TechNet Land Forces South
Army Data Center Consolidation Plan
(ADCCP) Overview
COL Chris E. Miller
MARCH 27-29
Tucson, AZ
Engagement Theater Session IV 28 March 2012/1600 hrs
2
Purpose
To provide background on data center
consolidation and the path which the Army is taking
to meet Presidential Guidance and the Office of
Management Budget’s Federal Data
Center Consolidation Initiative (FDCCI) while
recognizing and adapting to processing realities in
the field.
The Technology Dilemma
5 March 2012 3
We have to be better at being able to reach out, harness technology
and get it into the hands of our soldiers quickly.
– GEN Peter W. Chiarelli, Former Vice Chief of Staff of the Army
4
Modernizing Army Systems
“the Army’s sweeping network modernization
effort, its number one priority in modernization,
will require a
fundamental cultural change
”
Chief Information Officer
CIO/G-6, LTG Susan S. Lawrence
• Focusing on the End State
• Executive and Congressional Interest
• The Way Forward:
– Data Center Consolidation
– Application Rationalization
• Summary
Why Consolidate Our Data Centers?
Subject: Disposing of Unneeded Federal Real
Estate – Increasing Sales Proceeds, Cutting
Operation Costs, and Improving Energy Efficiency
“…in order to address the growth of data centers
across the Federal Government, agencies shall
immediately adopt a policy against expanding data centers beyond current levels, and shall develop plans to consolidate and significantly reduce data centers within 5 years.
Agencies shall submit their plans to OMB for
review by August 30, 2010.”
“…Stop Expanding Data
Centers…”
Presidential Memo – 10 June 2010
Congressional Interest
• Limitations on Obligations of Funds (FY2012 NDAA Language)
• During the period beginning on the date of the enactment of this Act and ending on May 1, 2012, a department, agency, or component of the Department of Defense may not obligate funds for a data server farm or data center unless approved by the Chief Information Officer of the Department of Defense or the Chief Information Officer of a component of the Department to whom the Chief Information Officer of the Department has specifically delegated such approval authority.
• After May 1, 2012, a department, agency, or component of the Department may not obligate funds for a data center, or any information systems technology used therein, unless that obligation is in accordance with DOD wide performance plan required by the Act.
• Approvals for funding • Prior to May 1, 2012
• An approval of the obligation of funds may not be granted unless the official granting the approval determines, in writing, that existing resources of the agency, component, or element concerned cannot affordably or practically be used or modified to meet the requirements to be met through the obligation of funds.
• After May 1, 2012
• An approval of the obligation of funds may not be granted unless the official granting the approval determines that:
(1) existing resources of the Department do not meet the operation requirements to be met through the obligation of funds; and (2) the proposed obligation is in accordance with the performance standards and measures established by the Chief Information Officer of the Department in the DOD Performance Plans.
• Reports of Approvals
• Not later than 30 days after the end of each calendar quarter, each Chief Information Officer of a component of the Department who grants an approval based on the authority delegated by the Chief Information office of the Department during such calendar quarter shall submit to the Chief Information Officer of the Department a report on the approval or approvals so granted during such calendar quarter.
The Magnitude of the Problem
• Over 435 Army data centers:
– Occupying more than 1.2 million square feet of floor
space.
– Containing over 26,000 servers.
– Housing almost 9,000 racks (which, if placed side by
side, would reach over 4 miles)
• Over 10,500 application records.
• And we know we don’t know everything yet!
As of 5 March 2012
268 182 6 2 1 0 50 100 150 200 250 300
CAT 2 CAT 3 CAT 4 CAT 7 CAT 9
Data Centers by Category CAT 2 CAT 3 CAT 4 CAT 7 CAT 9
The Target for Data Center Closures
Close 185 Army Data Center’s by FY15
.
Doing 1 task 185 times
CAT 2: Sustain CAT 3 Close CAT 4: Deployed OEF CAT 7 Pending CAT 9 Re-categorized 25 8 33 66 18 32 0 10 20 30 40 50 60 70
FY11 FY12 FY13 FY14 FY15
Close in FY
The Installation Approach
• To meet the Army's goal of 185 data center closures by FY2015, the
CIO/G-6, NETCOM/9th SC (A) and 7th SC (T) have recommended taking an
Installation Approach.
• The Installation Approach uses the Center of Excellence (CoE) Discovery teams more effectively by having them discover existing data center
information including; capacity, facility, storage, network, and application level data on an installation concurrently, allowing commands to make more informed decisions to support a
simultaneous, rapid collapse of the data centers on an installation. • The Installation approach is not meant to move away from the
command plans that were briefed at the ADCCP Summit in December 2011, or slow the pace of scheduled closures, but a means for our
organizations to work together to best utilize resources and further the goals of data center consolidation.
Installation Approach Discovery Goals
• Facility Infrastructure
• Utilized and Available Capacities
• Network and Storage Capacities
• Application level data
• Other Data Centers identified
Pre-Site Visit Prerequisites
12
To be completed prior to Site Visit, Center of
Excellence will coordinate with onsite POCs:
• High-level Installation Network Diagrams
• High-level individual data centers Network Diagrams
• Routers, switches and Firewalls Access Control Lists
(ACL)
• Existing List of Network Management Systems(NMS)
• Review of current DISA topology
Onsite Discovery Activities
• Conduct Onsite In-Brief
• Representatives of all Commands with Data Centers on the
Installation, Data Center Owners, IMCOM, DPW, Garrison Commander, HQDA CIO/G-6, and NETCOM
• Manual Data Collection (2 weeks)
• Physical Discovery Data
– Facility Condition, HVAC, Power, Cable Infrastructure, Floor/Rack Space, Network Connections, COOP, Physical Security,
Environmental Factors, Technical support availability, Network traffic flows, Virtualization Services
• High Level Application Data:
– Functional Description, Technical High-Level Description, Storage Allocation, Ports and Protocols, High-Level Network Topology
Onsite Discovery Activities (cont’d)
14
• Conduct Preliminary Analysis (1 week)
– Validation of tracking tool data
– Work with on-site experts to capture additional information required to support a recommendation for Installation Data Center Consolidation – Identification of constraints/limitations with existing infrastructure – Development of potential courses of action
• Conduct Onsite Out-Brief
– Representatives of all Commands with Data Centers on the Installation, Data Center Owners, IMCOM, DPW, Garrison Commander, HQDA CIO/G-6, and NETCOM
– Will include a “recommendation” for Installation Data Center Consolidation
Installation Approach: End State
Single Installation
Processing Node
(Data Center)
NETCOM FXXX_ST_NEC_01 TRADOC FXXX_ST_TRA_02 TRADOC FXXX_ST_TRA_01 HQDA G3 FXXX_ST_HG3_01 ATEC FXXX_ST_ATC_01 AMC FXXX_ST_AMC_01 AMC FXXX_ST_AMC_02 AMC FXXX_ST_AMC_03Application Rationalization & Disposition
16 White-Listed Apps ERP’s SharePoint Exchange Mail MS Project Server AtHOC OCS RM Online Distance Learning ETCEnterprise Servicing Applications Local Servicing Infrastructure
AD Controllers Switches/Routers TLA DNS Servers IPS Print Servers SONET ETC BIN Categorize Disposition War Fighting Mission Area Business Mission Area Enterprise Information Mission Area Inventory
Rationalize: Kill Retire Modernize Sustain
Manufacturing Syst C4IM Services
Thin Client
ETC
Local Servicing Applications
Cost Utilization Architecture Bandwidth Risk
Disposition MWR.COM .COM .ORG .EDU Infrastructure Enterprise Servicing Applications CDAE DCCE Local Servicing Consolidation CBA 16
Rationalization and Categorization Timeline
Task.5 Suspense
1. Rationalize Requirement: Identify each application as: kill, modernize, or sustain; and
2. Categorization Requirement: Identify each application as enterprise servicing or local servicing of Applications listed in the ADCCP Tracking Tool (C-1 List) which are hosted in data centers closing in FY12.
19 APR 2012
1. Rationalize Requirement: Identify each application as: kill, modernize, or sustain; and
2. Categorization Requirement: Identify each application as enterprise servicing or local servicing of Applications listed in the ADCCP Tracking Tool (C-1 List) which are hosted in data centers closing in FY13.
10 MAY 2012
1. Rationalize Requirement: Identify each application as: kill, modernize, or sustain; and
2. Categorization Requirement: Identify each application as enterprise servicing or local servicing of Applications listed in the ADCCP Tracking Tool (C-1 List) which are hosted in data centers closing in FY14.
31 MAY 2012
1. Rationalize Requirement: Identify each application as: kill, modernize, or sustain; and
2. Categorization Requirement: Identify each application as enterprise servicing or local servicing of Applications listed in the ADCCP Tracking Tool (C-1 List) which are hosted in data centers closing in FY15.
21 JUN 2012
Complete Rationalization and Categorization of 100% Applications listed in the ADCCP Tacking Tool (C-1
List). 28 JUN 2012
Notes:
18
Paths to Progress
Server Consolidation Platform as a Service (PaaS) Infrastructure as a Service (IaaS)Software as a Service
(SaaS)
Cultural Change Sa vi ng s & Ef ficie nc ie s$
$ 18Using ADCCP as the Path to the Cloud
Local applications Converted to
Enterprise Applications DISA, Commercial, &
IPN Hosting Enterprise Server Common Operating Environment Software as a Service Platform as a Service Infrastructure as a Service 20
The Goal
Army Application Portfolio Rationalization Common Operating Environments Application Hosting Business ManagementPoints of Contact
– CIO/G-6 ADCCP Team: COL Chris Miller/Mr. Neal Shelley/LTC Jeff Gribschaw
• [email protected]; (571) 256-8987
• [email protected]; (703) 693-3268
• [email protected]; (571) 256-8986
– HQDA CIO/G-6 Cyber Directorate: Mr. William Biggs
• [email protected]; (703) 545-1693
– Army Cyber Command: COL William “Max” Duggan
• [email protected]; (703) 706-2850
– ADCCP Project Office (Software Engineering Center Support): Dan Andrew
• [email protected]; (443) 861-8616
– ADCCP Links
• ADCCP Tracking Tool - https://hqdadst.army.mil
• ADCCP AKO Site: - https://www.us.army.mil/suite/page/643748
• ADCCP EXORD: https://www.us.army.mil/suite/doc/29849376
• MilboST: https://www.milsuite.mil/boST/groups/army-data-center-consolidation
• Closure Report Formats: https://www.us.army.mil/suite/files/26504905