FEB14 28SEP14

CO03 Bid & Award Project 60 29SEP14 27NOV14

CO01 Construction (IT Relocation)- Contract Duration 200 27NOV14 14JUN15

CO04 Commissioning Op.Center / Owner to Occupy 62 15JUN15 15AUG15*

N. Charleston Creative Arts ES (Wave 5- $27.1 M)

NC02 Design Phase 432 03JAN13 10MAR14

NC03 Bid & Award Project 59 11MAR14 08MAY14

NC01 Construction (Rebuild) - Contract Duration 552 08MAY14 10NOV15

NC04 Commissioning of School / Owner to Occupy 53 11NOV15 02JAN16*

Murray LaSaine ES (Wave 5 - $10 M)

ML02 Design Phase 330 12FEB13 07JAN14

ML03 Bid & Award Project 61 08JAN14 09MAR14

ML01 Construction (Renovation) - Contract Duration 420 09MAR14 02MAY15

ML04 Commissioning of School / Owner to Occupy 75 02MAY15 15JUL15*

Angel Oak ES (Wave 5 - $9.3 M)

AO02 Design Phase 330 12FEB13 07JAN14

AO03 Bid & Award Project 61 08JAN14 09MAR14

AO01 Construction (Renovation) - Contract Duration 420 09MAR14 02MAY15

AO04 Commissioning of School / Owner to Occupy 75 02MAY15 15JUL15*

Design Phase

Bid & Award Project Construction (Improvements) - Contract Duration

Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project Construction (IT Relocation)- Contract Duration

Commissioning Op.Center / Owner to Occupy

Design Phase

Bid & Award Project Construction (Rebuild) - Contract Duration

Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project Construction (Renovation) - Contract Duration

Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project Construction (Renovation) - Contract Duration

(7)

ID Description Dur u Start Finish

Springfield (Wave 5 - $33.1 M)

SP02 Design Phase - Building 415 19APR12* 13SEP13

SP021 Design Phase - Early Site 29 11NOV13* 09DEC13

SP031 Bid & Award Early Site Package 36 10DEC13 14JAN14

SP03 Bid & Award Building Package 85 08MAR14* 31MAY14

SP011 Construction - Early Site - Contract Duration 176 14JAN14 08JUL14

SP01 Construction - Building - Contract Duration 380 31MAY14 14JUN15

SP012 Demolition of Existing Springfield 60 11JUN15* 09AUG15

SP013 Fine Grading & Site Work @ Old Springfield Site 120 10AUG15 07DEC15

SP04 Commissioning of School / Owner to Occupy 60 15JUN15 13AUG15

Pinehurst ES -Roof & Wing (Wave 7 - $15.3 M)

PE02 Design Phase 366 02APR14 02APR15

PE03 Bid & Award Project 61 03APR15 02JUN15

PE01 Construction (Renovation) - Contract Duration 366 03JUN15 02JUN16

PE04 Commissioning of School / Owner to Occupy 74 03JUN16 15AUG16*

Stono Park Elem School (Wave 7-$26.6 M) ON HOLD

ST02 Design Phase 365 29JUL13 28JUL14

ST03 Bid & Award Project 61 29JUL14 27SEP14

ST01 Construction (Rebuild) - Contract Duration 600 27SEP14 18MAY16

ST04 Commissioning of School / Owner to Occupy 75 19MAY16 01AUG16*

2011-2016 Building Program - Contingent Projec

Athletic & Weight Rm Improvements ($4 M)

AA01 Advance Design & Permitting 1 01NOV13 01NOV13

AA03 Design Phase 366 01NOV13 01NOV14

AA04 Bid & Award Project 60 02NOV14 31DEC14

AA02 Construction - Contract Duration 519 31DEC14 01JUN16

Design Phase - Building Design Phase - Early Site

Bid & Award Early Site Package Bid & Award Building Package Construction - Early Site - Contract Duration

Construction - Building - Contract Duration

Demolition of Existing Springfield Fine Grading & Site Work @ Old Springfield Site Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project Construction (Renovation) - Contract Duration

Commissioning of School / Owner to Occupy

Design Phase

Bid & Award Project Construction (Rebuild) - Contract Duration

Commissioning of School / Owner to Occupy

Advance Design & Permitting Design Phase

Bid & Award Project Construction - Contract Duration

(8)

ID Description Dur u Start Finish

AA05 Commissioning / Owner to Occupy 75 02JUN16 15AUG16*

Carolina Bay- Aquire Land ($3.5 M)

CB01 Land & Road Improvements 1 01AUG16* 01AUG16

Azalea Bus Lot ($7.5 M)

AR02 Design Phase 180 01AUG15 27JAN16

AR03 Bid & Award Project 60 28JAN16 27MAR16

AR01 Construction (Renovation) - Contract Duration 130 27MAR16 03AUG16*

District 3 Bus Lot ($3.3 M)

DB02 Design Phase 180 01AUG15 27JAN16

DB03 Bid & Award Project 60 28JAN16 27MAR16

DB01 Construction - Contract Duration 130 27MAR16 03AUG16*

Ingleside Campus- Aquire Land ($3.5 M)

IC01 Land Purchase 1 01DEC16* 01DEC16

Commissioning / Owner to Occupy

Land & Road Improvements

Design Phase Bid & Award Project

Construction (Renovation) - Contract Duration

Design Phase Bid & Award Project

Construction - Contract Duration

References

Related documents

[r]

Audit Funding Small Business Lighting High Performance New Construction Existing Building Commissioning Retrofit Program

Enjoy the hearts celtic fc and driver was a first goal by david templeton takes the referee kevin kyle leaves the cookie set a great feeling.. Johnstone and into a penalty

For acquiring a building site, building or equipping a new school building, repairing, making additions to, or equipping a present school building, or purchasing new or used

Table 1: Strain Readings and Frame deflection for Experiment 1.. Complete the experimental force in Table 3.. From the Graph 1 and Graph 2 plotted for member 3 and 7, we obtain

No review by the DFCM or any entity/user, approval or acceptance, or payment for any of the services required under this Agreement shall be construed to operate as a waiver by

Figure 1 shows the 2d-DB spectra of the undeformed reference sample in comparison to pure annealed or ball-milled aluminum, to deformed pure copper as well as to the HPT sample..

Sometimes it's to facilitate another person (such as the profound energy created through the death of a child or suicide). So it can be part of an agreement with great energy around