Wind Power Programme in
India
Ministry of New & Renewable Energy
1
stAugust 2012, New Delhi
Renewable Power Sector in INDIA
70% 4%
13%
13%
Share of Installed Renewable Capacity Share of Installed Renewable Capacity Share of Installed Renewable Capacity Share of Installed Renewable Capacity
Wind Solar Hydro Biomass
•
Total installed Capacity: 25,410 MW
Global Scenario
Global Scenario
Global Scenario
Global Scenario –
–
– Wind Power
–
Wind Power
Wind Power
Wind Power
Total global installed capacity: 2,37,669 MW (Dec.2011) Country Installed capacity (MW)
Country Installed capacity (MW) Country Installed capacity (MW) Country Installed capacity (MW)
China 62,364 USA 46,919 Germany 29,060 Spain 21,674 India India India
India 16,084 (now 17,644)16,084 (now 17,644)16,084 (now 17,644)16,084 (now 17,644) France 6,800
Italy 6,737 U.K. 6,540 Rest of the World 41491
Wind Power
Wind Power
Wind Power
Wind Power ---- Progress
Progress
Progress
Progress
Potential (at 50 m) : 49,130 MW Achievement so far : 17,644 MW Achievement in 10th Plan : 5427 MW
11th Plan Target : 9,000 MW
Achievement during 11th Plan : 10,250 MW Achievement during 2011-12 : 3,196 MW Target for 12th Plan : 15,000 MW
Target for 2012-13 : 3,000 MW
Wind Power
Wind Power
Wind Power
Wind Power –
–
–
– Progress (Contd.)
Progress (Contd.)
Progress (Contd.)
Progress (Contd.)
Wind Power
Wind Power
Wind Power
Wind Power –
–
– Progress
–
Progress
Progress (Contd.)
Progress
(Contd.)
(Contd.)
(Contd.)
State Potential (MW) Achievement (MW)
Andhra Pradesh 5349 264 Gujarat 10609 3016 Karnataka 8591 2025 Madhya Pradesh 920 376 Maharashtra 5439 2772 Rajasthan 5005 2079 Tamil Nadu 5374 7072 Others 7843 40
Wind Power Policies
Income Tax Holiday under section 80 1A Excise Duty relief
Concessional Customs Import Duty on specified parts and components
IREDA provides loan for commercial wind power projects
Preferential Tariff by State regulators
Accelerated Depreciation (80%) in first year
(withdrawn w.e.f. 01.04.2012). Now an
Accelerated Depreciation of 35% for the first year Generation Based Incentive
Generation Based Incentive
Generation Based Incentive
Generation Based Incentive
Generation Based Incentive
To Encourage higher generation/improve CUF
Transition from investment based incentive to outcome based incentive
Scheme for 4,000 MW in 11th Plan
GBI- 50 paise/kWh subject to max. Rs. 62 lakh /MW Duration : > 4 years, and < 10 years
Total of 1900 MW projects installed Evaluation carried out by CRISIL
To increase from 50 p to 81 p
To continue during 12th Plan without any ceiling
GBI proposed to be continued in 12th Plan
Recent Developments
Guidelines for installation of prototype wind
turbines issued on 22.05.2012 - to facilitate
indigenization
Condition of min. 200 W/m2 of wind power
density withdrawn in September, 2011
Benefit of AD withdrawn w.e.f. 1
stApril, 2012
Import of parts/sub-parts of rotor blades now
covered under Concessional Customs Duty
Benefit
(Notification
No.
12/2012-Customs, 17.03.2012, of Min. of Finance, for
2012-13).
Renewable Regulatory Fund (RRF)
Mechanism
As per Grid Code, complementary commercial
mechanism was to be implemented from 01.01.2011 On request of IWTMA, implementation of RRF
Mechanism postponed to 01.01.2012
CERC directed MNRE to convene a meeting among stakeholders to resolve RRF related issues
Task Force constituted to resolve the RRF issues formed under the chairmanship of Shri S.K.
Soonee, CEO, POSOCO
After several rounds of discussions among the
stakeholders and experts, Task Force submitted its report recently which is under consideration
Wind Resource Assessment
Wind Resource Assessment
Wind Resource Assessment
Wind Resource Assessment –
–
–
– Issues
Issues
Issues
Issues
Wind Resource Re Wind Resource ReWind Resource Re
Wind Resource Re----assessment at 100 m heightassessment at 100 m heightassessment at 100 m heightassessment at 100 m height
Wind resource re-assessment at 100 m height to be done at 75 sites across seven states.
State State State
State NoNoNo.... ofNo ofofof sitessitessitessites NOCsNOCsNOCsNOCs awaitedawaitedawaitedawaited
Andhra Pradesh 10 -Karnataka 13 1 Rajasthan 12 12 Tamil Nadu 12 6 Maharashtra 8 -Gujarat 12 11 Madhya Pradesh 8
General Wind Resource Assessment
General Wind Resource Assessment
General Wind Resource Assessment
General Wind Resource Assessment
Programme of C
Programme of C
Programme of C
Programme of C----WET
WET
WET
WET
WRA for 54 sites sanctioned in 2010-11
27 stations already commissioned (AP–all 15; Karnataka-10; Kerala-2)
No response from Tamilnadu(3), Puducherry(2), Rajasthan(2) States are requested to commission the remaining sites
10 sites finalised under WRA Programme 2010-11 for NE States. NOCs for all 10 sites received .
Year 2011-12
Odisha - 7 sites finalised, masts being set-up
Offshore Wind Power in India
India has a coast line of about 7600 km.
Preliminary assessment at 54 locations on the coast in the states of Tamil Nadu, Gujarat, Odisha, Maharashtra, Andhra Pradesh, Karnataka, Kerala, West Bengal, Puducherry and Goa.
Offshore Wind Power in India
A Steering Committee formed by the Ministry
A subcommittee of the Steering committee assigned the task of preparing draft policy for offshore wind power development.
Preliminary assessment done by Scottish Agency shows a potential of around 1000 (Rameshwaram) and another 1000 MW (Kaniyakumari). This needs validation.
Re-powering of Old Sites
About 4000 MW with unit size below 500 kW
For better potential harnessing – replace old and smaller generators by larger capacity & new generation wind turbines.
Issues
-Land ownership,
land costing and decommissioning cost States reluctant to go for new PPA
Realistic assessment of re-powering potential
Creation of an appropriate policy framework for re-powering including- Revision of PPA for repowered projects, transmission of power to other
C-WET’S ROLE
Established at Chennai as an autonomous institution of MNRE
Objectives and Functions: Objectives and Functions: Objectives and Functions: Objectives and Functions:
Technical focal point for wind power development Wind Resource Assessment
Standardization and certification
Testing facilities as per international standards Type approval for wind turbines
Information, Training & Commercial Services Research and Development
Organization of C-WET
Divisions in C-WET:
The Centre for Wind Energy Technology is working with the following structure
Research & Development unit Wind Resource Assessment Unit Wind Turbine Testing Unit
Standards and Certification Unit
Information, Training & Commercial Service Unit Solar Radiation Resource Assessment
Issues in Wind Power Development
Forest land clearance, mainly in Karnataka
Creation of infrastructure for power evacuation and transmission facilities
Availability of land
Potential land mostly acquired by manufacturers/ developers
States to revise Tariff as per CERC guidelines
Development of scheduling and forecasting system – Industry and LDCs not yet fully prepared
Withdrawal of Accelerated Depreciation Continuation of GBI Scheme
State Specific Issues –
ANDHRAPRADESH
Target for 2012-13 is 500 MW.
Inadequate Tariff at low PLF sites.
For Captive Generation, Banking and Wheeling not permitted
Entire cost of evacuation infrastructure has to be borne by the developer
No time limit on private wind monitoring due to which a few developers are holding potential land for long time 150 MW installed but not commissioned (as on
State Specific Issues -
GUJARAT
Target for 2012-13 is 300 MW and for 12th Plan 2100
MW
Tariff control period and wind policy ending in current year
Identification and purchase of land for compensatory afforestation is costly and long drawn process
Direct purchase of private land is not allowed
Construction of evacuation lines has to be done by
developer without any assistance from GETCO/GUVNL
State Specific Issues -
KARNATAKA
Target for 2012-13 is 604 MW.
Difficulty in getting forest land clearances on Western Ghats retarding the growth.
Formulation of policy for private wind resource assessment in consultation with C-WET.
Purchase of private land by developer not allowed Procedure for conversion to Non-Agricultural use-Alienation Procedure is time consuming
Actual potential of the state not clear - required to have long-term plan for development of the sector. To take up repowering of the old sites in the state.
State Specific Issues -
KERALA
In potential sites, availability of land a major concern since most of them fall in tea or coffee estates.
Grid network in estate areas very weak, investments required from state government to strengthen the connectivity
State has to take pro-active approach to attract private investors
Delays in power evacuation clearances from KSEB
State Specific Issues -
MADHYA PRADESH
Target for 2012-13 is 250 MW and for 2013-14 its 590 MW.
Proposal for licensing of tribal land at the value of land for a fixed period.
Has prepared detailed guidelines for implementation of projects giving time lines
Time taken for various clearances long
To carry out survey for re-powering of old sites
Working on a model of repowering where the owner of the old machines may be given share as per the average generation of the old machines for the remaining period of the otherwise replaced project.
State Specific Issues -
MAHARASHTRA
Target for 12th Plan is 1800 MW
Only slight addition to the potential when revised from 50 m to 80 m mast height.
Difficulty in getting forest clearance in the buffer area at Tiger Reserves.
Different rates of Gram Panchayat Tax and Right of Way charges (for erection of poles) across the state which should be uniform.
Sharing of Capital Subsidy from State Government, between MSEDCL and developer.
Issue of Mining Royalty levied on Wind Power developers.
State Specific Issues -
RAJASTHAN
With most of the high wind potential areas utilized by developers, fresh studies are required to be carried at new sites on higher altitude
Grid needs to be strengthened in Jaisalmer region to support the development of more wind power projects A few instances of delay in payments have been
State Specific Issues -
TAMIL NADU
Target for 2012-13 is 1000 MW and for 12th Plan it is
5000 MW
Target for Repowering is 80 MW
During peak windy season, many wind power projects were disconnected from grid, which caused a lot of wastage of power
A few instances of delay in payments have been reported, which needs to be addressed.
TNEB has constraints in providing power evacuation facilities to the new developers